Loading...
HomeMy WebLinkAboutHEARTSIDE HILL RESIDENTIAL DEVELOPMENT - FDP230007 - DOCUMENT MARKUPS - ROUND 2 - EROSION CONTROL LETTER/REPORT EROSION CONTROL REPORT FOR Heartside Hill Prepared by: Highland Development Services 6355 Fairgrounds Ave, Suite 100 Windsor, Colorado 80550 Phone: 970.674.7550 Prepared for: CARE Housing, Inc. 1303 W. Swallow Road Fort Collins, CO 80525 Office: 970.282.7522 February 22, 2023 Job Number 21-1045-00 6355 FAIRGROUNDS AVE, SUITE 100, WINDSOR, COLORADO 80550 | PHONE 970.674.7550 February 14, 2023 Mr. Matt Simpson, P.E. City of Fort Collins Utilities – Stormwater Department 700 Wood Street Fort Collins, CO 80522 RE: Erosion Control Report/Stormwater Management Plan for Heartside HIll Fort Collins Stormwater Department, We are pleased to submit for your review, this Erosion Control Report/Stormwater Management Plan for the Heartside Hill subdivision. This report provides the City with an erosion control plan for the proposed development that addresses the topics outlined in the City Erosion Control Report Requirements. This plan mimics the State of Colorado General Permit and Stormwater Management Plan requirements. I appreciate your time and consideration in reviewing this submittal. Please call if you have any questions. Sincerely, Highland Development Services Zach Wiele Page i TABLE OF CONTENTS Table of Contents ............................................................................................................................. i General Description and Location .................................................................................................. 1 Site Description and Location ...................................................................................................... 1 Site Soils ....................................................................................................................................... 1 BMPs for Stormwater Pollution Prevention ................................................................................... 5 Erosion and Sediment Controls ................................................................................................... 5 Materials Handling and Spill Prevention ..................................................................................... 7 Stormwater Management Controls ................................................................................................ 9 Identification of Potential Pollution Sources ............................................................................... 9 Final Stabilization and Long-term Stormwater Management ...................................................... 11 Inspection and Maintenance ........................................................................................................ 12 SWMP Implementation................................................................................................................. 13 Appendix ....................................................................................................................................... 14 Appendix A – BMP Details ........................................................................................................... A Appendix B – Vicinity Map and Drainage & Erosion Control Plans ............................................. B Appendix C – Construction Sequence ......................................................................................... C Appendix D – Erosion Control Escrow Calculation ...................................................................... D Appendix E – Soil Information ..................................................................................................... E Appendix F – City of Fort Collins Standard Erosion Control Notes...............................................F Page 1 GENERAL DESCRIPTION AND LOCATION SITE DESCRIPTION AND LOCATION The project site is situated in the southeast quarter of Section 12, Township 6 North, Range 69 West of the 6th Principal Meridian, City of Fort Collins, County of Larimer, in the State of Colorado. The property consists of Lots 1 and 2, Block 1 of the Heart of the Rockies Second Subdivision, dated June 9, 1999. Heartside Hill is located within Lot 2, at the northwest corner of the intersection of S. Lemay Ave. and E. Trilby Rd. Lot 1 contains the existing Heart of the Rockies Christian Church. It is bounded by private residential lots to the north and west, E. Trilby Rd. to the south, and S Lemay Ave to the east. The existing church facilities are anticipated to remain. The site area is currently undeveloped and is approximately 8.84 acres. The development would consist of up to 72 CARE Housing for rent apartment units ([6] 12-unit buildings), 9 Habitat for Humanity (H4H) single-family detached lots, 2 L’arche group homes, and a planned shared community center to be designed and constructed at a future date. The project is anticipated to be completed in a single phase. The project site generally slopes from the southwest to the northeast at approximately 4% toward an existing pond at the northeast of the property. Storm runoff is currently conveyed from a grate inlet in the pond to a ditch along the east side of the property and into the existing storm drain sewer. The existing project site is approximately 0.0% impervious. No wetlands are located within the area of proposed development. The project site is not located within the FEMA floodway or floodplain and is within the non- printed FEMA FIRM panel 08069C1200F, effective 12/19/2006. The site is also not located within the City of Fort Collins floodplain. The proposed development includes six multi-family buildings with a clubhouse along with eleven low-income housing lots. The required parking areas, driveways, sidewalks, and open space are also included in the development. A rain garden is proposed to provide the stormwater quality enhancement requirement as a low impact development technique. SITE SOILS The Heartside Hill project site consists primarily of Renohill clay loam and a small portion of Longmont clay and are both classified as Type D hydrologic group. According to USDA/Natural Resource Conservation Group, Type D soils have a very slow infiltration rate when thoroughly wet. These soils consist chiefly of clays that have a high shrink-swell potential, soils that have a high-water table, soils that have a claypan or clay layer at or near the surface, and soils that are 2 shallow over nearly impervious material. These soils also have a very slow rate of water transmission. Per the “Preliminary Geotechnical Subsurface Exploration Report, Proposed Residential Development Lots 1 and 2, Heart of the Rockies Second Subdivision”, prepared by Soilogic, Inc. dated August 13, 2021: “The subsurface materials encountered in the completed site borings were quite variable across the site, but generally consisted of a thin mantle of vegetation and topsoil underlain by brown/beige/rust lean clay with varying amounts of sand. A portion of the near-surface lean clay encountered at the location of boring B-2 extending to a depth of about 3 to 4 feet below ground surface was somewhat mottled in color, appeared to contain bedrock fragments and was identified as possible existing fill material which may have been placed to develop present site grade. In general, the lean clay varied from medium stiff to very stiff in terms of consistency, exhibited variable swell potential (ranging from none to very high) at current moisture and density conditions and extended to depths between 2½ to 18 feet below present site grade, where it was underlain by brown/olive/beige/gray/rust interbedded claystone/siltstone/ sandstone bedrock of varying composition. The bedrock varied from weathered to very hard in terms of hardness, also exhibited variable swell potential (ranging from low to high) at in-situ moisture and density conditions and extended to the bottom of each boring at depths ranging from approximately 15 to 30 feet below present site grades. In general, we judge the bedrock unit underlying the site to possess moderate to high swell potential overall.” Groundwater was also observed during the subsurface soil exploration: “Groundwater was measured in borings B-1, B-2, B-3 and B-6 at depths between about 13 and 27 feet below ground surface, but was not encountered in any of the remaining site borings to the depths explored when checked immediately after completion of drilling. When checked seven (7) days after drilling, groundwater was measured in all borings with the exception of boring B-3 at depths between about 5 and 15 feet below ground surface. The ground surface in the area of boring B-3 had been disturbed, such that subsequent groundwater level measurements could not be completed.” SOIL TYPE PERCENT OF SITE HYDROLOGIC SOIL GROUP1 K FACTOR2 WIND GROUP3 Loveland clay, 0-3% slopes 6.2% D 0.24 4 Renohill clay loam, 3-9% slopes 93.8% D 0.24 6 3 1Hydrologic soil groups range from A to D with group A having a high infiltration rate and D having a very slow infiltration rate 2K factors range from 0.02 to 0.69. The higher value, the more susceptible the soil is to sheet and rill erosion by water. 3Soils assigned to wind group 1 are the most susceptible to wind erosion, soils assigned to wind group 8 are the least susceptible. Overall, the soils on site can be classified as moderately erodible and thus the project must implement an adequate erosion control strategy to control sediment migration from leaving the site. Please refer to Appendix E for the detailed on-site soil information from the NRCS Soil Survey of Larimer County. The anticipated sequence of construction shall progress as follows: 1) Installation of perimeter and offsite erosion control measures (mainly outlet protection at the detention pond outlet structures). Other measures as required for erosion control will be constructed throughout the project. 2) Clearing, stripping, stockpiling, and grading 3) Utility installation 4) Sub-grade preparation for the parking areas, drives and sidewalks 5) Curb, gutter, and sidewalks 6) Paving 7) Building construction (this may occur simultaneously with items 5 through 7) 8) Final grading and landscaping. All disturbed ground will be impervious (concrete, asphalt, or building), seeded and mulched, sodded or xeriscaped to permanently stabilize the site. The run-off coefficients associated with this project for onsite sub-basins are as follows: TRIBUTARY SUB-BASIN AREA (acres) RUNOFF COEFFIECENT C2 C100 OS1 2.033 0.72 0.89 D1 3.744 0.52 0.65 D2 4.646 0.53 0.66 Total 10.422 0.56 0.70 4 No outside sources of pollution currently exist on this site. Potential pollutant sources brought onto the site during construction will be discussed (along with spill prevention) below. The anticipated non-stormwater components of discharge with this project are landscape irrigation return flows. Runoff from the site will flow toward Rain Garden D1 into detention Pond D via swales, inlets, and storm sewer pipes. Stormwater detention and water quality enhancement are achieved through the use of detention Pond D and Rain Garden D1. Four-Phase Erosion and Sediment Control Plan The proposed plans include a 4-phase Erosion and Sediment Control Plan that has been developed in accordance with State recommendations. The plan outlines the installation and phasing of erosion and pollution control BMPs during construction, and the permanent BMPs to remain. The 4-phase plan is a set of snapshots in time, that show the following phases:  Phase 1, Grading Phase – BMPs for perimeter controls prior to clearing and grading  Phase 2, Infrastructure Phase – BMPs for utility, paving, curb and gutter during all phases of construction (temporary construction BMPs)  Phase 3, Vertical Construction Phase – BMPs for individual lot construction  Phase 4, Post construction and final stabilization (permanent BMPs and permanent stormwater quality BMPs) 5 BMPS FOR STORMWATER POLLUTION PREVENTION EROSION AND SEDIMENT CONTROLS STRUCTURAL PRACTICES: Structural practices for the site will consist mainly of vehicle tracking pads, concrete washout areas, temporary sediment basins, inlet protection, culvert protection, silt fencing, and rock socks which are described in detail in the following paragraphs. Detail drawings of these BMPs are also included in Appendix A. These BMPs are expected to change as the construction progresses and it is the responsibility of the contractor to ensure appropriate BMPs are in place and/or removed at the appropriate time in the construction sequence. All temporary and permanent erosion and sediment control practices must be maintained and repaired as needed to assure continued performance of their intended function. All BMPs shall be inspected and repaired or replaced as described further in this report and as required to satisfy the conditions of the Permit. The Heartside Hill project is anticipated to be constructed in 4 phases, with all grading and utility installation (water/sewer/storm) occurring during Phase 1. The existing church modular removal and NW rain garden outfall modification will occur with Phase 4. Phases may be combined sequentially as necessary. Refer to Erosion & Sedimentation Control Plans for detailed BMP sequencing and maintenance plans for the project through all stages of construction. Soil stockpiles should be kept below the locally mandated maximum height and surrounded with silt fencing or other acceptable means. If the storage of these soils is going to be for an extended period of time, then consider temporarily seeding the soil to minimize soil loss to wind and water erosion. Per the City of Fort Collins Stormwater Criteria Manual: No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be protected from sediment transport through the use of surface roughening, watering, and down gradient perimeter controls. All soil stockpiles shall be protected from sediment transport by wind in accordance with Municipal Code §12-150. All stockpiles shall be flattened to meet grade or removed from site as soon as practical, and no later than the completion of construction activities or abandonment of the project. All off-site stockpile storage locations in City limits shall have a stockpile permit from the City Engineering Department prior to using the area to store material. If frequent access from hardscape to the stockpile is needed a structural tracking Control Measure shall be implemented. 6 Vehicle tracking pads are intended to trap mud and sediment within coarse grain material and provide clean access to public roadways. Wherever construction vehicle access routes intersect paved public roads a vehicle tracking control pad shall be installed to minimize the transport of sediment (mud) by runoff or vehicles tracking onto the paved surface. Pads shall be maintained and refurbished when necessary to obtain their intended result. Concrete washout area is intended to contain washout liquids and solids that result from the cleaning of concrete trucks and pumps. Washouts should be placed near the area where the concrete is being poured and 50 ft from any stormwater or drainage course. Two bioretention ponds, Rain Garden D1 and Rain Garden OS1, will be utilized on this site for LID treatment. Rain gardens are to be installed at the conclusion of construction activities and concurrent with landscape installation. Necessary erosion control protection will be placed to minimize risk of native soils migrating to the rain garden growing media. The rain garden grading may be utilized as a sediment trap prior to the installation of the drainage course and growing media. Inlet protection, silt fencing, and rock socks prevent sediment from entering storm drainage systems prior to permanent stabilization of the disturbed site area via ponding and settling of sediment. Rock socks or gravel bags shall be placed at existing and proposed inlets on and near the site as inlet protection. Inlet protection must be inspected and maintained after every rainfall event that produces runoff. Sediment must be removed and rocks replaced. Silt fencing and rock socks will also be used as perimeter protection at the toe of slopes and landscaped areas. Silt fencing and rock socks shall be installed immediately upon completion of over-lot grading. NON-STRUCTURAL PRACTICES: All low sloped areas exposed during land disturbing activity (stripping, grading, utility installations, stockpiling, filling, etc.) shall be kept in a roughened condition by ripping or disking along land contours until mulch, vegetation or other permanent erosion control is installed. All steep sloped areas exposed during land disturbing activity (stripping, grading, utility installations, stockpiling, filling, etc.) shall have slope protection. The contractor shall use a "tracked" vehicle, run perpendicular to slope so that the tracking runs on the contour to inhibit rill/gully erosion; the contractor may use other windrow-type methods as necessary. No soil shall remain exposed by land disturbing activity for more than thirty (30) days. At that 7 time temporary or permanent erosion control seed/mulch, landscaping, etc. is required. Additional Non-Structural Practices are strongly encouraged such as minimizing the disturbance of soils and vegetation, providing educational materials on disposal /recycling, spill prevention / clean up, identification and elimination of illicit discharges, promotion of street sweeping and the development of public education programs. THE CONTRACTOR SHALL ADD ANY AND ALL BMP’S AND DETAILS NEEDED FOR SEDIMENT/EROSION CONTROL. MATERIALS HANDLING AND SPILL PREVENTION Potential impacts from significant materials and their handling are as follows: Chemicals, cleaning substances, and petroleum products related to the construction will be stored within the construction trailer or storage shed where it will not be in contact with precipitation. No storage of these materials will be allowed outside. Fueling and maintenance of equipment shall take place at the construction staging area. Fueling will be accomplished with fueling trucks on an as needed basis. Absorbent (kitty litter) will be in the construction trailer and applied on any spill immediately and the dry material disposed of properly and legally. All construction waste shall be disposed of in the available dumpsters throughout the workday. Liquid wastes will be hauled off site and disposed of properly and legally. Any cleaning or maintenance of small equipment will be required to be done within a containment device (horse trough or small “kiddy pool”) and the liquid disposed of properly and legally. In the event of any spill, the SWMP Administrator shall be immediately notified. Spills can be broken into three categories. Their definitions and the procedures required to address the spills are as follow: MINOR SPILL – A spill generally of less than 5 gallons which is unlikely to reach adjacent waters (i.e. equipment leak). Procedure: a. Stop the source of the spill. b. Contain the spillage. c. Contact the SWMP Administrator. d. Clean up the spill with on-site absorbent material (kitty litter) 8 e. Dispose of the dry material properly or legally. f. Document the spill and the response in the SWMP including dates and times – verify that the pollutants are completely cleaned up. g. Include incident in the following training meeting. h. Provide information to the City of Fort Collins at the next regular inspection. SIGNIFICANT SPILL – A spill of pollutants or oils of any size that will likely or has reached adjacent waters, may endanger health or the environment, or which may exceed a water quality standard. Procedure: a. Stop the source of the spill. b. Contain the spillage. c. Contact the SWMP Administrator. d. Clean up the spill with on-site absorbent material (kitty litter) e. Dispose of the dry material properly or legally. f. Document the spill and the response in the SWMP – verify that the pollutants are completely cleaned up. g. Notify the City of Fort Collins (970) 221-6700 and the Colorado Department of Public Health and Environment spill reporting line (877) 518-5608 of the spill. h. Notify the same two entities above with a written submission (outlined within the permit) within 5 calendar days. i. Include incident in the following training meeting. HAZARDOUS SPILL – A spill of a dangerous substance requiring expert cleanup. Procedure: a. Secure the area – do not approach the spill. b. Offer first aid to any injured parties. c. Call 911 and describe the nature of the spill and any injuries. d. If possible, isolate downstream areas from the spill (for example, cover an inlet that is downstream and a safe distance from the spill with plastic and soil). e. Contact the SWMP Administrator. f. Document the spill and the response in the SWMP g. Notify the City of Fort Collins (970) 221-6700 and the Colorado Department of Public Health and Environment spill reporting line (877) 518-5608 of the spill. h. Notify the same two entities above with a written submission (outlined within the permit) within 5 calendar days. i. Include incident in the following training meeting. 9 STORMWATER MANAGEMENT CONTROLS IDENTIFICATION OF POTENTIAL POLLUTION SOURCES The permit identifies 13 potential sources that must be evaluated for their potential to contribute pollutants to stormwater discharge. These items have been evaluated below for this project: 1. Disturbed and stored soil – YES – The construction will require that areas be disturbed exposing soil including foundation construction, paving and repaving, slope construction, and utility installation, and demolition required as shown on the plans. BMPs will include silt fence and sediment control logs and inlet protection on existing and proposed inlets, minimizing disturbance of existing vegetation and hard surfaces, and slope roughening and tracking of slopes after disturbance and prior to landscaping, paving, or building will be implemented. 2. Vehicle tracking of sediment – YES – The construction will require that subgrade be prepared for pavement and that vehicles drive on unpaved surfaces to the proposed buildings and utility improvement locations. BMPs will include a policy that vehicles be clean prior to entering the site and, if they become muddy during construction or earthwork activities, mud is removed by hand from the vehicle prior to departing the site in an area near the vehicle tracking pad. Any soil that is tracked from the site is to be disposed of in the trash dumpster by sweeping or scraping the material off the street. Any muddy vehicle will use the vehicle tracking pad prior to leaving the site. 3. Management of contaminated soil – NO – To our knowledge, there is not any existing soil contamination on-site. 4. Loading and unloading operations – YES – Chemicals and petroleum products will be brought to the site. Anytime these are being transported, they will be in a sealed container. 5. Outdoor storage activities – YES – Inert materials such as wood and stone will be stored outside and will likely be covered with tarps or plastic but are not pollutant sources and are not covered by the permit. Chemicals and petroleum products will be stored within the construction trailer or storage shed. Cement and mortar bags (if not contained in a vehicle or storage shed) will be completely covered with plastic to avoid contact with precipitation. 6. Vehicle and equipment maintenance and fueling – YES – Vehicle maintenance and fueling, associated with construction of the proposed improvements, will take place. No fuel will be stored on site. 7. Significant dust or particulate generating processes – YES – Most of the site will be exposed from the over-lot grading of the project. In order to control the dust or particulate generating process a water truck or similar watering device will be available at all times. The disturbed ground will be watered as needed to control 10 dust from leaving the site. The area of heavy construction is very limited and none of the operations are expected to generate significant dust. All dust control measures shall be completed in reference to the City’s Fugitive Dust Ordinance (Ordinance No. 044, 2016) and Dust Prevention and Control Manual. 8. Routine maintenance activities involving fertilizers, pesticides, detergents, fuels, solvents, oils, etc. – YES – Fertilizers and pesticides will not be used. Any cleaning or maintenance of small equipment will be required to be done within a containment device (horse trough or small “kiddy pool” and the liquid disposed of properly and legally. 9. On-site waste management – YES – The building and site construction will result in construction waste. A dumpster for trash and a dumpster for bulk recycling will be on the site. Waste will be hauled to the dumpsters by hand or in loaders. Dumpsters will be hauled off as needed. No construction waste will be left outside overnight without being located in a dumpster. No construction debris (including broken concrete) may be buried on the site. 10. Concrete truck/equipment washing – YES – A concrete washout will be provided on site. This will be used for trucks and for any masonry / concrete tools. 11. Dedicated asphalt of concrete batch plants – NO – None on this project. 12. Non-structural waste sources such as worker trash and portable toilets – YES – Trash dumpster will be available for worker’s trash and will be located near the construction trailer and emptied weekly. Portable toilets will be staked on site near the construction trailer. 13. Other areas where potential spills can occur – NO – The above 12 items are adequate for the anticipated construction process. THE CONTRACTOR IS TO UPDATE THE ABOVE INFORMATION WITH EXACT LOCATIONS OF THE CONSTRUCTION TRAILER, VEHICLE TRACKING PAD, CONCRETE WASHOUT, DUMPSTERS, AND PORTABLE TOILETS PRIOR TO COMMENCEMENT OF CONSTRUCTION AND UPDATE AS NECESSARY THROUGHOUT THE CONSTRUCTION SEQUENCE. 11 FINAL STABILIZATION AND LONG-TERM STORMWATER MANAGEMENT Final stabilization shall be considered achieved once all proposed site improvements are in place, all vegetation is established as identified on the landscape plan, all temporary BMPs are removed, and the downstream conveyances are inspected and certified to be clean and free from any construction debris resulting from the construction. Areas controlled by grass sod will be considered established upon the completion of the sod installation. Areas of seeding will be considered established at a vegetative density of 70%. Permanent Stormwater BMPs Grassed Swale with Permanent Turf Reinforcement Mat: A permanent grassed swale along the east of the site will treat basin B5.1 to reduce pollutant loading and runoff through infiltration. The swale is proposed to have Rollmax™ C350 Turf Reinforcement Mat (TRM) installed as a permanent BMP. The swale requires routine maintenance (mowing, turf maintenance, sediment and trash removal, etc.). The swale should be inspected at least twice yearly and immediately after major storm events for erosion, sediment build-up, vegetation health, etc. Permanent Riprap Outlet Protection: Permanent riprap protection has been proposed at the exit of all culvert pipes. The intent of the riprap aprons is to resist erosive forces from stormwater exiting the culverts. The riprap aprons require routine maintenance (sediment and trash removal, riprap required replacement etc.). The riprap aprons should be inspected at least twice yearly and immediately after major storm events for erosion, sediment build-up, rip-rap integrity, etc. 12 INSPECTION AND MAINTENANCE Site inspections will be performed to effectively address maintenance, repair, and adequacy of BMPs. The site inspections will be performed by the SWMP Administrator or his designee a minimum of once every fourteen (14) calendar days on active construction sites and within 24 hours after a significant storm event (event causing erosion). As part of the site inspections the inspector will keep documentation of all inspections and BMP maintenance, including updated Site Maps indicating new BMPs or the removal of BMPs since the previous inspection. Blank Site Maps will be utilized and will be redlined by the SWMP Administrator throughout construction to note all BMPs, pollutant sources, storage locations, etc. Any maintenance, repair, or necessary installation of BMPs that are noted during the inspection must begin immediately. The modifications shall be noted in the SWMP and the action taken as a result of the inspection shall be noted and certified on or attached to the original inspection report (date and time that the repair or change was started and finished and a certification that it was done properly). 13 SWMP IMPLEMENTATION It is the responsibility of the contractor to operate and maintain all facilities and systems of treatment and control which are installed to achieve compliance with the conditions of the permit. This includes effective performance, adequate funding, adequate staffing and training, etc. (see permit). All personnel on the construction site who will be in a position to affect or be affected by the SWMP shall be trained prior to beginning work. These individuals will be given general orientation information regarding the project and SWMP, shown where the SWMP is physically located, the SWMP will be explained to them and available for their review, and the enforcement policy will be reviewed. Throughout the construction, as a part of a weekly safety meeting, the SWMP will be reviewed with all attendees and any incidents discussed. All attendees shall be logged. 15 APPENDIX Appendix A – BMP Details Appendix B – Vicinity Map, Phasing Plan, and Drainage & Erosion Control Plans Appendix C – Construction Sequence Appendix D – Erosion Control Escrow Calculation Appendix E – Soil Information Appendix F – City of Fort Collins Standard Erosion Control Notes Appendix A APPENDIX A – BMP DETAILS REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION CONTROL DETAILS2/22/23 NA N/A ZMW JTC 21-1045-00 C4.00 18 24 CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION CONTROL DETAILS2/22/23 NA N/A ZMW JTC 21-1045-00 C4.01 19 24 CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R Appendix B APPENDIX B – VICINITY MAP AND DRAINAGE & EROSION CONTROL PLANS SITE Vicinity Map Scale: 1" = 1000' PROJECT DATUM: NAVD88 CITY OF FORT COLLINS BENCHMARK #24-94 ON THE NORTHEAST CORNER OF THE INTERSECTION OF EAST TRILBY ROAD AND PORTNER DRIVE, ON TOP OF THE WEST END OF A CONCRETE HEADWALL ELEV= 4960.69 CITY OF FORT COLLINS BENCHMARK #25-94 ON THE NORTHWEST CORNER OF THE INTERSECTION OF EAST TRILBY ROAD AND SOUTH LEMAY AVENUE, ON TOP OF THE SOUTHEAST EDGE OF THE CONCRETE RING TO AN ELECTRIC MANHOLE ELEV= 4913.16 PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) FOR THEIR VERTICAL DATUMS. IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATIONS SHOULD BE USED: NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4960.69 (NAVD88 DATUM) - 3.19' NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4913.16 (NAVD88 DATUM) - 3.19' E TRILBY RDS LEMAY AVEBRIT T A N Y S T AUTUMN RIDGE DRBRITTANY DRHEARTSIDE HILL TRILBY ROAD BRI T T A N Y S T R E E T LEMAY AVENUEBRITTANY STREETBRITTANY KNOLLS BRITTANY KNOLLS PARAGON POINTBLOCK 1 LOT 1 LOT 2 LOT 3 LOT 4 LOT 1 LOT 2 LOT 3 LOT 4 LOT 5 LOT 6 LOT 7 BLOCK 2 BLOCK 3 LOT 1 TRACT A (DRAINAGE & PRIVATE ACCESS EASEMENT) BLDG 1 BLDG 2 BLDG 3 BLDG 4 BLDG 5 BLDG 6 DETENTION POND D 100 YR PEAK INFLOW = 44.16 CFS 100 YR RELEASE RATE = 13.2 CFS 100-YR VOLUME = 0.90 AC-FT 100-YR WSE = 4911.03 FT WQCV (40-HR) = 0.08 AC-FT WQCV WSE = 4908.86 FT (STANDARD WQ - AREA NOT TREATED BY LID) RAIN GARDEN D1 WQCV (12-HR) = 2,914 CU-FT RAIN GARDEN OS1 WQCV (12-HR) = 1,845 CU-FT REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLDRAINAGE PLAN2/22/23 1" = 40' N/A JTC JTC 21-1045-00 C2.00 7 24 CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R N W E S 0 SCALE: 1" = 40' 80402040 LEGEND EXISTING MAJOR CONTOUR EXISTING MINOR CONTOUR PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR BASIN COEFFICIENT (100-YR) BASIN DESIGNATION BASIN AREA DESIGN POINT DRAINAGE FLOW ARROW DRAINAGE BASIN BOUNDARY DRAINAGE BASIN FLOW PATH NOTES 1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED WITH OWNER'S APPROVAL FOR REMOVAL. 2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION CONTROL AND MINIMIZE DOWNSTREAM WATERWAY POLLUTION. 3.LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO ADEQUATELY COMPLETE PROPOSED WORK. ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING, ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION. 4.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT. 5.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS. 6.ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS. 7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL. TRILBY ROAD BR I T T A N Y S T R E E T LEMAY AVENUEBRITTANY STREETAPPROX LIMIT OF DISTURBANCE (TYP) (Remove)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION & SEDIMENT CONTROL PLANPHASE 1 - GRADING2/22/23 1" = 40' N/A ZMW JTC 21-1045-00 C2.01 8 24 0 40' 80402040 SCALE: 1" = N W E S CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R DRAINAGE FLOW ARROW LEGEND EX MAJOR CONTOUR EX MINOR CONTOUR PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR CONSTRUCTION ENTRANCE W/ VEHICLE TRACKING CONTROL CONCRETE WASHOUT AREA SILT FENCE INLET PROTECTION OUTLET STRUCTURE PROTECTION ROCK SOCKS SEDIMENT CONTROL LOGS TEMPORARY SEDIMENT BASIN SURFACE ROUGHENING STABILIZED STAGING AREA TURF REINFORCEMENT MAT PERMANENT RIPRAP APRON LIMITS OF DISTURBANCE (APPROX) COFC STANDARD EROSION AND SEDIMENT CONTROL NOTES 1.THE CITY STORMWATER DEPARTMENT EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST 24 HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE. 2.ALL REQUIRED BMPS MUST BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING, GRADING, ETC). ALL REQUIRED EROSION CONTROL MEASURES MUST BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT. 3.PRE-DISTURBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. 4.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHTS OF WAY SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS BEFORE REQUIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED, UNLESS OTHERWISE APPROVED BY THE STORMWATER DEPARTMENT. 5.THE PROPERTY MUST BE WATERED AND MAINTAINED AT ALL TIMES DURING CONSTRUCTION ACTIVITIES SO AS TO PREVENT WIND-CAUSED EROSION. ALL LAND DISTURBING ACTIVITIES SHALL BE IMMEDIATELY DISCONTINUED WHEN FUGITIVE DUST IMPACTS ADJACENT PROPERTIES, AS DETERMINED BY THE CITY ENGINEERING DEPARTMENT. 6.ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES MUST BE INSPECTED AND REPAIRED OR RECONSTRUCTED AS NECESSARY AFTER EACH RUNOFF EVENT AND EVERY 14 DAYS IN ORDER TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGEWAY. 7.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE ROUGHENING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER 30 DAYS SHALL BE SEEDED AND MULCHED. 8.CITY ORDINANCE PROHIBITS THE TRACKING, DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY VEHICLE. ANY INADVERTENT DEPOSITED MATERIAL SHALL BE CLEANED IMMEDIATELY BY THE CONTRACTOR. EROSION CONTROL NOTES 1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED WITH APPROVAL FOR REMOVAL. 2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION CONTROL AND PREVENT OFFSITE SEDIMENTATION. ADDITIONAL MEASURES AND MEANS NOT SHOWN SHALL ALSO BE IMPLEMENTED AS NEEDED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE APPROPRIATE BMPS DEPICTED AND/OR NOT DEPICTED ON THIS PLAN. 3.CONTRACTOR TO MINIMIZE DISTURBED AREA AT ALL TIMES AND LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO ADEQUATELY COMPLETE PROPOSED WORK. AREAS SHALL NOT BE CLEARED UNTIL THEY ARE TO BE CONSTRUCTED UNLESS APPROVED BY THE BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING, ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION. ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS. 5.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT. 6.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS. 7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL. PHASE 1 - GRADING PHASE NOTES 1.THIS PLAN IS A LIVING DOCUMENT THAT MAY CHANGE AS WORK PROGRESSES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR UPDATING THESE EROSION CONTROL PLANS AS NEEDED DURING CONSTRUCTION ACTIVITIES TO REFLECT ACTUAL BMPS USED ONSITE, REASONS FOR CHANGES AND ANY DISTURBED AREAS. 2.DURING CONSTRUCTION, TEMPORARY EROSION CONTROL MEASURES SHALL BE IMPLEMENTED AS IMPROVEMENTS ARE INSTALLED, INCLUDING BUT NOT LIMITED TO INLET PROTECTION, SEDIMENT BASINS, BMP MAINTENANCE/PROTECTION AND TEMPORARY SEEDING. 3.THE CONTRACTOR MAY USE SUCH BMPS AS SILT FENCE OR COMPACTED EARTH BERM AS FORMAL CONSTRUCTION MARKER PERIMETER CONTROL AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.ALL ONSITE AND OFFSITE DRAINAGE PATTERNS ARE TO BE VERIFIED IN THE FIELD. PROVIDE ALL NECESSARY BMPS TO PROTECT IMMEDIATE DOWNSTREAM INLETS, CULVERTS, DRAINAGE WAYS, ETC. 5.OFFSITE INLET PROTECTIONS SHALL BE COMPLETED BY CURB INLET OR DROP INLET PROTECTION WHETHER BY MEANS OF GRATE FILTERS IN CONJUNCTION WITH CURBSIDE CHECKDAM OR OTHER MEASURES AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 6.ALL PERIMETER CONTROL BMPS SHALL INSTALLED IN PHASE 1. CONTRACTOR SHALL NOT PROCEED WITH CONSTRUCTION ACTIVITIES UNTIL ALL PHASE 1 BMPS ARE INSTALLED, INSPECTED, AND APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 7.CONTRACTOR SHALL INSTALL AND MAINTAIN AT LEAST ONE VEHICLE TRACKING PAD AND MAY INSTALL ADDITIONAL VEHICLE TRACKING PADS TO ACCOMMODATE CONSTRUCTION PROCESSES IN ACCORDANCE WITH THE STORMWATER MANAGEMENT PLAN. ALL VEHICLE TRACKING PADS MUST BE PRE-APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. CONSTRUCTION FENCE CULVERT PROTECTION TRILBY ROAD BR I T T A N Y S T R E E T LEMAY AVENUEBRITTANY STREETAPPROX LIMIT OF DISTURBANCE (TYP) (Remove)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION & SEDIMENT CONTROL PLANPHASE 2 - INFRASTRUCTURE2/22/23 1" = 40' N/A ZMW JTC 21-1045-00 C2.02 9 24 CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R COFC STANDARD EROSION AND SEDIMENT CONTROL NOTES 1.THE CITY STORMWATER DEPARTMENT EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST 24 HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE. 2.ALL REQUIRED BMPS MUST BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING, GRADING, ETC). ALL REQUIRED EROSION CONTROL MEASURES MUST BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT. 3.PRE-DISTURBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. 4.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHTS OF WAY SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS BEFORE REQUIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED, UNLESS OTHERWISE APPROVED BY THE STORMWATER DEPARTMENT. 5.THE PROPERTY MUST BE WATERED AND MAINTAINED AT ALL TIMES DURING CONSTRUCTION ACTIVITIES SO AS TO PREVENT WIND-CAUSED EROSION. ALL LAND DISTURBING ACTIVITIES SHALL BE IMMEDIATELY DISCONTINUED WHEN FUGITIVE DUST IMPACTS ADJACENT PROPERTIES, AS DETERMINED BY THE CITY ENGINEERING DEPARTMENT. 6.ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES MUST BE INSPECTED AND REPAIRED OR RECONSTRUCTED AS NECESSARY AFTER EACH RUNOFF EVENT AND EVERY 14 DAYS IN ORDER TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGEWAY. 7.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE ROUGHENING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER 30 DAYS SHALL BE SEEDED AND MULCHED. 8.CITY ORDINANCE PROHIBITS THE TRACKING, DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY VEHICLE. ANY INADVERTENT DEPOSITED MATERIAL SHALL BE CLEANED IMMEDIATELY BY THE CONTRACTOR. EROSION CONTROL NOTES 1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED WITH APPROVAL FOR REMOVAL. 2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION CONTROL AND PREVENT OFFSITE SEDIMENTATION. ADDITIONAL MEASURES AND MEANS NOT SHOWN SHALL ALSO BE IMPLEMENTED AS NEEDED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE APPROPRIATE BMPS DEPICTED AND/OR NOT DEPICTED ON THIS PLAN. 3.CONTRACTOR TO MINIMIZE DISTURBED AREA AT ALL TIMES AND LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO ADEQUATELY COMPLETE PROPOSED WORK. AREAS SHALL NOT BE CLEARED UNTIL THEY ARE TO BE CONSTRUCTED UNLESS APPROVED BY THE BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING, ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION. ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS. 5.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT. 6.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS. 7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL. PHASE 2 - INFRASTRUCTURE PHASE NOTES 1.CONTRACTOR SHALL GRADE AND INSTALL SEDIMENT BASINS BEFORE PROCEEDING WITH ANY PHASE 2 INFRASTRUCTURE CONSTRUCTION ACTIVITIES. 2.DURING CONSTRUCTION, TEMPORARY EROSION CONTROL MEASURES SHALL BE IMPLEMENTED AS IMPROVEMENTS ARE INSTALLED, INCLUDING BUT NOT LIMITED TO INLET PROTECTION, SEDIMENT BASINS, BMP MAINTENANCE/PROTECTION, TEMPORARY SEEDING AND MULCHING. 3.ONSITE & OFFSITE INLET PROTECTIONS SHALL BE COMPLETED PROTECTED BY CURB INLET OR DROP INLET PROTECTION WHETHER BY MEANS OF GRATE FILTERS IN CONJUNCTION WITH CURBSIDE CHECKDAM OR OTHER MEASURES AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.INFILTRATION GALLERIES TO BE CONSTRUCTED CONCURRENT WITH STORM SYSTEM INFRASTRUCTURE. CONSTRUCT TEMPORARY SEDIMENT BASIN AROUND OUTLET STRUCTURE. SEDIMENT SHALL BE REMOVED FROM INFILTRATION GALLERY ONCE SITE IS STABILIZED. 5.RAIN GARDENS TO BE INSTALLED AT THE CONCLUSION OF CONSTRUCTION ACTIVITIES AND CONCURRENT WITH LANDSCAPE INSTALLATION. PLACE NECESSARY EROSION CONTROL PROTECTION TO MINIMIZE RISK OF NATIVE SOILS MIGRATING TO THE RAIN GARDEN GROWING MEDIA. THE RAIN GARDEN GRADING MAY BE UTILIZED AS A SEDIMENT TRAP PRIOR TO THE INSTALLATION OF THE DRAINAGE COURSE AND GROWING MEDIA. 6.CONTRACTOR SHALL INSTALL AND MAINTAIN AT LEAST ONE VEHICLE TRACKING PAD AND MAY INSTALL ADDITIONAL VEHICLE TRACKING PADS TO ACCOMMODATE CONSTRUCTION PROCESSES IN ACCORDANCE WITH THE STORMWATER MANAGEMENT PLAN. ALL VEHICLE TRACKING PADS MUST BE PRE-APPROVED BY THE BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. DRAINAGE FLOW ARROW LEGEND EX MAJOR CONTOUR EX MINOR CONTOUR PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR CONSTRUCTION ENTRANCE W/ VEHICLE TRACKING CONTROL CONCRETE WASHOUT AREA SILT FENCE INLET PROTECTION OUTLET STRUCTURE PROTECTION ROCK SOCKS SEDIMENT CONTROL LOGS TEMPORARY SEDIMENT BASIN SURFACE ROUGHENING STABILIZED STAGING AREA TURF REINFORCEMENT MAT PERMANENT RIPRAP APRON LIMITS OF DISTURBANCE (APPROX) CONSTRUCTION FENCE CULVERT PROTECTION 0 40' 80402040 SCALE: 1" = N W E S TRILBY ROAD BR I T T A N Y S T R E E T LEMAY AVENUEBRITTANY STREETAPPROX LIMIT OF DISTURBANCE (TYP)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION & SEDIMENT CONTROL PLANPHASE 3 - VERTICAL CONSTRUCTION2/22/23 1" = 40' N/A ZMW JTC 21-1045-00 C2.03 10 24 PHASE 3 - VERTICAL CONSTRUCTION PHASE NOTES 1.DURING CONSTRUCTION, TEMPORARY EROSION CONTROL MEASURES SHALL BE IMPLEMENTED AS IMPROVEMENTS ARE INSTALLED, INCLUDING BUT NOT LIMITED TO INLET PROTECTION, SEDIMENT BASINS, PROTECTION, AND TEMPORARY SEEDING. 2.ANY COMMISSIONED STORM SEWER SYSTEM SHALL INLET AND OUTLET PROTECTION INSTALLED FOR ALL PHASE 3 OPERATIONS. 3.INLET PROTECTION SHALL BE COMPLETED BY CURB INLET OR DROP INLET PROTECTION WHETHER BY MEANS OF GRATE FILTERS IN CONJUNCTION WITH CURBSIDE CHECKDAM OR OTHER MEASURES AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.CONTRACTOR MAY PLACE PERIMETER SEDIMENT CONTROL LOG IN PLACE OF PERMANENT SEEDING IN BLOCKS THAT ANTICIPATE CONSTRUCTION. 5.PERMANENT SEEDING MAY BE REPLACED WITH PERMANENT PROPOSED LANDSCAPING AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R COFC STANDARD EROSION AND SEDIMENT CONTROL NOTES 1.THE CITY STORMWATER DEPARTMENT EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST 24 HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE. 2.ALL REQUIRED BMPS MUST BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING, GRADING, ETC). ALL REQUIRED EROSION CONTROL MEASURES MUST BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT. 3.PRE-DISTURBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. 4.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHTS OF WAY SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS BEFORE REQUIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED, UNLESS OTHERWISE APPROVED BY THE STORMWATER DEPARTMENT. 5.THE PROPERTY MUST BE WATERED AND MAINTAINED AT ALL TIMES DURING CONSTRUCTION ACTIVITIES SO AS TO PREVENT WIND-CAUSED EROSION. ALL LAND DISTURBING ACTIVITIES SHALL BE IMMEDIATELY DISCONTINUED WHEN FUGITIVE DUST IMPACTS ADJACENT PROPERTIES, AS DETERMINED BY THE CITY ENGINEERING DEPARTMENT. 6.ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES MUST BE INSPECTED AND REPAIRED OR RECONSTRUCTED AS NECESSARY AFTER EACH RUNOFF EVENT AND EVERY 14 DAYS IN ORDER TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGEWAY. 7.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE ROUGHENING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER 30 DAYS SHALL BE SEEDED AND MULCHED. 8.CITY ORDINANCE PROHIBITS THE TRACKING, DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY VEHICLE. ANY INADVERTENT DEPOSITED MATERIAL SHALL BE CLEANED IMMEDIATELY BY THE CONTRACTOR. EROSION CONTROL NOTES 1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED WITH APPROVAL FOR REMOVAL. 2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION CONTROL AND PREVENT OFFSITE SEDIMENTATION. ADDITIONAL MEASURES AND MEANS NOT SHOWN SHALL ALSO BE IMPLEMENTED AS NEEDED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE APPROPRIATE BMPS DEPICTED AND/OR NOT DEPICTED ON THIS PLAN. 3.CONTRACTOR TO MINIMIZE DISTURBED AREA AT ALL TIMES AND LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO ADEQUATELY COMPLETE PROPOSED WORK. AREAS SHALL NOT BE CLEARED UNTIL THEY ARE TO BE CONSTRUCTED UNLESS APPROVED BY THE BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING, ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION. ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS. 5.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT. 6.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS. 7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL. DRAINAGE FLOW ARROW LEGEND EX MAJOR CONTOUR EX MINOR CONTOUR PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR CONSTRUCTION ENTRANCE W/ VEHICLE TRACKING CONTROL CONCRETE WASHOUT AREA SILT FENCE INLET PROTECTION OUTLET STRUCTURE PROTECTION ROCK SOCKS SEDIMENT CONTROL LOGS TEMPORARY SEDIMENT BASIN SURFACE ROUGHENING STABILIZED STAGING AREA TURF REINFORCEMENT MAT PERMANENT RIPRAP APRON LIMITS OF DISTURBANCE (APPROX) CONSTRUCTION FENCE CULVERT PROTECTION 0 40' 80402040 SCALE: 1" = N W E S TRILBY ROAD BR I T T A N Y S T R E E T LEMAY AVENUEBRITTANY STREETAPPROX LIMIT OF DISTURBANCE (TYP) (Remove) (Remove)(Remove) (Remove) (Remove) (Remove) (Remove) (Remove)(Remove) (Remove) (Remove) (Remove)(Remove) (Remove)(Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove)(Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove) (Remove)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLEROSION & SEDIMENT CONTROL PLANPHASE 4 - PERMANENT BMP & FINAL STABILIZATION2/22/23 1" = 40' N/A ZMW JTC 21-1045-00 C2.04 11 24 CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R COFC STANDARD EROSION AND SEDIMENT CONTROL NOTES 1.THE CITY STORMWATER DEPARTMENT EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST 24 HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE. 2.ALL REQUIRED BMPS MUST BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING, GRADING, ETC). ALL REQUIRED EROSION CONTROL MEASURES MUST BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT. 3.PRE-DISTURBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. 4.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHTS OF WAY SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS BEFORE REQUIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED, UNLESS OTHERWISE APPROVED BY THE STORMWATER DEPARTMENT. 5.THE PROPERTY MUST BE WATERED AND MAINTAINED AT ALL TIMES DURING CONSTRUCTION ACTIVITIES SO AS TO PREVENT WIND-CAUSED EROSION. ALL LAND DISTURBING ACTIVITIES SHALL BE IMMEDIATELY DISCONTINUED WHEN FUGITIVE DUST IMPACTS ADJACENT PROPERTIES, AS DETERMINED BY THE CITY ENGINEERING DEPARTMENT. 6.ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES MUST BE INSPECTED AND REPAIRED OR RECONSTRUCTED AS NECESSARY AFTER EACH RUNOFF EVENT AND EVERY 14 DAYS IN ORDER TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGEWAY. 7.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE ROUGHENING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER 30 DAYS SHALL BE SEEDED AND MULCHED. 8.CITY ORDINANCE PROHIBITS THE TRACKING, DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY VEHICLE. ANY INADVERTENT DEPOSITED MATERIAL SHALL BE CLEANED IMMEDIATELY BY THE CONTRACTOR. EROSION CONTROL NOTES 1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED WITH APPROVAL FOR REMOVAL. 2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION CONTROL AND PREVENT OFFSITE SEDIMENTATION. ADDITIONAL MEASURES AND MEANS NOT SHOWN SHALL ALSO BE IMPLEMENTED AS NEEDED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE APPROPRIATE BMPS DEPICTED AND/OR NOT DEPICTED ON THIS PLAN. 3.CONTRACTOR TO MINIMIZE DISTURBED AREA AT ALL TIMES AND LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO ADEQUATELY COMPLETE PROPOSED WORK. AREAS SHALL NOT BE CLEARED UNTIL THEY ARE TO BE CONSTRUCTED UNLESS APPROVED BY THE BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING, ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION. ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS. 5.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT. 6.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS. 7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL. PHASE 4 - PERMANENT BMP AND FINAL STABILIZATION NOTES 1.LOTS AND BLOCKS ANTICIPATING CONSTRUCTION MAY UTILIZE SLOPE PROTECTION IN LIEU OF TEMPORARY SEEDING AND MULCHING AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 2.INLET PROTECTIONS SHALL BE COMPLETED BY CURB INLET OR DROP INLET PROTECTION WHETHER BY MEANS OF GRATE FILTERS IN CONJUNCTION WITH CURBSIDE CHECKDAM OR OTHER MEASURES AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 3.CONTRACTOR SHALL REMOVE ALL TEMPORARY BMPS PRIOR TO FINAL DEMOBILIZATION OR AS DIRECTED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 4.CONTRACTOR MAY PLACE PERIMETER SEDIMENT CONTROL LOG IN PLACE OF PERMANENT SEEDING IN BLOCKS THAT ANTICIPATE CONSTRUCTION. 5.PERMANENT SEEDING MAY BE REPLACED WITH PERMANENT PROPOSED LANDSCAPING AS APPROVED BY THE CITY OF FORT COLLINS EROSION CONTROL INSPECTOR. 6.CONTRACTOR TO INSTALL PROPOSED PERMANENT OUTLET PROTECTION WHEN FINALIZING STORM SEWER CONSTRUCTION WHICH MAY HAVE OCCURRED IN EARLIER PHASES. 7.CONTRACTOR TO CLEAN AND LEGALLY DISPOSE OF ALL SEDIMENT COLLECTED ONSITE DURING CONSTRUCTION PRIOR TO FINAL ACCEPTANCE. DRAINAGE FLOW ARROW LEGEND EX MAJOR CONTOUR EX MINOR CONTOUR PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR CONSTRUCTION ENTRANCE W/ VEHICLE TRACKING CONTROL CONCRETE WASHOUT AREA SILT FENCE INLET PROTECTION OUTLET STRUCTURE PROTECTION ROCK SOCKS SEDIMENT CONTROL LOGS TEMPORARY SEDIMENT BASIN SURFACE ROUGHENING STABILIZED STAGING AREA TURF REINFORCEMENT MAT PERMANENT RIPRAP APRON LIMITS OF DISTURBANCE (APPROX) CONSTRUCTION FENCE CULVERT PROTECTION 0 40' 80402040 SCALE: 1" = N W E S Appendix C APPENDIX C – CONSTRUCTION SEQUENCE (Construction Phases)Mobilization Demolition Grading Utilities Installation Flat work Installation Vertical Installation Landscape Demobilization Best Management Practices (BMPs) Structural "Installation" Silt Fence Barriers* Contour Furrows (Ripping / Disking) Sediment Trap / Filter* Vehicle Tracking Pad* Flow Barriers Inlet protection*Any prior inlets that could use protecting Rock Bags*Any prior inlets that could use protecting Terracing Rip Rap Collecting Asphalt / Concrete Saw Cutting Waste *All BMPs to be Removed once Construction is Complete, with the exception of silt fencing, which shall remain in place until seeded areas are established. Vegetative Temporary Seeding Planting Any time the site will sit dorment longer than 30 Days. Mulching/Sealant Any time the site will sit dorment longer than 30 Days. Permanent Seeding Planting Sod Installation Rolled Products : Netting/Blankets/Mats Any time the site will sit dorment longer than 30 Days. Appendix D APPENDIX D – EROSION CONTROL ESCROW CALCULATION 8/28/2019 Project:Disturbed Acres:51.20 EROSION CONTROL BMPs Units Estimated Quantity Unit Price Total Price L.F. 2144 $2.50 $5,360.00 each 16 $150.00 $2,400.00 each 3 $500.00 $1,500.00 each 11 $300.00 $3,300.00 each 2 $800.00 $1,600.00 LS 1 $7,500.00 $7,500.00 Sub-Total: $21,660.00 1.5 x Sub-Total: $32,490.00 Amount of security: $32,490.00 AC 8.427 $2,000.00 $16,854.00 Sub-Total: $16,854.00 1.5 x Sub-Total: $25,281.00 Amount to Re-seed: $25,281.00 Minimum escrow amount: $3,000.00 Erosion Control Escrow:$32,490.00 Miniumum Escrow Amount Northfield Subdivision - PHASE 1 Seeding “The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand dollars ($3,000) for commercial development” Rock Sock Vehicle Tracking Control Pad Final Escrow Amount (Maximum between BMP, Reseeding and Minimum Escrow) Outlet Protection Erosion and Sediment Control Escrow/Security Calculation for The City of Fort Collins BMP Amount Silt Fence Inlet Protection Street Sweeping and Cleaning Reseeding Amount 2/22/2023 10:51 AM G:\Projects\21-1045-00 HRCC\03 Design Documents\Drainage\EC Report\HRCC Erosion Control Escrow.xls Appendix E APPENDIX E – SOIL INFORMATION Hydrologic Soil Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 1 of 444826504482690448273044827704482810448285044828904482650448269044827304482770448281044828504482890494720494760494800494840494880494920494960495000495040495080495120 494720 494760 494800 494840 494880 494920 494960 495000 495040 495080 495120 40° 29' 48'' N 105° 3' 44'' W40° 29' 48'' N105° 3' 27'' W40° 29' 39'' N 105° 3' 44'' W40° 29' 39'' N 105° 3' 27'' WN Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84 0 50 100 200 300 Feet 0 25 50 100 150 Meters Map Scale: 1:1,880 if printed on A landscape (11" x 8.5") sheet. Soil Map may not be valid at this scale. MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Rating Polygons A A/D B B/D C C/D D Not rated or not available Soil Rating Lines A A/D B B/D C C/D D Not rated or not available Soil Rating Points A A/D B B/D C C/D D Not rated or not available Water Features Streams and Canals Transportation Rails Interstate Highways US Routes Major Roads Local Roads Background Aerial Photography The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: Larimer County Area, Colorado Survey Area Data: Version 16, Sep 2, 2021 Soil map units are labeled (as space allows) for map scales 1:50,000 or larger. Date(s) aerial images were photographed: Aug 11, 2018—Aug 12, 2018 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. Hydrologic Soil Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 2 of 4 Hydrologic Soil Group Map unit symbol Map unit name Rating Acres in AOI Percent of AOI 63 Longmont clay, 0 to 3 percent slopes D 0.8 6.2% 90 Renohill clay loam, 3 to 9 percent slopes D 12.8 93.8% Totals for Area of Interest 13.6 100.0% Description Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long-duration storms. The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (A/D, B/D, and C/D). The groups are defined as follows: Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission. Group B. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture. These soils have a moderate rate of water transmission. Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission. Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group D are assigned to dual classes. Rating Options Aggregation Method: Dominant Condition Hydrologic Soil Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 3 of 4 Component Percent Cutoff: None Specified Tie-break Rule: Higher Hydrologic Soil Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 4 of 4 K Factor, Whole Soil—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 1 of 344826504482690448273044827704482810448285044828904482650448269044827304482770448281044828504482890494720494760494800494840494880494920494960495000495040495080495120 494720 494760 494800 494840 494880 494920 494960 495000 495040 495080 495120 40° 29' 48'' N 105° 3' 44'' W40° 29' 48'' N105° 3' 27'' W40° 29' 39'' N 105° 3' 44'' W40° 29' 39'' N 105° 3' 27'' WN Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84 0 50 100 200 300 Feet 0 25 50 100 150 Meters Map Scale: 1:1,880 if printed on A landscape (11" x 8.5") sheet. Soil Map may not be valid at this scale. MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Rating Polygons .02 .05 .10 .15 .17 .20 .24 .28 .32 .37 .43 .49 .55 .64 Not rated or not available Soil Rating Lines .02 .05 .10 .15 .17 .20 .24 .28 .32 .37 .43 .49 .55 .64 Not rated or not available Soil Rating Points .02 .05 .10 .15 .17 .20 .24 .28 .32 .37 .43 .49 .55 .64 Not rated or not available Water Features Streams and Canals Transportation Rails Interstate Highways US Routes Major Roads Local Roads Background Aerial Photography The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: Larimer County Area, Colorado Survey Area Data: Version 16, Sep 2, 2021 Soil map units are labeled (as space allows) for map scales 1:50,000 or larger. Date(s) aerial images were photographed: Aug 11, 2018—Aug 12, 2018 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. K Factor, Whole Soil—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 2 of 3 K Factor, Whole Soil Map unit symbol Map unit name Rating Acres in AOI Percent of AOI 63 Longmont clay, 0 to 3 percent slopes .24 0.8 6.2% 90 Renohill clay loam, 3 to 9 percent slopes .24 12.8 93.8% Totals for Area of Interest 13.6 100.0% Description Erosion factor K indicates the susceptibility of a soil to sheet and rill erosion by water. Factor K is one of six factors used in the Universal Soil Loss Equation (USLE) and the Revised Universal Soil Loss Equation (RUSLE) to predict the average annual rate of soil loss by sheet and rill erosion in tons per acre per year. The estimates are based primarily on percentage of silt, sand, and organic matter and on soil structure and saturated hydraulic conductivity (Ksat). Values of K range from 0.02 to 0.69. Other factors being equal, the higher the value, the more susceptible the soil is to sheet and rill erosion by water. "Erosion factor Kw (whole soil)" indicates the erodibility of the whole soil. The estimates are modified by the presence of rock fragments. Factor K does not apply to organic horizons and is not reported for those layers. Rating Options Aggregation Method: Dominant Condition Component Percent Cutoff: None Specified Tie-break Rule: Higher Layer Options (Horizon Aggregation Method): Surface Layer (Not applicable) K Factor, Whole Soil—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 3 of 3 Wind Erodibility Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 1 of 344826504482690448273044827704482810448285044828904482650448269044827304482770448281044828504482890494720494760494800494840494880494920494960495000495040495080495120 494720 494760 494800 494840 494880 494920 494960 495000 495040 495080 495120 40° 29' 48'' N 105° 3' 44'' W40° 29' 48'' N105° 3' 27'' W40° 29' 39'' N 105° 3' 44'' W40° 29' 39'' N 105° 3' 27'' WN Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84 0 50 100 200 300 Feet 0 25 50 100 150 Meters Map Scale: 1:1,880 if printed on A landscape (11" x 8.5") sheet. Soil Map may not be valid at this scale. MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Rating Polygons 1 2 3 4 4L 5 6 7 8 Not rated or not available Soil Rating Lines 1 2 3 4 4L 5 6 7 8 Not rated or not available Soil Rating Points 1 2 3 4 4L 5 6 7 8 Not rated or not available Water Features Streams and Canals Transportation Rails Interstate Highways US Routes Major Roads Local Roads Background Aerial Photography The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: Larimer County Area, Colorado Survey Area Data: Version 16, Sep 2, 2021 Soil map units are labeled (as space allows) for map scales 1:50,000 or larger. Date(s) aerial images were photographed: Aug 11, 2018—Aug 12, 2018 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. Wind Erodibility Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 2 of 3 Wind Erodibility Group Map unit symbol Map unit name Rating Acres in AOI Percent of AOI 63 Longmont clay, 0 to 3 percent slopes 4 0.8 6.2% 90 Renohill clay loam, 3 to 9 percent slopes 6 12.8 93.8% Totals for Area of Interest 13.6 100.0% Description A wind erodibility group (WEG) consists of soils that have similar properties affecting their susceptibility to wind erosion in cultivated areas. The soils assigned to group 1 are the most susceptible to wind erosion, and those assigned to group 8 are the least susceptible. Rating Options Aggregation Method: Dominant Condition Component Percent Cutoff: None Specified Tie-break Rule: Lower Wind Erodibility Group—Larimer County Area, Colorado Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 12/21/2021 Page 3 of 3 Appendix F APPENDIX F – CITY OF FORT COLLINS STANDARD EROSION CONTROL NOTES CALL UTILITY NOTIFICATION CENTER OF COLORADO CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. before you dig.CallKnow what's below. R 1.ALL MATERIALS, WORKMANSHIP, AND CONSTRUCTION OF PUBLIC IMPROVEMENTS SHALL MEET OR EXCEED THE STANDARDS AND SPECIFICATIONS SET FORTH IN THE LARIMER COUNTY URBAN AREA STREET STANDARDS AND APPLICABLE STATE AND FEDERAL REGULATIONS. WHERE THERE IS CONFLICT BETWEEN THESE PLANS AND THE SPECIFICATIONS, OR ANY APPLICABLE STANDARDS, THE MOST RESTRICTIVE STANDARD SHALL APPLY. ALL WORK SHALL BE INSPECTED AND APPROVED BY THE LOCAL ENTITY. 2.ALL REFERENCES TO ANY PUBLISHED STANDARDS SHALL REFER TO THE LATEST REVISION OF SAID STANDARD, UNLESS SPECIFICALLY STATED OTHERWISE. 3.THESE PUBLIC IMPROVEMENT CONSTRUCTION PLANS SHALL BE VALID FOR A PERIOD OF THREE YEARS FROM THE DATE OF APPROVAL BY THE LOCAL ENTITY ENGINEER. USE OF THESE PLANS AFTER THE EXPIRATION DATE WILL REQUIRE A NEW REVIEW AND APPROVAL PROCESS BY THE LOCAL ENTITY PRIOR TO COMMENCEMENT OF ANY WORK SHOWN IN THESE PLANS. 4.THE ENGINEER WHO HAS PREPARED THESE PLANS, BY EXECUTION AND/OR SEAL HEREOF, DOES HEREBY AFFIRM RESPONSIBILITY TO THE LOCAL ENTITY, AS BENEFICIARY OF SAID ENGINEER'S WORK, FOR ANY ERRORS AND OMISSIONS CONTAINED IN THESE PLANS, AND APPROVAL OF THESE PLANS BY THE LOCAL ENTITY ENGINEER SHALL NOT RELIEVE THE ENGINEER WHO HAS PREPARED THESE PLANS OF ALL SUCH RESPONSIBILITY. FURTHER, TO THE EXTENT PERMITTED BY LAW, THE ENGINEER HEREBY AGREES TO HOLD HARMLESS AND INDEMNIFY THE LOCAL ENTITY, AND ITS OFFICERS AND EMPLOYEES, FROM AND AGAINST ALL LIABILITIES, CLAIMS, AND DEMANDS WHICH MAY ARISE FROM ANY ERRORS AND OMISSIONS CONTAINED IN THESE PLANS. 5.ALL SANITARY SEWER, STORM SEWER, AND WATER LINE CONSTRUCTION, AS WELL AS POWER AND OTHER "DRY" UTILITY INSTALLATIONS, SHALL CONFORM TO THE LOCAL ENTITY STANDARDS AND SPECIFICATIONS CURRENT AT THE DATE OF APPROVAL OF THE PLANS BY THE LOCAL ENTITY ENGINEER. 6.THE TYPE, SIZE, LOCATION AND NUMBER OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN SHOWN ON THE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE DEVELOPER TO VERIFY THE EXISTENCE AND LOCATION OF ALL UNDERGROUND UTILITIES ALONG THE ROUTE OF THE WORK BEFORE COMMENCING NEW CONSTRUCTION. THE DEVELOPER SHALL BE RESPONSIBLE FOR UNKNOWN UNDERGROUND UTILITIES. 7.THE CONTRACTOR SHALL CONTACT THE UTILITY NOTIFICATION CENTER OF COLORADO (UNCC) AT 1-800-922-1987, AT LEAST 2 WORKING DAYS PRIOR TO BEGINNING EXCAVATION OR GRADING, TO HAVE ALL REGISTERED UTILITY LOCATIONS MARKED. OTHER UNREGISTERED UTILITY ENTITIES (I.E. DITCH / IRRIGATION COMPANY) ARE TO BE LOCATED BY CONTACTING THE RESPECTIVE REPRESENTATIVE. UTILITY SERVICE LATERALS ARE ALSO TO BE LOCATED PRIOR TO BEGINNING EXCAVATION OR GRADING. IT SHALL BE THE RESPONSIBILITY OF THE DEVELOPER TO RELOCATE ALL EXISTING UTILITIES THAT CONFLICT WITH THE PROPOSED IMPROVEMENTS SHOWN ON THESE PLANS. 8.THE DEVELOPER SHALL BE RESPONSIBLE FOR PROTECTING ALL UTILITIES DURING CONSTRUCTION AND FOR COORDINATING WITH THE APPROPRIATE UTILITY COMPANY FOR ANY UTILITY CROSSINGS REQUIRED. 9.IF A CONFLICT EXISTS BETWEEN EXISTING AND PROPOSED UTILITIES AND/OR A DESIGN MODIFICATION IS REQUIRED, THE DEVELOPER SHALL COORDINATE WITH THE ENGINEER TO MODIFY THE DESIGN. DESIGN MODIFICATION(S) MUST BE APPROVED BY THE LOCAL ENTITY PRIOR TO BEGINNING CONSTRUCTION. 10.THE DEVELOPER SHALL COORDINATE AND COOPERATE WITH THE LOCAL ENTITY, AND ALL UTILITY COMPANIES INVOLVED, TO ASSURE THAT THE WORK IS ACCOMPLISHED IN A TIMELY FASHION AND WITH A MINIMUM DISRUPTION OF SERVICE. THE DEVELOPER SHALL BE RESPONSIBLE FOR CONTACTING, IN ADVANCE, ALL PARTIES AFFECTED BY ANY DISRUPTION OF ANY UTILITY SERVICE AS WELL AS THE UTILITY COMPANIES. 11.NO WORK MAY COMMENCE WITHIN ANY PUBLIC STORM WATER, SANITARY SEWER OR POTABLE WATER SYSTEM UNTIL THE DEVELOPER NOTIFIES THE UTILITY PROVIDER. NOTIFICATION SHALL BE A MINIMUM OF 2 WORKING DAYS PRIOR TO COMMENCEMENT OF ANY WORK. AT THE DISCRETION OF THE WATER UTILITY PROVIDER, A PRE-CONSTRUCTION MEETING MAY BE REQUIRED PRIOR TO COMMENCEMENT OF ANY WORK. 12.THE DEVELOPER SHALL SEQUENCE INSTALLATION OF UTILITIES IN SUCH A MANNER AS TO MINIMIZE POTENTIAL UTILITY CONFLICTS. IN GENERAL, STORM SEWER AND SANITARY SEWER SHOULD BE CONSTRUCTED PRIOR TO INSTALLATION OF THE WATER LINES AND DRY UTILITIES. 13.THE MINIMUM COVER OVER WATER LINES IS 4.5 FEET AND THE MAXIMUM COVER IS 5.5 FEET UNLESS OTHERWISE NOTED IN THE PLANS AND APPROVED BY THE WATER UTILITY. 14.A STATE CONSTRUCTION DEWATERING WASTEWATER DISCHARGE PERMIT IS REQUIRED IF DEWATERING IS REQUIRED IN ORDER TO INSTALL UTILITIES OR WATER IS DISCHARGED INTO A STORM SEWER, CHANNEL, IRRIGATION DITCH OR ANY WATERS OF THE UNITED STATES. 15.THE DEVELOPER SHALL COMPLY WITH ALL TERMS AND CONDITIONS OF THE COLORADO PERMIT FOR STORM WATER DISCHARGE (CONTACT COLORADO DEPARTMENT OF HEALTH, WATER QUALITY CONTROL DIVISION, (303) 692-3590), THE STORM WATER MANAGEMENT PLAN, AND THE EROSION CONTROL PLAN. 16.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF STORM DRAINAGE FACILITIES LOCATED ON PRIVATE PROPERTY. MAINTENANCE OF ONSITE DRAINAGE FACILITIES SHALL BE THE RESPONSIBILITY OF THE PROPERTY OWNER(S). 17.PRIOR TO FINAL INSPECTION AND ACCEPTANCE BY THE LOCAL ENTITY, CERTIFICATION OF THE DRAINAGE FACILITIES, BY A REGISTERED ENGINEER, MUST BE SUBMITTED TO AND APPROVED BY THE STORMWATER UTILITY DEPARTMENT. CERTIFICATION SHALL BE SUBMITTED TO THE STORMWATER UTILITY DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF A CERTIFICATE OF OCCUPANCY FOR SINGLE FAMILY UNITS. FOR COMMERCIAL PROPERTIES, CERTIFICATION SHALL BE SUBMITTED TO THE STORMWATER UTILITY DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF ANY BUILDING PERMITS IN EXCESS OF THOSE ALLOWED PRIOR TO CERTIFICATION PER THE DEVELOPMENT AGREEMENT. 18.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR ANY DAMAGES OR INJURIES SUSTAINED IN THIS DEVELOPMENT AS A RESULT OF GROUNDWATER SEEPAGE, WHETHER RESULTING FROM GROUNDWATER FLOODING, STRUCTURAL DAMAGE OR OTHER DAMAGE UNLESS SUCH DAMAGE OR INJURIES ARE SUSTAINED AS A RESULT OF THE LOCAL ENTITY FAILURE TO PROPERLY MAINTAIN ITS WATER, WASTEWATER, AND/OR STORM DRAINAGE FACILITIES IN THE DEVELOPMENT. 19.ALL RECOMMENDATIONS OF THE FINAL DRAINAGE AND EROSION CONTROL STUDY, FINAL DRAINAGE REPORT FOR HEARTSIDE HILL BY HIGHLAND DEVELOPMENT SERVICES SHALL BE FOLLOWED AND IMPLEMENTED. 20.TEMPORARY EROSION CONTROL DURING CONSTRUCTION SHALL BE PROVIDED AS SHOWN ON THE EROSION CONTROL PLAN. ALL EROSION CONTROL MEASURES SHALL BE MAINTAINED IN GOOD REPAIR BY THE DEVELOPER, UNTIL SUCH TIME AS THE ENTIRE DISTURBED AREAS IS STABILIZED WITH HARD SURFACE OR LANDSCAPING. 21.THE DEVELOPER SHALL BE RESPONSIBLE FOR INSURING THAT NO MUD OR DEBRIS SHALL BE TRACKED ONTO THE EXISTING PUBLIC STREET SYSTEM. MUD AND DEBRIS MUST BE REMOVED WITHIN 24 HOURS BY AN APPROPRIATE MECHANICAL METHOD (I.E. MACHINE BROOM SWEEP, LIGHT DUTY FRONT-END LOADER, ETC.) OR AS APPROVED BY THE LOCAL ENTITY STREET INSPECTOR. 22.NO WORK MAY COMMENCE WITHIN ANY IMPROVED OR UNIMPROVED PUBLIC RIGHT-OF-WAY UNTIL A RIGHT-OF-WAY PERMIT OR DEVELOPMENT CONSTRUCTION PERMIT IS OBTAINED, IF APPLICABLE. 23.THE DEVELOPER SHALL BE RESPONSIBLE FOR OBTAINING ALL NECESSARY PERMITS FOR ALL APPLICABLE AGENCIES PRIOR TO COMMENCEMENT OF CONSTRUCTION. THE DEVELOPER SHALL NOTIFY THE LOCAL ENTITY ENGINEERING INSPECTOR (FORT COLLINS - 221-6605) AND THE LOCAL ENTITY EROSION CONTROL INSPECTOR (FORT COLLINS - 221-6700) AT LEAST 2 WORKING DAYS PRIOR TO THE START OF ANY EARTH DISTURBING ACTIVITY, OR CONSTRUCTION ON ANY AND ALL PUBLIC IMPROVEMENTS. IF THE LOCAL ENTITY ENGINEER IS NOT AVAILABLE AFTER PROPER NOTICE OF CONSTRUCTION ACTIVITY HAS BEEN PROVIDED, THE DEVELOPER MAY COMMENCE WORK IN THE ENGINEER ABSENCE. HOWEVER, THE LOCAL ENTITY RESERVES THE RIGHT NOT TO ACCEPT THE IMPROVEMENT IF SUBSEQUENT TESTING REVEALS AN IMPROPER INSTALLATION. 24.THE DEVELOPER SHALL BE RESPONSIBLE FOR OBTAINING SOILS TESTS WITHIN THE PUBLIC RIGHT-OF-WAY AFTER RIGHT OF WAY GRADING AND ALL UTILITY TRENCH WORK IS COMPLETE AND PRIOR TO THE PLACEMENT OF CURB, GUTTER, SIDEWALK AND PAVEMENT. IF THE FINAL SOILS/PAVEMENT DESIGN REPORT DOES NOT CORRESPOND WITH THE RESULTS OF THE ORIGINAL GEOTECHNICAL REPORT, THE DEVELOPER SHALL BE RESPONSIBLE FOR A RE-DESIGN OF THE SUBJECT PAVEMENT SECTION OR, THE DEVELOPER MAY USE THE LOCAL ENTITY'S DEFAULT PAVEMENT THICKNESS SECTION(S). REGARDLESS OF THE OPTION USED, ALL FINAL SOILS/PAVEMENT DESIGN REPORTS SHALL BE PREPARED BY A LICENSED PROFESSIONAL ENGINEER. THE FINAL REPORT SHALL BE SUBMITTED TO THE INSPECTOR A MINIMUM OF 10 WORKING DAYS PRIOR TO PLACEMENT OF BASE AND ASPHALT. PLACEMENT OF CURB, GUTTER, SIDEWALK, BASE AND ASPHALT SHALL NOT OCCUR UNTIL THE LOCAL ENTITY ENGINEER APPROVES THE FINAL REPORT. 25.THE CONTRACTOR SHALL HIRE A LICENSED ENGINEER OR LAND SURVEYOR TO SURVEY THE CONSTRUCTED ELEVATIONS OF THE STREET SUBGRADE AND THE GUTTER FLOWLINE AT ALL INTERSECTIONS, INLETS, AND OTHER LOCATIONS REQUESTED BY THE LOCAL ENTITY INSPECTOR. THE ENGINEER OR SURVEYOR MUST CERTIFY IN A LETTER TO THE LOCAL ENTITY THAT THESE ELEVATIONS CONFORM TO THE APPROVED PLANS AND SPECIFICATIONS. ANY DEVIATIONS SHALL BE NOTED IN THE LETTER AND THEN RESOLVED WITH THE LOCAL ENTITY BEFORE INSTALLATION OF BASE COURSE OR ASPHALT WILL BE ALLOWED ON THE STREETS. 26.ALL UTILITY INSTALLATIONS WITHIN OR ACROSS THE ROADBED OF NEW RESIDENTIAL ROADS MUST BE COMPLETED PRIOR TO THE FINAL STAGES OF ROAD CONSTRUCTION. FOR THE PURPOSES OF THESE STANDARDS, ANY WORK EXCEPT C/G ABOVE THE SUBGRADE IS CONSIDERED FINAL STAGE WORK. ALL SERVICE LINES MUST BE STUBBED TO THE PROPERTY LINES AND MARKED SO AS TO REDUCE THE EXCAVATION NECESSARY FOR BUILDING CONNECTIONS. 27.PORTIONS OF LARIMER COUNTY ARE WITHIN OVERLAY DISTRICTS. THE LARIMER COUNTY FLOODPLAIN RESOLUTION SHOULD BE REFERRED TO FOR ADDITIONAL CRITERIA FOR ROADS WITHIN THESE DISTRICTS. 28.ALL ROAD CONSTRUCTION IN AREAS DESIGNATED AS WILD FIRE HAZARD AREAS SHALL BE DONE IN ACCORDANCE WITH THE CONSTRUCTION CRITERIA AS ESTABLISHED IN THE WILD FIRE HAZARD AREA MITIGATION REGULATIONS IN FORCE AT THE TIME OF FINAL PLAT APPROVAL. 29.PRIOR TO THE COMMENCEMENT OF ANY CONSTRUCTION, THE CONTRACTOR SHALL CONTACT THE LOCAL ENTITY FORESTER TO SCHEDULE A SITE INSPECTION FOR ANY TREE REMOVAL REQUIRING A PERMIT. 30.THE DEVELOPER SHALL BE RESPONSIBLE FOR ALL ASPECTS OF SAFETY INCLUDING, BUT NOT LIMITED TO, EXCAVATION, TRENCHING, SHORING, TRAFFIC CONTROL, AND SECURITY. REFER TO OSHA PUBLICATION 2226, EXCAVATING AND TRENCHING. 31.THE DEVELOPER SHALL SUBMIT A CONSTRUCTION TRAFFIC CONTROL PLAN, IN ACCORDANCE WITH MUTCD, TO THE APPROPRIATE RIGHT-OF-WAY AUTHORITY. (LOCAL ENTITY, COUNTY OR STATE), FOR APPROVAL, PRIOR TO ANY CONSTRUCTION ACTIVITIES WITHIN, OR AFFECTING, THE RIGHT-OF-WAY. THE DEVELOPER SHALL BE RESPONSIBLE FOR PROVIDING ANY AND ALL TRAFFIC CONTROL DEVICES AS MAY BE REQUIRED BY THE CONSTRUCTION ACTIVITIES. 32.PRIOR TO THE COMMENCEMENT OF ANY CONSTRUCTION THAT WILL AFFECT TRAFFIC SIGNS OF ANY TYPE, THE CONTRACTOR SHALL CONTACT LOCAL ENTITY TRAFFIC OPERATIONS DEPARTMENT, WHO WILL TEMPORARILY REMOVE OR RELOCATE THE SIGN AT NO COST TO THE CONTRACTOR; HOWEVER, IF THE CONTRACTOR MOVES THE TRAFFIC SIGN THEN THE CONTRACTOR WILL BE CHARGED FOR THE LABOR, MATERIALS AND EQUIPMENT TO REINSTALL THE SIGN AS NEEDED. 33.THE DEVELOPER IS RESPONSIBLE FOR ALL COSTS FOR THE INITIAL INSTALLATION OF TRAFFIC SIGNING AND STRIPING FOR THE DEVELOPMENT RELATED TO THE DEVELOPMENT'S LOCAL STREET OPERATIONS. IN ADDITION, THE DEVELOPER IS RESPONSIBLE FOR ALL COSTS FOR TRAFFIC SIGNING AND STRIPING RELATED TO DIRECTING TRAFFIC ACCESS TO AND FROM THE DEVELOPMENT. 34.THERE SHALL BE NO SITE CONSTRUCTION ACTIVITIES ON SATURDAYS, UNLESS SPECIFICALLY APPROVED BY THE LOCAL ENTITY ENGINEER, AND NO SITE CONSTRUCTION ACTIVITIES ON SUNDAYS OR HOLIDAYS, UNLESS THERE IS PRIOR WRITTEN APPROVAL BY THE LOCAL ENTITY. 35.THE DEVELOPER IS RESPONSIBLE FOR PROVIDING ALL LABOR AND MATERIALS NECESSARY FOR THE COMPLETION OF THE INTENDED IMPROVEMENTS, SHOWN ON THESE DRAWINGS, OR DESIGNATED TO BE PROVIDED, INSTALLED, OR CONSTRUCTED, UNLESS SPECIFICALLY NOTED OTHERWISE. 36.DIMENSIONS FOR LAYOUT AND CONSTRUCTION ARE NOT TO BE SCALED FROM ANY DRAWING. IF PERTINENT DIMENSIONS ARE NOT SHOWN, CONTACT THE DESIGNER FOR CLARIFICATION, AND ANNOTATE THE DIMENSION ON THE AS-BUILT RECORD DRAWINGS. 37.THE DEVELOPER SHALL HAVE, ONSITE AT ALL TIMES, ONE (1) SIGNED COPY OF THE APPROVED PLANS, ONE (1) COPY OF THE APPROPRIATE STANDARDS AND SPECIFICATIONS, AND A COPY OF ANY PERMITS AND EXTENSION AGREEMENTS NEEDED FOR THE JOB. 38.IF, DURING THE CONSTRUCTION PROCESS, CONDITIONS ARE ENCOUNTERED WHICH COULD INDICATE A SITUATION THAT IS NOT IDENTIFIED IN THE PLANS OR SPECIFICATIONS, THE DEVELOPER SHALL CONTACT THE DESIGNER AND THE LOCAL ENTITY ENGINEER IMMEDIATELY. 39.THE DEVELOPER SHALL BE RESPONSIBLE FOR RECORDING AS-BUILT INFORMATION ON A SET OF RECORD DRAWINGS KEPT ON THE CONSTRUCTION SITE, AND AVAILABLE TO THE LOCAL ENTITY'S INSPECTOR AT ALL TIMES. UPON COMPLETION OF THE WORK, THE CONTRACTOR(S) SHALL SUBMIT RECORD DRAWINGS TO THE LOCAL ENTITY ENGINEER. 40.PROJECT BENCHMARKS: PROJECT DATUM: NAVD88 CITY OF FORT COLLINS BENCHMARK #24-94 ON THE NORTHEAST CORNER OF THE INTERSECTION OF EAST TRILBY ROAD AND PORTNER DRIVE, ON TOP OF THE WEST END OF A CONCRETE HEADWALL ELEV= 4960.69 CITY OF FORT COLLINS BENCHMARK #25-94 ON THE NORTHEWEST CORNER OF THE INTERSECTION OF EAST TRILBY ROAD AND SOUTH LEMAY AVENUE, ON TOP OF THE SOUTHEAST EDGE OF THE CONCRETE RING TO AN ELECTRIC MANHOLE ELEV= 4913.16 PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) FOR THEIR VERTICAL DATUMS. IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY PURPOSE,THE FOLLOWING EQUATIONS SHOULD BE USED: NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4960.69 (NAVD88 DATUM) - 3.19 NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4913.16 (NAVD88 DATUM) - 3.19 HORIZONTAL DATUM: COLORADO STATE PLAN COORDINATES NAD 83(2007) DATUM. HORIZONTAL CONTROL BASED VRS. 41.ALL STATIONING IS BASED ON FLOWLINE OF ROADWAYS UNLESS OTHERWISE NOTED. 42.DAMAGED CURB, GUTTER AND SIDEWALK EXISTING PRIOR TO CONSTRUCTION, AS WELL AS EXISTING FENCES, TREES, STREETS, SIDEWALKS, CURBS AND GUTTERS, LANDSCAPING, STRUCTURES, AND IMPROVEMENTS DESTROYED, DAMAGED OR REMOVED DUE TO CONSTRUCTION OF THIS PROJECT, SHALL BE REPLACED OR RESTORED IN LIKE KIND AT THE DEVELOPER'S EXPENSE, UNLESS OTHERWISE INDICATED ON THESE PLANS, PRIOR TO THE ACCEPTANCE OF COMPLETED IMPROVEMENTS AND/OR PRIOR TO THE ISSUANCE OF THE FIRST CERTIFICATE OF OCCUPANCY. 43.WHEN AN EXISTING ASPHALT STREET MUST BE CUT, THE STREET MUST BE RESTORED TO A CONDITION EQUAL TO OR BETTER THAN ITS ORIGINAL CONDITION. THE EXISTING STREET CONDITION SHALL BE DOCUMENTED BY THE LOCAL ENTITY CONSTRUCTION INSPECTOR BEFORE ANY CUTS ARE MADE. PATCHING SHALL BE DONE IN ACCORDANCE WITH THE LOCAL ENTITY STREET REPAIR STANDARDS. THE FINISHED PATCH SHALL BLEND IN SMOOTHLY INTO THE EXISTING SURFACE. ALL LARGE PATCHES SHALL BE PAVED WITH AN ASPHALT LAY-DOWN MACHINE. IN STREETS WHERE MORE THAN ONE CUT IS MADE, AN OVERLAY OF THE ENTIRE STREET WIDTH, INCLUDING THE PATCHED AREA, MAY BE REQUIRED. THE DETERMINATION OF NEED FOR A COMPLETE OVERLAY SHALL BE MADE BY THE LOCAL ENTITY ENGINEER AND/OR THE LOCAL ENTITY INSPECTOR AT THE TIME THE CUTS ARE MADE. 44.UPON COMPLETION OF CONSTRUCTION, THE SITE SHALL BE CLEANED AND RESTORED TO A CONDITION EQUAL TO, OR BETTER THAN, THAT WHICH EXISTED BEFORE CONSTRUCTION, OR TO THE GRADES AND CONDITION AS REQUIRED BY THESE PLANS. 45.STANDARD HANDICAP RAMPS ARE TO BE CONSTRUCTED AT ALL CURB RETURNS AND AT ALL "T" INTERSECTIONS. 46.AFTER ACCEPTANCE BY THE LOCAL ENTITY, PUBLIC IMPROVEMENTS DEPICTED IN THESE PLANS SHALL BE GUARANTEED TO BE FREE FROM MATERIAL AND WORKMANSHIP DEFECTS FOR A MINIMUM PERIOD OF TWO YEARS FROM THE DATE OF ACCEPTANCE. 47.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF ROADWAY AND APPURTENANT IMPROVEMENTS, INCLUDING STORM DRAINAGE STRUCTURES AND PIPES, FOR THE FOLLOWING PRIVATE STREETS: NO PRIVATE STREET PROPOSED. 48.APPROVED VARIANCES ARE LISTED AS FOLLOWS: N/A CITY OF FORT COLLINS CONSTRUCTION NOTES A.STANDARD GRADING AND EROSION AND SEDIMENT CONTROL CONSTRUCTION PLAN NOTES GENERAL EROSION CONTROL REQUIREMENTS THESE NOTES ARE A SUMMARY FOR THE LEGAL REQUIREMENTS, THAT ARE SET FORTH IN THE FORT COLLINS STORMWATER CRITERIA MANUAL (FCSCM), AND THAT ANY CONFLICT IS RESOLVED BY THE MORE STRINGENT REQUIREMENT CONTROLLING. 1.THE PROPERTY OWNER, OWNER'S REPRESENTATIVE, DEVELOPER, DESIGN ENGINEER, GENERAL CONTRACTOR, SUB-CONTRACTORS, OR SIMILAR TITLE FOR THE DEVELOPING ENTITY (HERE AFTER REFERRED TO AS THE DEVELOPER) HAS PROVIDED THESE EROSION CONTROL MATERIALS IN ACCORDANCE WITH EROSION CONTROL CRITERIA SET FORTH IN THE MANUAL AS AN ATTEMPT TO IDENTIFY EROSION, SEDIMENT, AND OTHER POTENTIAL POLLUTANT SOURCES ASSOCIATED WITH THESE CONSTRUCTION ACTIVITIES AND PREVENTING THOSE POLLUTANTS FROM LEAVING THE PROJECT SITE AS AN ILLICIT DISCHARGE. FULL CITY REQUIREMENTS AND ARE OUTLINED AND CLARIFIED IN THE MANUAL UNDER CHAPTER 4: CONSTRUCTION CONTROL MEASURES AND SHOULD BE USED TO IDENTIFY AND DEFINE WHAT IS NEEDED ON A PROJECT. 2.THE DEVELOPER SHALL MAKE THEMSELVES THOROUGHLY FAMILIAR WITH THE PROVISIONS AND THE CONTENT OF THE SPECIFICATIONS LAID OUT IN THE MANUAL, THE DEVELOPMENT AGREEMENT, THE EROSION CONTROL MATERIALS COMPILED FOR THIS PROJECT, AND THE FOLLOWING NOTES AS ALL THESE MATERIALS ARE APPLICABLE TO THIS PROJECT. 3.THE DEVELOPER SHALL IMPLEMENT AND MAINTAIN CONTROL MEASURES FOR ALL POTENTIAL POLLUTANTS FROM THE START OF LAND DISTURBING ACTIVITIES UNTIL FINAL STABILIZATION OF THE CONSTRUCTION SITE. 4.THE CITY EROSION CONTROL INSPECTOR SHALL BE NOTIFIED AT LEAST TWENTY-FOUR (24) HOURS PRIOR TO THE DESIRED START OF ANY CONSTRUCTION ACTIVITIES ON THIS SITE TO ALLOW ADEQUATE TIME FOR ON-SITE CONFIRMATION (INITIAL INSPECTION WHICH CAN TAKE UP TO TWO BUSINESS DAYS AFTER RECEIVING THE REQUEST) THAT THE SITE IS IN FACT PROTECTED FROM SEDIMENT AND POLLUTANTS DISCHARGES OFF SITE. PLEASE CONTACT EROSION@FCGOV.COM EARLY TO SCHEDULE THOSE INITIAL EROSION CONTROL INSPECTIONS WELL IN ADVANCE SO THAT DEMOLITION, CLEARING, GRUBBING, TREE REMOVAL, AND SCRAPING MAY BEGIN WITHOUT DELAY. FAILURE TO RECEIVE AN ON-SITE CONFIRMATION BEFORE CONSTRUCTION ACTIVITIES COMMENCE IS AN AUTOMATIC “NOTICE OF VIOLATION” AND CAN RESULT IN FURTHER ENFORCEMENT ACTIONS. 5.THE DEVELOPER SHALL PROACTIVELY PROVIDE ALL APPROPRIATE CONTROL MEASURES TO PREVENT DAMAGE TO ADJACENT DOWNSTREAM AND LEEWARD PROPERTIES. THIS INCLUDES BUT IS NOT LIMITED TO: TREES, SHRUBS, LAWNS, WALKS, PAVEMENTS, ROADWAYS, STRUCTURES, CREEKS, WETLANDS, STREAMS, RIVERS, AND UTILITIES THAT ARE NOT DESIGNED FOR REMOVAL, RELOCATION, OR REPLACEMENT IN THE COURSE OF CONSTRUCTION. 6.AT ALL TIMES THE DEVELOPER SHALL BE RESPONSIBLE TO ENSURE ADEQUATE CONTROL MEASURES ARE DESIGNED, SELECTED, INSTALLED, MAINTAIN, REPAIRED, REPLACED, AND ULTIMATELY REMOVED IN ORDER TO PREVENT AND CONTROL EROSION SUSPENSION, SEDIMENT TRANSPORTATION, AND POLLUTANT DISCHARGE AS A RESULT OF CONSTRUCTION ACTIVITIES ASSOCIATED WITH THIS PROJECT. 7.ALL APPLICABLE CONTROL MEASURES BASED UPON THE SEQUENCING AND/OR PHASING OF THE PROJECT SHALL BE INSTALLED PRIOR TO THOSE CONSTRUCTION ACTIVITIES COMMENCING. 8.AS DYNAMIC CONDITIONS (DUE TO THE NATURE, TIMING, SEQUENCE, AND PHASING OF CONSTRUCTION) IN THE FIELD MAY WARRANT CONTROL MEASURES IN ADDITION, OR DIFFERENT, TO WHAT IS SHOWN ON THESE PLANS, THE DEVELOPER SHALL AT ALL TIMES BE RESPONSIBLE TO IMPLEMENT THE CONTROL MEASURES THAT ARE MOST EFFECTIVE WITH THE CURRENT STATE AND PROGRESS OF CONSTRUCTION. THE DEVELOPER SHALL IMPLEMENT WHATEVER MEASURES ARE DETERMINED NECESSARY, AND/OR AS DIRECTED BY THE CITY EROSION CONTROL INSPECTOR. THE DEVELOPER SHALL INSURE THAT ALL EROSION CONTROL PLANS (MAPS) OR SWMP DOCUMENTS ARE UPDATED TO REFLECT THE CURRENT SITE CONDITIONS, WITH UPDATES BEING INITIALED AND DATED. THESE SITE INSPECTIONS AND SITE CONDITION UPDATES SHALL BE MADE AVAILABLE UPON REQUEST BY THE CITY. 9.ALL LISTINGS, PROVISIONS, MATERIALS, PROCEDURES, ACTIVITIES, SITE WORK AND THE LIKE ARTICULATED IN THIS OR OTHER WRITTEN SITE-SPECIFIC DOCUMENTS (INCLUDING BUT NOT LIMITED TO THE EROSION CONTROL REPORTS, DEVELOPMENT AGREEMENTS, LANDSCAPE, AND DRAINAGE MATERIALS) SHALL MEET OR EXCEED THE MOST RESTRICTIVE LANGUAGE FOR CITY, COUNTY, STATE, AND FEDERAL REGULATIONS WITH REGARDS TO EROSION, SEDIMENT, POLLUTANT, AND OTHER POLLUTION SOURCE CONTROL MEASURES. THE DEVELOPER SHALL BE RESPONSIBLE TO COMPLY WITH ALL OF THESE AFOREMENTIONED LAWS AND REGULATIONS. 10.THE DEVELOPER SHALL ENSURE THAT ALL APPROPRIATE PERMITS (CDPS GENERAL PERMIT STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY, DEWATERING, CLEAN WATER ACT, ARMY CORPS OF ENGINEERS' 404 WETLANDS MITIGATION PERMIT, ETC.) HAVE BEEN ATTAINED PRIOR TO THE RELEVANT ACTIVITY HAS BEGUN. THESE PERMITS OR COPIES SHALL BE MADE AVAILABLE UPON REQUEST BY THE CITY. 11.THE DEVELOPER SHALL FURNISH ALL CONVENIENCES AND ASSISTANCES TO AID THE EROSION CONTROL INSPECTORS OF MATERIALS, WORKMANSHIP, RECORDS, AND SELF-INSPECTIONS, ETC. OF THE CONTROL MEASURES INVOLVED IN THE CONSTRUCTION ACTIVITIES. 12.THE DEVELOPER SHALL REQUEST CLARIFICATION OF ALL APPARENT SITE CONSTRUCTION ISSUES THAT MAY ARISE DUE TO INCONSISTENCIES IN CONSTRUCTION PLANS FOR THE SITE OR SITE CONDITIONS AROUND THE SELECTED CONTROL MEASURES BY CONTACTING THE EROSION CONTROL INSPECTOR. THE EROSION CONTROL INSPECTOR WILL NOT BE RESPONSIBLE FOR ANY EXPLANATIONS, INTERPRETATIONS, OR SUPPLEMENTARY DATA PROVIDED BY OTHERS. 13.ALL CONTROL MEASURES SHALL BE INSTALLED IN ACCORDANCE WITH THE MANUAL. 14.THE CITY RESERVES THE RIGHT TO REQUIRE ADDITIONAL CONTROL MEASURES AS SITE CONDITIONS WARRANT, TO THE EXTENT AUTHORIZED BY RELEVANT LEGAL AUTHORITY. 15.AS WITH ANY CONSTRUCTION STANDARDS, OCCASIONS MAY ARISE WHERE THE MINIMUM EROSION CONTROL STANDARDS ARE EITHER INAPPROPRIATE OR CANNOT BE JUSTIFIED. IN THESE CASES, A VARIANCE TO THESE STANDARDS MAY BE APPLIED FOR PURSUANT TO THE TERMS, CONDITIONS, AND PROCEDURES OF THE MANUAL. 16.INSPECTION. THE CONTRACTOR SHALL INSPECT SITE POLLUTANT SOURCES AND IMPLEMENT CONTROL MEASURES AT A MINIMUM OF ONCE EVERY TWO WEEKS DURING CONSTRUCTION AND WITHIN 24 HOURS FOLLOWING A PRECIPITATION EVENT. DOCUMENTATION OF EACH INSPECTION SHALL BE RECORDED AND RETAINED BY THE CONTRACTOR. 17.ALL TEMPORARY CONTROL MEASURES SHALL BE CLEANED, REPAIRED, OR RECONSTRUCTED AS NECESSARY IN ORDER TO ASSURE CONTINUAL PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGE WAY. 18.ANY CONTROL MEASURE MAY BE SUBSTITUTED FOR ANOTHER STANDARD CONTROL MEASURE SO LONG AS THAT CONTROL MEASURE IS EQUAL TO, OR OF GREATER PROTECTION THAN THE ORIGINAL CONTROL MEASURE THAT WAS TO BE USED IN THAT LOCATION. (EX. SILT FENCE, FOR WATTLES, OR FOR COMPACT BERMS) WATTLE ALONE ON COMMERCIAL CONSTRUCTION SITES HAVE SHOWN TO BE AN INEFFECTIVE SUBSTITUTE FOR SILT FENCE OR COMPACT BERMS UNLESS IT IS ACCOMPANIED BY A CONSTRUCTION FENCE TO PREVENT VEHICLE TRAFFIC. 19.ANY IMPLEMENTATION OR REPLACEMENT OF EXISTING CONTROL MEASURES FOR A NON-STANDARD CONTROL, OR ALTERNATIVE CONTROL MEASURE, SHALL REQUIRE THE REVIEW AND ACCEPTANCE BY THE CITY EROSION CONTROL STAFF BEFORE THE MEASURE WILL BE ALLOWED TO BE USED ON THIS PROJECT. THESE CONTROL MEASURES' DETAILS SHALL BE SUBMITTED, REVIEWED AND ACCEPTED TO BE IN ACCORDANCE WITH THE EROSION CONTROL CRITERIA BASED UPON THE FUNCTIONALITY AND EFFECTIVENESS IN ACCORDANCE WITH SOUND ENGINEERING AND HYDROLOGICAL PRACTICES LAND DISTURBANCE, STOCKPILES, AND STORAGE OF SOILS 20.THERE SHALL BE NO EARTH-DISTURBING ACTIVITY OUTSIDE THE LIMITS DESIGNATED ON THE ACCEPTED PLANS. OFF ROAD STAGING AREAS OR STOCKPILES MUST BE PREAPPROVED BY THE CITY. DISTURBANCES BEYOND THESE LIMITS WILL BE RESTORED TO ORIGINAL CONDITION. 21.PRE-DISTURBANCE VEGETATION SHALL BE IDENTIFIED, PROTECTED, AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. THIS SHOULD INCLUDE SEQUENCING AND PHASING CONSTRUCTION ACTIVITIES IN A WAY SO THAT THE SOIL IS NOT EXPOSED FOR LONG PERIODS OF TIME BY SCHEDULE OR LIMIT GRADING TO SMALL AREAS. THIS SHOULD ALSO INCLUDE WHEN PRACTICAL ADVANCING THE SCHEDULE ON STABILIZATION ACTIVITIES SUCH THAT LANDSCAPING TAKES PLACE SHORTLY IF NOT IMMEDIATELY AFTER GRADING HAS OCCURRED. VEGETATION EFFORTS SHALL START AS SOON AS POSSIBLE TO RETURN THE SITE TO A STABILIZED CONDITION. SENSITIVE AREAS SHOULD AVOID CLEARING AND GRADING ACTIVITIES AS MUCH POSSIBLE. 22.ALL EXPOSED SOILS OR DISTURBED AREAS ARE CONSIDERED A POTENTIAL POLLUTANT AND SHALL HAVE CONTROL MEASURES IMPLEMENTED ON THE SITE TO PREVENT MATERIALS FROM LEAVING THE SITE. 23.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION AT ALL TIMES BY EQUIPMENT TRACKING, SCARIFYING OR DISKING THE SURFACE ON A CONTOUR WITH A 2 TO 4 INCH MINIMUM VARIATION IN SOIL SURFACE UNTIL MULCH, VEGETATION, AND/OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. 24.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT THROUGH THE USE OF SURFACE ROUGHENING, WATERING, AND DOWN GRADIENT PERIMETER CONTROLS. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY WIND IN ACCORDANCE WITH MUNICIPAL CODE §12-150. ALL STOCKPILES SHALL BE FLATTENED TO MEET GRADE OR REMOVED FROM SITE AS SOON AS PRACTICAL, AND NO LATER THAN THE COMPLETION OF CONSTRUCTION ACTIVITIES OR ABANDONMENT OF THE PROJECT. ALL OFF-SITE STOCKPILE STORAGE LOCATIONS IN CITY LIMITS SHALL HAVE A STOCKPILE PERMIT FROM THE CITY ENGINEERING DEPARTMENT PRIOR TO USING THE AREA TO STORE MATERIAL. IF FREQUENT ACCESS FROM HARDSCAPE TO THE STOCKPILE IS NEEDED A STRUCTURAL TRACKING CONTROL MEASURE SHALL BE IMPLEMENTED. 25.ALL REQUIRED CONTROL MEASURES SHALL BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING, GRADING, ETC.). ALL OF THE REQUIRED EROSION CONTROL MEASURES MUST BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT. 26.ALL INLETS, CURB-CUTS, CULVERTS, AND OTHER STORM SEWER INFRASTRUCTURE WHICH COULD BE POTENTIALLY IMPACTED BY CONSTRUCTION ACTIVITIES SHALL BE PROTECTED WITH CONTROL MEASURES. MATERIAL ACCUMULATED FROM THIS CONTROL MEASURE SHALL BE PROMPTLY REMOVED AND IN CASES WHERE THE PROTECTION HAS FAILED, THE PIPES SHALL BE THOROUGHLY CLEANED OUT. 27.ALL STREAMS, STREAM CORRIDORS, BUFFERS, WOODLANDS, WETLANDS, OR OTHER SENSITIVE AREAS SHALL BE PROTECTED FROM IMPACT BY ANY CONSTRUCTION ACTIVITY THROUGH THE USE OF CONTROL MEASURES. 28.ALL EXPOSED DIRT SHALL HAVE PERIMETER CONTROL. ANY PERIMETER CONTROLS THAT DRAIN OFF OR HAS THE ABILITY TO BE TRACKED ONTO THE NEARBY HARDSCAPE SHALL HAVE SOME FORM OF EFFECTIVE SEDIMENT CONTROL AS THE, OR AS PART OF THE, PERIMETER CONTROL. 29.ALL EXPOSED SLOPES SHOULD BE PROTECTED. ALL EXPOSED STEEP SLOPES (STEEPER THAN 3:1 H:V) SHALL BE PROTECTED FROM EROSION AND SEDIMENT TRANSPORT THROUGH USE OF CONTROL MEASURES. 30.NO SOILS SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS AFTER ACTIVITY HAS CEASED BEFORE REQUIRED TEMPORARY SEEDING OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED. THIS IS NOT JUST LIMITED TO PROJECTS THAT ARE ABANDONED; THIS INCLUDES ANY PROJECT THAT IS TEMPORARILY HALTED AND NO IMMEDIATE ACTIVITY IS TO RESUME WITHIN THE NEXT THIRTY (30) DAYS, UNLESS OTHERWISE APPROVED BY THE CITY EROSION CONTROL INSPECTOR. DURING A SEASON WHEN SEEDING DOES NOT PRODUCE VEGETATIVE COVER, ANOTHER TEMPORARY EROSION CONTROL SHALL BE IMPLEMENTED WITH OR UNTIL TEMPORARY SEEDING OR PERMANENT EROSION CONTROL CAN BE PERFORMED. 31.ALL INDIVIDUAL LOTS SHALL HAVE EFFECTIVE SEDIMENT CONTROLS LOCATED ON THE STREET SIDE AND ANY DOWN GRADIENT SIDE. TYPICALLY MOST LOTS DRAIN TO THE FRONT YET ON THOSE CASES WHERE HOUSES ARE ALONG A POND OR DRAINAGE SWALE HAVE THE LOT DRAIN IN A DIFFERENT DIRECTION THAN THE STREET, THOSE INDIVIDUAL LOTS WILL NEED PROTECTION ON THAT DOWN GRADIENT SIDE TO PREVENT SEDIMENT FROM LEAVING THE LOT. SEE THE INDIVIDUAL LOT DETAILS FOR FURTHER CLARIFICATION. VEHICLE TRACKING 32.AT ALL POINTS WHERE VEHICLES EXIT OR LEAVE THE EXPOSED DIRT AREA ON TO A HARDSCAPE OR SEMI HARDSCAPE (CONCRETE, ASPHALT, ROAD BASE, ETC.) SHALL HAVE INSTALLED AT LEAST ONE STRUCTURAL TRACKING CONTROL MEASURE TO PREVENT VEHICLE TRACKING. ALL AREAS NOT PROTECTED BY AN ADEQUATE PERIMETER CONTROL SHALL BE CONSIDERED A POINT WHERE VEHICLES EXIT THE SITE. ACCESS POINTS SHOULD BE LIMITED TO AS FEW ENTRANCES AS POSSIBLE (ALL PERIMETER AREAS SHALL BE PROTECTED FROM TRACKING ACTIVITIES). 33.IN ALL AREAS THAT THE STRUCTURAL TRACKING CONTROL MEASURES FAIL TO PREVENT VEHICLE TRACKING, COLLECTION AND PROPER DISPOSAL OF THAT MATERIAL IS REQUIRED. ALL INLETS LOCATED NEAR ACCESS POINTS AND AFFECTED BY TRACKING ACTIVITIES SHALL BE PREVENTED FROM THE INTRODUCTION OF SEDIMENT INTO THE DRAINAGE SYSTEM. 34.CITY MUNICIPAL CODE §20-62, AMONG OTHER THINGS, PROHIBITS THE TRACKING, DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY SOURCE. CITY MUNICIPAL CODE, §26-498, AMONG OTHER THINGS, PROHIBITS THE DISCHARGE OF POLLUTANTS ON PUBLIC OR PRIVATE PROPERTY IF THERE IS A SIGNIFICANT POTENTIAL FOR MIGRATION OF SUCH POLLUTANT. THEREFORE, ALL TRACKED OR DEPOSITED MATERIALS (INTENTIONAL OR INADVERTENT) ARE NOT PERMITTED TO REMAIN ON THE STREET OR GUTTER AND SHALL BE REMOVED AND LEGALLY DISPOSED OF BY THE DEVELOPER IN A TIMELY AND IMMEDIATE MANNER. DIRT RAMPS INSTALLED IN THE CURB-LINES ARE NOT EXEMPT TO THESE SECTIONS OF CODE AND SHALL NOT BE PERMITTED IN THE STREET RIGHT OF WAY (PUBLIC OR PRIVATE). 35.IF REPEATED DEPOSIT OF MATERIAL OCCURS ON A SITE, ADDITIONAL STRUCTURAL TRACKING CONTROLS MAY BE REQUIRED OF THE DEVELOPER BY THE CITY EROSION CONTROL INSPECTOR. LOADING AND UNLOADING OPERATIONS 36.THE DEVELOPER SHALL APPLY CONTROL MEASURE TO LIMIT TRAFFIC (SITE WORKER OR PUBLIC) IMPACTS AND PROACTIVELY LOCATE MATERIAL DELIVERED TO THE SITE IN CLOSE PROXIMITY TO THE WORK AREA OR IMMEDIATELY INCORPORATED IN THE CONSTRUCTION TO LIMIT OPERATIONAL IMPACTS TO DISTURBED AREAS, VEHICLE TRACKING, AND SEDIMENT DEPOSITION THAT COULD IMPACT WATER QUALITY. OUTDOOR STORAGE OR CONSTRUCTION SITE MATERIALS, BUILDING MATERIALS, FERTILIZERS, AND CHEMICALS 37.ANY MATERIALS OF A NON-POLLUTING NATURE (STEEL, ROCK, BRICK, LUMBER, ETC.) SHALL BE INSPECTED FOR ANY RESIDUE COMING OFF THE MATERIAL DURING ROUTINE INSPECTION AND WILL GENERALLY BE LOCATED WHERE PRACTICAL AT LEAST FIFTY (50) FEET FROM ANY PERMANENT OR INTERIM DRAINAGE WAYS. 38.ANY HIGH ENVIRONMENTAL IMPACT POLLUTANT MATERIALS THAT HAVE A HIGH LIKELIHOOD TO RESULT IN DISCHARGE WHEN IN CONTACT WITH STORMWATER (LUBRICANTS, FUELS, PAINTS, SOLVENTS, DETERGENTS, FERTILIZERS, CHEMICAL SPRAYS, BAGS OF CEMENT MIX, ETC.) SHOULD NOT BE KEPT ON SITE WHERE PRACTICAL. WHEN NOT PRACTICAL, THEY SHOULD BE STORED INSIDE (VEHICLE, TRAILER, CONNEX, BUILDING, ETC.) AND OUT OF CONTACT WITH STORMWATER OR STORMWATER RUNOFF. WHERE NOT AVAILABLE, THEY SHALL BE STORED OUTSIDE IN A RAISED (HIGH SPOTS OR ON PALLETS), COVERED (PLASTIC OR TARPED), AND SEALED (LEAK PROOF CONTAINER) IN SECONDARY CONTAINMENT LOCATION. THE SECONDARY CONTAINMENT OR OTHER CONTROL MEASURE SHALL BE ADEQUATELY SIZED, LOCATED, WHERE PRACTICAL, AT LEAST FIFTY (50) FEET FROM ANY PERMANENT OR INTERIM STORMWATER STRUCTURES OR DRAINAGE WAYS AND SHALL BE MONITORED AS PART OF THE ROUTINE INSPECTIONS. VEHICLE AND EQUIPMENT MAINTENANCE AND FUELING 39.PARKING, REFUELING, AND MAINTENANCE OF VEHICLES AND EQUIPMENT SHOULD BE LIMITED IN ONE AREA OF THE SITE TO MINIMIZE POSSIBLE SPILLS AND FUEL STORAGE AREAS. THIS AREA SHALL BE LOCATED, WHERE PRACTICAL, AT LEAST FIFTY (50) FEET FROM ANY PERMANENT OR INTERIM STORMWATER STRUCTURES OR DRAINAGE WAYS AND SHALL BE MONITORED AS PART OF THE ROUTINE INSPECTIONS. ALL AREAS SHALL KEEP SPILL KITS AND SUPPLIES CLOSE. SIGNIFICANT DUST OR PARTICULATE GENERATING PROCESS 40.THE PROPERTY MUST BE ACTIVELY PREVENTING THE EMISSION OF FUGITIVE DUST AT ALL TIMES DURING CONSTRUCTION AND VEGETATION ACTIVITIES. ALL LAND DISTURBING ACTIVITIES THAT RESULT IN FUGITIVE DUST SHALL BE IN ACCORDANCE WITH MUNICIPAL CODE §12-150 TO REDUCE THE IMPACTS TO ADJACENT PROPERTIES AND COMMUNITY HEALTH. ALL REQUIRED PRACTICES SHALL BE IMPLEMENTED AND ADDITIONAL ONES SHALL BE FOLLOWED. THESE PRACTICES INCLUDE WATERING THE SITES AND DISCONTINUING CONSTRUCTION ACTIVITIES UNTIL THE WIND SUBSIDES AS DETERMINED BY ANY CITY INSPECTORS. CONCRETE TRUCK / EQUIPMENT WASHING, INCLUDING THE CONCRETE TRUCK CHUTE AND ASSOCIATED FIXTURES AND EQUIPMENT 41.ALL CONCRETE AND EQUIPMENT WASHING SHALL USE STRUCTURAL CONTROL MEASURES APPROPRIATE TO THE VOLUME OF WASH AND FREQUENCY OF USE. THESE CONTROL MEASURES SHALL BE LOCATED, WHERE PRACTICAL, AT LEAST FIFTY (50) FEET FROM ANY PERMANENT OR INTERIM STORMWATER STRUCTURES OR DRAINAGE WAYS AND SHALL BE MONITORED AS PART OF THE ROUTINE INSPECTIONS. THESE AREAS SHALL BE CLEARLY IDENTIFIED AND PROTECTED FROM ANY WASH FROM LEAVING THE CONTROL MEASURE. IF FREQUENT ACCESS FROM HARDSCAPE TO THE CONTROL MEASURE IS TO OCCUR, A STRUCTURAL TRACKING CONTROL MEASURE SHALL BE IMPLEMENTED. THESE CONTROL MEASURES SHALL BE FREQUENTLY CLEANED OUT. 42.THE DEVELOPER IS RESPONSIBLE FOR ENSURING WASHING ACTIVITY IS TAKING PLACE AT THE APPROPRIATE CONTROL MEASURE AND SITE WORKERS ARE NOT WASHING OR DUMPING WASH WATER ON TO THE DIRT OR OTHER UNCONTROLLED LOCATIONS. DEDICATED ASPHALT AND CONCRETE BATCH PLANTS 43.DEDICATED ASPHALT AND CONCRETE BATCH PLANTS ARE NOT ACCEPTABLE ON CONSTRUCTION SITES WITHIN THE CITY OF FORT COLLINS WITHOUT AN EXPRESSED WRITTEN REQUEST AND PLAN TO REDUCE POLLUTANTS ASSOCIATED WITH THAT TYPE OF ACTIVITY AND APPROVAL BY THE CITY OF FORT COLLINS SPECIFICALLY THE EROSION CONTROL INSPECTOR. THE DEVELOPER SHALL INFORM THE EROSION CONTROL INSPECTION STAFF OF ANY DEDICATED ASPHALT, OR CONCRETE BATCH PLANTS THAT IS TO BE USED ON SITE. CONCRETE SAW CUTTING MATERIALS 44.SAW CUTTING MATERIAL SHALL BE IN ACCORDANCE WITH MUNICIPAL CODE §12-150 FOR AIR EMISSIONS AND ALL WATER APPLICATIONS TO THE SAW CUTTING SHALL PREVENT MATERIAL FROM LEAVING THE IMMEDIATE SITE AND COLLECTED. THESE CUTTING LOCATIONS, ONCE DRIED, SHALL BE SWEPT AND SCRAPED OF ALL MATERIAL AND SHALL HAVE PROPER AND LEGAL DISPOSAL. WASTE MATERIALS STORAGE AND SANITARY FACILITIES 45.TRASH, DEBRIS, MATERIAL SALVAGE, AND/OR RECYCLING AREAS SHALL BE, WHERE PRACTICAL, AT LEAST FIFTY FEET FROM ANY PERMANENT OR INTERIM STORMWATER STRUCTURES OR DRAINAGE WAYS AND SHALL BE MONITORED AS PART OF THE ROUTINE INSPECTIONS. THESE FACILITIES SHOULD BE LOCATED OUT OF THE WIND AND COVERED AS ABLE. WHERE NOT ABLE TO COVER, LOCATING SAID AREAS ON THE SIDE OF OTHER STRUCTURES TO REDUCE EXPOSURE TO WINDS, AND FOLLOW MAXIMUM LOADING GUIDELINES AS MARKED ON THE CONTAINER. THE DEVELOPER IS REQUIRED TO PRACTICE GOOD HOUSEKEEPING TO KEEP THE CONSTRUCTION SITE FREE OF LITTER, CONSTRUCTION DEBRIS, AND LEAKING CONTAINERS. 46.SANITARY FACILITIES SHALL BE PREVENTED FROM TIPPING THROUGH THE USE OF ANCHORING TO THE GROUND OR LASHING TO A STABILIZED STRUCTURE. THESE FACILITIES SHALL ALSO BE LOCATED AS FAR AS PRACTICAL FROM AN INLET, CURB CUT, DRAINAGE SWALE OR OTHER DRAINAGE CONVEYANCES TO PREVENT MATERIAL TRANSPORT FROM LEAVING THE LOCAL AREA. THIS CONSISTS OF THE FACILITY BEING LOCATED, WHERE PRACTICAL, AT LEAST FIFTY (50) FEET FROM ANY PERMANENT OR INTERIM DRAINAGE WAYS. OTHER SITE OPERATIONS AND POTENTIAL SPILL AREAS 47.SPILLS: FOR THOSE MINOR SPILLS THAT; ARE LESS THAN THE STATE'S REPORTABLE QUANTITY FOR SPILLS, STAY WITHIN THE PERMITTED AREA, AND IN NO WAY THREATEN ANY STORMWATER CONVEYANCE, NOTIFY THE CITY OF FORT COLLINS UTILITIES BY EMAIL AT EROSION@FCGOV.COM OR PHONE (970) 817-4770. FOR ANY SIGNIFICANT, MAJOR, OR HAZARDOUS SPILLS, NOTIFY THE CITY OF FORT COLLINS UTILITIES BY PHONE ONLY AFTER EMERGENCY RESPONSE (911) HAS BEEN NOTIFIED AND IS ON ROUTE, COUNTY HEALTH DEPARTMENT (LCDHE) HAS BEEN NOTIFIED THROUGH LARIMER COUNTY SHERIFF DISPATCH (970) 416-1985, AND THE STATE SPILL HOTLINE INCIDENT REPORTING HAVE BEEN CONTACTED 1-877-518-5608. WRITTEN DOCUMENTATION SHALL BE PROVIDED TO THE CITY WITHIN 5 DAYS OF THE EVENT. ALL SPILLS SHALL BE CLEANED UP IMMEDIATELY. 48.SELECTION OF “PLASTIC WELDED” EROSION CONTROL BLANKETS SHALL NOT BE USED IN AREAS THAT WILDLIFE, SUCH AS SNAKES, ARE LIKELY TO BE LOCATED AS THESE HAVE PROVEN TO CAUSE ENTRAPMENT ISSUES. FINAL STABILIZATION AND PROJECT COMPLETION 49.ANY STORMWATER FACILITIES USED AS A TEMPORARY CONTROL MEASURE WILL BE RESTORED AND STORM SEWER LINES WILL BE CLEANED UPON COMPLETION OF THE PROJECT AND BEFORE TURNING THE MAINTENANCE OVER TO THE OWNER, HOMEOWNERS ASSOCIATION (HOA), OR OTHER PARTY RESPONSIBLE FOR LONG TERM MAINTENANCE OF THOSE FACILITY. 50.ALL FINAL STABILIZATION SPECIFICATIONS SHALL BE DONE IN ACCORDANCE WITH THE MANUAL, CHAPTER 4: CONSTRUCTION CONTROL MEASURES. 51.ALL DISTURBED AREAS DESIGNED TO BE VEGETATED SHALL BE AMENDED, SEEDED & MULCHED, OR LANDSCAPED AS SPECIFIED IN THE LANDSCAPE PLANS WITHIN 14 WORKING DAYS OF FINAL GRADING. 52.SOIL IN ALL VEGETATED (LANDSCAPED OR SEEDED) AREAS, INCLUDING PARKWAYS AND MEDIANS SHALL COMPLY WITH ALL REQUIREMENTS SET FORTH IN SECTIONS 12-130 THROUGH 12-132 OF THE CITY MUNICIPAL CODE, AS WELL AS SECTION 3.8.21 FOR THE CITY LAND USE CODE. 53.ALL SEEDING SHALL REFER TO LANDSCAPING PLANS FOR SPECIES MIXTURE AND APPLICATION RATES AND DEPTHS REQUIREMENTS. 54.ALL SEED SHALL BE DRILLED WHERE PRACTICAL TO A DEPTH BASED UPON THE SEED TYPE. BROADCAST SEEDING SHALL BE APPLIED AT DOUBLE THE RATE AS PRESCRIBED FOR DRILL SEEDING AND SHALL BE LIGHTLY HAND RAKED AFTER APPLICATION. HYDROSEEDING MAY BE SUBSTITUTED FOR DRILL SEEDING ON SLOPES STEEPER THAN 3(H):1(V) OR ON OTHER AREAS NOT PRACTICAL TO DRILL SEED AND CRIMP AND MULCH. ALL HYDROSEEDING MUST BE CONDUCTED AS TWO SEPARATE PROCESSES OF SEEDING AND TACKIFICATION. 55.ALL SEEDED AREAS MUST BE MULCHED WITHIN TWENTY-FOUR (24) AFTER PLANTING. ALL MULCH SHALL BE MECHANICALLY CRIMPED AND OR ADEQUATELY APPLIED TACKIFIER. THE USE OF CRIMPED MULCH OR TACKIFIER MAY REQUIRE MULTIPLE RE-APPLICATIONS IF NOT PROPERLY INSTALLED OR HAVE WEATHERED OR DEGRADED BEFORE VEGETATION HAS BEEN ESTABLISHED. AREAS OF EMBANKMENTS HAVING SLOPES GREATER THAN OR EQUAL TO 3H:1V SHALL BE STABILIZED WITH AN EROSION MAT OR APPROVED EQUAL TO ENSURE SEED WILL BE ABLE TO GERMINATE ON THE STEEP SLOPES. DURING A SEASON WHEN SEEDING DOES NOT PRODUCE VEGETATIVE COVER, ANOTHER TEMPORARY EROSION CONTROL SHALL BE IMPLEMENTED ALONG WITH, OR UNTIL, TEMPORARY SEEDING OR PERMANENT EROSION CONTROL CAN BE PERFORMED. 56.THE DEVELOPER SHALL WARRANTY AND MAINTAIN ALL VEGETATIVE MEASURES FOR TWO GROWING SEASONS AFTER INSTALLATION OR UNTIL SEVENTY PERCENT (70%) VEGETATIVE COVER HAS BEEN ESTABLISHED, WHICHEVER IS LONGER AND MEETS ALL THE CRITERIA OUTLINED IN THE FORT COLLINS STORMWATER CRITERIA MANUAL CHAPTER 4: CONSTRUCTION CONTROL MEASURES. 57.THE DEVELOPER SHALL MAINTAIN, MONITOR, REPAIR, AND REPLACE ANY AND ALL APPLICABLE CONTROL MEASURES UNTIL FINAL STABILIZATION HAS BEEN OBTAINED. ALL CONTROL MEASURES MUST REMAIN UNTIL SUCH TIME AS ALL UPSTREAM CONTRIBUTING POLLUTANT SOURCES HAVE BEEN VEGETATED OR REMOVED FROM THE SITE. WHEN ANY CONTROL MEASURE IS REMOVED, THE DEVELOPER SHALL BE RESPONSIBLE FOR THE CLEANUP AND REMOVAL OF ALL SEDIMENT AND DEBRIS FROM THAT CONTROL MEASURE. AT THE POINT AT WHICH THE SITE HAS BEEN DEEMED STABILIZED AND VERIFIED BY CITY EROSION CONTROL INSPECTOR, ALL TEMPORARY CONTROL MEASURES CAN THEN BE FULLY REMOVED. ALL MEASURES SHALL BE REMOVED WITHIN 30 DAYS AFTER FINAL STABILIZATION IS ACHIEVED. 58.THE RESPONSIBLE PARTY SHALL MAINTAIN AND KEEP CURRENT ALL PAYMENTS OR RELATED FORMS OF SECURITY FOR THE EROSION CONTROL ESCROW UNTIL 1) STABILIZATION HAS BEEN REACHED AND 2) ALL CONTROL MEASURES AND/OR BMPS HAVE SEDIMENT MATERIALS COLLECTED AND THE CONTROL MEASURE REMOVED FROM THE SITE. AT THAT TIME THE SITE WILL BE CONSIDERED COMPLETED AND ANY REMAINING EROSION CONTROL ESCROW SHALL BE RETURNED TO THE APPROPRIATE PARTIES. B.STREET IMPROVEMENT NOTES 1.ALL STREET CONSTRUCTION IS SUBJECT TO THE GENERAL NOTES ON THE COVER SHEET OF THESE PLANS AS WELL AS THE STREET IMPROVEMENTS NOTES LISTED HERE. 2.A PAVING SECTION DESIGN, SIGNED AND STAMPED BY A COLORADO LICENSED ENGINEER, MUST BE SUBMITTED TO THE LOCAL ENTITY ENGINEER FOR APPROVAL, PRIOR TO ANY STREET CONSTRUCTION ACTIVITY, (FULL DEPTH ASPHALT SECTIONS ARE NOT PERMITTED AT A DEPTH GREATER THAN 8 INCHES OF ASPHALT). THE JOB MIX SHALL BE SUBMITTED FOR APPROVAL PRIOR TO PLACEMENT OF ANY ASPHALT. 3.WHERE PROPOSED PAVING ADJOINS EXISTING ASPHALT, THE EXISTING ASPHALT SHALL BE SAW CUT, A MINIMUM DISTANCE OF 12 INCHES FROM THE EXISTING EDGE, TO CREATE A CLEAN CONSTRUCTION JOINT. THE DEVELOPER SHALL BE REQUIRED TO REMOVE EXISTING PAVEMENT TO A DISTANCE WHERE A CLEAN CONSTRUCTION JOINT CAN BE MADE. WHEEL CUTS SHALL NOT BE ALLOWED UNLESS APPROVED BY THE LOCAL ENTITY ENGINEER. 4.STREET SUBGRADES SHALL BE SCARIFIED THE TOP 12 INCHES AND RE-COMPACTED PRIOR TO SUBBASE INSTALLATION. NO BASE MATERIAL SHALL BE LAID UNTIL THE SUBGRADE HAS BEEN INSPECTED AND APPROVED BY THE LOCAL ENTITY ENGINEER. 5.FT. COLLINS ONLY. VALVE BOXES AND MANHOLES ARE TO BE BROUGHT UP TO GRADE AT THE TIME OF PAVEMENT PLACEMENT OR OVERLAY. VALVE BOX ADJUSTING RINGS ARE NOT ALLOWED. 6.WHEN AN EXISTING ASPHALT STREET MUST BE CUT, THE STREET MUST BE RESTORED TO A CONDITION EQUAL TO OR BETTER THAN ITS ORIGINAL CONDITION. THE EXISTING STREET CONDITION SHALL BE DOCUMENTED BY THE INSPECTOR BEFORE ANY CUTS ARE MADE. CUTTING AND PATCHING SHALL BE DONE IN CONFORMANCE WITH CHAPTER 25, RECONSTRUCTION AND REPAIR. THE FINISHED PATCH SHALL BLEND SMOOTHLY INTO THE EXISTING SURFACE. THE DETERMINATION OF NEED FOR A COMPLETE OVERLAY SHALL BE MADE BY THE LOCAL ENTITY ENGINEER. ALL OVERLAY WORK SHALL BE COORDINATED WITH ADJACENT LANDOWNERS SUCH THAT FUTURE PROJECTS DO NOT CUT THE NEW ASPHALT OVERLAY WORK. 7.ALL TRAFFIC CONTROL DEVICES SHALL BE IN CONFORMANCE WITH THESE PLANS OR AS OTHERWISE SPECIFIED IN M.U.T.C.D. (INCLUDING COLORADO SUPPLEMENT) AND AS PER THE RIGHT-OF-WAY WORK PERMIT TRAFFIC CONTROL PLAN. 8.THE DEVELOPER IS REQUIRED TO PERFORM A GUTTER WATER FLOW TEST IN THE PRESENCE OF THE LOCAL ENTITY INSPECTOR AND PRIOR TO INSTALLATION OF ASPHALT. GUTTERS THAT HOLD MORE THAN ¼ INCH DEEP OR 5 FEET LONGITUDINALLY, OF WATER, SHALL BE COMPLETELY REMOVED AND RECONSTRUCTED TO DRAIN PROPERLY. 9.PRIOR TO PLACEMENT OF H.B.P. OR CONCRETE WITHIN THE STREET AND AFTER MOISTURE/DENSITY TESTS HAVE BEEN TAKEN ON THE SUBGRADE MATERIAL (WHEN A FULL DEPTH SECTION IS PROPOSED) OR ON THE SUBGRADE AND BASE MATERIAL (WHEN A COMPOSITE SECTION IS PROPOSED), A MECHANICAL "PROOF ROLL" WILL BE REQUIRED. THE ENTIRE SUBGRADE AND/OR BASE MATERIAL SHALL BE ROLLED WITH A HEAVILY LOADED VEHICLE HAVING A TOTAL GVW OF NOT LESS THAN 50,000 LBS. AND A SINGLE AXLE WEIGHT OF AT LEAST 18,000 LBS. WITH PNEUMATIC TIRES INFLATED TO NOT LESS THAT 90 P.S.I.G. “PROOF ROLL” VEHICLES SHALL NOT TRAVEL AT SPEEDS GREATER THAN 3 M.P.H. ANY PORTION OF THE SUBGRADE OR BASE MATERIAL WHICH EXHIBITS EXCESSIVE PUMPING OR DEFORMATION, AS DETERMINED BY THE LOCAL ENTITY ENGINEER, SHALL BE REWORKED, REPLACED OR OTHERWISE MODIFIED TO FORM A SMOOTH, NON-YIELDING SURFACE. THE LOCAL ENTITY ENGINEER SHALL BE NOTIFIED AT LEAST 24 HOURS PRIOR TO THE “PROOF ROLL.” ALL “PROOF ROLLS” SHALL BE PREFORMED IN THE PRESENCE OF AN INSPECTOR. C.TRAFFIC SIGNING AND PAVEMENT MARKING CONSTRUCTION NOTES 1.ALL SIGNAGE AND MARKING IS SUBJECT TO THE GENERAL NOTES ON THE COVER SHEET OF THESE PLANS, AS WELL AS THE TRAFFIC SIGNING AND MARKING CONSTRUCTION NOTES LISTED HERE. 2.ALL SYMBOLS, INCLUDING ARROWS, ONLYS, CROSSWALKS, STOP BARS, ETC. SHALL BE PRE-FORMED THERMO-PLASTIC. 3.ALL SIGNAGE SHALL BE PER LOCAL ENTITY STANDARDS AND THESE PLANS OR AS OTHERWISE SPECIFIED IN MUTCD. 4.ALL LANE LINES FOR ASPHALT PAVEMENT SHALL RECEIVE TWO COATS OF LATEX PAINT WITH GLASS BEADS. 5.ALL LANE LINES SHALL BE LATEX PAINT. 6.PRIOR TO PERMANENT INSTALLATION OF TRAFFIC STRIPING AND SYMBOLS, THE DEVELOPER SHALL PLACE TEMPORARY TABS OR TAPE DEPICTING ALIGNMENT AND PLACEMENT OF THE SAME. THEIR PLACEMENT SHALL BE APPROVED BY THE LOCAL TRAFFIC ENGINEER PRIOR TO PERMANENT INSTALLATION OF STRIPING AND SYMBOLS. 7.PRE-FORMED THERMO-PLASTIC APPLICATIONS SHALL BE AS SPECIFIED IN THESE PLANS AND/OR THESE STANDARDS. 8.LATEX PAINT APPLICATIONS SHALL BE APPLIED AS SPECIFIED IN CDOT STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION. 9.ALL SURFACES SHALL BE THOROUGHLY CLEANED PRIOR TO INSTALLATION OF STRIPING OR MARKINGS. 10.ALL SIGN POSTS SHALL UTILIZE BREAK-AWAY ASSEMBLIES AND FASTENERS PER THE STANDARDS. 11.A FIELD INSPECTION OF LOCATION AND INSTALLATION OF ALL SIGNS SHALL BE PERFORMED BY THE LOCAL ENTITY ENGINEER. ALL DISCREPANCIES IDENTIFIED DURING THE FIELD INSPECTION MUST BE CORRECTED BEFORE THE 2-YEAR WARRANTY PERIOD WILL BEGIN. 12.THE DEVELOPER INSTALLING SIGNS SHALL BE RESPONSIBLE FOR LOCATING AND PROTECTING ALL UNDERGROUND UTILITIES. 13.SPECIAL CARE SHALL BE TAKEN IN SIGN LOCATION TO ENSURE AN UNOBSTRUCTED VIEW OF EACH SIGN. 14.SIGNAGE AND STRIPING HAS BEEN DETERMINED BY INFORMATION AVAILABLE AT THE TIME OF REVIEW. PRIOR TO INITIATION OF THE WARRANTY PERIOD, THE LOCAL ENTITY ENGINEER RESERVES THE RIGHT TO REQUIRE ADDITIONAL SIGNAGE AND/OR STRIPING IF THE LOCAL ENTITY ENGINEER DETERMINES THAT AN UNFORESEEN CONDITION WARRANTS SUCH SIGNAGE ACCORDING TO THE MUTCD OR THE CDOT M AND S STANDARDS. ALL SIGNAGE AND STRIPING SHALL FALL UNDER THE REQUIREMENTS OF THE 2-YEAR WARRANTY PERIOD FOR NEW CONSTRUCTION (EXCEPT FAIR WEAR ON TRAFFIC MARKINGS). 15.SLEEVES FOR SIGN POSTS SHALL BE REQUIRED FOR USE IN ISLANDS/MEDIANS. REFER TO CHAPTER 14, TRAFFIC CONTROL DEVICES, FOR ADDITIONAL DETAIL. 16.CONTRACTOR IS RESPONSIBLE FOR REMOVING ALL ANCHORS, POSTS, SIGNS, AND/OR DELINEATORS IN CONSTRUCTION AREA. CONTRACTOR MAY KEEP THE SIGNS, OR CALL THE CITY TRAFFIC DIVISION TO HAVE THEM REMOVED. 17.NO "RESET" ANCHORS, POSTS, SIGNS, AND/OR DELINEATORS WILL BE ACCEPTED. 18.ALL ANCHORS, POSTS, SIGNS, AND/OR DELINEATORS SHALL BE NEW AND BE CONSISTENT WITH THE LCUASS CRITERIA. D.STORM DRAINAGE NOTES 1.THE CITY OF FORT COLLINS SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF STORM DRAINAGE FACILITIES LOCATED ON PRIVATE PROPERTY. MAINTENANCE OF ONSITE DRAINAGE FACILITIES SHALL BE THE RESPONSIBILITY OF THE PROPERTY OWNER(S). 2.ALL RECOMMENDATIONS OF THE FINAL DRAINAGE AND EROSION CONTROL STUDY, FINAL DRAINAGE REPORT FOR HEARTSIDE HILL BY HIGHLAND DEVELOPMENT SERVICES, SHALL BE FOLLOWED AND IMPLEMENTED. 3.SEE CITY OF FORT COLLINS STORMWATER CRITERIA MANUAL - APPENDIX F CONSTRUCTION CONTROL MEASURES STANDARD NOTES AND STANDARD EROSION CONTROL NOTES. FORT COLLINS - LOVELAND WATER DISTRICT AND SOUTH FORT COLLINS SANITATION DISTRICT NOTES 1.ALL WATER AND SANITARY SEWER CONSTRUCTION SHALL BE PERFORMED ACCORDING TO THE FORT COLLINS - LOVELAND WATER DISTRICT AND THE SOUTH FORT COLLINS SANITATION DISTRICT STANDARDS AND SPECIFICATIONS. 2.CONSTRUCTION OF WATER AND SEWER FACILITIES REQUIRE A PRECON MEETING WITH DISTRICT OPERATIONS STAFF PRIOR TO CONSTRUCTION. 3.CONTRACTOR SHALL NOTIFY DISTRICT INSPECTORS PRIOR TO STARTING WORK. 4.CONTRACTOR SHALL CONTACT THE SANITATION DISTRICT FOR SEWER INSPECTION 48 HOURS PRIOR TO CONNECTING TO EXISTING SEWER STUBS. 5.ALL COMMERCIAL DOMESTIC SERVICES REQUIRE A REDUCED PRESSURE BACKFLOW PREVENTION DEVICE. 6.ALL WATER LINES SHALL BE A MINIMUM OF (5) FIVE FEET AND A MAXIMUM OF (6) SIX FEET BELOW FINAL GRADE. 7.ALL DISTRICT VALVES SHALL ONLY BE OPERATED BY DISTRICT OPERATIONS STAFF. 8.PIPE PRESSURE AND VACUUM TESTING SHALL BE WITNESSED BY DISTRICT INSPECTORS. WATERLINE BACTERIA TESTS SHALL ALSO BE TAKEN BY DISTRICT INSPECTORS. 9.ONCE THE SYSTEM IS OPERATIONAL AND ALL TESTS HAVE PASSED, CONTRACTOR SHALL REQUEST SUBSTANTIAL COMPLETION WITH A LETTER TO THE DISTRICT THAT INCLUDES THE DOLLAR VALUE OF THE WATER AND SEWER IMPROVEMENTS LISTED SEPARATELY. 10.AS-BUILTS SHALL BE SUBMITTED IN PDF AND DWG TO THE DISTRICT FOR FINAL APPROVAL. 11.IF GROUNDWATER IS ENCOUNTERED WITHIN THE DEPTH OF SEWER CONSTRUCTION, MANHOLES MUST BE WATER-PROOFED. 12.A REDUCED PRESSURE PRINCIPLE BACK-FLOW-PREVENTION-DEVICE (BFPD) IS REQUIRED ON THE FIRE LINE AND THE DOMESTIC WATER SERVICE LINE. 13.TREES AND OTHER LANDSCAPING ARE NOT ALLOWED WITHIN 10 FEET OF DISTRICT FACILITIES. CITY OF FORT COLLINS GENERAL NOTES REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE DIRECT SUPERVISION OF: FOR AND ON BEHALF OF HIGHLAND DEVELOPMENT SERVICES REVIEW SET NOT FOR CONSTRUCTION OFSHEET DRAWN BY CHECKED BY DATE SCALE (H) HDS PROJECT # SCALE (V)HEARTSIDE HILLGENERAL NOTES2/22/23 N/A N/A ZMW JTC 21-1045-00 C0.01 2 24