December 15, 2016
Ted Shepard
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
Re: Midtown Gardens Marketplace — King Soopers Store #146— Preliminary Design
Review, PDR 160005, Round Number (Applicable Conceptual � Response Letter)
Dear Ted,
Please find below our re=submittal package addressing the comments reeeived on May 9, 2016.
To facilitate your review, we have included the original comments in italicized font, and have
provided our responses in bold.
Planning Services
1. 05/Q3>2016: As we have discussed with the applicant and the consulting team, fhe proposed
redeVelopment does not meet fhe policy expectations as documented in the City of Forf Collins
Midtown Plan adopted by Gity Council on October 1, 2013. For example, on page 1-5, fhe Plan
stafes:
"Midfown should inelude a rich mix of uses, and at higher densities than exist today. Commercial
businesses will continue to be an important part of fhe formula, and mor� housing should be
introduced, as well as civic and institutional uses. Housing, in the form of apartments and
townhouses, should be developed fo take advantage of the MAX transit system and help create
more ridership for the MAX service, and to make more e�cient use of land that is close fo #he ciiy
center. Some of this housing would be developed as upper levels of mixed use buildings thaf face
onto College Qvenue, while others would orient to cross streets, Mason Street, and to the MAX
line. Housing should address a diversity of markets, including sfudenfs, young professionals,
families and seniors. n
Response: The Midtown Plan area boundary extends along College Avenue from
Prospect Road on fhe north to Fairview Lane on the south. Although individual
parcels do not each include a mix of uses, the plan area as a whole does include a
mix of uses. The proposed site has been designed for a King Soopers Marketplace
along with the existing retail building at, the southeast corner of the site along
College Avenue. The site includes an easement area for 60 shared parking spaces
and access benefitting MAX/BRT users. Housing will not be included on the
Galloway & Company, Inc. . 303.770.8884 • 6162 S. Willow Drive, Suite 320 • Greenwood vllage, CO 80111 • www.GallowayUS.com
f
Ted Shepard
Kmart Redevelopment
December 15,2016
proposed site. The nature of the Midtown Plan is visionary, not regulatory; we
cannot take on implementation of this Midtown Plan vision by ourselves; King
Soopers is not a housing develope�; the resou�ces needed to solicit, negotiate
and redesign to involve a housing developer partner are not feasible.
2. 05/03/2016: Sfaff encourages fhe applicant to explore more creative opportunities to enrich the mix
of uses, particularly mul#i-family housing: Fort Collins is currently aftracting strong interest from a
variety of multi-family developers who operate at fhe national scale. It appears #haf giyen #he close
proximity to the MAX, both King Soopers and the national multi-family industry would find mutual
benefit in co-developing this site in a joinf venfure arrangement. Adding multi-family housing would
allow the project to better fit the vision as called for in the Midtown Plan.
Response: The Midtown Plan area boundary extends along College Avenue from
Prospect Road on the north to Fairview Lane on the south� Although individual
parcels do not each include a mix of uses, the plan area as a whole does include a
mix of uses. The proposed site has been designed for a King Soopers Marketplace
along with the existing retail building at the southeast corner of fhe site along
College Avenue. The site includes an easement area for 60 shared parking spaces
and access benefitting MAX/BRT users. Housing wiil not be included on the
proposed site.
3. 05/03/2016: As proposed, the building is set back from both arterial streets by a significant
distance. In addition, the areas belween fhe building and fhe streets are large fields of parking and
private access drives. This arrangement is reflective of a single-use, auto-dominated suburban
development pattern. As such, the site needs to be designed in such a way as to break down this
pattern and mitigate the impacts that face pedestrians; bicyclists and MAX riders.
Response: The building has been oriented to allow pedestrian/bicyclists,
MAX/BRT, and vehicular access to the site in a way to utilize the ezisting access
points. Landscape islands within the parking lot have been inciuded, and two
pedestrian corridors are included to bring pedestrians into the site from College
Avenue. The pedestrian corridors provide cross connection to adjacent
development through the site, and also allow access between College Avenue and
the MAX/BRT station.
4. 05/03/2016: Since Drake Road is the nearest public street, the private access drive that intersects
with Drake Road must be upgraded. Sidewalks musf be placed on both sides (Section 3.2.2(C)(5)..
These sidewalks must be detached and feature a parkway that is no less than six feet in width
excluding fhe curb. The parkway then must be landscaped wifb street trees spaced af uniform
intervals not to exceed 40 feet. To accomplish this, the landscape islands on fhe north side must
be widened. (The project narrative refers to an east=west pedestrian corridor but such a feature is
not shown on the site qlan.)
Galioway & Company, Inc. e 303.770.8884 e 6162 S. Willow Drive, Suite 320 • Greenwood vllage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: The main access from Drake Road has been upgraded to
accommodate recommendations from the traffic impact study for the site. A
detached sidewalk has been provided on the west side of the access. The eastern
side of the access drive includes an existing sidewalk located on the adjacent site,
which is proposed to remain.
5. 05/03/2016: The building must feature a well-designed, prominent outdoor plaza and gathering
area at its soufheast comer where the aforementioned sidewalks wrll terminate. Such a plaza will
help activate the north-south private drive.
Response: An outdoor plaza area has been included on the south side of the King
Soopers building, and connects pedestcians to College Avenue and the MAX
station. This area features bicycle parking, and also inciudes a covered
patio/gathering area at the southeast corner of the building made more
comfortable by shade trees and benches.
6. 05/Q3/2016` While the project narrative indicates that a plaza is planned for this area, there
appears to be no accommodation for such amenities on the sife plan, (The site plan shows an
outdoor patio area but in the northeast cornerof the building.) in fact, the soufh side of the building
is given over to two auto-related components which would have the opposite effecf. Staff
recommends that fhe multiple drive-through lanes for the pharmacy and "click-lisY' functions be
relocated to the north side of the building away from the view from Drake Road and away from the
_
pedestrian amenities that are intended fo activafe the southeast corner of the building. In addition,
these two drive-through features inhibit pedestrian connectivify befinreen fhe MAX and the sfore
entrance. It would be safer to separate pedestrians from drive-through lanes than to combine
them. (Section 3.2.2(H).
Response: Based on feedback provided, the interior layout of the proposed
building has been reversed in order to move the auto-related components (drive-
thru pharmacy and online pickup location) to the north side of the building. This
orientation allows the easte�n and southern sitles of the b"uiiding to remain
pedestrian focused. Pedestrian waikways providing cross connection with
adjacent development and between Coilege Avenue and the MAX/BRT station
have been included to encourage pedestrian use of the site.
7. 05/03/2016: As depicted, the number of drive-through lanes assigned to fhe pharmacy is.
excessive.
Response: The number of drive-thru lanes for the pharmacy has been reduced to
two.
8. 05/03/2016: The plaza at the southeast corner of the building should be exfended wesf fo connecf
Gallcway & Company, Inc. e 303.770.8884 � 6162 5. Willow Drive, Suite 320 . Greenwood �ilage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
and fuily integrate with the MAX stafion. This area should be actNa#ed with a variety of landscaping
and hardscaping with direct access to indoor function such as the coffee shop, deli, and prepared
take-out items. With southem exposure, please explore use of shade structures, pergolas and the
like, upon whieh solar panels could be mounted.
Response: The plaza on the south side of the building has been expanded into a
larger area that connects the MAX station and the pedestrian waikway to College
Avenue. The patio/gathering area included at the southeast corner of the building
has been expanded to include covered seating and direct access to the store.
9. 05l03/2016: The southeasf and soufh ptaza should not only connect to the MAX station but also to
the Grand Promenade as called for in the Midtown Plan (page 1-14). This urban design feature
would run along the west side of the store befween the Spring Creek Station and fhe Drake Road
Stafion in order to accommodate bikes and pedestrians. The redevelopment of this site should
proyide for this extra wide multi-use path and screen the back of the store operations appropriately.
Response: The proposed King Soopers building has been shifted east, in order to
provide the land area along fhe western property boundary to accommodate the
cross-section of the Grand Promenade as shown in the MidTown plan. The plaza
along the south side of the building provides access to the Grand Promenade and
_.
MAX%BRT area. The proposed King Soopers loading dock areas include masonry
walis along the wes# side in order to provide screening of this area from the west.
10. 05/03/2016: Landscaping within the souti►east and south-facing plaias should be reflect the Upper
Midtown - Gardens theme as described in the Midfown Plan (page 1-7).
Resp.onse: The Gardens theme found within the Midtown plan has been
incorporated with the landscape design in the following ways:
o Planting design features drought tolerant and native shrubs and grasses.
a Planting areas will incorporate botanical signage where possible for
interpretation and connection to the nearby CSU demonstration garden.
o The landscape treatment along the pedestrian corridor connecting College
Avenue and the MAX BRT station will consist of deciduous shade trees and
_ _.. . .. ..
flowering perenniais.
o The plaza south of the building functions as a small park space with open
lawn, accent planting areas, vine treliis and upright evergreens for
screening.
11. 05/03/2016: In order to better esfablish a pedestrian-scaled presence along Drake Road, the
southeasf comer of fhe building must feature a sfrong iconic architectural element that is clearly
distinc#ive from ihe front and side elevations. Such a feature helps mitigate the aspects of the
parking lots and auto-dominanf environment. For reference, Walmart provided such a feature
between the main entranee and Lemay Avenue and Home Depof did likewise between its entry
Galloway & Company, inc: 0 303.770.8884 e 6162 5. Willow Drive, Suite 320 e Greenwood Yllage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
and Magnolia Street. Such features help break down the large building mass and promofe a more
pedestrian-scaled environmenf.
Response: A"tower-like" architectural element has been added to the southeast
corner.
12. 05/03/2016: One or _fwo pedestrian walkways are needed to connecf the store entrance to South
College Avenue (the North College store has two). Staff recommends that at least one of these
walkways be placed in the middle of fhe parking bay ihat features fhe handicap parking stalls
_ _
closest fo the inain entry. (Again, for reference, please see the multiple walkways that bisecf fhe
larg�e parking lofs at Walma�t and Home Depot at Mulberry Street and l:emay Avenue.) These
walkways wi11 help facil'�tate east-west intemal circulation as called for in the Midtown Plan (page
1-13).
Response: Two pedestrian walkways have been incorporated through the parking
lot connecting the proposed King Soopers store to College Avenue. The southern
walkway also provides cross-access to the existing retail building along College
Avenue, as well as to the MAX BRT station.
13. 05/03/2016: The pedestrian walKway between the proposed retail building and the store must
include frees in grates.
Response: Landscape islands have been included within the parking lot and
provide planting areas better suited for tree growth.
14. 05/03/2016: All connecting walkways should feature trees in grates where full landscape is/ands
are not feasible.
Response: Landscape islands have been included within the parking lot and
provide planting areas better suited fortree growth.
15. 05/03/2016: If the proposed right-in/right-out access drive is approved, then if too must have
detached sidewalks, with parkways and street trees on both sides per the standard.
Response: The previously shown cight in/right out access driye along the north
side of the site has been removed.
16. 05/03/2016: !n general, the bicycle/pedestrian network must be design in such a way as to have an
overall organizing principle that is self-eyident and logical. It must encourage biking and walking
and must, above all, be safe.
Galloway & Company, inc. . 303.7Z0.8884 • 6162 S. �Ilow Drive, Suite 320 • Greenwood vllage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: Two pedestrian walkways have been incorporated through the parking
lot connecting the MAX/BRT station, buildings, and College Avenue. These
walkways provide areas for pedestrians to enter the site and ultimately reach the
MAX/BRT station. Additionally, bicycle parking has been 'incorporated info the
design of the plaza area. The Grand Promenade has been added to the west side
of the site and runs parailel to the MAX/BRT bus line per the Midtown Plan.
17. 05/03/2016: Staff is concemed about the large parking freld between the store and Soufh College
Avenue. Please note the Midtown Plan states:
"Keep parking subordinate to the street characfer along College Avenue and east-west streets.
One goal in the redevelopment of Midtown is to transition away from the large surface parking
areas #hat abut College Avenue and create a more urban environmenf along the corridor. As such,
developers should be encouraged to locate structures along the College Avenue and construct
parking areas behind fhe building, so that they are shielded from the stree%"
Response: The proposed redevelopment of the site has been oriented in such a
way to allow for pedestriaNbicycie, MAXIBRT and vehicular access to the site.
The building has been shifted to the east in order to accommodate the Grand
Promenade area, which has reduced the area allocated for vehicular parking
spaces. Based on feedback from the neighborhood meeting, there is a concern
from the community regarding availability of customer parking due to the large
amount of MAX/BRT parking that occurs at this site. Given this concern, the
previously retail building that was previously shown at the northeast corner of the
site has been removed.
18. 05/03/2016: Staff acknowledges fhat the proposed refail store will contribute fo screening the large
parking lo#. Other measures, however, will be required to mitigate the overall impasf of a Iarge
parking field. Firsf, the parking lots must feature landscape islands at least every 15 spaces.
Second, fhe parking lo# perimeter must be scr�ened with a continuous screen of plant material or
by a solid, decorative screen wall.
Response: Landscape islands are included within the site plan to pravide no
more than 15 parking spaces in a row. Given the maturity of existing landscaping
along College Ave. & Drake Rd., the plan proposes to allow for a large amount of
the existing landscaping to remain, in order to provide screening of the parking
from the streets.
19. 05/03/2016: Another method of breaking down the large parking field is to cover one or two bays
w'�th a carporf-like structure upon which to place solar collecfors; Or, one or two of the bisecting
walkways could be sovered with a solar installation. Since the parking bays and walkways are
arrayed in an east-west orientation, fhe site lends itself perfectly to solar capability.
Galloway & Company, Inc. . 303.770.8884 • 6162 S. �Ilow Drive, Suite 320 . Greenwood �Ilage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: Due to the large amount of vehicles parking within the existing lot for
MAX/BRT use, there is an operational concern that MAX/BRT users would utilize
any parking under a canopy for extended periods, thus further reducing the
vehicular parking available for King Soopers/retail customers. Given the already
reduced amount of parking proposed at #his site, compared to a typical King
Soopers Marketplace site, this concern is even greater.
20. 05/03/2016: Another mefhod of breaking down fhe large parking field is to cover one or fwo bays
with a carport-like structure upon which to place solar collectors. Or, one or two of the bisecfing
walkways could be covered with a solar installation. Since fhe parking bays and walkways are
arrayed in an east-wesf orientation, the site lends itself perfectly to solar capability.
Responsec Repeat comment, please refer to response to #19.
21. 05/03/2016: Please explore other mitigation techniques to break down the large expanse of
asphalf and tireak the monotony of the parking surface. Where there is su�cient land area,
undulafing earthen berms should be employed. Goniferous trees and shrubs must be part of the
mix. Decorative fences; vines, trellises and other elements of landscape design must be
considered.
Response: Landscape islands have also been provided throughout the site to
ensure no more than 15 spaces in a row. Additionally, the landscape treatment
along the pedestrian corridor connecting College Avenue and the transit station
will consist of deciduous shade trees and flowering perennials.
22:. 05/03/2016: As the design of the site progresses, a detail of the plaza at a larger scale may be
needed.
Response; A detail of the plaza has been included with this submittal.
23. 05/03/2016: Bicycie parking must be near both the main entrance and plaza. ldeally, this parking
is covered for partial weather protection. Racks must be anchored in conerete and not interfere
with either landscaping or walkways. As such, the design of the bike parking must be not be
afterthought kut is integrated into the design at fhe beginning of sife planning prosess. As a point
of emphasis, the design and locafion of the bike parking should not be merely assigned to left-over
spaces.
Response: Bicycie parking has been provided in the plaza area along the south
side of the building.
Galloway & Company, inc. 0 303J70.8884 e 6162 S. wllow Drive, Suite 320 o Greenwood Vllage, CO 80111 o www.GallowayUS.mm
Ted Shepard
Kmart Redevelopment
December 15,2016
24. 05/03/2016: As noted, the building's sef back from the public sfreets requires mitigation techniques
to es#ablish a better relafionship to ihe surrounding community. One technique is to provide as
much storefront glazing along the east and soufh elevations as feasible. Please consider the use
of overhead garage-like doors along the southeast and south elevations to fuifher activate fhe
plaza. Blank walls facing fhe streets do not create a pedestrian-scale environmen%
Response: The east elevation features extensive amounts of giazing at each entry
vestibule, which extends above and below the enfry canopies. The east elevation
also features glazing between #he two entry elements and at the southeast corner,
which is the location of the cafe. Mezzanine level glazing also exists at the
southeast corner #o serve associate and office functions. The internal function of
_
the building along the south elevation includes kitchen prep areas and storage
rooms like coolers and freezers. The nafure of these spaces prohibits #he use of
glazing along the entirety of the south elevation, however, the amount of giazing
at the southeast corner has been increased to enhance and further accentuate the
indoor/outdoor caf� seating area. In addition, the south side of the building
features a pedestrian plaza and multiple landscape enhancements, including a
living wall, to create and enhance the pedestrian-scale environment.
25. 05/Q312016: To add emphasis to this need for storefront glazing, please note the Midtown Plan
states:
"Buildings should be urban in nature, w'�th active street edges and a generous amounf of
transparency at the ground level to invite passersby and promote shopper viewing."
Responsec The east elevation features extensive amounts of glazing at the
ground level to invite the shopper and promote viewing. The function of the area
between the two main entries is for seasonal sales and features ground-level
glazing, which draws pedestrians and activity. The southeast corner of the
building features the indoor/outdoor cafe seating, which will also create interest
and activity along the street edge.
26. 05/03/2016: Rega�ding building design, the Midtown Plan states:
"Buildings should use materials that are durabfe and well detailed. Masonry, in the form of stone,
brick, and high quality architectural metals, should be encouraged and defailed to provide a human
scale and convey a sense of permanence."
Response: The proposed design features durable and lasting materials. The
composition consists of integraily-colored, decorative masonry units with multiple
textures (smooth-face, split-face and ground-face) that help reduce large-scale
walis to a pedestrian scale. The masonry units feature integral water repellant and
anti-graffiti coating, which makes them easy to clean and maintain over the life of
the building. The design also features fiber cement siding, aluminum storefront
giazing and metal canopies. The fiber cement siding features an integral wood
Galloway & Company, inc. 0 303.770.8884 0 6162 S. Willow Drive, Suite 320 o Greenwood vllage, CO 80111 e www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
grain texture and factory-applied finish coating, which is "resistant to cracking,
fading and chipping. The product carries a 50-year warranty from the
manufacturer related to material or workmanship failure.
27. 05/03/2016,, Staff encourages fhe use of locally-source stone as a building componenf to help the
building tie into some of the larger buildings at the Natural Resources Research Center and the
CSU Main Campus. Combining stone from the local quarries w'�th Spruce trees (mulfiple culfivars
are available for sommercial settings) creates an effect that is found on the C.S.U. campus and is
found to be very attractive.
Response: Stone and/or stone veneer is not a cornerstone of the design concept
and the Owner/design team feel that adding small portions of stone will detcact
from the design rather than enhance it. Note that the featured decorative masonry
units are manufactured and provided by Basalite, which is a well-known, long-time
supplier of masonry products along the front range and throughout Colorado.
Norway spruce trees have been incorporated into the Plaza area design for
screening. Additionally� planting areas will incorporate botanical signage where
possible for interpretation and connection to the nearby CSU demonstration
garden.
28. 05/03%2016: The operational activities in #he back of fhe sfore (compacfor; recycling, composfing,
trash, palettes, shelving components, loading dock, etc.) must be tofally screened from the MAX by
use of screen walls that are integral to the overall building. This will eontribute to the building
having four-sided architecfure.
Response: Screen walls along the west side of the loading docks at the back of
the building have been included to screen the areas from the west.
Engineering Development Review
1. 05/04/2016: Larimer County Road Impacf Feesand Sfreet Oversizing Fees are due at the time of
building permit. Please contact Matt Baker at 224-6108 if you have any questions.
Response: These fees will be paid at the time of Building Permit.
2. 05104/2016: The City's Transportation Development Review Fee (TDRF) is due at fhe time of
submittal. For additional information on these fees, please see:
http://www: fcgov. com/engineering/dev-revie w. php
Response: The TransporEation Development Review Fee will be paid at the time of
submittal.
Galloway & Company, Inc. 0 303.770.8884 e 6162 S. Wllow Drive, Suite 320 o Greenwood Yllage, CO 80111 o www.GallowayUS.ccm
Ted Shepard
Kmart Redevelopment
December 15,2016
3. 05/04/2016: Any damaged curb, gutter and sidewalk existing prior to construetion, as well as
streets; sidewalks, curbs and gutters, destroyed, damaged or removed due to construstion of this
project, shall be replaced or restored to City of Fort Collins standards at the Developer's expense
prior to the acceptance of completed improvements and/or prior to the issuance of the �rst
Certificate of Occupancy.
Response: The developer will coordinate with the City regarding repairs required.
4. Q5/04/2016: All pubiic sidewalk, driveways and ramps existing or proposed adjacent or within the
site need to meet ADA standards, if they currently do not, they will need to be reconstrucfed so that
fhey do meet curreht ADA standards as a part of this project
Response: The developer will coordinate with the City regarding repairs required.
5. 05/04/2016: Any public improvements must be designed and built in accordance with the Larimer
County Urban Area Sfreet Standards (LCUASS). They are available online af:
httpJ/www.larimer.org/enqineering/GMARdStds/UrbanSt.hCm
Response: Comment noted.
6. 05/04/2016: This project is responsible for dedicating any right-of-way and easements that are
necessary or required by the City for this project. Most easements to be dedicated need to be
public easements dedica#ed to the City. This shall including the standard utility easements fhat are
fo be provided behind the right-of-way (15 foot along a. n arterial, 8 foot along an alley, and 9 foot
along all other street classifications); Information on the dedication process can be found at:
http://www. fcqov. com/enQineerinq/devrev. php
Response: Applicable right-of-way and easements for the site have been shown
on the replat:
7. 05/04f2016: Detached sidewalks will be needed along Easf Drake Road and S. CoOege Avenue in
accordance w'rth the Midtown Plan. Refer to Cross Section 8(6 Lane Arterial with 12' walks) for the
College Avenue frontage and Cross Section F(4 Lane Arterial with 10' waiks) for Drake Road.
Please see the following link for the Mid#own Plan cross sections:
http://www. fcqov. com/mason/pdf/midtown-plan-ap pendix-2.,odf? 1378481152
Responsec A detached meandering sidewalk has been proposed along the College
Avenue property frontage. The existing landscaping along the west side of
Galloway & Company, Inc. • 303.770.8884. 6162 S: �Ilow Drive, Suite 320 o Gree�wood vllage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
College Avenue, to the south of the proposed full motion access is proposed to
remain, given its maturity, and based on coordination with City staff, the sidewalk
meanders appropriately through this area. Based on the City's request for a bus
pull-off along Drake Rd., and further coordination with City staff, an attached
sidewalk is proposed along Drake Road. This allows for the bus pull-off to be
provided, without negatively impacting the heavily used MAX/BRT parking
easement area on the proposed site.8. 05/04/2016: Improvements to accesses,
interseetions, etc. wil! be looked at closer once we receive a tca�c study and determine what
imprbvements are needed. ,
Response: A traffic study has been prepared and included with this submittal for
review.
9. 05/04/2016: Utility plans will be required and a Development Agreement will be recorded once the
project is finalized.
Response: Utility plans have been included with this submittal for review. A
Development Agreement will be coo�dinated between the Cify and King Soopers
as applicable.
10. Q5/04/2016: As of January 1, 2015 all development plans are required to be on the NAVD88
vertical dafum. Please make your consultants aware of fhis, prior to any surveying and/or design
work.
Response: The site will be on the NAVD88 vertical datum.
11. 05/04/2016: This site is adjacenf to CDOT roadway and all access to fhe site is govemed by an
access control plan. The access confro! plan will need to be followed and implemented with any
project. Plans wil! be routed to CDOT for review and approval and fhe applicant may need to
obtain access permifs from CDOT. The proposed new right-in right-out access on College Avenue
will not be allowed.
Response: The previously shown right-in/right-out access along Coliege Ave. has
been removed from the site plan.
12. 05/04/2016: A Development Construction Permit (DCP) will need to be obtained prior fo starting
any work on the sife. �
Galloway & Company, Mc. e 303.770.8884. 6162 5. Willow Drive, Suite 320 • Greenwood Yllage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: The developer will obtain a Development Construction Permit prior to
starting any work on the site.
13. 05704/2016: A utility coordination meeting on this site is suggested. Utility coordinafion meetings if
requested are typically scheduled after the preliminary submittal of the projecf, but can be
scheduled prior to submittal upon requesf. Please provide a site plan with preliminary util.'�ty layout
for routing with the meeting notice. If you are interesfed in having a utility coordinafion meeting,
please contact the development review engineer for scheduling.
Response: The developer and/or their consuitants will schedule a utility
coordination meeting.
14. 05/04/2016: LCUASS parking setbacks (Figure 19-6) apply and will need to be followed depending
on parking design.
Response: LCUASS parking setbacks will be followed where applicable.
15. 05/04/2016: All fences, barriers, posts or other encroachments within the public ►ight-of-way are
only permitted upon approval of an encroachment pemiit. Applications for encroachment permits
shall be made to Engineering Department for review and approval prior to installation.
Encroachment items shall not be shown on the site plan as they may not be approved, need to be
modified or moved, or if the permit is revoked fhen the site/ landscape plan is in non-compliance.
Response: An encroachment permit will be prepared and submitted to the Cifiy if
the finai design warrants the permit.
16. 05/04/2016: Any cain gardens w'�thin the right-of-way cannot be used fo treat the development/ site
storm runoff. We can look at the use of rain gardens to treaf str�et tlows — fhe design standards for
these are stil! in development.
Response: Comment noted. If the site incorporates rain gardens into the design,
which have been discussed and coordinated with City staff during the design
process.
17. 05/04/2016: Bike parking required for the project cannot be placed within the right-of-way and if
placed just behind fhe right-of-way need fo be placed so that when bikes are parked they do not
eztend into the right-of-way.
Response: Bike parking has been included in the plaza area along the south side
of the building.
Galloway & Company, Inc. 0 303,770.8884 e 6162 S. wll.ow Dr.ive, Suite 320 o Greenwood vllage, CO 80111 o www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
18. 05/04/2016: In regards to construction of this site, fhe public right-of-way shall not be used for
sfaging or storage of materials or equipment associated with the Development, nor shall it be used
for parking by any contractors, subcontracfors, or other personnel working for or hired by the
Developer #o construct the Development. The Developer wili need to �nd a location(s) on private
property to accommodate any necessary Staging and/or parking needs associated with the
completion of the Development Information on the location(s) of these areas will be required to be
provided to the City as a part of the Development Construction Permit applicafion.
Response: Comment noted.
Environmentai Planning
1. 04/28/2016: An Ecological Characferization Study is required by Secfion 3.4.1(D)(1) as the site is
within 500 feet of a known natural habitaf (pond to the wesf). However, as there are intervening
parcels, fhe railroad and MAX comdor befween the pond and this property, and fhe standard buffer
would not extend to this project's parcel, the ECS is waived for this site. Please consider the use of
native plants and grasses to complement fhe natural feature, in accordance with Article 3.2.1
(�(2)(3) of fhe Land Use Code.
Response: Comment noted. An Ecological Characterization Study will not be
prepared and submitted.
2. 04/28/2016: With respect to landscaping and design, the City of Fort Collins Land Use Code, in
Article 3.2.1 (E)(3), requires that you use low-water-use plants and grasses in your landscaping or
re-landscaping and reduce bluegrass lawns as much as possible. Native and wildlife-friendly
landscaping is encouraged as well.
Response: The planting design for the site features drought tolerant and native
shrubs and grasses. '
3. 04/28/2016: The applicant should make note of Article 3.2.1(C) that requires developments to
submit a landscape and tree protection plan, and if receiving water service from the Cify, an
irrigafion plan, that: "...(4) protects significant trees, natural systems, and habitat; and (5) enhances
the pedestrian environment" Note that a signifieant tree is defined as a tree having DBH (Diameter
at Breasf Height) of six inches or more. If any of the trees within fhis site ha�e a DBH of greater
than six inches, a review of the trees shall be conducted with Tim Buchanan, Cify Forester
(970-221-6361 or tbuchanan@fcgov.somJ to determine the status of fhe existing trees and any
Galloway & Company, Inc. • 303.770.8884 • 6162 5. Willow DriVe, Suite 320 • Greenwood �Ilage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15;2016
mitigation requirements that couid result from the proposed development.
Response: A meeting at the site with the City Forester to determine the status of
the existing trees on fhe site was completed on August 23, 2016. A tree
preservation plan and a hydcozone plan have been included with this submittal,
4. 04/28/2016: If tree mitigation is necessary, please include the following note on #he tree mitigation
plan and/or landscape plan, as appropriate: °All tree removal shown shall be completed outside of
the songbird nesting season (Feb 1= July 31) or a sunrey will be conducted of the trees to be
removed to ensure tliat no aetive nests are present." �
Response: This note has been included on the tree pceservation plan.
5. 04/28/2016: In regard to LED light fixtures, IDA (Intemational Dark-3ky Associafion) recommends
using lighting fhat has a color temperafure of no more than 3000 degrees Kelvin in order fo limit the
amount of 61ue light in the night environment, as blue light brightens the night sky more than any
other color of light. Both LED and metal halide fixfures contain large amounfs of blue light in their
spectrum, and exposure to blue light at night has been shown to harm human healfh and endanger
wildlife. Please eonsider a warmer color temperature (warm white, 3000K or less) for your LED
light fixtures. Please also consider ��ures with dimming capabilities so that light levels can be
adjusted as needed.
Response: The City's lighting recommendations listed above will be taken into
consideration as part of the overall lighting design for the site.
6. 04/28/2016: Our city has an established ideniity as a forward-thinking community that cares about
the quality of life if offers its citizens and has many sustainability programs and goals that may
beneft your project Of particular interest may be fhe:
1: Climate�se program; fcgov.com/climafewise/
2. Zero Wasfe Plan and the Waste Reduction and Recycling Assistance Program (WRAP):
fcgov.com/recycling/pdf/ 20120404_WRAP ProgramOvenriew.pdf, contacf Caroline Mitchell af
970-221-6288 or cmtichell@fcgov.com
3: Green Building Program: fcgov.com/enviro/green-building.php, contacf Tony Raeker at
970-416-4238 or traeker@fcgov. com
4. Solar Energy.• www.fcgov.com/solar, confact Norm Weaver at 970-416-2312
or nweavera)fcgov.com
5. Integrated Design Assisfance Program: fcgov.com/idap, con#act Gary
Schroeder at 970-224-6003 or gschroeder@fcgov.com
6. Nature in the City Strategic Plan: fcgov.com/planning/nafureinthecify/?
Galloway & Company, Inc. e 303.770.8884 e 6162 5. Willow Drive, Suite 320 • Greenwood vllage, CO 80111 e www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
key=advanceplanning/natureinthecity/, contast Jusffi Scharton at 970-221-6213
or jscharton@fcgov.com
In addition, fhe City of Fort Collins is a leader in climate action and resilience planning, and this
redevelopment site offers a unique opportunity to showcase the City's Climate Aetion Plan
priorities. Staff strongly recommends that the applicant considers incorporafing the following
enhancements and additions:
- Inclusion of residential or other non-retail uses on the site to adtl density and create a mix of uses
(e:g;, office or r�sidential above the grocery stor�)
- Reuse/recycling of materials from the existing building(s) in the demolition and construction
processes
- Above-code energy management and e�ciency strategies
- Rooftop solar production and use
- On-site recycling and composfing facilities
Please consider the City's sustainabil'►ty goals and ways for your development to engage w'�th these
effods, and let me know if 1 can help connecf you to these programs or provide add'�fional
resources.
Response: The Developer has many sustainable programs in place for fheir
stores, and will look into the City programs where applicable.
7. 05/03/2016: Environmental Services Department (ESD) staff is happy to learn that King Soopers is
going to source-separate organic materials (i.e., trimmings from the produce section, expired
bakery items, etc.) from fhe rest of the waste stream at the new groeery store (formerly the K-Mart),
#o be used to make compost at a commercially operated, state permitted facii�ty. Since King
Soopers is a corporation that has already begun using this "Zero Wasten approach at some of its
other groceries in Fort Collins, we are confident they know abouf "good housekeeping" and design
considerations for composfing, which the City will expect them to apply, including:
-Ensure su�icient space is dedicated within trash enclosure structures to accommodate the
appropriately sized carts and/or Dumpsters to contain the amount of organic debris that will be
generated
-Contract with a reputable service provider that will collect the organics in a freguent and timely
manner to prevenf nuisance cond'►fions from occumng
-Post guidelines/signage and frain employees in how fo be successful at source-separafing
organics from trash, so that the quality of fhe compost is not contaminated w'�th non-accepted
materials that compromises that quality of the compost '
The City of Fort Collins' goals for Zero Waste (see httpJ/www.fegov.com/zerowasfe/) and Climate
Action Plan are very specifc about reducing the amount of wasted food in fhe community that gets
Gailoway & Company, Inc. • 303.770.8884. 6162 5. Willow Drive, Suite 320 . Greenwood �Ilage, GO 80111 . www.GallowayUS.co.m
Ted Shepard
Kmart Redevelopment
December 15',2016
landfilled - thereby causing damaging greenhouse gas emissions. ESD sfaff would like to follow=up
with representatives for fhe King Soopers project about how the new store can play a role in
supporting Fort Gollins' vision. At the earliest convenience of the developer; staff would be
pleased to schedule a meeting to exchange information and ideas (contact Susie Gordon, Sr.
Environmental Planner, at 970,221.6265 or sgordon@fcgov.com ).
Response: The Developer will contact the ESD staff in the future to discuss the
City's vision.
Internal Services
04/29/2016: Please schedule a pre-submittal meeting for this project. Pre-Submittal meetings
assist the designer/builder by assuring, early on in the design, thaf the new projects are on track to
complying with all of fhe adopted City codes and Standards listed below. The proposed project
should be in the early to mid-design stage for this meeting to be effective. Applicants of new
projects should email scarter@fcgov,com to schedule a pre-submittal meeting. Applicanis should
be prepared to present site plans; floor plans; and elevafions and be able to discuss code issues of
occupancy, square footage and type of construction being proposed.
Response: Comment noted. Light and Power
1. 05/03/2016: Light and Power has electric facilities existing along the rear of`the property, adjacenf
Co the MAX bus line that could be utilized to provide power. Electric facilities also exist along the
north side of W Drake Rd that could be used to provide power.
Response: Comment noted. The design team will look into connecting to these
electric facilities. •
2. 05/03/2016: Electric capacity fees, development fees, building site charges and any system
modi�cation charges necessary to feed the site will apply to this development. Please visit the
following website for an estimate of charges and fees:
http://www. fcgov.com/utilities/business7builder5-and-developers/plant-investment-development-fee
Response: Comment noted.
3. 05/03/2016: Transformer locafions and electric meter locations will need to be coordinated w'�th
Light & Power. Transformers must be placed within 1.Oft of a drivable surface for installation and
maintenance purposes. The transformer must also have a front clearance of 10ft and side/rear
clearance of 3ft minimum.
Galloway & Company, Inc. • 303.770.8884 • 6162 5. Willow Drive, Suite 320 • Greenwood Yllage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: The design team will coordinate with Light and Power to determine the
best locations for proposed electric facilities.
4. 05/03/2016: A commercial service information form (C-1 form) and a one line diagram for each
commercial meter will need to be completed and submitted to Light & Power Engineering. A link to
the C-1 form is below:
http://www. fcgov: com/utilities/business/builders-and-developers/development-forms-guidelines-regulations
Response: Comment noted. A C-1 form, and one line diagram will be submitted to
Light and Power Engineering.
_
5. 05/03/2016: Please document the size of the electrical service that feeds fhe building prior to
demo.
Response: The design team will work with the owner regarding the existing
electric service size prior to demolition.
6. 05/03/2016; Light & Power will need AutoCAD files of the approved site plan; ufility plans, and
landscape drawings before design of the elect�ic facilifies will begin:
Response: All required AutoCAD files for the site will be provided to Light and
Powe"r for design coordination:
7. 05/03/2016: Please contact Tyler Siegmund at light & Power Engineering if you have any
quesfions at 970.416.2772. Please reference our policies, construction practices, development
charge prosesses, and use our fee esfimator at
http://www, fspov. com/utilities/business/builders-and-de velopers
Response: Comment noted.
Poudre Fire Authority
1. 04/28/2016: WATER SUPPLYA hydrant is required w'�thin 300' of any commercial building. The
existing hydrants locafed on the property should be suffcient for all buildings; however it is fhe
applicant's responsibility to verify hydrant function, pressure and volume. Code language provided
below.
Galloway & Company, inc. . 303.770.8884 • 6162 5. Willow Drive, Suite 320 • Greenwood Yllage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Ftedevelopment
December 15,2016
> IFC 508.1 and Appendix 8: COMMERCIAL REQUIREMENTS: Hydrants fo provide 1,500 gpm at
20 psi residual pressure, spaced not further than 300 feet to the building, on 600-foot centers
thereafter
PHYSICAL PROT€GTION
IFC 508.5.6: Where fire hydrants are subject to impact by a motor vehicle, guard post or other
approved means shall comply w'�th section 312
Response: Fire hydrant locations will be verified through the design process.
2. 04%28%2016: FIRE CONTAINMENT
The proposed 7;200 sq ft retail building af the SE comer of the property exceeds 5040 square feet
and shall be sprinklered or fire con#ained. If containmenf is used, the containment construction
shall be reviewed and approved by the Poudre Fire Au#hor'�ty prior to installation.
Response: Comment noted.
3: 04/28f2016: FIRE LANES
Fire access is required fo w'►thin 150' of all portions of the building perimeter and dedicated as an
Emergency Access Easement. If an EAE does nof exist from the previous developmenf; one will be
required at this fime. Code language and fire lane specifications provided below,
> IFC 503.1.1: Approved fire Lanes shall be provided for every facility, buifding or porfion of a
building hereafter constructed or moved into or within the jurisdiction. The fire apparatus aceess
road shall comply with the requirements of this section and shall extend to w'�thin 950 feet of all
portions of the facility and all portions of the exterior walls of the first story of the building as
measured by an approved route around the exterior of the building or facility. When any porfion of
the facility or any portion of an exterior wall of the �rsf sfory of the building is located more than 150
feet from fire apparaCus access; the fire code o�cial is authorized fo increase the dimension if fhe
building is equipped throughout with an approved, automatic frre-sprinkler system.
FIRE LANE SPECIFICATIONS
Fire lane plan shall be submitted for approvai prior to installation. In addition to fhe design criteria
already contained in relevant standards and policies, any new fire lane must meet the following
general requirements:
> Shall be designated on fhe plat as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed widtb & 14 foof minimum overhead
clearance.
> Be designed as a flat, hard, a1l-weather driving surface capable of supporting 40 tons.
> Dead-end fire access roads in excess of 150 feet in lengfh shall be provided wifh an approved
area for tuming around fre apparaCus.
> The required turning radii of a fire apparatus acsess road shall be a minimum of 25 feet inside
Galloway & Company, Inc. e 303.770.8884 e 6162 S. Willow Drive, Suite 320 e Greenwood �Ilage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
and 50 feet outside. Tuming radii shall be detailed on submitted plans.
> Be visible by painfing and/or signage, and maintained unobstructed at all times.
> Addifional access requirements exist for buildings greater than 30' in height. Refer fo Appendix D
of the 20121FG or contact PFA for details. lntemafionai Fire Code 503.2.3, 503.2.4, 503.2.5, 503.3,
503.4 and Appendix D; FCLUC 3.:6.2(8) 2006 and Local Amendments:
Response: Adequate fire lanes have been included as part of the proposed. site
plan.
4: 04/28/2016: FIRE LANE MARKING
> IFC503.3: Where required by the fire code official, approved signs or other approved notises that
include the words NO PARKING - FIRE LANE shall be proVided for fire apparatus access roads to
identify such roads or prohibit fhe obstruction thereof. The means by which fre lanes are
designaied shall be mainfained in a clean and legible condition at ail fimes ad be replaced or
repaired when necessary to provide adequate visibility.
> IFC D103.6 - SIGNS: Where required by fhe fire code o�cial, fire apparatus access roads shall
be marked with permanenf NO PARKING - FIRE LANE signs complying w"�th Figure D103.6. Signs
shaN have a minimum dimension of 12 inches wide by 18 inches high and have red lefters on a
white reflective background. Signs shall be posted on one or both sides of the fire apparatus road
as required by Section D103.6:1 or D103.6.2.
Response: Fire lane markings and signs will.be included as part of the proposed
site plan.
5. 05/05f2016: AUTOMATIG FIRE SPRINKLER SYSTEM
_ _ _ . -_
This building will require a NFPA13 automatic fire sprinkler system under a separate permit. Please
contact Assisfant Fire Marshal, Joe Jaramillo with any fire sprinkler relafed questions at
970-416-2868.
Response: Comment noted.
6. 05/05/2016: FDC - IFC 912:2: Fire Department Connections shall be instalied in accordance with
NFPA standards. Fire department connections shall be located on the street side of buildings, fully
visible and recognizable from fhe street or nearest point of fire department �ehicle access. The
location of the FDC shall be approved by the fire department.
Response: Comment noted.
7. 05/05/2016: PUBLIC-SAFETY RADIO AMPLIFICATION SYSTEM TEST
_
An emergency radio ampl'�cation evaluation is required for the King Soopers building after the
core/shell is constructed but prior to �nal build out. For the purposes of this secfion, fire walls shall
Galloway & Company, Ine. . 303.770.8884• 6162 S. Willow Drive, Suite 320 . Greenwood Vilage, CO 80111 . www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
not be used to define separate buildings. Where adequate radio coverage cannot be established
within a building, public-safety radio amplification systems shall be designed and installed in
accordance with criteria established by fhe Poudre Fire Authority. Poudre Fi're Autho�ty Bureau
Admin Policy#07-01
Response: Comment noted.
Stormwater Engineering
1. 05/04/2016: The design of this site must conform to fhe drainage basin design of the Spring Creek
Master Drainage Plan as well the Fort Collins Sformwafer Criteria Manual.
Response: Comment noted.
2. 05/04/2016: If a new building is being constructed in the Iocation of the existing Kmart or in a
different location on fhe sife, or if there are modifications to the parking lot, a drainage report and
construction plans are required and they must be prepared by a Professional Engineer regisfered
in the State of Colorado. The drainage report must address fhe four-step process for selecting
strucfural BMPs. There is a final site inspection required when the project is complete and the
maintenance is handed over to an HOA or another mai'ntenance organizafion.
Response: Comment noted. A drainage report for the site has been prepared and
is included with this submittai.
_ _
3. 05/04/2016: There are several priyate sform lines within fhe limits of this parcel: There was some
field investigation done on these storm lines a few years ago thaf indicated that the pipes were in
poor condition and don't function properly. Redevelopmenf of fhis site will require that new storm
infras#ructure be installed to provide adequate stormwafer drainage.
Response: Video Inspection of lines has been pert'ormed to determine the extent
of replacement/maintenance required. Maintenance will be completed by the
applicant as needed.
4. 05/04/2016: If the site is required to meet present Land Use Code requirements, onsite water
quality treatment of fhe runoff is required. Water quality treatment methods are described in the
Fort Collins Stormwater Manual, Volume 3-Besf Management Practices (BMPs). A method that
could be used on an existing site is to direct the downspoufs to a landscape area. Another is if
perimeter landscape buffers or parking lot medians are required, they could be used to treat the
runoff in bio-retenfion areas or rain gardens.
(http://www. fcgov. com/utilities/business/builders-and-developers/development-forms-guidelines-reg
Galloway & Company, inc. e 303.770.8884 • 6162 S. Wiliow Drive, Suite 320 • Greenwood Yllage, CO 80111 e www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
ulations/stormwater-criterial
Response: The design team has been coordinating with City staff to determine
and design the best method for water quality on the site. Piease refer to the
drainage study included with this submittal.
5. 05/04/2016: Low Impact Development (LID) requirements are required on all new or redeveloping
property which includes sites required to be brought info compliance with the Land Use Code..
These require a higher degree of water quality treatment wifh one of the two following options:
a. 50% of the newly added or modified impervious area must be freated by LID teehniques and
25% of new paved areas musf be pervious.
b. 75% of all newly added or modified impervious area must be treated by LID techniques.
Response: Comment noted. The site has been designed to conform to the LID
requirements for redeveloped areas within the property. Please refer to the
drainage study included with this submittal.
05/04f2016; Standard operating procedures (SOPs) for all onsite drainage facilifies will be
included as part of the Deve/opment Agreement: More information and links can be found at:
http://www. fcqov, com/utilities/what-we-do/stormwater/stormwater-pualityAow-impact-de velopment
Response: Comment Noted.
�
7. 05/04/2016: Per Colorado Revised Statute §37-92-602 (8) effective August 5; 2015, criteria
regarding detention drain time will apply to this project. As parf of the drainage design, the
engineer will be required to show compliance w'�th this stafute using a standard spreadsheet
(availab/e on request) that will need to be included in the drainage report. Upon completion of the
project, fhe engineer will also be required fo upload the approved spreadsheet onto the Statewide
Gompliance Portal. This will apply to any volume based stormwater storage, including extended
detention basins.
Response: Per discussion with the City Staff, this is not needed since there is no
on-site detention.
8. 05/04/2016: The 2016 city wide Stormwater development fee (PIF) is $8,217/acre for new
impervious area over 350 sq.-ft., and there is a$1,045.00/acre review fee. No fee is charged for
existing impervious area. These fees are to be paid at the time each building permit is issued.
Information on fees can be found at:
Galloway & Company, inc. . 303J70.8884 0 6162 S: Willow Driqe, Suite 3.20 . Greenwood vllage, CO 80111 • www.GallowayUS:com
Ted Shepard
Kmart Redevelopment
December 15,2016
http://www. fcgov. com/utilities/business/builders-and-developers/plant-investment-development-fee
s or contact Jean Pakech at 221-6375 for questions on fees. There is also an erosion coritrol
escrow required before the Developmenf Consfruction permit is issued. The amount of the escrow
is determined by the design engineer, and is based on fhe site disturbance area, cost of the
measures, or a minimum a►nount in accordance with the Forf Collins Stormwater Manual.
Response: Comment noted.
Technical Services
1. 05/02/2016: As of January 1, 2045 all development plans are required to be on the NAVD88
yertical datum; Plea. se make your consultants aware of this, prior to any surveying and/or design
work.
Response: Comment noted,
Traffic Operation
1. 05703/2016: The anticipafed traffic volume from this development meets the threshold for needing
a full Tra�c Impact Study. Please have your tra�c engineer contact me to scope the sfudy. Note
that the intersection of Drake/College is congested, and will need� careful review to determine
whether it meets standards with the new development.
Response: The traffic engineer has coordinated with City transportation staff
regarding this project. A traffic study has been completed and included with this
submittal.
2> 05/03/2016: US287 (College Avenue) is under the jurisdiction of fhe Colorado Department of
Transportafion (CDO�. They will be heavily involved with the review of the project, and will need
#o approve change in use or new access permits.
Response: Comment noted. The design team will coordinate with CDOT as
required.
3. 05/03/2016: The new access onto College without removing any existing accesses onto College is
not likely to be supported by the City or CDOT.
Response: The right-in/right-out previously shown on the site pian at the PDR
meeting has been removed from the plan.
Galloway & Company, Inc. . 303.770,8884 • 6162 5. VVillow Drive, Suite 320 • Greenwood Vllage, CCO 80111 • www.GallowayUS,com
Ted Shepard
Kmart Redevelopment
December 15,2016 '
4. 05/03/2016: The movement types for the accesses will need to be addressed in the su6mittal, and
it may be that full movement accesses sannot be maintained.
Response: Comment noted. A traffic study has been completed and included with
this submittal. �
5. Q5/03/2016: Adjacent street frontage improve►nents will need to be addressed. Standards would
include a detached walk along Drake, and the Midtown in Motion adopted plan shows a 10 ft trail
along College.
Response: The design team has been coordlnating with City staff regarding the
proposed sfreet frontage improvements as shown as a part of this submittal.
6; 05703/2016: Please see fhe Midtown Plan concept for the frontage along Mason and any
requirements for that area.
Response: The MidTown Plan has been reviewed during the design process for
this submittal.
T�ansportation Planning
1. 05703/2016: Transforf is very interesfed in partnering with you to help create a great station area
for the Drake Station and Park-n-Ride adjacent to your site. Please contact me with questions..
Response: A bus pull-off along the Drake Rd. frontage has been provided, and
will be coordinated with Tcansfort.
_
2. Q5/03/2016: The TOD requires a plaza, loeating fhat near fhe Drake station would be preferred..
Response: A plaza area has been located on the south side of the proposed King
Soopers building with pedestrian access provided from Drake.
3. 05/03/2016: The Midtown in Motion and Midtown Urban Design Plan identified a pedestrian
pathway that should run adjacent to the MAX guideway. Please see these plans for how to
comply.
Galloway & Company, Inc. • 303.770.8884 • 6162 5. Willow Drive, Suite 320 o Greenwood Vllage, CO 80111 • www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
December 15,2016
Response: The building has been shifted east to accommodate the Grand
Promenade which wiil run parallel to the MAX/BRT bus line on the western edge of
the site per the MidTown Pian.
4. 05/03f2016: A Type 3 bus stop is on Drake adjacent to your site. This bus stop will need to be
upgraded to meet current Bus Stop Design Standards. Please contacf ine with questions.
Response: A bus pullout and pad have been provided and are shown on this
submittal.
Water-Wastewater Engineering
_ _
05/04/2016: There is an existing 8-inch waterline through the parking Iof in front of Kmart. There
are two hydCants off of this line.
Response: Comment Noted.
2. 05/04/2096: There is an existing 8-ineh waterline west of fhe Kmart building.
a. This 8-fich line will need to be connected to another existing 8-inch Iine running in the east-west
direcfion, south of the McDonalds to complete a loop and provide adequate flow and water quality.
b. The existing water services and fire services to the Kmart building connect to this westerly line.
The existing water services are a 3-inch senrice and a 1-inch. The existing fire services are 6-inch
and 8-inch.
c. The 3-inch water service and meter for Kmart is old and wiU need to be upgraded to a service
and meter that meets current standards. This may also be true for fhe 1-inch service: The fire
services into the Kmart building will also need to be upgCaded to meet current sfanda. rds.
d. The hydrant on the west side of Kmart wouid need to be replaced with a new hydran# locafed in
an area where it can be operated. Currently, fhe hydrant sits too close to the building to operate at
all.
e. It appears as though none of the water infrastructure on fhe west side of Kmart is in an
easement, so a utility easement will need fo be dedicated with this redevelopment.
Response: Comments noted. The design team will look into the proposed water
system improvements for the site and make improvements where required, to
serve the proposed development. Easements for the utilities wili be granted on
the Final Plat for the site.
3. 05/04f2016: There is an existing 8-inch sewer main along the wesf side of #he Kmart building fhaf
proVides sewer service fo the building. Records indicafe fhat fhere are a few low spots in the sewer
Galloway & Company, Inc. � 303.770.88840 6162 5. wllow Drive, Suite 320 o Greenwood vllage, CO 80111 e www.GallowayUS.com
TecJ Shepard
Kmart Redevelopment
December 15,2016
line and rehabilitation of this line may be warranted w'�th the redevelopment.
Response: Video Inspec#ion of lines has been performed to determine the extent
of replacement/maintenance required. The developer will work to idenfify the
location of sanita.ry lines which need to be replaced and/or require maintenance.
_ _ _ _
4. 05/04/2016: The water conservation standards for landscape and irrigafion will apply. Information
on these requirements can be found at: http://wcww.fcgov.com/standar.ds
Response: Comment noted.
5. 05/04/2016: Development fees and water righfs will be due at building permit.
Response: Comment noted.
Zoning
1, ADA spaces with at least 1 van-accessibie space wili be reguired for 7200 sq ft Proposed Retail
area and existing Larkbucger Building.
Response: Comment noted. Accessible parking spaces have been added at the
requested locations.
2. LUC 3.5.3(2) Orientation to Build-to Lines for Sfreet front Buildings. Build=to lines based on a
consistent relationship of buildings to the street sidewalk shall be esfablished by for new buildings
in order to form a visually conti'nuous, pedesfrian-oriented street fronts with no vehicular use area
between buifding faces and the street Exceptions, however, are pe►mitted. .
(d) Exceptions to the build-to line standards shall be permitted:
3. In the case of Large Retail Establishments, Supermarkets or other anchor-tenant buildings thaf
face intemal eonnecting walkways w'rfh pedestrian frontage in a development that includes
additional outlying buildings abutting the street(s).
Response: The front of the building faces a wide pedestrian entrance and
walkway, and the site provides a system of internal connecting walkways that
allow pedestrian/bicyclists; MAX/BRT, and vehicular access to the site in a way to
utilize the existing access points. Landscape islands within the parking lot have
been included, and two pedestrian corridors are included to bring pedestrians into
the site from College Avenue. The pedestrian corridors provide cross connection
to adjacent development fhrough the. site, and also allow access between College
Avenue and the MAX/BRT station.
Galloway & Company, Inc. 0 3Q3.770.8884 e b162 S. Willow Drive, Suite 320 • Greenwood Yllage, CO 80111 + www.GallowayUS.com
Ted Shepard
Kmart Redevelopment
Deeember 15,2016
3. LUC 3:10.3 (A) - Buiiding Orientation. Primary commercial and residential building entrances shaU
face streets, connecting walkways, plazas, parks or similar outdoor spaces, but not parking lots.
Buildings shall face all street frontages to the maximum extent feasible, with highest priority given
to east-west streets that lead from transitstations to destinations:
(B) - Central Feature or Gathering Place. At least one (1) prominent or central bcation within each
transit stafion area shall include a convenient outdoor open space or plaza with amenifies such as
benches; monuments, kiosks or public arf. This feature and its amenities shall be placed adjacent
to a transit station, to the extent reasonably feasible:
(C) - Outdoor Spaces. To the extent reasonably feasible, buildings and extensions of buildings
shall be designed fo form outdoor spaces such as sourtyards; plazas, arcades, terraces, balconies
and decks for residents' and workers' use and interacfion, and to integrate the development wifh
fhe adjacent physical context. To the extent reasonably feasible, a confinuous walkway system
linking such ouidoor spaces shall be developed, and shall include coordinated linkages between
separate developments:
Response: The front of the building faces a wide pedestrian entrance and
walkway, and the site provides a system of in#ernal connection walkways that
allow pedestrian/bicyclists, MAX/BRT, and vehicular access to the site in a way to
utilize the existing access points. Two pedestrian corridors are included to bring
pedest�ians into fhe site from College Avenue. The pedestrian corridors provide
cross connection to adjacent development through the site, and also allow access
between Coliege Ayenue and the MAX/BRT station. A large plaza area and
covered seating have been proposed on the south side of the King Soopers
building.
4. Parking lot interior landscaping required as part of LUC 32.1(E)(5)
Response: Interior parking lot landscaping islands have been incorporated ihto
the site plan.
5. LUC 3.10.4) Off=street parking shall be located behind, above, within or below sfreet-facing
buildings to fhe maximum extent feasible. No parking will be allowed between the street and fhe
front or side of a building.
Response: The building has been oriented to allow pedestrian/bicyclists,
MAX/BRT, and vehicular access to the site in a way to utilize the existing access
points. The prohibition of parking lots between the street and the front or side of
the building does not apply and, instead, the parking lot location regulation found
in the Large Retail Establishment, Sec. 3.5.4(D)(3)(b), is applicable. While this
secfion does not allow more than 50% of the off-street parking to be located
between the front of the building and the street, it also specifically exempts
Supermarkets from the requirement, meaning that there is no restriction on the
amount of parking that can be located between the Supermarket and the street.
Galloway & Company, Inc. . 303.770.8884. 6162 S, Willow Drive, Suite 320 • Greenwood vllage, CO 80111 • www,GallowayUS.com
.�
Ted Shepard
Kmart Redevelopment
December 15;2016
Note, however, that we have incorporated numerous layout and design elements
to mitigate the impact of the parking fields.
6. LUC 3.2.2(L)(1) Standard Spaces. Parking spaces for sfandard vehicles shall conform with the
dimensions shown on Table A and 8.
Response: Comment noted.
LUC 3.2.2(C)(4)(b) Bicycle Parking Space Requirements. The minimum bicycle parking
requirements are set forth in the table below. For uses fhaf are not specifically listed in fhe table,
the number of bicycle parking spaces required shall be the number required for the most similar
use listed. Grocery Store, Supermarket: Bicycle Parking Space Minimums- 1/3,000 sq. ft.,
minimum of 4Percent of Enclosed Bicycle Parking-20% Percent of Fixed Bicycle Racks-80%
Response: Comment noted. Bicycle parking has been provided.
8. Please include are your plans the meshanical equipment and how it is to be sereened.
Add�tionally, trash and recycling enclosures are required. These should be locafed on a concrete
pad and at least 20ft from a public sidewalk
Response: A trash compactor is provided within the truck loading dock area on
the west side of the building, and provides direct connection to the
building. Screening along the west side of the loading docks has been
provided. Locations of rooftop mechanical equipment is conceptual at this time,
but the intent is to screen rooftop equipment using building wails or individual
rooftop screens when viewed from ground level at the property line.
9. LUC 3.2.2(E)(4) Landscaped Islands. To the maximum extent feasible, landseaped islands with
raised curbs shall be used to define parking fot entrances, fhe ends of all parking aisles and the
location and pattern of primary intemal access drives, and to provide pedestrian refuge areas and
walkways.
Response: Landscape islands have been included within the parking lot area. It
is the developer's request for islands not to be placed in front of the building for
safety operational purposes as discussed in the PDR meeting.
10. LUC 3.2.4 (C) Lighting plan is required; this should include a photometric site plan with catalog
cuf-sheets offhe fixfures.
Response: A lighting plan has been included with this submittal.
Galloway & Company, Inc. . 303J70.8884. 6162 S. Willow Drive, Suite 320 • Greenwood Yllage, CO 80111 r www.GallowayUS.com
R
�'=`,
Ted Shepard
Kmart Redevelopment
December 15,2016
Sincerely,
Galloway & Company, Inc.
Galloway & Company, inc. e 303.770.8884. 6162 S. Willow Drive, Suite 320 . Greenwood vllage, CO 80111 . www.GallowayUS.com