HomeMy WebLinkAbout209 CHERRY STREET - MIXED USE - PDP230006 - SUBMITTAL DOCUMENTS - ROUND 2 - DRAINAGE REPORT
PRELIMINARY
DRAINAGE AND EROSION CONTROL REPORT
LOT 1 PENNY FLATS SUBDIVISION,
SECOND REPLAT
Prepared for:
Tribe Development Company, LLC
244 N. College Ave., Suite 130
Fort Collins, CO 80524
Prepared by:
Wilson & Company
4065 St Cloud Drive, Suite 201
Loveland, Colorado 80538
970-834-6364
July 19, 2023
Job Number 22-100-356-00
4065 St. Cloud, Suite.201
Loveland, CO 80538
970-834-6364 phone
July 19, 2023
Mr. Wes Lamarque
City of Fort Collins Stormwater Engineering
700 Wood Street
Fort Collins, CO 80522
RE: Preliminary Drainage and Erosion Control Report for Lot 1 Penny Flats Subdivision,
Second Replat
Dear Wes,
I am pleased to submit for your review and approval, this Preliminary Drainage and Erosion
Control Report for Lot 1 Penny Flats Subdivision, Second Replat development. I certify that this
report for the drainage design was prepared in accordance with the criteria in the Fort Collins
Stormwater Criteria Manual.
We are requesting two variances in this report. It is our understanding that the formal variance
form will be provided to us by the City later in the review process.
City of Fort Collins review comments dated April 4, 2023 have been addressed in this report.
I appreciate your time and consideration in reviewing this submittal. Please call if you have any
questions.
Sincerely,
Erika Schneider Michael Oberlander, P.E.
Colorado Professional Engineer
No. 41777
Colorado Professional Engineer
No. 34288
4065 St. Cloud, Suite.201
Loveland, CO 80538
970-834-6364 phone
ENGINEER’S CERTIFICATION
“I hereby attest that this report for the final drainage design for the Lot 1 Penny Flats Subdivision,
Second Replat development was prepared by me or under my direct supervision, in accordance
with the provisions of the Fort Collins Stormwater Criteria Manual. I understand that the City of
Fort Collins does not and will not assume liability for drainage facilities designed by others.”
____________________________________________ _______________________
Registered Professional Engineer Date
Michael Oberlander, PE
Registered Professional Engineer
State of Colorado No. 34288
For and on behalf of Wilson & Company
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page i
Table of Contents
1. GENERAL LOCATION AND DESCRIPTION ................................................................. 1
1.1 Location ........................................................................................................................... 1
1.2 Description of Property and Project............................................................................. 1
1.3 Floodplain Submittal Requirements ............................................................................ 1
2. DRAINAGE BASINS AND SUB-BASINS .......................................................................... 2
2.1 Major Basin Description ................................................................................................ 2
2.2 Sub-basin Description .................................................................................................... 2
3. DRAINAGE DESIGN CRITERIA ....................................................................................... 2
3.1 Regulations ...................................................................................................................... 2
3.2 Directly Connected Impervious Area (DCIA) Discussion .......................................... 2
3.3 Development Criteria Reference and Constraints ...................................................... 3
3.4 Hydrological Criteria ..................................................................................................... 4
3.5 Hydraulic Criteria .......................................................................................................... 6
3.6 Low Impact Development (LID) Conformance .......................................................... 6
3.7 Water Quality (WQ) Treatment Criteria .................................................................... 7
3.8 Detention Requirements ................................................................................................ 7
3.9 Floodplain Regulations Compliance ............................................................................. 7
3.10 Modifications of Criteria ............................................................................................... 8
4. DRAINAGE FACILITY DESIGN ....................................................................................... 8
4.1 General Concept ............................................................................................................. 8
4.2 Specific Details ................................................................................................................ 9
4.3 LID, WQ and Detention .............................................................................................. 10
5. SEDIMENT AND EROSION CONTROL ........................................................................ 11
6. CONCLUSIONS .................................................................................................................. 12
6.1 Compliance with Standards ........................................................................................ 12
6.2 Drainage Concept ......................................................................................................... 12
7. REFERENCES ..................................................................................................................... 12
APPENDIX A VICINITY MAP AND DRAINAGE PLAN....................................................... A
APPENDIX B HYDROLOGIC COMPUTATIONS ................................................................... B
APPENDIX C HYDRAULIC CALCULATIONS (TO BE COMPLETED AT FINAL)............ C
APPENDIX D LID CALCS AND COMMUNICATION RE ON-SITE DETENTION ............. D
APPENDIX E SOILS AND FLOODPLAIN INFORMATION .................................................. E
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 1
1. GENERAL LOCATION AND DESCRIPTION
1.1 Location
Lot 1 Penny Flats Subdivision, Second Replat is in the Northeast ¼ of Section 11,
Township 7 North, Range 69 West of the 6th Principal Meridian, City of Fort Collins,
County of Larimer, State of Colorado. It is in Old Town Fort Collins and is bounded on
the north by Cherry Street, on the east by North Mason Street, on the south by Lots 1A and
1B of Penny Flats Subdivision and on the west by City of Fort Collins owned property
(Municipal Railway Carbarn). Please refer to the Vicinity Map located in Appendix A.
1.2 Description of Property and Project
The lot is 0.87 acres and is currently vacant with no hardscape improvements.
The project proposes to develop a multifamily project including 1 story of underground
parking and wet and dry utilities. The project will also include extending the enhanced
pedestrian alley between Mason Street and Howes Street. The Zone District of the project
site is the Downtown District.
Offsite flow does not contribute to the site from any direction.
According to Natural Resources Conservation Service Web Soil Survey, the soils onsite
consist of Paoli fine sandy loam, 0 to 1 percent slopes, Soil Group A. Please refer to
Appendix E for the Hydrologic Soil Group – Larimer County Area map that includes this
site.
1.3 Floodplain Submittal Requirements
The area is designated as Zone X, Area of Minimal Flood Hazard, on FIRM Panel
08069C0979H, dated 5/02/2012 and is therefore not within any FEMA mapped floodplain.
The site does not have any adjacent City of Fort Collins local floodplains. A Floodplain
Submittal is not required and has not been included with this report. Please refer to
Appendix E for the National Flood Hazard Layer FIRMette.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 2
2. DRAINAGE BASINS AND SUB-BASINS
2.1 Major Basin Description
Lot 1 Penny Flats Subdivision, Second Replat is part of the Old Town Basin Master
Drainage Plan. The basin is in north-central Fort Collins and is urbanized. All the water
from the basin drains to the Poudre River located north of the site.
2.2 Sub-basin Description
The property is in the north central part of the Old Town Basin and drains to the storm
system in Mason and Cherry. This system releases flow to the Howes Street Outfall Box
Culvert and then the Cache la Poudre River.
3. DRAINAGE DESIGN CRITERIA
3.1 Regulations
This report was prepared to meet or exceed the “Fort Collins Stormwater Criteria Manual”
(FCSCM) specifications. Where applicable, the criteria established in the Mile High Flood
District’s (MHFD) “Urban Storm Drainage Criteria Manual” (USDCM), developed by the
Denver Regional Council of Governments, has been used.
3.2 Directly Connected Impervious Area (DCIA) Discussion
The USDCM recommends a four-step process for receiving water protection that focuses
on reducing runoff volumes, treating the water quality capture volume (WQCV),
stabilizing drainageways and implementing long-term source controls. The Four Step
Process applies to the management of smaller, frequently occurring events.
Step 1: Employ Runoff Reduction Practices
To reduce runoff peaks, volumes, and pollutant loads from urbanizing areas, implement
Low Impact Development (LID) strategies, including Minimizing Directly Connected
Impervious Areas (MDCIA).
Runoff from the site shall be conveyed to a water quality facility which promotes
settlement of particles and will slow the "first flush" from all storms entering the public
street and storm sewer system.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 3
Step 2: Implement BMPs that Provide a Water Quality Capture Volume with Slow
Release
Runoff from the site shall be conveyed to a water quality facility that will reduce the rate
of runoff and promote settlement of particles.
Step 3: Stabilize Drainageways
Natural Drainageways are subject to bed and bank erosion due to increases in frequency,
duration, rate, and volume of runoff during and following development. Because the site
will drain to an existing storm system, bank stabilization is unnecessary with this project.
Step 4: Implement Site Specific and Other Source Control BMPs
The proposed project will control pollutants by encouraging them to settle out in a water
quality facility before being released from the site. The proposed project will proactively
control pollutants at their source by preventing pollution rather than removing
contaminants once they have entered the stormwater system as compared to historic
conditions.
3.3 Development Criteria Reference and Constraints
The subject property was previously studied in the “Final Drainage and Erosion
Control Report for Penny Flats” prepared by Jim Sell Design and dated August 18, 2006.
The historic drainage for the site is based on this plan and proposed designs will conform
to this plan.
All basins in Fort Collins are required to provide LID water quality. This will be discussed
in subsequent sections of the report.
The stormwater outfall for this site is the existing storm system in Mason and Cherry
Streets. The Cache la Poudre River is the ultimate outfall.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 4
3.4 Hydrological Criteria
The City of Fort Collins requires that all drainage system design and construction take into
consideration two design storms: the minor storm and the major storm. The “minor storm”
is the 2-year storm or the 50th percentile storm event. The “major storm” is the 100-year
storm or the one percentile storm event.
Runoff computations were prepared for the 2-year minor and 100-year major storm
frequencies utilizing the Rational Method. The study was divided into five onsite basins
that can be identified on the Drainage Plan in Appendix A.
Percentage impervious values were based on proposed land surface types and are specified
in the following table from the FCSCM.
Table 1. Recommended Percentage Imperviousness Values.
The runoff coefficients are based on surface type and specified in the following table from
the FCSCM. The site is classified as NRCS Hydrologic Soil Group A.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 5
Table 2. Surface Type – Runoff Coefficients.
The City of Fort Collins requires a Frequency Adjustment Factor for the 100-year Storm
Return Period. The following table lists this factor, Cf.
Table 3. Frequency Adjustment Factors.
The rainfall intensities used in the Rational Method computation of runoff were obtained
from the Fort Collins Rainfall IDF Curve contained in the figure below.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 6
Figure 1. Rainfall IDF Curve – Fort Collins.
All hydrological calculations including a summary of the calculated minor and major
rainfall event flows are provided in Appendix B.
3.5 Hydraulic Criteria
All hydraulic calculations within this report have been prepared in accordance with the
FCSCM and/or the USDCM. Final hydraulic calculations will be included in future
submittals.
3.6 Low Impact Development (LID) Conformance
Integration of LID systems into the drainage design is required for all development
projects. The implementation of LID systems requires one of the following two options:
1. 50% of the newly added or modified impervious area must be treated by
LID techniques and 25% of new paved (vehicle use) areas must be pervious.
2. 75% of newly added or modified impervious area must be treated by LID
techniques.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 7
The project does not have any surface parking; therefore, the 50% of the newly added or
modified impervious area must be treated by LID techniques rule has been implemented
by incorporating a sand filter.
Please refer to the Existing vs Proposed Impervious Area Exhibit in Appendix D for
comparison of the impervious areas.
3.7 Water Quality (WQ) Treatment Criteria
Standard WQ treatment (40 hour drain time) is required for all portions of a development
site that is not treated through LID systems. Therefore, the development is required to treat
100% of the site’s impervious area for water quality with at least 50% being LID.
3.8 Detention Requirements
Typically, on-site detention is required for the runoff volume difference between the 100-
year developed inflow rate and the 2-year historic release rate. This lot’s proposed percent
imperviousness was determined to be 85%. Because the City’s Master Plan model for this
site already shows all of Penny Flats modeled with 90% imperviousness, the City has
agreed that there is no need to provide an updated hydrology model run to prove a “beat-
the-peak” justification for this site and would allow discharge without detention into the
Howes pipe system. A typical “beat the Peak” study would compare the existing model
with an undeveloped impervious percentage to the proposed developed imperviousness. In
this case, since the model already assumes more impervious than is proposed, a comparison
would actually show slightly less flow regardless of time of concentration. The City also
emphasized that another pipe cut into the side of the large Howes box will not be allowed.
Please refer to Appendix D for correspondence between the City and Wilson & Company
regarding the Master Plan modeling of this area.
3.9 Floodplain Regulations Compliance
The project is not within any FEMA mapped floodplain. Therefore, a Floodplain Submittal
is not required and has not been included with this report.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 8
3.10 Modifications of Criteria
Two Modifications of Criteria will be requested for this project.
The first is the modification to the additional 20% of required Water Quality Capture
Volume storage for sedimentation accumulation. This requirement was not intended to
apply to LID facilities but is not written as such in the FCSCM. Because sand filters should
be maintained several times per year and sediment accumulation over time will not be an
issue the additional 20% was added to the sand filter capture volume calculations. This is
consistent with the method that Mile High Flood District uses to size LID.
The second is the modification to the requirement that 100% of the site’s impervious area
be treated for water quality. The City has stated that the site is not allowed to drain directly
to the box culvert on the west side of the site (no new connections). Because of this, the
portion of the site west of the building can only be directed to Cherry Street and cannot be
captured for water quality. We request that the City vary this standard to allow 79% of the
site to be treated for Water Quality (the entire building) as the remainder of the site is not
able to be captured.
After preliminary review by the City of the two variance requests, formal submittal will be
provided on the Stormwater Alternative Compliance/Variance Application form during
final compliance.
4. DRAINAGE FACILITY DESIGN
4.1 General Concept
The storm runoff of the proposed development will be conveyed to the existing storm
system in Cherry and Mason Streets via sheet flow to existing inlets, roof drains and
proposed storm system. 79% of the impervious area of the site will pass through a proposed
sand filter water quality treatment system. Details for LID water quality will continue to
be developed as the project design progresses.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 9
4.2 Specific Details
A summary of the drainage patterns within each basin is provided in the following
paragraphs. Please refer to Appendix A for the drainage plan.
Basin A is 0.66 acres and contains the proposed building. This basin will produce 1.8 cfs
and 6.6 cfs during the 2-year and 100-year events, respectively. This flow will travel to
the Sand Filter located at the southeast corner of the building. The sand filter will be
connected to an existing inlet in Mason Street.
Basin B is 0.07 acres and is located in the south and southeast corner of the site. It contains
the driveway into the parking structure off of Mason and the pedestrian walkway between
the proposed building and Penny Flats Subdivision Lot 1A and Lot 1B. This basin drains
to the existing storm inlet at design point b in Mason Street and will produce 0.3 cfs and
0.7 cfs during the 2-year and 100-year events, respectively.
Basin C 0.03 acres and is located just east of the building. The basin contains concrete
walk and a small portion of Mason Street (concrete parallel parking area) and drains north
along the curb and gutter of North Mason Street to design point c and then into basin E.
This basin will produce 0.1 cfs and 0.3 cfs during the 2-year and 100-year events,
respectively.
Basin D is 0.33 acres and contains the west and north portions of the development. The
basin contains concrete walks and landscaping. The west portion drains to a concrete pan
and sidewalk chase that directs flow to Cherry Street. The north portion sheets directly to
Cherry Street. Flow is then collected in the large bank of existing inlets at design point d.
This basin will produce 0.4 cfs and 2.0 cfs during the 2-year and 100-year events,
respectively.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 10
Basin E is 0.05 acres and contains the curb and sidewalk in the northeast corner of the
development (Cherry and Mason Streets). The basin sheets to design point e on Mason
Street where flow is collected by a proposed City of Fort Collins curb inlet (Detail D-43).
This basin will produce 0.1 cfs and 0.5 cfs during the 2-year and 100-year events,
respectively. Any overtopping of this inlet will sheet east and is the current drainage pattern
for this basin.
4.3 LID, WQ and Detention
The project is required to treat 50% of on-site new impervious area with LID. For this
initial submittal, LID treatment has been identified as a sand filter. The LID sand filter
will treat 79% of the on-site impervious area (the entire roof area). Appendix D includes
preliminary calculations for LID treatment.
Table 4. LID Summary Table
On-site detention for this site is not required due a “beat-the-peak” philosophy because the
Master Plan already assumes the site is 90% impervious and adequate conveyance capacity
to the Poudre River is provided.
50% On-Site Treatment by LID Requirement
New or Modified Impervious Area 32,194 sf
Required Minimum Impervious Area to be Treated 16,097 sf
Treatment - Sand Filtration 25,370 sf
Total impervious Area Treated 25,370 sf
Actual % of Impervious Area On-Site Treated by LID 79 %
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 11
5. SEDIMENT AND EROSION CONTROL
The disturbed area is greater than 1 acre and will require a State of Colorado Discharge
Permit and City of Fort Collins plan and report.
Temporary Sediment and Erosion Control
Erosion and sedimentation will be controlled on-site during construction by use of vehicle
tracking control pad, concrete washout area, silt fence, rock socks in adjacent existing curb
and gutter, inlet protection, sediment control logs in swales, and seeding and mulch. The
measures will be designed to limit the overall sediment yield increase due to construction
as required by the City of Fort Collins. During grading, the soil will be roughened and
furrowed perpendicular to the prevailing winds.
During the performance of the work required by these specifications or any operations
appurtenant thereto, whether on right-of-way provided by the City or elsewhere, the
contractor shall furnish all labor, equipment, materials, and means required to comply with
applicable permits. The Contractor shall carry out proper efficient measures wherever and
as necessary to reduce dust nuisance, and to prevent dust nuisance that has originated from
his operations from damaging crops, orchards, cultivated fields, and dwellings, or causing
naissance to persons. The Contractor will be held liable for any damage resulting from
dust originating from his operations under these specifications on right-of-way or
elsewhere.
Wherever construction vehicles access routes or intersect paved public roads, provisions
must be made to minimize the transport of sediment by runoff or vehicles tracking onto the
paved surface. The contractor will be responsible for clearing mud tracked onto city streets
daily.
All temporary erosion and sediment control practices must be maintained and repaired as
needed to assure continued performance of their intended function.
An Erosion Control Report will be submitted during Final Compliance.
Lot 1 Penny Flats Subdivision, Second Replat
4065 Saint Cloud Drive; Suite 201, Loveland, CO 80538 phone: 970.834.6364 Page 12
6. CONCLUSIONS
6.1 Compliance with Standards
All computations that have been completed within this report are in compliance with the
City of Fort Collins Storm Drainage Design Criteria Manual.
6.2 Drainage Concept
The proposed drainage concepts presented in this report and on the preliminary
construction plans adequately provide for stormwater quantity and quality treatment of
proposed impervious areas. Conveyance elements have been designed to pass required
flows and to minimize future maintenance.
If, at the time of construction, groundwater is encountered, a Colorado Department of
Health Construction Dewatering Permit will be required.
7. REFERENCES
1. “Final Drainage and Erosion Control Report for: Penny Flats”, Jim Sell Design,
dated August 18, 2006.
2. City of Fort Collins, “Fort Collins Stormwater Criteria Manual”, adopted
December 2018.
3. Mile High Flood District, “Urban Storm Drainage Criteria Manual”, Volume 1
(revised August 2018), Volume 2 (revised September 2017), and Volume 3
(updated January 2021).
A
APPENDIX A
VICINITY MAP AND
DRAINAGE PLAN
SITE
VICINITY MAP
SCALE: 1"=500'
LOT 2
PENNY FLATS SUBDIVISION, SECOND REPLAT
XXXXXXXXXFO
RD
RD
S
SS
W
S
W
W
S
S
S
4
9
8
5 498449824
9
8
1
49
8
1
4982
49834984498549814
9
8
2
4983498549844984LOT 9, BLOCK 33
LOT 10, BLOCK 33
LOT 11-14, BLOCK 33
PENNY FLATS, FTC
LOT 3
PENNY FLATS SUB
LOT 1A
PENNY FLATS SUB
LOT 1B
CHERRY STREET
NORTH MASON STREET10' UE, DE, PEPROP
5' DE
4983
49844985
4985
49854
9
8
4 49824982
EX STORM MH
RIM=4982.04
INV=4971.47 (E) (48" RCP)
INV=4969.84 (W) (48" RCP)
EX STORM MH
RIM=4985.10
BOTTOM OF BOX=4970.35
EX STORM MH
RIM=4981.68
INV=4971.57 (SE) (48" RCP)
INV=4971.41 (W) (48" RCP)
EX STORM MH
RIM=4981.40
EX INV=4972.60 (S) (36" RCP)
EX INV=4972.31 (SE) (18" RCP)
EX INV=4971.79 (NW) (48" RCP)
INV=
EX STORM INLET
RIM=4981.74
EX INV=4978.11 (N) (18" RCP)
EX INV (EST.)=4973.5 (36" RCP)
PROP INV=4978.0 (18" HDPE)
EX STORM GRATES
RIM=4980.61
CONC CULVERT=4973.70
EX STORM GRATE
RIM=4980.77
CONC CULVERT=4973.51
EX STORM MH
RIM=4983.18
INV=4978.33 (E) (18" RCP)
INV=4974.13 (N) (36" RCP)
INV=4974.03 (S) (36" RCP)
PROPOSED SAND FILTER
PROPOSED
SW CHASE
PROPOSED
2' CONC PAN
4984.67
EX 5'X16' BOX CULVERT
(HOWES STREET
OUTFALL
EX 25'
UE, DE,
PE
EX 100' ROWEX 100' ROWCITY OF FORT COLLINS
CURB INLET (DETAIL D-43)
CONNECT 15" RCP
TO EX MH
PROP DEPENNY FLATS SUBTRACT A UE, DE, PEENCLOSURE
WALL
8" COURSE AGGREGATE
18" OF SAND FILTER
MATERIAL
TOP=4980.5
36" PONDING ABOVE SAND FILTER MEDIA
4983.5
18" HDPE OUTLET PIPE
INV=4978.5
REQUIRED FLAT SURFACE AREA = 350 SF
REQUIRED VOLUME = 933 CF (7,000 GALLONS)
4" DIAMETER PERFORATED
PVC UNDERDRAIN
4978.3
BOTTOM SLAB
24" NYLOPLAST OVERFLOW INLET
W/ DOME GRATE
4983.5 RIM
4984.5 SPILLWAY NOTCH
TOP OF EAST WALL
4985.5 TOP OF WALL
SOUTH AND WEST
EX MASON STORM INLET
RIM=4981.74
EX INV=4978.11 (N) (18" RCP)
EX INV (EST.)=4973.5 (36" RCP)
PROP INV=4978.0 (18" HDPE)
SAND FILTER
N.T.S.
20.6 LF 18" HDPE OUTLET PIPE
TO MASON STORM INLET
TOP OF
WALK=4984.67
TOP OF
WALK=4983.50
CONC WALK
SOUTH OF WALL
DRAINAGE
PLAN
6
MPO
ES
ES
22-100-356-00
JULY 19, 20234065 SAINT CLOUD DRIVE, SUITE 201LOVELAND, CO 80538PHONE: 970-834-6364www.wilsonco.comDRAWN BY:
CHECKED BY:
DATE:DESCRIPTIONDATEPROPERTY OWNERSEALPROJECT NAMEPROJECT NO:
DESIGNED BY:
SHEET NO:
SHEET TITLE REV.BYPRE
LI
MI
N
A
R
Y
S
U
B
MI
T
T
A
L
NOT
F
O
R
CON
S
T
R
U
C
TI
O
N
EXISTING MAJOR CONTOUR
BASIN COEFFICIENT (100-YR)
DRAINAGE BASIN AREA
DRAINAGE BASIN NUMBER
DESIGN POINT
PROPOSED DRAINAGE BASIN DIVIDE LINE
FLOW PATH
LEGEND
EXISTING MINOR CONTOUR
PROPOSED MINOR CONTOUR
PROPOSED MAJOR CONTOUR
TRIBE DEVELOPMENT244 N COLLEGE AVESUITE 130FORT COLLINS, CO 80524LOT 1 PENNY FLATSSUBDIVISION, SECONDREPLAT811
B
APPENDIX B
HYDROLOGIC COMPUTATIONS
Wilson & CompanyDRAINAGE SUMMARY TABLEDesign Tributary Area C (2 & 10) C (100) tc (2 & 10) tc (100) Q(2)tot Q(10)tot Q(100)totSub-basinREMARKSPoint (ac)(min) (min) (cfs) (cfs) (cfs)a A 0.66 0.94 1.00 5.0 5.0 1.8 3.0 6.6 Sand Filterb B 0.07 0.88 1.00 5.0 5.0 0.2 0.3 0.7 Existing inlet on North Mason Streetc C 0.03 0.94 1.00 5.0 5.0 0.1 0.2 0.3 Existing inlet on North Mason Streetd D 0.33 0.50 0.62 5.0 5.0 0.4 0.8 2.0 Existing bank of inlets on Cherry Streete E 0.05 0.78 0.97 5.0 5.0 0.1 0.2 0.5 Cherry Street230216 COFC FLOW (209 CHERRY).xlsB1
Wilson & Company
RUNOFF COEFFICIENTS & % IMPERVIOUS
LOCATION:209 CHERRY (PENNY FLATS)
PROJECT NO:22-100-356
COMPUTATIONS BY:es
DATE:2/16/2023
Recommended Runoff Coefficients from Table 3.2-2 of City of Fort Collins Stormwater Criteria Manual
Recommended % Impervious from Table 4.1-3 of City of Fort Collins Stormwater Criteria Manual
Hydrologic Soil Group Type A
Runoff %
coefficient Impervious
C
Asphalt, Concrete: 0.95 100
Rooftop: 0.95 90
Gravel: 0.50 40
Landscape Areas (Flat slope, clay) : 0.20 2
Landscape Areas (Avg slope, clay) : 0.25 2
SUBBASIN TOTAL TOTAL LANDSCAPE RUNOFF %
DESIGNATION AREA AREA ROOFTOP ASPHALT, CONCRETE GRAVEL (Flat slope, clay) COEFF. Impervious REMARKS
(ac.) (sq.ft) (sq.ft) (sq.ft) (sq.ft) (sq.ft)
(C)
Existing
LOT 0.87 38,042 0 0 38,042 0 0.50 40
OFFSITE (LOT BOUNDARY TO LOD) 0.18 7,808 0 3,189 0 4,619 0.39 42
Total 1.05 45850 0 3189 38042 4619 0.48 40
Proposed
LOT 0.87 38,042 28,008 6,767 408 2,859 0.89 85
OFFSITE (LOT BOUNDARY TO LOD) 0.18 7,808 0 5,435 0 2,374 0.72 70
TOTAL 1.05 45850 28008 12202 408 5232 0.86 82
Equations
- Calculated C coefficients & % Impervious are area weighted
C = S (Ci Ai) / At
Ci = runoff coefficient for specific area, Ai
Ai = areas of surface with runoff coefficient of Ci
n = number of different surfaces to consider
At = total area over which C is applicable; the sum of all Ai's
230216 COFC FLOW (209 CHERRY).xls
B2
Wilson & Company
RUNOFF COEFFICIENTS & % IMPERVIOUS
LOCATION:209 CHERRY (PENNY FLATS)
PROJECT NO:22-100-356
COMPUTATIONS BY:es
DATE:2/23/2023
Recommended Runoff Coefficients from Table 3.2-2 of City of Fort Collins Stormwater Criteria Manual
Recommended % Impervious from Table 4.1-3 of City of Fort Collins Stormwater Criteria Manual
Hydrologic Soil Group Type A
Runoff %
coefficient Impervious
C
Asphalt, Concrete: 0.95 100
Rooftop: 0.95 90
Gravel: 0.50 40
Landscape Areas (Flat slope, clay) : 0.20 2
Landscape Areas (Avg slope, clay) : 0.25 2
SUBBASIN TOTAL TOTAL LANDSCAPE RUNOFF %
DESIGNATION AREA AREA ROOFTOP ASPHALT, CONCRETE GRAVEL (Flat slope, clay) COEFF. Impervious REMARKS
(ac.) (sq.ft) (sq.ft) (sq.ft) (sq.ft) (sq.ft)
(C)
A 0.66 28,922 28,008 485 408 21 0.94 89
B 0.07 3,230 0 2,934 0 296 0.88 91
C 0.03 1429 0 1411 0 19 0.94 99
D 0.33 14287 0 5681 0 8,606 0.50 41
E 0.05 2099 0 1613 0 486 0.78 77
Total 1.15 49,967 28,008 12,124 408 9,428 0.80 75
Equations
- Calculated C coefficients & % Impervious are area weighted
C = S (Ci Ai) / At
Ci = runoff coefficient for specific area, Ai
Ai = areas of surface with runoff coefficient of Ci
n = number of different surfaces to consider
At = total area over which C is applicable; the sum of all Ai's
230216 COFC FLOW (209 CHERRY).xls
B3
Wilson & Company
STANDARD FORM SF-2
TIME OF CONCENTRATION - 2 and 10 YR
LOCATION: 209 CHERRY (PENNY FLATS)
PROJECT NO: 22-100-356
COMPUTATIONS BY: es
DATE: 2/16/2023
2 and 10-yr storm Cf = 1.00 from Table RO-12 of City of Fort Collins Stormwater Code, Volume I
SUB-BASIN INITIAL /OVERLAND TRAVEL TIME / GUTTER OR CHANNEL FLOW tc CHECK FINAL REMARKS
DATA TIME (ti) (tt)(URBANIZED BASIN) tc
DESIGN SUBBASIN(s) Area C Length Slope ti Length Slope n Vel. tt tc = Total L tc=(l/180)+10
PONIT (ac) (ft) (%) (min) (ft) (%) Manning (ft/s) (min) ti + tt (ft) (min) (min)
(1) (2) (3) (4) (5) (6) (7) (8) rough. (9) (10) (11) (12) (13) (14)
a A 0.66 0.94 5 2.0 0.5 200 2.0 0.012 3.8 0.9 1.4 205 11.1 5.0
b B 0.07 0.88 5 2.0 0.7 200 2.0 0.012 3.8 0.9 1.6 205 11.1 5.0
c C 0.03 0.94 5 2.0 0.5 200 2.0 0.012 3.8 0.9 1.4 205 11.1 5.0
d D 0.33 0.50 5 2.0 2.0 200 2.0 0.012 3.8 0.9 2.9 205 11.1 5.0
e E 0.05 0.78 5 2.0 1.1 200 2.0 0.012 3.8 0.9 2.0 205 11.1 5.0
EQUATIONS:Overland Flow Length
tc = ti + tt Equation 5-3 L=200' Max in developed areas
L=500' Max in undeveloped areas
ti = [1.87 (1.1 - CCf ) L0.5 ] / S Equation 3.3-2
tt = L/(V*60)Equation 5-5
V=1.49/n * R^2/3*S^1/2 Equation 5-4
final tc = minimum of ti + tt and urbanized basin check
min. tc = 5 min. due to limits of IDF curves
230216 COFC FLOW (209 CHERRY).xls
B4
Wilson & Company
STANDARD FORM SF-2
TIME OF CONCENTRATION - 100 YR
LOCATION: 209 CHERRY (PENNY FLATS)
PROJECT NO: 22-100-356
COMPUTATIONS BY: es
DATE: 2/16/2023
100-yr storm Cf = 1.25 from Table RO-12 of City of Fort Collins Stormwater Code, Volume I
SUB-BASIN INITIAL /OVERLAND TRAVEL TIME / GUTTER OR CHANNEL FLOW tc CHECK FINAL REMARKS
DATA TIME (ti)(tt)(URBANIZED BASIN) tc
DESIGN SUBBASIN(s) Area C C*Cf Length Slope ti Length Slope n Vel. tt tc = Total L tc=(l/180)+10
PONIT (ac)(ft) (%) (min) (ft) (%) Manning (ft/s) (min) ti + tt (ft) (min) (min)
(1) (2) (3) (4) (5) (6) (7) (8) rough. (9) (10) (11) (12) (13) (14)
a A 0.66 0.94 1.00 5 2.0 0.3 200 2.0 0.012 3.8 0.9 1.2 205 11.1 5.0
b B 0.07 0.88 1.00 5 2.0 0.3 200 2.0 0.012 3.8 0.9 1.2 205 11.1 5.0
c C 0.03 0.94 1.00 5 2.0 0.3 200 2.0 0.012 3.8 0.9 1.2 205 11.1 5.0
d D 0.33 0.50 0.62 5 2.0 1.6 200 2.0 0.012 3.8 0.9 2.5 205 11.1 5.0
e E 0.05 0.78 0.97 5 2.0 0.4 200 2.0 0.012 3.8 0.9 1.3 205 11.1 5.0
EQUATIONS:Overland Flow Length
tc = ti + tt Equation 5-3 L=200' Max in developed areas
L=500' Max in undeveloped areas
ti = [1.87 (1.1 - CCf ) L0.5 ] / S Equation 3.3-2
tt = L/(V*60)Equation 5-5
V=1.49/n * R^2/3*S^1/2 Equation 5-4
final tc = minimum of ti + tt and urbanized basin check
min. tc = 5 min. due to limits of IDF curves
230216 COFC FLOW (209 CHERRY).xls
B5
Wilson & Company
RATIONAL METHOD PEAK RUNOFF
(City of Fort Collins, 2-Yr Storm)
LOCATION: 209 CHERRY (PENNY FLATS)
PROJECT NO: 22-100-356
COMPUTATIONS BY: es
DATE: 2/16/2023
2 yr storm, Cf = 1.00
DIRECT RUNOFF CARRY OVER TOTAL REMARKS
Design Tributary A C Cf tc i Q (2) from Q (2) Q(2)tot
Sub-basin Design
Point (ac) (min) (in/hr) (cfs) Point (cfs) (cfs)
a A 0.66 0.94 5.0 2.85 1.8 1.8
b B 0.07 0.88 6.0 2.66 0.2 0.2
c C 0.03 0.94 7.0 2.53 0.1 0.1
d D 0.33 0.50 8.0 2.42 0.4 0.4
e E 0.05 0.78 9.0 2.32 0.1 0.1
Q = Cf C iA
Q = peak discharge (cfs)
C = runoff coefficient
Cf = frequency adjustment factor
i = rainfall intensity (in/hr) from City of Fort Collins IDF curve
A = drainage area (acres)i = 24.221 / (10+ tc)0.7968
230216 COFC FLOW (209 CHERRY).xls
B6
Wilson & Company
RATIONAL METHOD PEAK RUNOFF
(City of Fort Collins, 10-Yr Storm)
LOCATION: 209 CHERRY (PENNY FLATS)
PROJECT NO: 22-100-356
COMPUTATIONS BY: es
DATE: 2/16/2023
10 yr storm, Cf = 1.00
DIRECT RUNOFF CARRY OVER TOTAL REMARKS
Design Tributary A C Cf tc i Q (10) from Q (10) Q(10)tot
Sub-basin Design
Point (ac) (min) (in/hr) (cfs) Point (cfs) (cfs)
a A 0.66 0.94 5.0 4.87 3.0 3.0
b B 0.07 0.88 5.0 4.87 0.3 0.3
c C 0.03 0.94 5.0 4.87 0.2 0.2
d D 0.33 0.50 5.0 4.87 0.8 0.8
e E 0.05 0.78 5.0 4.87 0.2 0.2
Q = Cf C iA
Q = peak discharge (cfs)
C = runoff coefficient
Cf = frequency adjustment factor
i = rainfall intensity (in/hr) from City of Fort Collins IDF curve
A = drainage area (acres)i = 41.44 / (10+ tc)0.7974
230216 COFC FLOW (209 CHERRY).xls
B7
Wilson & Company
RATIONAL METHOD PEAK RUNOFF
(City of Fort Collins, 100-Yr Storm)
LOCATION: 209 CHERRY (PENNY FLATS)
PROJECT NO: 22-100-356
COMPUTATIONS BY: es
DATE: 2/16/2023
100 yr storm, Cf = 1.25
DIRECT RUNOFF CARRY OVER TOTAL REMARKS
Des. Area A C Cf tc i Q (100) from Q (100) Q(100)tot
Design
Point Design. (ac) (min) (in/hr) (cfs) Point (cfs) (cfs)
a A 0.66 1.00 5.0 9.95 6.6 6.6
b B 0.07 1.00 5.0 9.95 0.7 0.7
c C 0.03 1.00 5.0 9.95 0.3 0.3
d D 0.33 0.62 5.0 9.95 2.0 2.0
e E 0.05 0.97 5.0 9.95 0.5 0.5
Q = C iA
Q = peak discharge (cfs)
C = runoff coefficient
i = rainfall intensity (in/hr) from City of Fort Collins IDF curve
A = drainage area (acres)i = 84.682 / (10+ tc)0.7975
230216 COFC FLOW (209 CHERRY).xls
B8
City of Fort Collins Stormwater Criteria Manual
B9
City of Fort Collins Stormwater Criteria Manual
B10
C
APPENDIX C
HYDRAULIC CALCULATIONS
(TO BE COMPLETED AT FINAL)
D
APPENDIX D
LID CALCULATION AND COMMUNICATION REGARDING ON-SITE DETENTION
CHERRY STREET
NORTH MASON STREETPENNY FLATS SUBTRACT AIIIIIIIIIIIIIIIIIIIIIIIIXXI
I
I
I
I
I
I
I
I
I
I
I
IIIIIIIIIIII
IIIIII
IIIIII
IIIIII
IIIII
IIIIIII
IIIIII
IIIIII
SS
W
W
W
S
S
S
CHERRY STREET
NORTH MASON STREETPENNY FLATS SUBTRACT AXXSS
W
W
W
S
S
S
IMPERVIOUS
AREA
EXHIBIT
1
MPO
ES
MPO
22-100-356-004065 SAINT CLOUD DRIVE, SUITE 201LOVELAND, CO 80538PHONE: 970-834-6364www.wilsonco.comDRAWN BY:
CHECKED BY:
DATE:DESCRIPTIONDATEPROPERTY OWNERSEALPROJECT NAMEPROJECT NO:
DESIGNED BY:
SHEET NO:
SHEET TITLE REV.BYPRE
LI
MI
N
A
R
Y
S
U
B
MI
T
T
A
L
NOT
F
O
R
CON
S
T
R
U
C
TI
O
N
EXISTING PROPOSED
SURFACE AREA (SF)% IMPERVIOUS IMPERVIOUS AREA
(SF)
ROOF 0 90 0
CONCRETE/ASPHALT 0 100 0
GRAVEL 38042 40 15217
LANDSCAPE 0 2 0
TOTAL 38042 15217
SURFACE AREA (SF)% IMPERVIOUS IMPERVIOUS AREA
(SF)
ROOF 28008 90 25207
CONCRETE/ASPHALT 6767 100 6767
GRAVEL 408 40 163
LANDSCAPE 2859 2 57
TOTAL 38042 32194 TRIBE DEVELOPMENT244 N COLLEGE AVESUITE 130FORT COLLINS, CO 80524LOT 1 PENNY FLATSSUBDIVISION, SECONDREPLATJULY 12, 2023
New or Modified Impervious Area 32,194 sf
Required Minimum Impervious Area to be Treated 24,146 sf
Treatment - Sand Filtration 25,370 sf
Total impervious Area Treated 25,370 sf
Actual % of Impervious Area On-Site Treated by LID 79 %
75% On-Site Treatment by LID Requirement
LID Table
D2
Sheet 1 of 2
Designer:
Company:
Date:
Project:
Location:
1. Basin Storage Volume
A) Effective Imperviousness of Tributary Area, Ia Ia =100.0 %
(100% if all paved and roofed areas upstream of sand filter)
B) Tributary Area's Imperviousness Ratio (i = Ia/100)i = 1.000
C) Water Quality Capture Volume (WQCV) Based on 12-hour Drain Time WQCV = 0.40 watershed inches
WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i)
D) Contributing Watershed Area (including sand filter area)Area = 28,008 sq ft
E) Water Quality Capture Volume (WQCV) Design Volume VWQCV =934 cu ft
VWQCV = WQCV / 12 * Area
F) For Watersheds Outside of the Denver Region, Depth of d6 = in
Average Runoff Producing Storm
G) For Watersheds Outside of the Denver Region, VWQCV OTHER =cu ft
Water Quality Capture Volume (WQCV) Design Volume
H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER =cu ft
(Only if a different WQCV Design Volume is desired)
2. Basin Geometry
A) WQCV Depth DWQCV =3.0 ft
B) Sand Filter Side Slopes (Horizontal distance per unit vertical, Z = 0.00 ft / ft
4:1 or flatter preferred). Use "0" if sand filter has vertical walls.
C) Minimum Filter Area (Flat Surface Area)AMin =350 sq ft
D) Actual Filter Area AActual =350 sq ft
E) Volume Provided VT =1050 cu ft
3. Filter Material
4. Underdrain System
A) Are underdrains provided?1
B) Underdrain system orifice diameter for 12 hour drain time
i) Distance From Lowest Elevation of the Storage y =ft
Volume to the Center of the Orifice
ii) Volume to Drain in 12 Hours Vol12 =cu ft
iii) Orifice Diameter, 3/8" Minimum DO = in
209 CHERRY ST.
Fort Collins
Design Procedure Form: Sand Filter (SF)
ES
WILSON & CO
March 2, 2023
UD-BMP (Version 3.07, March 2018)
Choose One
Choose One
18" CDOT Class B or C Filter Material
Other (Explain):
YES
NO
UD-BMP_v3.07.xlsm, SF 3/2/2023, 1:11 PM
D3
Sheet 2 of 2
Designer:
Company:
Date:
Project:
Location:
5. Impermeable Geomembrane Liner and Geotextile Separator Fabric
A) Is an impermeable liner provided due to proximity
of structures or groundwater contamination?
PROVIDE A 30 MIL (MIN) PVC GEOMEMBRANE PER TABLE
SF-4 WITH SEPARATOR FABRIC (PER TABLE SF-3) ABOVE IT.
PROVIDE SEPARATOR FABRIC BELOW THE GEOMEMBRANE
AS WELL IF SUBGRADE IS ANGULAR OR COULD OTHERWISE
PUNCTURE THE GEOMEMBRANE.
6. Inlet / Outlet Works
A) Describe the type of energy dissipation at inlet points and means of
conveying flows in excess of the WQCV through the outlet
Notes:
Design Procedure Form: Sand Filter (SF)
ES
WILSON & CO
March 2, 2023
209 CHERRY ST.
Fort Collins
Choose One
YES NO
UD-BMP_v3.07.xlsm, SF 3/2/2023, 1:11 PM
D4
1
Schneider, Erika
From:Matt Simpson <masimpson@fcgov.com>
Sent:Thursday, February 23, 2023 9:04 AM
To:Oberlander, Michael
Cc:Schneider, Erika
Subject:RE: 209 Cherry St - Building Section with Box Culvert
Hi Mike,
Based on this information, there is no need to provide an updated hydrology model run – and would allow you to
discharge w/o detention into the Howes pipe system. With the note (again) that we do not want another pipe cut into
the side of the large Howes box.
Thanks, Matt
Matt Simpson, PE, CFM
Water Utility Development Review Engineer
City of Fort Collins
970-416-2754 office
From: Oberlander, Michael <Michael.Oberlander@wilsonco.com>
Sent: Monday, February 20, 2023 4:16 PM
To: Matt Simpson <masimpson@fcgov.com>
Cc: Schneider, Erika <Erika.Schneider@wilsonco.com>
Subject: [EXTERNAL] RE: 209 Cherry St - Building Section with Box Culvert
Matt-
The concept review comments state that we need to show that we beat the peak for the site to not require detention
(we will have more than the 5000 SF of new hard surface). Dan had a copy of the model from ICON and it shows all of
Penny Flats (including the lot we are looking at) and the impervious percentage in the model is 90% already. He thinks
they modeled gravel lots as 90% as a rule.
How do we proceed – we effectively wouldn’t be changing the model. Do we need to run the model “corrected
effective” with this block at maybe 70% to 80% that it is today, or are we covered since it is already right about where
we will be?
Thanks- If we do need to re-run anything, please provide files.
Mike
Michael P. Oberlander, PE
Operations Manager, Northern Colorado | Wilson & Company, Inc., Engineers & Architects | 970 834 6365 (direct) | 970 631 2671 (cell)
From: Matt Simpson <masimpson@fcgov.com>
Sent: Friday, February 3, 2023 4:39 PM
To: Oberlander, Michael <Michael.Oberlander@wilsonco.com>
Subject: RE: 209 Cherry St - Building Section with Box Culvert
Hi Mike,
D5
2
For Sand Filters in parking garages, you can see the following projects:
· The Standard (blocked in behind a wall… LOL… don’t go see this one..)
· Confluence
· Union on Elizabeth.
· District at Campus West
To find plans for these, you will need to go to Engineering Link and search for them by name.
https://records.fcgov.com/EngineeringLink/Welcome.aspx?dbid=0&repo=FortCollins
Thanks, Matt
Matt Simpson, PE, CFM
Water Utility Development Review Engineer
City of Fort Collins
970-416-2754 office
From: Oberlander, Michael <Michael.Oberlander@wilsonco.com>
Sent: Wednesday, February 1, 2023 12:19 PM
To: Matt Simpson <masimpson@fcgov.com>
Subject: [EXTERNAL] RE: 209 Cherry St - Building Section with Box Culvert
Thanks Matt – hopefully the City doesn’t ask for more than 10 feet since that was what was in the concept review
comments. Very much appreciate your help. One thing (and I’ve been a little scattered). Did you give me a project
name for a sand filter in a parking structure? I think you said Dan had one like that (that wasn’t encased in
concrete)! I’d just like to see the approach – there are so many utilities on all sides of this site (not just the box culvert
side), that I think we are going to have to think “within”.
Michael P. Oberlander, PE
Operations Manager, Northern Colorado | Wilson & Company, Inc., Engineers & Architects | 970 834 6365 (direct) | 970 631 2671 (cell)
From: Matt Simpson <masimpson@fcgov.com>
Sent: Wednesday, February 1, 2023 12:06 PM
To: Mary Taylor <mtaylor@russellmillsstudios.com>; Oberlander, Michael <Michael.Oberlander@wilsonco.com>
Cc: Nathan Starck <nstarck@russellmillsstudios.com>; Don Bernholtz <don@vfla.com>; Chris Aronson
<Chris@vfla.com>; Will Lindsey <wlindsey@fcgov.com>; Brandy Bethurem Harras <BBethuremHarras@fcgov.com>
Subject: RE: 209 Cherry St - Building Section with Box Culvert
Hi Mary, Mike and team,
FYI, I ran both of these exhibits by my manager, Heidi Hansen, and she wants to take more time to evaluate this
situation. It will most likely involve a discussion with senior utilities leadership (above Ken Sampley). With that said, I do
not think the requested 5-feet of separation from the existing concrete storm box pipe will be agreed to. Probably 10-
feet at best – but maybe more. We will be running these conversations internally, so stay tuned for further follow
up. Sorry this is not the news you were hoping for. Feel free to check back with me though in about a week.
Thanks, Matt
Matt Simpson, PE, CFM
Water Utility Development Review Engineer
D6
3
City of Fort Collins
970-416-2754 office
From: Matt Simpson
Sent: Thursday, January 26, 2023 1:09 PM
To: Mary Taylor <mtaylor@russellmillsstudios.com>
Cc: Nathan Starck <nstarck@russellmillsstudios.com>; Don Bernholtz <don@vfla.com>; Oberlander, Michael
<Michael.Oberlander@wilsonco.com>; Chris Aronson <Chris@vfla.com>
Subject: RE: [EXTERNAL] 209 Cherry St - Building Section with Box Culvert
Hi Mary and team,
Thank you for sending this over. My workload is heavy at the moment. I will need 1-2 weeks to get back with you. Feel
free to follow up at the end of next week.
Thanks, Matt
Matt Simpson, PE, CFM
Water Utility Development Review Engineer
City of Fort Collins
970-416-2754 office
From: Mary Taylor <mtaylor@russellmillsstudios.com>
Sent: Tuesday, January 24, 2023 3:08 PM
To: Matt Simpson <masimpson@fcgov.com>
Cc: Nathan Starck <nstarck@russellmillsstudios.com>; Don Bernholtz <don@vfla.com>; Oberlander, Michael
<Michael.Oberlander@wilsonco.com>; Chris Aronson <Chris@vfla.com>
Subject: [EXTERNAL] 209 Cherry St - Building Section with Box Culvert
Hi Matt,
Thanks for your time last week.
Please see the attached PDF that includes our proposed section showing the box culvert and building location. We are
still working on the streetscape and landscape items (for example, no seatwalls), but this should be what you are looking
for in terms of the box culvert.
Let us know what you think.
Thanks and have a great rest of the week--
Mary
Mary Taylor, RLA, ASLA
Senior Landscape Architect
mtaylor@russellmillsstudios.com
| www.russellmillsstudios.com
M: 636.675.4122
| O: 970.484.8855
D7
D8
3
Dan Evans, PE, CFM
Stormwater Practice Lead, Northern Colorado
Wilson & Company, Inc., Engineers & Architects
4065 Saint Cloud Drive, Suite 201 | Loveland, CO 80538
970 834 6371 (direct) | 970 420 1134 (cell)
wilsonco.com
D9
E
APPENDIX E
SOILS AND FLOODPLAIN INFORMATION
Hydrologic Soil Group—Larimer County Area, Colorado
(209 Cherry Street)
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/16/2023
Page 1 of 44493410449342044934304493440449345044934604493470449348044934104493420449343044934404493450449346044934704493480493230493240493250493260493270493280493290493300493310493320493330
493230 493240 493250 493260 493270 493280 493290 493300 493310 493320 493330
40° 35' 31'' N 105° 4' 48'' W40° 35' 31'' N105° 4' 43'' W40° 35' 29'' N
105° 4' 48'' W40° 35' 29'' N
105° 4' 43'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84
0 25 50 100 150
Feet
0 5 10 20 30
Meters
Map Scale: 1:516 if printed on A landscape (11" x 8.5") sheet.
Soil Map may not be valid at this scale.
E1 E1
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Rating Polygons
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Lines
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Points
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:24,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: Larimer County Area, Colorado
Survey Area Data: Version 17, Sep 7, 2022
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Jul 2, 2021—Aug 25,
2021
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Hydrologic Soil Group—Larimer County Area, Colorado
(209 Cherry Street)
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/16/2023
Page 2 of 4
E2
E2
Hydrologic Soil Group
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
81 Paoli fine sandy loam, 0
to 1 percent slopes
A 0.9 100.0%
Totals for Area of Interest 0.9 100.0%
Description
Hydrologic soil groups are based on estimates of runoff potential. Soils are
assigned to one of four groups according to the rate of water infiltration when the
soils are not protected by vegetation, are thoroughly wet, and receive
precipitation from long-duration storms.
The soils in the United States are assigned to four groups (A, B, C, and D) and
three dual classes (A/D, B/D, and C/D). The groups are defined as follows:
Group A. Soils having a high infiltration rate (low runoff potential) when
thoroughly wet. These consist mainly of deep, well drained to excessively
drained sands or gravelly sands. These soils have a high rate of water
transmission.
Group B. Soils having a moderate infiltration rate when thoroughly wet. These
consist chiefly of moderately deep or deep, moderately well drained or well
drained soils that have moderately fine texture to moderately coarse texture.
These soils have a moderate rate of water transmission.
Group C. Soils having a slow infiltration rate when thoroughly wet. These consist
chiefly of soils having a layer that impedes the downward movement of water or
soils of moderately fine texture or fine texture. These soils have a slow rate of
water transmission.
Group D. Soils having a very slow infiltration rate (high runoff potential) when
thoroughly wet. These consist chiefly of clays that have a high shrink-swell
potential, soils that have a high water table, soils that have a claypan or clay
layer at or near the surface, and soils that are shallow over nearly impervious
material. These soils have a very slow rate of water transmission.
If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is
for drained areas and the second is for undrained areas. Only the soils that in
their natural condition are in group D are assigned to dual classes.
Rating Options
Aggregation Method: Dominant Condition
Component Percent Cutoff: None Specified
Hydrologic Soil Group—Larimer County Area, Colorado 209 Cherry Street
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/16/2023
Page 3 of 4
E3
Tie-break Rule: Higher
Hydrologic Soil Group—Larimer County Area, Colorado 209 Cherry Street
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/16/2023
Page 4 of 4
E4
National Flood Hazard Layer FIRMette
0 500 1,000 1,500 2,000250
Feet
Ü
SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT
SPECIAL FLOOD
HAZARD AREAS
Without Base Flood Elevation (BFE)
Zone A, V, A99
With BFE or DepthZone AE, AO, AH, VE, AR
Regulatory Floodway
0.2% Annual Chance Flood Hazard, Areas
of 1% annual chance flood with average
depth less than one foot or with drainage
areas of less than one square mileZone X
Future Conditions 1% Annual
Chance Flood HazardZone X
Area with Reduced Flood Risk due to
Levee. See Notes.Zone X
Area with Flood Risk due to LeveeZone D
NO SCREEN Area of Minimal Flood Hazard Zone X
Area of Undetermined Flood HazardZone D
Channel, Culvert, or Storm Sewer
Levee, Dike, or Floodwall
Cross Sections with 1% Annual Chance
17.5 Water Surface Elevation
Coastal Transect
Coastal Transect Baseline
Profile Baseline
Hydrographic Feature
Base Flood Elevation Line (BFE)
Effective LOMRs
Limit of Study
Jurisdiction Boundary
Digital Data Available
No Digital Data Available
Unmapped
This map complies with FEMA's standards for the use of
digital flood maps if it is not void as described below.
The basemap shown complies with FEMA's basemap
accuracy standards
The flood hazard information is derived directly from the
authoritative NFHL web services provided by FEMA. This map
was exported on 1/16/2023 at 10:55 AM and does not
reflect changes or amendments subsequent to this date and
time. The NFHL and effective information may change or
become superseded by new data over time.
This map image is void if the one or more of the following map
elements do not appear: basemap imagery, flood zone labels,
legend, scale bar, map creation date, community identifiers,
FIRM panel number, and FIRM effective date. Map images for
unmapped and unmodernized areas cannot be used for
regulatory purposes.
Legend
OTHER AREAS OF
FLOOD HAZARD
OTHER AREAS
GENERAL
STRUCTURES
OTHER
FEATURES
MAP PANELS
8
B 20.2
The pin displayed on the map is an approximate
point selected by the user and does not represent
an authoritative property location.
1:6,000
105°5'3"W 40°35'45"N
105°4'26"W 40°35'18"N
Basemap: USGS National Map: Orthoimagery: Data refreshed October, 2020
E5
SITE
E5
4065 St. Cloud, Suite.201
Loveland, CO 80538
970-834-6364 phone