February 17, 2023
Peter Carey
Up Architecture
5305 Spine Rd Suite F
Boulder, CO 80301
RE: 209 Troutman Paint Booth Addition (With Plat), MA190088, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of 209 Troutman Paint Booth Addition. If you have questions
about any comments, you may contact the individual commenter or direct your questions
through your Development Review Coordinator, Todd Sullivan via phone at 970-221-6695
or via email at tsullivan@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Todd Sullivan, 970-221-6695, tsullivan@fcgov.com
Topic: General
Comment Number: 1
02/14/2023: INFORMATION: I will be your primary point of contact throughout
the development review and permitting process. If you have any questions, need
additional meetings with the project reviewers, or need assistance throughout
the process, please let me know and I can assist you and your team. Include me
in all email correspondence with other reviewers and keep me informed of any
phone conversations. Thank you!
Acknowledged
Comment Number: 2
02/14/2023: SUBMITTAL:
As part of your resubmittal, you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color.
2
When replying to the comment letter please be detailed in your responses, as
all comments should be thoroughly addressed. Comments requiring action
should NOT have a response such as noted or acknowledged. You will need to
provide references to specific project plans, pages, reports, or explanations of
why comments have not been addressed [when applicable].
Understood
Comment Number: 3
02/14/2023: SUBMITTAL:
Please follow the Electronic Submittal Requirements and File Naming
Standards found at https://www.fcgov.com/developmentreview/files/electronic
submittal requirements and file naming standards_v1_8 1 19.pdf?1566857888.
File names should begin with the file type, followed by the project information,
and round number.
Example: UTILITY PLANS_PROJECT NAME_PDP_Rd2.pdf
File type acronyms maybe appropriate to avoid extremely long file names.
Example: TIS for Traffic Impact Study, ECS for Ecological Characterization
Study.
Reach out to me if you would like a list of suggested names.
*Please disregard any references to paper copies, flash drives, or CDs.
Electronic submittal requirements will be followed per document.
Comment Number: 4
02/14/2023: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and
remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be
removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the
PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-Aut
oCAD.html
PDF documents will be saved as described
Comment Number: 5
02/14/2023: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced
notice as possible.
Noted
Comment Number: 6
02/14/2023: INFORMATION:
3
Please resubmit within 180 days, approximately 6 months, to avoid the
expiration of your project.
Acknowledged
Comment Number: 7
02/14/2023: INFORMATION:
ANY project that requires four or more rounds of review would be subject to an
additional fee of $3,000.00.
Understood
Comment Number: 8
02/14/2023: FOR FINAL APPROVAL:
The Director shall issue a written decision to approve, approve with conditions,
or deny the development application based on compliance with the standards
referenced in Step 8 of the Common Development Review Procedures
(Section 2.2.8).
The written decision shall be mailed to the applicant, to any person who
provided comments during the comment period and to the abutting property
owners and shall also be posted on the City's website at www.fcgov.com.
Noted
Comment Number: 9
02/14/2023: FOR FINAL APPROVAL:
If the project is approved by the Director, there is a two-week appeal period
from the date of the decision. The project is not able to be recorded until it is
confirmed there are no appeals.
Understood
Comment Number: 10
02/14/2023: FOR FINAL APPROVAL:
All "For Final Approval / For Approval" comments need to be addressed and
resolved prior to moving forward with the final documents and recording of this
project. I will provide a recording checklist and process information when we
are closer to this step.
Acknowledged, thank you.
Department: Planning Services
Contact: Jill Baty, jbaty@fcgov.com
Topic: General
Comment Number: 1
02/10/2023: FOR APPROVAL: In order to build the addition, as it seems to be
planned, you will need vacate a portion of the blanket easement.
Lot line will be vacated per Troutman PUD Phase One, Replat No. 1 provided by Baseline.
Comment Number: 2
02/10/2023: FOR INFORMATION: The CG Zone District does not have
4
minimum building setbacks, but please note Internal Services' Comment
Number 4 regarding Fire Code regulations for buildings closer than 10' from a
property line, especially with regards to the western section of the proposed addition.
Department: Zoning
Contact: Rob Bianchetto, rbianchetto@fcgov.com
Topic: General
Comment Number: 2
2/8/23: UNRESOLVED
Please revise the proposed concept plan on page A1.1 to show that the
building expansion will not encroach into the west side easement.
Building location has been revised in Civil sheet C4 to remain outside of west side
easement.
12/31/2019: Structures may not be erected within easements. The paint booth
appears to be proposed within an existing 6' utility easement on the west side
of this property. Please note the entire lot, other than the existing building
footprint, is within a blanket utility, drainage, and access easement.
http://citydocs.fcgov.com/?
cmd=convert&vid=51&docid=7317&dt=S-SUBDIVISION+PLAT Easements
would need to be assessed for existing equipment and determined if any
portion of said easement(s) may be vacated (through Engineering) in order for
approval of this addition to be considered.
Comment Number: 3
2/8/23: UNRESOLVED
Please revise the site plan to show the parking spaces (minimum of 8). At least
1 ADA space must be provided, which needs to be a minimum of 16' wide to
accommodate the parking space (8') as well as the hashed loading area (8') to
make it van-accessible.
Sheet C3 includes 14 total spaces (1 ADA, 4 Standard, and 9 vehicle bays). Parking
requirements have been added to the Land Use Table on Sheet C3.
12/31/2019: The proposed addition within the TOD overlay zone requires 3
additional parking spaces, for a total of 10 minimum at 2/1000sf accounting for
the existing building. Will parking requirements be met, or affected by the
addition? **Please provide a parking table and lot striping on site plan with
required, existing and proposed number of vehicle parking spaces including
required (1) ADA accessible space. Vehicle bays may count toward
requirements.
Comment Number: 4
2/8/23: UNRESOLVED
12/31/2019: 4 bicycle parking spaces are required. Please note current
location and number of spaces on plan, or add the minimum 4 spaces on site.
Sheet C3 shows two U-racks which will provide 4 bicycle parking spaces.
Comment Number: 5
5
2/8/23: UNRESOLVED
Please include dimensions of trash enclosure and bins on the site plan. Please
refer to 3.2.5(C) for trash enclosure standards. Please include separate plans
that show detailed elevations of the trash enclosure, calling out height and
materials. Trash enclosure needs to include separate pedestrian entrance,
bollards or other protective features, and service pad.
Existing trash enclosure is called out and shown on Sheet C2/C3.
12/31/2019: Please note location of required trash and recycling enclosure on
site plan.
Comment Number: 7
2/8/23: UNRESOLVED
12/31/2019: Please include building exterior materials and colors with
elevations, demonstrating continuity with the adjacent buildings.
Noted. See Architectural sheet A4.1 for material list and colors
Comment Number: 8
02/08/2023: FOR APPROVAL:
Please provide a separate landscape plan that calls out the exact location of
existing and proposed plantings/ trees, and their species. Please refer to
3.2.2(M) for landscaping standards within the parking lot.
Landscape plans and notes have been provided as Sheets 9-13 of plan set.
Comment Number: 9
02/08/2023: FOR APPROVAL
Please provide a Land Use Table on the site plan. This should include the Zone
District (General Commercial (CG)), proposed use for the site (vehicle major
repair), the square footage of the parking lot, and the total number of parking
spaces, ADA parking spaces, and bike parking spaces that will be available on site.
Land Use Table added to sheet C3.
Comment Number: 10
02/08/2023: FOR APPROVAL
Will any additional lighting be added to the site (on the building, in the lot etc.),
or will existing fixtures be retrofitted? If so, please provide a light fixture
schedule or the cut/spec sheet of the new fixtures that show bug rating and color
temperature. Also call out the location of the fixtures on the elevations.
Refer to Architectural sheet A0.2 for new lighting and specifications. All site lighting to be
limited to wall mounted full cut off wall packs. Existing non complaint wall fixtures will be
retrofitted.
Comment Number: 11
02/08/2023: FOR APPROVAL
Will new rooftop mechanical units be added to the building? Please note per
LUC 3.5.1 (I) (6) All rooftop mechanical equipment shall be screened from
public view from both above and below by integrating it into building and roof
design to the maximum extent feasible. If new units are being added, please
demonstrate or explain how the units will be screened.
6
No rooftop mechanical units are proposed. Proposed exhaust penetrations are noted on
mechanical plans.
Comment Number: 12
02/08/2023: INFORMATION ONLY
Please note per LUC 3.5.1 (I) (3) Conduit, meters, vents and other equipment
attached to the building or protruding from the roof shall be painted to match
surrounding building surfaces.
Noted
Department: Historic Preservation
Contact: Jim Bertolini, 970-416-4250, jbertolini@fcgov.com
Topic: General
Comment Number: 1
02/06/2023: NO HISTORIC REVIEW REQUIRED: This proposal does not
require historic review because there are no designated historic resources on
the site and the nature of the project does not impact any historic resources that
may lie on the development site or within 200 feet of the site.
Understood.
Department: Engineering Development Review
Contact: Tim Dinger, tdinger@fcgov.com
Topic: General
Comment Number: 2
02/01/2023: UPDATED:
This comment still applies. If any other civil/utility drawings are required by other
departments, engineering will need to review.
Civil site, grading, and utility drawings added for review
12/16/2019: If civil (utility) plan drawings are required from other departments, I
would want to review with future submittals.
Comment Number: 3
02/08/2023: INFORMATION:
Coordinate with Poudre Fire Authority on dedicating an emergency access
easement within the lot in order to provide emergency services to the building.
Nearby hydrants plus sprinkler system provide adequate spacing for emergency response.
This was confirmed with Marcus Glasgow.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Comment Number: 2
02/13/2023: COMMENT UNRESOLVED: No materials submitted.
12/26/2019: Please provide a grading plan for the new addition with a
proposed F.F. elevation for the addition and spot elevations documenting the
grading around the building.
Sheet C4 shows proposed grading for building and parking area.
7
Department: Water-Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Comment Number: 1
12/26/2019: The building addition is being proposed over an existing sewer
service. Please provide a Utility Plan documenting changes to the sewer
service.
Sheets C5/C6 show proposed utility revisions for building expansion
Comment Number: 2
02/13/2023: COMMENT UNRESOLVED: No materials submitted.
12/26/2019: Please show all existing water and sewer services on the provided
Utility Plan.
Sheet C5 shows known existing water and sewer services
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreager@fcgov.com
Topic: General
Comment Number: 1
12/11/2019: It is the understanding of Light and Power that this minor
amendment will not cause a change to the electric capacity needs or the
location of our facilities. If this an incorrect understanding or if plans change,
please contact me directly at akreager@fcgov.com or (970)224-6152. Thank you.
Acknowledged.
Department: Environmental Planning
Contact: Kristie Raymond, kraymond@fcgov.com
Topic: General
Comment Number: 6
01/30/2023: INFORMATION ONLY: City of Fort Collins Land Use Code
[Section 3.2.1 (E)(3)], requires that to the extent reasonably feasible, all plans
be designed to incorporate water conservation materials and techniques. This
includes use of low-water-use plants and grasses in landscaping or
re-landscaping and reducing bluegrass lawns as much as possible. Native
plants and wildlife-friendly (ex: pollinators, butterflies, songbirds) landscaping
and maintenance are also encouraged. Please refer to the Fort Collins
Vegetation Database at https://www.fcgov.com/vegetation/ and the Natural
Areas Department’s Native Plants document for guidance on native plants:
http://www.fcgov.com/naturalareas/pdf/nativeplants2013.pdf.
Acknowledged. See proposed landscaping on Sheet LP-1
8
Comment Number: 7
01/30/2023: FOR APPROVAL: The City of Fort Collins is designated as a bird
sanctuary for the refuge of wild birds (Municipal Code Chapter 4, Division 8 -
Wild Birds: https://library.municode.com/co/fort_collins/codes/municipal_code?
nodeId=CH4ANIN_ARTIIAN_DIV8WIBI) and in order to satisfy the federal
Migratory Bird Treaty Act requirements, it is prohibited for any person at any
time in the City to abuse or injure any wild bird or damage a nest with eggs or
injure the young of any such bird. A professional ecologist or wildlife biologist is
required to complete the nesting survey linked below 5-7 days before
conducting tree removal or trimming. If tree removal or trimming is planned,
please include the following note on the tree mitigation plan and landscape plan,
as appropriate:
"NO TREES SHALL BE REMOVED DURING THE SONGBIRD NESTING
SEASON (FEBRUARY 1 TO JULY 31) WITHOUT FIRST HAVING A
PROFESSIONAL ECOLOGIST OR WILDLIFE BIOLOGIST COMPLETE A
NESTING SURVEY 5-7 DAYS BEFORE TREE REMOVAL OR TRIMMING TO
IDENTIFY ANY ACTIVE NESTS EXISTING ON THE PROJECT SITE. THE
SURVEY SHALL BE SENT TO THE CITY ENVIRONMENTAL PLANNER. IF
ACTIVE NESTS ARE FOUND, THE CITY WILL COORDINATE WITH
RELEVANT STATE AND FEDERAL REPRESENTATIVES TO DETERMINE
WHETHER ADDITIONAL RESTRICTIONS ON TREE REMOVAL AND
CONSTRUCTION APPLY."
The Songbird Nesting Survey document will be provided with the comment letter
for you to fill out.
This note was included as Note 9) on sheet TP-1
Comment Number: 8
01/30/2023: INFORMATION ONLY: The City of Fort Collins Lighting Land Use
Code was updated in 2021. Please ensure that requirements outlined in
Section 3.2.4(C)(3) are met.
Plans meet this criteria
Department: Forestry
Contact: Freddie Haberecht, fhaberecht@fcgov.com
Topic: Landscape Plans
Comment Number: 1
2/9/2023: FOR APPROVAL UPDATED
Since there are existing trees on site, please contact City Forestry to schedule
an on-site meeting to obtain tree inventory and mitigation information. This
meeting should occur prior to the next round of review.
Site visit was coordinated. Tree inventory and mitigation information shown on Sheet TP-1
Comment Number: 2
2/9/2023: FOR APPROVAL UPDATED
Please include City Forestry’s Tree Protection Notes on the plans.
Tree protection notes included on sheet TP-1
9
Comment Number: 3
2/9/2023: FOR APPROVAL UPDATED
Is any new landscaping proposed for this site? If so, please provide a
landscape plan that meets the Land Use Code 3.2.1 requirements. This should
include the existing tree inventory and any proposed tree plantings (including
species, size, quantity and method of transplant).
Landscaping plan, notes, and details have been provided. Please see Sheets 9-12 of
Minor Amendment plan set
Department: PFA
Contact: Marcus Glasgow, 970-416-2869, marcus.glasgow@poudre-fire.org
Topic: General
Comment Number: 6
02/13/2023: FIRE LANE
Fire access can only be considered from the public street (Troutman Pkwy)
unless a fire lane meeting specifications is provided and an emergency access
easement is dedicated.
No updated floor plans or site plans have been submitted so I am assuming the
building will contain an automatic fire sprinkler system. The fire access
distance can be extended due to the sprinkler system so access from Troutman
would be acceptable.
The next submittal will need to show a detailed site plan with the included
addition and fire lanes if applicable. If the building contains or will contain a fire
sprinkler system, this shall be noted on the plans or in the comment response
letter.
Sheet C3 shows the detailed site plan. An automatic fire sprinkler system shall be provided
to meet Code requirements.
Contact: Sarah Carter, 970-416-2864, scarter@poudre-fire.org
Topic: General
Comment Number: 1
12/23/2019: SPRAY FINISHING
Spray booths require separate permitting by Poudre Fire Authority and fully
compliant with Section 2404 of the International Fire Code as follows:
> IFC 2402: The application of flammable or combustible liquids by means of
spray apparatus in continuous or intermittent processes shall be in accordance
with the requirements of Sections 2403 and 2404.2 through 2404.9.4.
If the spray application of flammable finishes operations are to be conducted
within the structure, there shall be at least one approved spray application of
flammable finishes booth or spray room within the structure. Such booths shall
be listed and labeled units with ventilation (exhaust and make-up air) systems
10
designed and all plans stamped by a Colorado Registered Mechanical
Engineer. Spray rooms required total design by a Colorado Registered
Mechanical Engineer with Structural Engineers assistance.
Noted and provided
Comment Number: 2
12/23/2019: BUILDING PERMITS
When submitting for building permit though the City of Fort Collins please be
advised Poudre Fire Authority is an additional and separate submittal. The link
for Poudre Fire Authority’s plan review application can be found at
https://www.poudre-fire.org/online-services/contractors-plan-reviews-and-permit
s/new-building-plan-review-application.
Noted
Comment Number: 3
12/23/2019: FIRE LANES
Fire access is required to within 150' of all exterior portions of any building, or
facility as measured by an approved route around the perimeter. For the
purposes of this section, fire access cannot be measured from an arterial road.
Any private alley, private road, or private drive serving as a fire lane shall be
dedicated as an Emergency Access Easement (EAE) and be designed to
standard fire lane specifications. In addition, aerial apparatus access
requirements are triggered for buildings in excess of 30' in height. Code
language and fire lane specifications provided below.
> IFC 503.1.1: Approved fire Lanes shall be provided for every facility, building
or portion of a building hereafter constructed or moved into or within the
jurisdiction. The fire apparatus access road shall comply with the requirements
of this section and shall extend to within 150 feet of all portions of the facility and
all portions of the exterior walls of the first story of the building as measured by
an approved route around the exterior of the building or facility. When any
portion of the facility or any portion of an exterior wall of the first story of the
building is located more than 150 feet from fire apparatus access, the fire code
official is authorized to increase the dimension if the building is equipped
throughout with an approved, automatic fire-sprinkler system.
Per coordination with Marcus Glasgow, a sprinklered building will allow for enough
distance to accommodate fire response without the addition of a platted Fire Lane
Comment Number: 4
12/23/2019: FIRE LANE SPECIFICATIONS
A fire lane plan shall be submitted for approval prior to installation. In addition to
the design criteria already contained in relevant standards and policies, any
new fire lane must meet the following general requirements:
> Fire lanes established on private property shall be dedicated by plat or
separate document as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed width & 14 foot minimum
overhead clearance. Where road widths exceed 20 feet in width, the full width
shall be dedicated unless otherwise approved by the AHJ.
> Be designed as a flat, hard, all-weather driving surface capable of supporting
11
40 tons.
> Dead-end fire access roads in excess of 150 feet in length shall be provided
with an approved turnaround area for fire apparatus.
> Dead-end roads shall not exceed 660' in length without providing for a second
point of access. Dead-end access roads in excess of 1320 feet in length
require a third point of access. Dead-end access roads in excess of 2640 feet
in length require a fourth point of access.
> The required turning radii of a fire apparatus access road shall be a minimum
of 25 feet inside and 50 feet outside. Turning radii shall be detailed on
submitted plans.
> Dedicated fire lanes are required to connect to the Public Way unless
otherwise approved by the AHJ.
> Be visible by red curb and/or signage, and maintained unobstructed at all
times. Sign locations or red curbing should be labeled and detailed on final
plans. Refer to LCUASS detail #1418 & #1419 for sign type, placement, and
spacing. Appropriate directional arrows required on all signs.
Understood.
Comment Number: 5
12/23/2019: FIRE CONTAINMENT
The proposed building size exceeds 5,000 square feet and shall be sprinklered
or fire contained. If containment is used, the containment construction shall be
reviewed and approved by the Poudre Fire Authority prior to installation.
Sprinklers are proposed and noted on plans. Sprinkler design by others will be provided to
Poudre Fire Authority prior to installation
Department: Building Services
Contact: Katy Hand, khand@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
12/16/2019: INFORMATIONAL: Please visit our website for a list of current
adopted building codes and local amendments for building permit submittal:
https://www.fcgov.com/building/codes.php
Noted
Comment Number: 2
12/16/2019: REQUIRED - Addition cannot cross lot line.
Lot line has been vacated by separate document.
Comment Number: 3
12/16/2019: MUST BE ADDRESSED AT TIME OF BUILDING PERMIT:
Buildings greater than 5,000 sf will need to be fire contained or fire sprinkled
Sprinklers are proposed and noted on plans. Sprinkler design by others will be provided to
Poudre Fire Authority prior to installation
Comment Number: 4
12/16/2019: MUST BE ADDRESSED AT TIME OF BUILDING PERMIT:
Exterior walls closer than 10ft from property lines must be fire rated with limited
openings.
12
No changes to existing fire access appear to be required
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 5
02/13/2023: The following are requirements for paint spray booths and rooms.
A building permit is required from Building Services and also from the Fire
Department (PFA).
1. Must comply with 2012 IBC section 416 and IFC chap 15.
2. Automatic fire extinguishing system required per IBC section 416.5 and
903.
3. Must provide ventilation per IFC section 1504.7 & 2012 IMC section 502.7.
The exhaust outlet termination must be 30 feet from a property line and 10 feet
away from openings into the building.
4. Must comply with National Electrical Code section 516.
5. Spray-in truck bed liner complying with IFC 1504.2 excep #1 is a ‘Spray
Area’ and the only requirement is ventilation.
6. Spray Booth:
a. Is an appliance and main occupancy does not change.
b. IFC requires 3ft of clearance all the way around spray booth.
7. Spray Room:
a. Is an H-2 occupancy with flammable and combustible liquids.
b. Paint spray room must be a 1-hour enclosure per 416.
Noted and provided.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations
Comment Number: 3
02/14/2023: FOR FINAL APPROVAL-UNRESOLVED:
No plans were provided for review. We will need to review before plans are filed.
12/24/2019: There is text that needs to be masked. Mask all text in hatched
areas. See redlines.
New site improvement plans have been provided for review. Text above other linework is
masked as necessary for legibility
Comment Number: 4
02/14/2023: FOR FINAL APPROVAL-UNRESOLVED:
No plans were provided for review. We will need to review before plans are filed.
12/24/2019: The smaller text does not scan or reproduce well. The text needs
to increase in size. See examples of problem text on redlines.
New site improvement plans have been provided for review. Text should be legible on all
sheets.
13
Comment Number: 5
02/14/2023: FOR FINAL APPROVAL-UNRESOLVED:
No plans were provided for review. We will need to review before plans are filed.
12/24/2019: There are line over text issues. See redlines.
Every effort has taken to avoid line over text issues with the new plan set submittal.
Topic: General
Comment Number: 7
02/14/2023: FOR FINAL APPROVAL:
Please provide a closure report for the outer boundary of this Subdivision Plat.
Provided
Topic: Plat
Comment Number: 6
02/14/2023: FOR FINAL APPROVAL:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the redlines, please contact John
Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
Provided
Topic: Site Plan
Comment Number: 1
02/14/2023: FOR FINAL APPROVAL-UNRESOLVED:
No plans were provided for review. We will need to review before plans are filed.
12/24/2019: Please revise the legal description as marked. See redlines.
Legal description on Site Plan revised to match Replat.
Comment Number: 2
02/14/2023: FOR FINAL APPROVAL-UNRESOLVED:
No plans were provided for review. We will need to review before plans are filed.
12/24/2019: There are line over text issues. See redlines.
Plans have been provided with this submittal.
Department: Water Conservation
Contact: Emma Pett, epett@fcgov.com
Topic: General
Comment Number: 1
01/25/2023: Please advise if there will be changes or additions to current landscaping or
irrigation.
Landscape Plans have been provided with this submittal (Sheets 9-12).