HomeMy WebLinkAboutHEARTSIDE HILL COMMUNITY FACILITY - PDP230016 - SUBMITTAL DOCUMENTS - ROUND 2 - STAFF'S PROJECT COMMENTSPage 1 of 13
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6689
970.224.6134 - fax
fcgov.com/developmentreview
January 12, 2024
Kim Iwanski
Community at Heart, LLC
1303 W Swallow Road, Building 11
Fort Collins, CO 80526
RE: Heartside Hill Community Facility, PDP230016, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Heartside Hill Community Facility. If you have questions
about any comments, you may contact the individual commenter or direct your questions
through your Development Review Coordinator, Todd Sullivan via email at tsullivan@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Todd Sullivan tsullivan@fcgov.com 970-221-6695
Topic: General
Comment Number: 1
INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email correspondence
with other reviewers and keep me informed of any phone conversations. Thank you!
Comment Number: 2
SUBMITTAL:
As part of your resubmittal, you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a different font color.
When replying to the comment letter please be detailed in your responses, as
all comments should be thoroughly addressed. Comments requiring action
should NOT have a response such as noted or acknowledged. You will need to
provide references to specific project plans, pages, reports, or explanations of
why comments have not been addressed [when applicable].
Page 2 of 13
Comment Number: 3
SUBMITTAL:
Correct file naming is required as part of a complete submittal. Please follow
the Electronic Submittal Requirements and File Naming Standards found here:
https://www.fcgov.com/developmentreview/files/electronic-submittal-requiremen
ts-and-file-naming-standards_v1_8-1-19.pdf?1680306305.
File names should have the corresponding number, followed by the file type
prefix, project information, and round number. For example: 1_SITE PLAN_Project Name_FDP_Rd1.
A list of numbers and prefixes for each file can be found at the link above.
Comment Number: 4
SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove this feature, type
"EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-AutoCAD.html
Comment Number: 5
SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced notice as possible.
Comment Number: 6
INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration of your project.
Comment Number: 7
INFORMATION:
ANY project that requires four or more rounds of review would be subject to an additional fee of $3,000.00.
Comment Number: 8
NOTICE:
A Development Review sign will be posted on the property. This sign will be posted through the final
decision and appeal process. A request for the removal of signs will be made by your Development
Review Coordinator at the appropriate time.
Comment Number: 9
FOR HEARING:
All "For Hearing" comments need to be addressed and resolved prior to moving forward with scheduling
the Hearing. Staff will need to agree the project is ready for Hearing approximately 4 to 8 weeks prior to
the hearing.
Page 3 of 13
Comment Number: 10
FOR HEARING:
The proposed development project is subject to a Type 1 Review. The decision
maker for your project will be an Administrative Hearing Officer at a public
hearing. For the hearing, we will formally notify surrounding property owners
within 800 feet (excluding public right-ofway- and publicly owned open space). As your
Development Review Coordinator, I will assist with preparing the mailing and coordinating the
hearing date with your team.
Department: Planning Services
Contact: Katelyn Puga kpuga@fcgov.com
Topic: General
Comment Number: 1
01/08/2024: FOR INFORMATION - BUILDING PLACEMENT
The City prefers that buildings with community uses are placed in locations that
anchor the site at corners through build-to-line requirements and are easily
accessible to the public and neighborhood that it serves. There seems to be an
opportunity to locate the community building at the corner and the child-care phase closer
to the church. Please provide clarification on the consideration of this configuration.
RESPONSE: The Phase 1 Community Center was located based on project requirement for this
facility to have close proximately and a direct connection to the existing Heart of the Rockies
church since they have partial ownership and use of the Phase 1 Community Building. The
Phase 2 childcare center currently has no funding sources and its timeline for construction is
unknown at this time. In addition, the amount of area on the site required for outdoor playground
spaces to support the Phase 2 childcare center also dictated the placement of Phase 2 since there
would not have been enough space to provide this function while providing a direct connection
between Phase 1 and the church.
Comment Number: 2
01/08/2024: FOR HEARING - SHARED ACCESS
Please demonstrate that the site has access to utilize the church parking lot and
existing trash enclosure onsite. A shared access easement or shared access
agreement between the church and the community facility uses would satisfy
this requirement. Please reference the shared access on the site plan by
including a note on the cover sheet that details all site elements that are require
the shared access between the properties.
RESPONSE: A draft MOU is included.
Comment Number: 3
01/08/2024: FOR HEARING - BUILDING DESIGN
Buildings are required to be articulated and subdivided into massing that is
proportional to the mas and scale of other structures on the same block face or
opposing block face. The design of the south section of the child-care facility
building needs to be designed in a manner that provides more dimension and
breaks in the massing to match the massing and scale of multi-family building facades.
RESPONSE: This facade has been redesigned to meet the requirements with the revised 2nd PDP
submitttal.
Comment Number: 4
01/08/2024: FOR HEARING - BUILDING DESIGN
Page 4 of 13
Building materials are required to be similar to the materials already being used
in the neighborhood. Please demonstrate how the proposed building materials
are similar to the materials used in the church and multi-family buildings. Please
revise accordingly as necessary to meet this standard (Section 3.5.1.E)
RESPONSE: Please see below for the list of proposed materials and their
context in the surrounding neighborhood:
•30-year high-profile architectural asphalt shingles – similar to new
apartments
•Synthetic stone veneer – Coronado Stone Urbana Split – selected to
emulate Split Face CMU on existing Heart of the Rockies Church
•Synthetic stone veneer – Coronado Stone Old World Ledge – Huron –
similar to new apartments.
•3-coat portland cement based stucco system – similar to existing Heart of
the Rockies Church.
•Horizontal fiber cement lap siding – similar to new apartments.
Comment Number: 5
01/08/2024: FOR HEARING - BUILDING DESIGN
Provide window square footage on plans for all elevations that face streets or
Connecting pedestrian frontage (west and south elevations) to demonstrate that
a minimum of 50 percent of the facade has windows, entrances, arcades,
arbors, awnings, or treillage with vines.
RESPONSE: This measurement has been included to show compliance with this LUC section with the
revised 2nd PDP submittal.
Comment Number: 7
01/08/2024: FOR HEARING - SITE DESIGN
Design of access to the community center should provide direct access to the
residents to the facilities. There is an opportunity to provide a more direct
connection between the community facility and the park facility for the residents
use. Please consider direct connections between these facilities for us of the neighborhood.
RESPONSE: As discussed on our call, we would like to table the conversation until the church has more
defined plans for that area – community gardens, etc.
Comment Number: 8
01/08/2024: FOR HEARING - LANDSCAPING
Full tree stocking is required in all landscape areas within 50 ft. of the building.
Additional trees are required to meet this standard and can be designed in
formal or informal groupings that meet the spacing dimensions for the following tree groups:
1. Canopy shade trees - 30- 40 ft. spacing
2. Coniferous evergreen trees - 20-40 ft. spacing
3. Ornamental trees - 20'-40' spacing
RESPONSE: 2 shade and 2 ornamental trees have been added within 50’ of building.
Comment Number: 9
01/08/2024: FOR HEARING - LANDSCAPING
Planting beds along the high use and -high visibility- sides of the building (west
and south sides) are required to be at least 5 ft. wide along 50 percent of walls.
Please demonstrate on plans and revise accordingly as needed.
RESPONSE: Shrub beds have been widened on the east side of site.
Comment Number: 10
Page 5 of 13
01/08/2024: FOR HEARING - LIGHTING
The site is zoned LMN and is located within the Lighting Context Area 1 (LC1).
Please revise the Lighting Plan accordingly to meet the standards for LC1 rather than LC3.
RESPONSE: The site photometric plan has been revised to meet the requirements with the revised 2nd
PDP submittal.
Comment Number: 11
01/08/2024: FOR HEARING - SITE PLAN REDLINES
Please refer to the redlines provided on the site plan for additional planning comments to be addressed.
RESPONSE: Redlines have been addressed.
Comment Number: 12
01/08/2024: FOR HEARING - BUILDING ELEVATIONS REDLINES
Please refer to the redlines provided on the building elevations for additional
planning comments to be addressed.
RESPONSE: These comments have been addressed with the revised 2nd PDP submitttal.
Comment Number: 13
01/08/2024: FOR HEARING - LANDSCAPING PLAN REDLINES
Please refer to the redlines provided on the landscaping plan for additional
planning comments to be addressed.
RESPONSE: Landscape plan redlines have been addressed.
Comment Number: 14
01/08/2024: FOR HEARING - LIGHTING PLAN REDLINES
Please refer to the redlines provided on the lighting plan for additional planning
comments to be addressed.
RESPONSE: The site photometric plan has been revised to meet the requirements with the revised 2nd
PDP submittal.
Department: Engineering Development Review
Contact: John Gerwel jgerwel@fcgov.com
Topic: General
Comment Number: 1
01/05/2024: FOR HEARING:
Is the property (Lot 1, Block 3 of the proposed plat on MA230145) on which the
temporary grading easement is proposed owned by a different party? If so, then
we will need a signed Letter of Intent (LOI) from the property owner prior to
hearing. It would be good to submit that TCE for review as well so it doesn't hold
anything up in the FDP review. The same goes for the sidewalk/ADA ramp - LOI
will need to include that if an LOI is needed. I would also recommend adding a
private access easement that covers the ramp onto the plat and expand the
TCE to cover the construction of that path.
RESPONSE: The temp grading easement is a part of the Minor Amendment & Minor Subdivision
that is currently under review. The church is a part of the Minor Subdivision Plat as owners and
signers.
Comment Number: 2
01/05/2024: FOR HEARING:
The drainage infrastructure and the grading on the east poses a similar
question. Is the owner of Tract A separate from the owner of this property? If so,
then we need an LOI. That area should also be amended on the plat to include a
Page 6 of 13
drainage easement, and you may want to extend that TCE to cover this area as well.
RESPONSE: RESPONSE: The temp grading easement is a part of the Minor Amendment & Minor
Subdivision that is currently under review. The church is a part of the Minor Subdivision Plat as
owners and signers.
Comment Number: 3
01/09/2024: FOR HEARING:
The sharing of parking spaces and the trash enclosure will require a signed LOI
as well. Regarding all of these Letters of Intent, we only need one letter per
owner, not per issue. So the parking, trash, access ramp, and part of the
drainage outfall can all get lumped into one letter with the church. The rest of the
drainage outfall and grading can be another letter for that other owner.
RESPONSE: A draft MOU is included.
Comment Number: 4
01/10/2024: FOR FINAL APPROVAL:
We will want to see phasing on the utility plans.
RESPONSE: There will be no phasing of the utilities. The building phases are labeled accordingly.
Also it should be noted that the utility providers are FCLWD and SFCSD.
Department: Traffic Operation
Contact: Steve Gilchrist sgilchrist@fcgov.com 970-224-6175
Topic: General
Comment Number: 1
01/04/2024: INFORMATION: Thank you for providing the narrative clarifying
the intended use and impacts the community center will have on the overall trip
generation for this site. No further traffic evaluation is required unless significant
changes occur within the site plan that would increase the number of trips to this site.
TIS waived.
Department: Stormwater Engineering
Contact: Basil Hamdan bhamdan@fcgov.com 970-222-1801
Topic: Erosion Control
Comment Number: 3
01/05/2024: FOR FINAL:
Please prove calculations for total disturbed area for fee calculations.
Please call out seeding and mulching of all disturbed areas.
RESPONSE: Will do, thank you
Topic: General
Comment Number: 1
01/05/2024: FOR FINAL:
Please provide temporary grading easement by separate document.
RESPONSE: RESPONSE: The temp grading easement is a part of the Minor Amendment & Minor
Subdivision that is currently under review. The easement dedication by separate document should
be complete prior to the community building approval
Comment Number: 2
Page 7 of 13
01/05/2024: FOR FINAL:
Please address comments on drainage memo and Utility plans.
RESPONSE: Will do, Thank you.
Department: Light And Power
Contact: Rob Irish rirish@fcgov.com 970-224-6167
Topic: General
Comment Number: 1
01/08/2024: Information Only: The primary electric feed for the proposed
transformer will come from an existing electric primary vault that will be installed
with the Heartside Hill multi-family project. Once this vault is set, it will provide
for a 3-phase transformer to feed the Community Facility.
Comment Number: 2
01/08/2024: For Approval: Please indicate the location of the proposed electric
meter. Looks to be on the East side of Phase 1 but not entirely sure.
This project will need to comply with our electric metering standards. Electric
meter locations will need to be coordinated with Light and Power Engineering.
Reference Section 8 of our Electric Service Standards for electric metering
standards. A link has been provided below.
https://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStanda
rds_FINAL_18November2016_Amendment.pdf
RESPONSE: Yes, the proposed main electrical service will be located on the east side of the
Phase 1 building near the south end.
Comment Number: 3
01/08/2024: For Approval: A Customer Service Information form (C-1 form)
and a one-line- diagram for all commercial meters will need to be completed and
submitted to Light & Power Engineering for review prior to Final Plan. A link to
the C-1 form is below:
http://zeus.fcgov.com/utilsprocedures/files/EngWiki/WikiPdfs/C/C1Form.pdf
RESPONSE: The electrical design is in the preliminary stages. For the phase 1 portion of this
project the anticipated main service size is 400amps (120/208-volt, three-phase, four-wire). Note
that the phase 2 building is also proposed to be served from the same pad mounted transformer
with an anticipated main service size at 400amp service.
Comment Number: 4
01/08/2024: Information Only: The secondary services to the buildings will be
consider commercial; therefore, the service line from the transformer to the
meter is required to be installed, owned and maintained by the property owner.
Comment Number: 5
01/08/2024: Information Only: Electric capacity fee, building site charges, and
any system modification charges necessary to feed the site will apply to this
development. Please contact me or visit the following website for an estimate
of charges and fees related to this project:
http://www.fcgov.com/utilities/business/builders-anddevelopers/-plant-investment-development-fees
Page 8 of 13
Department: Water Conservation
Contact: Emma Pett epett@fcgov.com
Topic: General
Comment Number: 1
01/09/2024:
INFORMATION: Final irrigation plans are due at building permit application, but
we encourage you to submit them earlier in case changes need to be made.
Detailed irrigation submittal requirements can be found here:
https://www.fcgov.com/utilities//img/site_specific/uploads/irrigation-plan-submittal-reqs.pdf?1649260267
RESPONSE: Irrigation plans will be submitted with next round.
Department: Environmental Planning
Contact: Kristie Raymond kraymond@fcgov.com
Topic: General
Comment Number: 1
12/19/2023: FOR FINAL APPROVAL:
Thank you for providing Low Grow Native Seed Mix notes, however, please
ensure the following standard Native Seed Mix Notes are included in your notes:
NATIVE SEED MIX NOTES
1. THE TIME OF YEAR SEEDING IS TO OCCUR SHOULD BE OCTOBER THROUGH EARLY
MAY.
2.PREPARE SOIL AS NECESSARY AND APPROPRIATE FOR NATIVE SEED MIX SPECIES
THROUGH LOOSENING AND ADDITION OF AMENDMENTS THAT PROMOTE WATER
ABSORPTION AND RELEASE, THEN SEED IN TWO DIRECTIONS TO DISTRIBUTE SEED
EVENLY OVER ENTIRE AREA. DRILL SEED ALL INDICATED AREAS AS SOON AS POSSIBLE
AFTER COMPLETION OF GRADING OPERATIONS.
3. IF CHANGES ARE TO BE MADE TO SEED MIX BASED ON SITE CONDITIONS THEN
APPROVAL MUST BE PROVIDED BY CITY ENVIRONMENTAL PLANNER.
4. APPROPRIATE NATIVE SEEDING EQUIPMENT WILL BE USED (STANDARD TURF
SEEDING EQUIPMENT OR AGRICULTURE EQUIPMENT SHALL NOT BE USED).
5. DRILL SEED APPLICATION RECOMMENDED PER SPECIFIED APPLICATION RATE TO
NO MORE THAN ½ INCH DEPTH. FOR BROADCAST SEEDING INSTEAD OF DRILL SEEDING
METHOD DOUBLE SPECIFIED APPLICATION RATE. REFER TO NATIVE SEED MIX TABLE
FOR SPECIES, PERCENTAGES AND APPLICATION RATES.
6. PREPARE A WEED MANAGEMENT PLAN TO ENSURE THAT WEEDS ARE PROPERLY
MANAGED BEFORE, DURING AND AFTER SEEDING ACTIVITIES.
7. AFTER SEEDING THE AREA SHALL BE COVERED WITH CRIMPED STRAW, JUTE MESH,
OR OTHER APPROPRIATE METHODS. PLASTIC-BASED EROSION CONTROL MATERIALS
(I.E., PLASTIC-WELDED BLANKETS) SHALL NOT BE USED WITHOUT EXPRESS
PERMISSION FROM THE ENVIRONMENTAL PLANNER AS THESE MATERIALS HAVE
PROVEN TO CAUSE WILDLIFE ENTRAPMENT ISSUES.
8. WHERE NEEDED, TEMPORARY IRRIGATION SHOULD BE PROVIDED UNTIL SEED IS
GERMINATED THEN WEEN THE SEED FROM IRRIGATION. IF IRRIGATION IS USED, THE
IRRIGATION SYSTEM FOR SEEDED AREAS SHALL BE FULLY OPERATIONAL AT THE TIME
OF SEEDING AND SHALL ENSURE 100% HEAD-TO-HEAD COVERAGE OVER ALL SEEDED
AREAS. ALL METHODS AND REQUIREMENTS IN THE APPROVED IRRIGATION PLAN SHALL
BE FOLLOWED.
9. CONTRACTOR SHALL MONITOR SEEDED AREA FOR PROPER IRRIGATION, EROSION
Page 9 of 13
CONTROL, GERMINATION AND RESEEDING AS NEEDED TO ESTABLISH COVER.
10. THE APPROVED NATIVE SEED MIX AREA IS INTENDED TO BE MAINTAINED IN A
NATURAL LIKE LANDSCAPE AESTHETIC. DO NOT MOW DURING HOT, DRY PERIODS. DO
NOT MOW LOWER THAN 6 TO 8 INCHES IN HEIGHT TO AVOID INHIBITING NATIVE PLANT
GROWTH.
11. NATIVE SEED AREA WILL BE CONSIDERED ESTABLISHED WHEN SEVENTY PERCENT
VEGETATIVE COVER IS REACHED WITH LESS THAN TEN PERCENT OF COVER
CONSISTING OF NOXIOUS WEEDS, NO BARE SPOTS LARGER THAN ONE FOOT SQUARE,
AND/OR UNTIL DEEMED ESTABLISHED BY CITY PLANNING SERVICES AND EROSION
CONTROL.
12. THE DEVELOPER AND/OR LANDSCAPE CONTRACTOR IS RESPONSIBLE FOR
ADEQUATE SEEDLING COVERAGE AND GROWTH AT THE TIME OF FINAL STABILIZATION,
AS DEFINED BY STATE AND LOCAL AGENCIES. IF FINAL STABILIZATION IS NOT ACHIEVED
TO THE SATISFACTION OF THE AGENCY, THE DEVELOPER AND/OR LANDSCAPE
CONTRACTOR SHALL BE RESPONSIBLE FOR ADDITIONAL CORRECTIVE MEASURES TO
SATISFY FINAL VEGETATIVE REQUIREMENTS FOR CLOSEOUT.
RESPONSE: Native Seed Mix Notes have been added to sheet LS00.
Comment Number: 2
12/19/2023: INFORMATION ONLY:
Please note that 1.5" river rock will cover ground but will not function as a mulch to deter weeds
and retain moisture. If a rock mulch is desired, then 3/4" of 1/2" screen or smaller would be
necessary.
RESPONSE: Revised to specify ½" - ¾" cobble mulch.
Comment Number: 3
12/19/2023: INFORMATION ONLY:
For the low grow native mix it would be nice to add some wildflower seed to the
mix to promote pollination. This can provide corridors for pollinators as they
move to an area. This is also a great opportunity to maximize bloom times and
colors in this section of your plan. Some species to consider are:
Blanketflower (Gaillardia pinnatifida)
Purple Coneflower (Echinacea angustifolia)
Rocky Mountain Penstemon (Penstemon strictus)
Beebalm (Monarda fistulosa)
These are just some examples, but there are many other species that would do
great in this area and add environmental and aesthetic value.
RESPONSE: Added wildflower mix to the native seed mix specs.
Department: Forestry
Contact: Christine Holtz choltz@fcgov.com
Topic: General
Comment Number: 1
01/08/2024: FOR HEARING
As per planning's comments, please include a few more trees along perimeter of the Day Care
center. You can find a list of approved shade trees on our website fcgov.com-/forestry – and
there is a more extensive list available from Forestry if needed (choltz@fcgov.com). Please
increase diversity with additional plantings in both species and genus.
RESPONSE: Additional trees have been added.
Page 10 of 13
Comment Number: 2
01/08/2024: FOR INFORMATION
Please keep in mind the following separation requirements: Utility/Tree Separation:
10’ between trees and public water, sanitary, and storm sewer main lines
6’ between trees and water or sewer service lines
4’ between trees and gas lines
10’ between trees and electric vaults
RESPONSE: Acknowledged. Thank you.
Department: Park Planning
Contact: Missy Nelson mnelson@fcgov.com
Topic: General
Comment Number: 1
01/09/2024: No comments from Parks or Park Planning and Development, thank you.
Department: PFA
Contact: Marcus Glasgow marcus.glasgow@poudre-fire.org 970-416-2869
Topic: General
Comment Number: 1
01/10/2024: FOR FINAL
AUTOMATIC FIRE SPRINKLER SYSTEM - Group A-3 Occupancy
IFC 903.2.1.3: An automatic sprinkler system shall be provided for Group A-3
occupancies where one of the following conditions exists:
1. The fire area exceeds 5,000 square feet;
2. The fire area has an occupant load of 300 or more; or
3. The fire area is located on a floor other than the level of exit discharge serving such occupancies.
AUTOMATIC FIRE SPRINKLER SYSTEM - GROUP I
An automatic sprinkler system shall be provided throughout buildings with a
Group I fire area. See Exceptions. (IFC 903.2.6)
It has been communicated that the intent is to only install a sprinkler system in
the group I (phase2) portion of this building. In order to do this, the occupant
load will need to be under 300 in the community room. Also, a Fire Wall will be
required for separation between the 2 buildings.
RESPONSE: Comments Acknowledged.
Comment Number: 2
01/10/2024: FOR FINAL
FIRE DEPARTMENT HOSE CONNECTION
- IFC 912.2: Fire Department Connections shall be installed in accordance with
NFPA standards. Fire department connections shall be located on the street
side of buildings, fully visible and recognizable from the street or nearest point
of fire department vehicle access. The location of the FDC will be reviewed at
construction and the sprinkler system permit.
An underground fire line permit is required by the Poudre Fire Authority. As per
Colorado state law (8 CRR 1507-11), individuals or companies installing
Page 11 of 13
underground supply lines from public water supplies to fire sprinkler system
risers, standpipes, and other fire protection systems must be registered with the
State of Colorado Division of Fire Prevention and Control (DFPC) as a “FIRE
SUPPRESSION SYSTEM CONTRACTOR – UNDERGROUND”. Permit
applications should include a current business name and registration number.
As per DFPC records, currently registered individuals and companies can be found here:
https://dfpc.colorado.gov/sites/dfpc/files/2021%20Suppression%20Contractor%20Registrations.pdf
Additional information regarding requirements of Colorado state law can be
found here:
https://dfpc.colorado.gov/fire-suppression-system-contractors
Comment Number: 3
01/10/2024: FOR FINAL
FIRE LANE SIGNS
The limits of the fire lane shall be fully defined and fire lane sign locations should
be indicated on future plan sets. Refer to LCUASS detail #1418 & #1419 for
sign type, placement, and spacing. Appropriate directional arrows required on
all signs. Posting of additional fire lane signage may be determined at time of
fire inspection. Code language provided below.
- IFC D103.6: Where required by the fire code official, fire apparatus access
roads shall be marked with permanent NO PARKING - FIRE LANE signs
complying with Figure D103.6. Signs shall have a minimum dimension of 12
inches wide by 18 inches high and have red letters on a white reflective
background. Signs shall be posted on one or both sides of the fire apparatus
road as required by Section D103.6.1 or D103.6.2.
- IFC D103.6.1; ROADS 20 TO 26 FEET IN WIDTH: Fire lane signs as
specified in Section D103.6 shall be posted on both sides of fire apparatus
access roads that are 20 to 26 feet wide.
- IFC D103.6.1; ROADS MORE THAN 26 FEET IN WIDTH: Fire lane signs as
specified in Section D103.6 shall be posted on one side of fire apparatus
access roads more than 26 feet wide and less than 32 feet wide.
Comment Number: 4
01/10/2024: FOR FINAL
FIRE LANE LOADING - IFC Appendix D102.1 amendment
Fire lanes shall be designed as a flat, hard, all-weather driving surface capable
of supporting 80,000 pounds. Private drives used for fire lanes shall provide
information confirming the design can handle fire truck loading. A note shall be
added to the civil plans indicating all areas dedicated as EAE are capable of
supporting 80,000 pounds.
Comment Number: 5
01/10/2024: FOR HEARING
TURNING RADII
- IFC 503.2.4 and Local Amendments: The required turning radii of a fire
apparatus access road shall be a minimum of 25 feet inside and 50 feet outside.
The EAE in the parking lot does not meet this minimum requirement. A turning
exhibit showing no body or wheel overhang can be submitted for review.
RESPONSE: The EAE is aligned with the existing parking lot, not adjustments are anticipated
within the existing parking lot. A turning exhibit has been prepared and is included for
Page 12 of 13
consideration.
Comment Number: 6
01/10/2024: FOR FINAL
PREMISE IDENTIFICATION: ADDRESS POSTING & WAYFINDING – IFC section 505.1.1 amendment
Where possible, the naming of private drives is usually recommended to aid in
wayfinding. New and existing buildings shall be provided with approved
address identification. The address identification shall be legible and placed in
a position that is visible from the street or road fronting the property. Address
identification characters shall contrast with their background. Address numbers
shall be arabic numbers or alphabetical letters. Numbers shall not be spelled
out. The address numerals for any commercial or industrial buildings shall be
placed at a height to be clearly visible from the street. They shall be a minimum
of 8 inches in height unless distance from the street or other factors dictate
larger numbers. Refer to Table 505.1.3 of the 2021 IFC as amended. If bronze
or brass numerals are used, they shall only be posted on a black background for
visibility. Monument signs may be used in lieu of address numerals on the
building as approved by the fire code official. Buildings, either individually or
part of a multi- building complex, that have emergency access lanes on sides
other than on the addressed street side, shall have the address numbers and
street name on each side that fronts the fire lane.
Please update note 17 to show 8-inch numerals.
RESPONSE: Elevations have been updated.
Department: Internal Services
Contact: Russell Hovland rhovland@fcgov.com 970-416-2341
Topic: Building Insp Plan Review
Comment Number: 1
01/08/2024: Commercial Construction shall comply with adopted codes as
amended. Current adopted codes are:
2021 International Building Code (IBC) with local amendments
2021 International Existing Building Code (IEBC) with local amendments
2021 International Energy Conservation Code (IECC) with local amendments
2021 International Mechanical Code (IMC) with local amendments
2021 International Fuel Gas Code (IFGC) with local amendments
2021 International Swimming Pool and Spa Code (ISPSC) with local amendments
Colorado Plumbing Code & state amendments (currently 2021 IPC)
2023 National Electrical Code (NEC) as amended by the State of Colorado
Projects shall comply with the current adopted building codes, local
amendments and structural design criteria can be found here: https://www.fcgov.com/building/codes
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017.
Snow Live Load: Ground Snow Load 35 PSF.
Frost Depth: 30 inches.
Wind Loads: Risk Category II (most structures):
140mph (Ultimate) exposure B or Front Range Gust Map published by The
Structural Engineer's Association of Colorado
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code: 2021 IECC commercial chapter.
Page 13 of 13
INFORMATIONAL ITEMS:
Commercial occupancies must provide 10ft to 30ft of fire separation (setback)
from property lines and 20 feet between other buildings or provide fire rated
walls and openings per chapter 6 and 7 of the IBC.
City of Fort Collins adopted International Fire Code (IFC) and amendments to
the 2018/2021 IFC require a full NFPA-13 sprinkler system per IBC chapter 9 or
when building exceeds 5000 sq.ft. (or meet fire containment requirements).
Buildings using electric heat, must use heat pump equipment.
A City licensed commercial general contractor is required to construct any new commercial structure.
Plans must be signed and stamped by a Colorado licensed architect or
engineer and must be included in the permit application.
Electric vehicle parking spaces are now required per local amendment to the IBC. See section 3604.
For projects located in Metro Districts, there are special additional code
requirements for new buildings. Please contact the plan review team to obtain
the requirements for each district.
Department: Technical Services
Contact: Jeff County jcounty@fcgov.com 970-221-6588
Topic: General
Comment Number: 1
01/08/2024: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at FDP.
RESPONSE: Acknowledged.
Department: Outside Agencies
Contact: Cory Thelen, Xcel Energy, Cory.M.Thelen@xcelenergy.com
Topic: General
Comment Number: 2
Where is the gas meter proposed on the new building?
RESPONSE: The gas meter is currently being proposed in the northeast corner of the building.
Contact: Jacy McNulty, Larimer County Planning, Planning@larimer.org
Topic: General
Comment Number: 1
Larimer County Planning and Engineering have no comments.