HomeMy WebLinkAboutPOWERHOUSE 2 - FDP220015 - DOCUMENT MARKUPS - ROUND 3 - UTILITY PLANS (3)E. VINE DRIVEN. COLLEGE AVENUECHERRY STREET
CAC
H
E
L
A
P
O
U
D
R
E
R
I
V
E
R
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
CS1 COVER SHEET1
MARCH 2023 CONTACT INFORMATION
PROJECT TEAM:
VICINITY MAP
NORTH
PROJECT DATUM: NAVD88
CITY OF FORT COLLINS BENCHMARK 1-00
ON A CATCH BASIN AT THE SOUTHEAST CORNER OF VINE DR. AND COLLEGE AVE.
ELEV.=4968.74
CITY OF FORT COLLINS BENCHMARK 3-13
APPROX. 40 FT SOUTH OF THE LINDEN ST. BRIDGE OVER THE POUDRE RIVER, ON
THE WEST SIDE OF LINDEN ST. , ON A STORM INLET.
ELEV.=4962.27
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM.
SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR
VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE
FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.18'
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE LINE OF THE SOUTHWEST QUARTER
OF SECTION 1-7-69 AS BEARING SOUTH 00° 38' 34" WEST (ASSUMED BEARING)
AND MONUMENTED AS SHOWN ON PLAT.
PROJECT BENCHMARKS:
POWERHOUSE 2
PROJECT TEAM:
Roger Sherman
BHA Design Incorporated
1603 Oakridge Drive, Suite 100
Fort Collins, Colorado 80525
(970)223-7577
Colorado State University
Bryan Willson
Executive Director, CSU Energy Institute
450 N College Ave.
Fort Collins, CO 80524
(970)227-5164
Northern Engineering Services, Inc.
Andy Reese
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
(970) 221-4158
PLANNER/
LANDSCAPE ARCHITECT
OWNER/APPLICANT
SITE ENGINEER
SHEET INDEX
A PARCEL OF LAND LOCATED IN THE SOUTHWEST QUARTER OF SECTION 1, TOWNSHIP 7 NORTH,
RANGE 69 WEST OF THE 6TH P.M., CITY OF FORT COLLINS, COUNTY OF LARIMER, STATE OF COLORADO
Northern Engineering Services, Inc.
Bob Tessely, PLS
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
(970) 221-4158
SITE SURVEYOR
TYPICAL SECTIONS
1 CS1 COVER SHEET
2 CS2 GENERAL & CONSTRUCTION NOTES
3 CS3 EROSION CONTROL NOTES
4 EX1 EXISTING CONDITIONS & DEMOLITION PLAN
5 PV1 PAVING & SIGNAGE PLAN
UTILITY SHEETS
6 OU1 UTILITY PLAN
SANITARY SHEETS
7 SS1 OFFSITE SANITARY SEWER PLAN & PROFILE
8 SS2 SANITARY SEWER B PLAN & PROFILE
STORM SHEETS
9 ST1 POND OUTFALL PLAN & PROFILE
10 ST2 STORM DRAIN C PLAN & PROFILE
11 ST3 STORM DRAIN D PLAN & PROFILE
GRADING SHEETS
12 OG1 OVERALL GRADING PLAN
13 - 14 G1 - G2 GRADING PLAN
RAIN GARDEN SHEETS
15 RG1 NORTH RAIN GARDEN PLAN & DETAILS
16 RG2 SOUTH RAIN GARDEN PLAN
DETAIL SHEETS
17 - 21 D1 - D5 SITE DETAILS
22 - 24 D6 - D8 UTILITY DETAILS
25 - 30 D9 - D14 DRAINAGE DETAILS
DRAINAGE SHEETS
31 EC1 INITIAL EROSION CONTROL PLAN
32 EC2 INTERIM EROSION CONTROL PLAN
33 EC3 FINAL EROSION CONTROL PLAN
34 - 35 EC4 - EC5 EROSION CONTROL DETAILS
36 DR1 DEVELOPED DRAINAGE EXHIBIT
37 FP1 FLOODPLAIN EXHIBIT
FINAL CONSTRUCTION PLANS FOR
E N G I N E E R N GI
EHTRON R N
E N G I N E E R N GI
EHTRON R N
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
PROJECT
LOCATION
UTILITY CONTACT LIST: *
UTILITY COMPANY
* This list is provided as a courtesy reference only. Northern Engineering Services assumes no responsibility for
the accuracy or completeness of this list. In no way shall this list relinquish the Contractor's responsibility for
locating all utilities prior to commencing any construction activity. Please contact the Utility Notification Center of
Colorado (UNCC) at 811 for additional information.
PHONE NUMBER
APPROVED:
City Engineer:Approved Sheets Date
Water & Wastewater Utility Approved Sheets Date
Stormwater Utility Approved Sheets Date
Park Planning and Development Approved Sheets Date
Traffic Operations Approved Sheets Date
Environmental Planner Approved Sheets Date
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
APPROVED:
APPROVED:
APPROVED:
APPROVED:
APPROVED:
Field Survery:
Northern Engineering Services, Inc.
Date: October 25, 2019
FIELD SURVEY BY:
These plans have been reviewed by the City of Fort Collins for concept only. The review does not imply responsibility
by the reviewing department, the City of Fort Collins Engineer, or the City of Fort Collins for accuracy and correctness
of the calculations. Furthermore, the review does not imply that quantities of items on the plans are the final quantities
required. The review shall not be construed for any reason as acceptance of financial responsibility by the City of Fort
Collins for additional quantities of items shown that may be required during the construction phase.
DISCLAIMER STATEMENT:
CTL Thompson, Inc
Geotechnical Investigation Proposed Improvements
Powerhouse 2
Project No. FC10223-125
Date: March 14, 2022
SUBSURFACE EXPLORATION BY:
Travel
69' ROW (min.)
42' Roadway
5'
Walk
(min.)(min.)
Pkwy.
8.5'
Pkwy.
5'
(min.)
8.5'
11'
Util.
Esmt.
9'
Esmt.
Util.
9'
(min.)
Walk
Travel
11'
7'
Lane
Bike
3'7'
Lane
Bike
3'
Bike
Lane
Buffer
Bike
Lane
Buffer
2 LANE ARTERIAL w/ PARALLEL PARKING
(EAST VINE DRIVE)
2 LANE COLLECTOR
(JEROME STREET)
(min.)
Walk
84' ROW (min.)
52' Roadway
7'
Pkwy.
6'
(min.)
8'
Esmt.
Util.
15'
Center
10'
Travel
11'
Travel
11'
3'
Lane
Bike
7'3'
Bike
Lane
Buffer
Bike
Lane
Buffer
Lane
Bike
(min.)
Walk
84' ROW (min.)
52' Roadway
7'
Walk
(min.)
(min.)
Pkwy.
10'
Pkwy.
6'
(min.)
10'
Util.
Esmt.
15'
Esmt.
Util.
15'
Center
10'
Travel
11'
Travel
11'
3'
Lane
Bike
7'3'
Bike
Lane
Buffer
6'
Bike
Lane
Buffer
Lane
Bike
8'
Parallel
Parking
(min.)
Walk
Pkwy.
6'
(min.)
8'
Esmt.
Util.
15'
8'
Parallel
Parking
2 LANE ARTERIAL
(EAST VINE DRIVE)
Pedestrain
Access Easement
Pedestrain
Access Easement
LAKE CANAL
GAS-----------------Xcel Energy-----------------------------Cory Thelen (970) 225-7843
ELECTRIC--------City of Fort Collins Light & Power--Cody Snowdon (970) 416-2306
CABLE-------------Comcast----------------------------------Don Kapperman (970) 567-0425
TELECOM.--------Lumen-------------------------------Brady Craddock (970) 342-3431
WATER------------City of Fort Collins Utilities-----------Jim McChesney (970) 556-8179
WASTEWATER--City of Fort Collins Utilities-----------Jim McChesney (970) 556-8179
STORMWATER-City of Fort Collins Utilities-----------Heidi Hansen (970) 221-6854
UTILITY PLAN APPROVAL
BOXELDER SANITATION DISTRICT
CACHE LA POUDRE
RESERVOIR COMPANY
UTILITY PLAN REVIEW
EAST LARIMER COUNTY WATER DISTRICT
Does not match the most current
format. See written comments.
3/28/2023
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
CS2 CONSTRUCTION NOTESGENERAL &2
A. GENERAL NOTES
1.All materials, workmanship, and construction of public improvements shall meet or exceed the standards and specifications set forth in the Larimer
County Urban Area Street Standards and applicable state and federal regulations. Where there is conflict between these plans and the
specifications, or any applicable standards, the most restrictive standard shall apply. All work shall be inspected and approved by the City of Fort
Collins.
2.All references to any published standards shall refer to the latest revision of said standard, unless specifically stated otherwise.
3.These public improvement construction plans shall be valid for a period of three years from the date of approval by the City of Fort Collins Engineer.
Use of these plans after the expiration date will require a new review and approval process by the City of Fort Collins prior to commencement of
any work shown in these plans.
4.The engineer who has prepared these plans, by execution and/or seal hereof, does hereby affirm responsibility to the City of Fort Collins, as
beneficiary of said engineer's work, for any errors and omissions contained in these plans, and approval of these plans by the City of Fort Collins
Engineer shall not relieve the engineer who has prepared these plans of all such responsibility. Further, to the extent permitted by law, the engineer
hereby agrees to hold harmless and indemnify the City of Fort Collins, and its officers and employees, from and against all liabilities, claims, and
demands which may arise from any errors and omissions contained in these plans.
5.All storm sewer construction, as well as power and other "dry" utility installations, shall conform to the City of Fort Collins standards and
specifications current at the date of approval of the plans by the City of Fort Collins Engineer.
6.The type, size, location and number of all known underground utilities are approximate when shown on the drawings. It shall be the responsibility of
the Developer to verify the existence and location of all underground utilities along the route of the work before commencing new construction. The
Developer shall be responsible for unknown underground utilities.
7.The Developer shall contact the Utility Notification Center of Colorado (UNCC) at 1-800-922-1987, at least 2 working days prior to beginning
excavation or grading, to have all registered utility locations marked. Other unregistered utility entities (i.e. ditch / irrigation company) are to be
located by contacting the respective representative. Utility service laterals are also to be located prior to beginning excavation or grading. It shall be
the responsibility of the Developer to relocate all existing utilities that conflict with the proposed improvements shown on these plans.
8.The Developer shall be responsible for protecting all utilities during construction and for coordinating with the appropriate utility company for any
utility crossings required.
9.If a conflict exists between existing and proposed utilities and/or a design modification is required, the Developer shall coordinate with the engineer
to modify the design. Design modification(s) must be approved by the City of Fort Collins prior to beginning construction.
10.The Developer shall coordinate and cooperate with the City of Fort Collins, and all utility companies involved, to assure that the work is
accomplished in a timely fashion and with a minimum disruption of service. The Developer shall be responsible for contacting, in advance, all
parties affected by any disruption of any utility service as well as the utility companies.
11.No work may commence within any public storm water, sanitary sewer or potable water system until the Developer notifies the utility provider.
Notification shall be a minimum of 2 working days prior to commencement of any work. At the discretion of the water utility provider, a
pre-construction meeting may be required prior to commencement of any work.
12.The Developer shall sequence installation of utilities in such a manner as to minimize potential utility conflicts. In general, storm sewer and sanitary
sewer should be constructed prior to installation of the water lines and dry utilities.
13.The minimum cover over water lines is 4.5 feet and the maximum cover is 5.5 feet unless otherwise noted in the plans and approved by the Water
Utility.
14.A State Construction Dewatering Wastewater Discharge Permit is required if dewatering is required in order to install utilities or if water is
discharged into a storm sewer, channel, irrigation ditch or any waters of the United States.
15.The Developer shall comply with all terms and conditions of the Colorado Permit for Storm Water Discharge (Contact Colorado Department of
Health, Water Quality Control Division, (303) 692-3590), the Storm Water Management Plan, and the Erosion Control Plan.
16.The City of Fort Collins shall not be responsible for the maintenance of storm drainage facilities located on private property. Maintenance of onsite
drainage facilities shall be the responsibility of the property owner(s).
17.Prior to final inspection and acceptance by the City of Fort Collins, certification of the drainage facilities, by a registered engineer, must be
submitted to and approved by the Stormwater Utility Department. Certification shall be submitted to the Stormwater Utility Department at least two
weeks prior to the release of a certificate of occupancy for single family units. For commercial properties, certification shall be submitted to the
Stormwater Utility Department at least two weeks prior to the release of any building permits in excess of those allowed prior to certification per the
Development Agreement.
18.The City of Fort Collins shall not be responsible for any damages or injuries sustained in this Development as a result of groundwater seepage,
whether resulting from groundwater flooding, structural damage or other damage unless such damage or injuries are sustained as a result of the
City of Fort Collins failure to properly maintain its water, wastewater, and/or storm drainage facilities in the development.
19.All recommendations of the Final Drainage Report, dated March 1, 2023 by Northern Engineering shall be followed and implemented.
20.Temporary erosion control during construction shall be provided as shown on the Erosion Control Plan. All erosion control measures shall be
maintained in good repair by the Developer, until such time as the entire disturbed areas is stabilized with hard surface or landscaping.
21.The Developer shall be responsible for insuring that no mud or debris shall be tracked onto the existing public street system. Mud and debris must
be removed within 24 hours by an appropriate mechanical method (i.e. machine broom sweep, light duty front-end loader, etc.) or as approved by
the the City of Fort Collins street inspector.
22.No work may commence within any improved or unimproved public Right-of-Way until a Right-of-Way Permit or Development Construction Permit
is obtained, if applicable.
23.The Developer shall be responsible for obtaining all necessary permits for all applicable agencies prior to commencement of construction. The
Developer shall notify the the City of Fort Collins Inspector (Fort Collins - 221-6605) and the City of Fort Collins Erosion Control Inspector (Fort
Collins - 221-6700) at least 2 working days prior to the start of any earth disturbing activity, or construction on any and all public improvements. If
the City of Fort Collins Engineer is not available after proper notice of construction activity has been provided, the Developer may commence work
in the Engineer absence. However, the City of Fort Collins reserves the right not to accept the improvement if subsequent testing reveals an
improper installation.
24.The Developer shall be responsible for obtaining soils tests within the Public Right-of-Way after right of way grading and all utility trench work is
complete and prior to the placement of curb, gutter, sidewalk and pavement. If the final soils/pavement design report does not correspond with the
results of the original geotechnical report, the Developer shall be responsible for a re-design of the subject pavement section or, the Developer may
use the City of Fort Collins' default pavement thickness section(s). Regardless of the option used, all final soils/pavement design reports shall be
prepared by a licensed Professional Engineer. The final report shall be submitted to the Inspector a minimum of 10 working days prior to placement
of base and asphalt. Placement of curb, gutter, sidewalk, base and asphalt shall not occur until the City of Fort Collins Engineer approves the final
report.
25.The contractor shall hire a licensed engineer or land surveyor to survey the constructed elevations of the street subgrade and the gutter flowline at
all intersections, inlets, and other locations requested by the the City of Fort Collins inspector. The engineer or surveyor must certify in a letter to
the City of Fort Collins that these elevations conform to the approved plans and specifications. Any deviations shall be noted in the letter and then
resolved with the City of Fort Collins before installation of base course or asphalt will be allowed on the streets.
26.All utility installations within or across the roadbed of new residential roads must be completed prior to the final stages of road construction. For the
purposes of these standards, any work except c/g above the subgrade is considered final stage work. All service lines must be stubbed to the
property lines and marked so as to reduce the excavation necessary for building connections.
27.Portions of Larimer County are within overlay districts. The Larimer County Flood Plain Resolution should be referred to for additional criteria for
roads within these districts.
28.All road construction in areas designated as Wild Fire Hazard Areas shall be done in accordance with the construction criteria as established in the
Wild Fire Hazard Area Mitigation Regulations in force at the time of final plat approval.
29.Prior to the commencement of any construction, the contractor shall contact the Local Entity Forester to schedule a site inspection for any tree
removal requiring a permit.
30.The Developer shall be responsible for all aspects of safety including, but not limited to, excavation, trenching, shoring, traffic control, and security.
Refer to OSHA Publication 2226, Excavating and Trenching.
31.The Developer shall submit a Construction Traffic Control Plan, in accordance with MUTCD, to the appropriate Right-of-Way authority. (The City of
Fort Collins, Larimer County, Colorado), for approval, prior to any construction activities within, or affecting, the Right-of-Way. The Developer shall
be responsible for providing any and all traffic control devices as may be required by the construction activities.
32.Prior to the commencement of any construction that will affect traffic signs of any type, the contractor shall contact the City of Fort Collins Traffic
Operations Department, who will temporarily remove or relocate the sign at no cost to the contractor, however, if the contractor moves the traffic
sign then the contractor will be charged for the labor, materials and equipment to reinstall the sign as needed.
33.The Developer is responsible for all costs for the initial installation of traffic signing and striping for the Development related to the Development's
local street operations. In addition, the Developer is responsible for all costs for traffic signing and striping related to directing traffic access to and
from the Development.
34.There shall be no site construction activities on Saturdays, unless specifically approved by the City of Fort Collins Engineer, and no site
construction activities on Sundays or holidays, unless there is prior written approval by City of Fort Collins.
35.The Developer is responsible for providing all labor and materials necessary for the completion of the intended improvements, shown on these
drawings, or designated to be provided, installed, or constructed, unless specifically noted otherwise.
36.Dimensions for layout and construction are not to be scaled from any drawing. If pertinent dimensions are not shown, contact the Designer for
clarification, and annotate the dimension on the as-built record drawings.
37.The Developer shall have, onsite at all times, one (1) signed copy of the approved plans, one (1) copy of the appropriate standards and
specifications, and a copy of any permits and extension agreements needed for the job.
38.If, during the construction process, conditions are encountered which could indicate a situation that is not identified in the plans or specifications,
the Developer shall contact the Designer and the City of Fort Collins Engineer immediately.
39.The Developer shall be responsible for recording as-built information on a set of record drawings kept on the construction site, and available to the
Larimer County's Inspector at all times. Upon completion of the work, the contractor(s) shall submit record drawings to the City of Fort Collins
Engineer.
40.The Designer shall provide, in this location on the plan, the location and description of the nearest survey benchmarks (2) for the project as well as
the basis of bearings. The information shall be as follows:
PROJECT DATUM: NAVD88
City of Fort Collins Benchmark 1-00
On a catch basin at the southeast corner of Vine Dr. and College Ave.
ELEV.=4968.74
City of Fort Collins Benchmark 3-13
Approx. 40 ft south of the Linden St. bridge over the Poudre River, on the west side of Linden St. , on a storm inlet.
ELEV.=4962.27
Please Note: This plan set is using NAVD88 for a vertical datum. Surrounding developments have used NGVD29 Unadjusted for
their vertical datums.
If NGVD29 Unadjusted Datum is required for any purpose, the following equation should be used:
NGVD29 Unadjusted = NAVD88 - 3.18'
Basis of Bearings
The Basis of Bearings is the West line line of the Southwest Quarter of Section 1-7-69 as bearing South 00° 38' 34" West (assumed
bearing) and monumented as shown on Plat.
41.All stationing is based on centerline of roadways unless otherwise noted.
42.Damaged curb, gutter and sidewalk existing prior to construction, as well as existing fences, trees, streets, sidewalks, curbs and gutters,
landscaping, structures, and improvements destroyed, damaged or removed due to construction of this project, shall be replaced or restored in like
kind at the Developer's expense, unless otherwise indicated on these plans, prior to the acceptance of completed improvements and/or prior to the
issuance of the first Certificate of Occupancy.
43.When an existing asphalt street must be cut, the street must be restored to a condition equal to or better than its original condition. The existing
street condition shall be documented by the City of Fort Collins Construction Inspector before any cuts are made. Patching shall be done in
accordance with the City of Fort Collins Street Repair Standards. The finished patch shall blend in smoothly into the existing surface. All large
patches shall be paved with an asphalt lay-down machine. In streets where more than one cut is made, an overlay of the entire street width,
including the patched area, may be required. The determination of need for a complete overlay shall be made by the Larimer County Engineer
and/or the City of Fort Collins Inspector at the time the cuts are made.
44.Upon completion of construction, the site shall be cleaned and restored to a condition equal to, or better than, that which existed before
construction, or to the grades and condition as required by these plans.
45.Standard Handicap ramps are to be constructed at all curb returns and at all "T" intersections.
46.After acceptance by the City of Fort Collins, public improvements depicted in these plans shall be guaranteed to be free from material and
workmanship defects for a minimum period of two years from the date of acceptance.
47.The City of Fort Collins shall not be responsible for the maintenance of roadway and appurtenant improvements, including storm drainage
structures and pipes, for the following private streets: N.A.
48.Approved Variances are listed as follows:
1) N/A
CONSTRUCTION NOTES
A. Grading and Erosion Control Notes
1.The erosion control inspector must be notified at least twenty-four (24) hours prior to any construction on this site.
2.There shall be no earth-disturbing activity outside the limits designated on the accepted plans.
3.All required perimeter silt and construction fencing shall be installed prior to any land disturbing activity (stockpiling, stripping, grading, etc). All
other required erosion control measures shall be installed at the appropriate time in the construction sequence as indicated in the approved project
schedule, construction plans, and erosion control report.
4.At all times during construction, the Developer shall be responsible for preventing and controlling on-site erosion including keeping the property
sufficiently watered so as to minimize wind blown sediment. The Developer shall also be responsible for installing and maintaining all erosion
control facilities shown herein.
5.Pre-disturbance vegetation shall be protected and retained wherever possible. Removal or disturbance of existing vegetation shall be limited to the
area(s) required for immediate construction operations, and for the shortest practical period of time.
6.All soils exposed during land disturbing activity (stripping, grading, utility installations, stockpiling, filling, etc.) shall be kept in a roughened condition
by ripping or disking along land contours until mulch, vegetation, or other permanent erosion control BMPs are installed. No soils in areas outside
project street rights-of-way shall remain exposed by land disturbing activity for more than thirty (30) days before required temporary or permanent
erosion control (e.g. seed/mulch, landscaping, etc.) is installed, unless otherwise approved by the City/County.
7.In order to minimize erosion potential, all temporary (structural) erosion control measures shall:
a.Be inspected at a minimum of once every two (2) weeks and after each significant storm event and repaired or reconstructed as necessary in
order to ensure the continued performance of their intended function.
b.Remain in place until such time as all the surrounding disturbed areas are sufficiently stabilized as determined by the erosion control inspector.
c.Be removed after the site has been sufficiently stabilized as determined by the erosion control inspector.
8.When temporary erosion control measures are removed, the Developer shall be responsible for the clean up and removal of all sediment and
debris from all drainage infrastructure and other public facilities.
9.The contractor shall immediately clean up any construction materials inadvertently deposited on existing streets, sidewalks, or other public rights of
way, and make sure streets and walkways are cleaned at the end of each working day.
10.All retained sediments, particularly those on paved roadway surfaces, shall be removed and disposed of in a manner and location so as not to
cause their release into any waters of the United States.
11.No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be protected from sediment transport by surface roughening, watering,
and perimeter silt fencing. Any soil stockpile remaining after thirty (30) days shall be seeded and mulched.
12.The stormwater volume capacity of detention ponds will be restored and storm sewer lines will be cleaned upon completion of the project and
before turning the maintenance over to the City/County or Homeowners Association (HOA).
13.City Ordinance and Colorado Discharge Permit System (CDPS) requirements make it unlawful to discharge or allow the discharge of any pollutant
or contaminated water from construction sites. Pollutants include, but are not limited to discarded building materials, concrete truck washout,
chemicals, oil and gas products, litter, and sanitary waste. The developer shall at all times take whatever measures are necessary to assure the
proper containment and disposal of pollutants on the site in accordance with any and all applicable local, state, and federal regulations.
14.A designated area shall be provided on site for concrete truck chute washout. The area shall be constructed so as to contain washout material and
located at least fifty (50) feet away from any waterway during construction. Upon completion of construction activities the concrete washout
material will be removed and properly disposed of prior to the area being restored.
15.Conditions in the field may warrant erosion control measures in addition to what is shown on these plans. The Developer shall implement whatever
measures are determined necessary, as directed by the City.
16.For additional information see separate Stormwater Management Plan / Erosion Control Report for Powerhouse 2.
B. Street Improvement Notes
1.All street construction is subject to the General Notes on the cover sheet of these plans as well as the Street Improvements Notes listed here.
2.A paving section design, signed and stamped by a Colorado licensed Engineer, must be submitted to the City of Fort Collins Engineer for approval,
prior to any street construction activity, (full depth asphalt sections are not permitted at a depth greater than 8 inches of asphalt). The job mix shall
be submitted for approval prior to placement of any asphalt.
3.Where proposed paving adjoins existing asphalt, the existing asphalt shall be saw cut, a minimum distance of 12 inches from the existing edge, to
create a clean construction joint. The Developer shall be required to remove existing pavement to a distance where a clean construction joint can
be made. Wheel cuts shall not be allowed unless approved by the City of Fort Collins Engineer in Fort Collins.
4.Street subgrades shall be scarified the top 12 inches and re-compacted prior to subbase installation. No base material shall be laid until the
subgrade has been inspected and approved by the City of Fort Collins Engineer.
5.Ft. Collins only. Valve boxes and manholes are to be brought up to grade at the time of pavement placement or overlay. Valve box adjusting rings
are not allowed.
6.When an existing asphalt street must be cut, the street must be restored to a condition equal to or better than its original condition. The existing
street condition shall be documented by the Inspector before any cuts are made. Cutting and patching shall be done in conformance with Chapter
25, Reconstruction and Repair. The finished patch shall blend smoothly into the existing surface. The determination of need for a complete overlay
shall be made by the City of Fort Collins Engineer. All overlay work shall be coordinated with adjacent landowners such that future projects do not
cut the new asphalt overlay work.
7.All traffic control devices shall be in conformance with these plans or as otherwise specified in M.U.T.C.D. (including Colorado supplement) and as
per the Right-of-Way Work Permit traffic control plan.
8.The Developer is required to perform a gutter water flow test in the presence of the City of Fort Collins Inspector and prior to installation of asphalt.
Gutters that hold more than 1/4 inch deep or 5 feet longitudinally, of water, shall be completely removed and reconstructed to drain properly.
9.Prior to placement of H.B.P. or concrete within the street and after moisture/density tests have been taken on the subgrade material (when a full
depth section is proposed) or on the subgrade and base material (when a composite section is proposed), a mechanical "proof roll" will be required.
The entire subgrade and/or base material shall be rolled with a heavily loaded vehicle having a total GVW of not less than 50,000 lbs. and a single
axle weight of at least 18,000 lbs. with pneumatic tires inflated to not less that 90 p.s.i.g. "Proof roll" vehicles shall not travel at speeds greater than
3 m.p.h. Any portion of the subgrade or base material which exhibits excessive pumping or deformation, as determined by the City of Fort Collins
Engineer, shall be reworked, replaced or otherwise modified to form a smooth, non-yielding surface. The City of Fort Collins Engineer shall be
notified at least 24 hours prior to the "proof roll." All "proof rolls" shall be preformed in the presence of an Inspector.
C. Traffic Signing and Pavement Marking Construction Notes
1.All signage and marking is subject to the General Notes on the cover sheet of these plans, as well as the Traffic Signing and Marking Construction
Notes listed here.
2.All symbols, including arrows, ONLYS, crosswalks, stop bars, etc. shall be pre-formed thermo-plastic.
3.All signage shall be per the City of Fort Collins Standards and these plans or as otherwise specified in MUTCD.
4.All lane lines for asphalt pavement shall receive two coats of latex paint with glass beads.
5.All lane lines for concrete pavement should be epoxy paint.
6.Prior to permanent installation of traffic striping and symbols, the Developer shall place temporary tabs or tape depicting alignment and placement
of the same. Their placement shall be approved by the City of Fort Collins Traffic Engineer prior to permanent installation of striping and symbols.
7.Pre-formed thermo-plastic applications shall be as specified in these Plans and/or these Standards.
8.Epoxy applications shall be applied as specified in CDOT Standard Specifications for Road and Bridge Construction.
9.All surfaces shall be thoroughly cleaned prior to installation of striping or markings.
10.All sign posts shall utilize break-away assemblies and fasteners per the Standards.
11.A field inspection of location and installation of all signs shall be performed by the City of Fort Collins Traffic Engineer. All discrepancies identified
during the field inspection must be corrected before the 2-year warranty period will begin.
12.The Developer installing signs shall be responsible for locating and protecting all underground utilities.
13.Special care shall be taken in sign location to ensure an unobstructed view of each sign.
14.Signage and striping has been determined by information available at the time of review. Prior to initiation of the warranty period,the City of Fort
Collins Traffic Engineer reserves the right to require additional signage and/or striping if the City of Fort Collins Traffic Engineer determines that an
unforeseen condition warrants such signage according to the MUTCD or the CDOT M and S Standards. All signage and striping shall fall under the
requirements of the 2-year warranty period for new construction (except fair wear on traffic markings).
15.Sleeves for sign posts shall be required for use in islands/medians. Refer to Chapter 14, Traffic Control Devices, for additional detail.
D. Storm Drainage Notes
1.The City of Fort Collins shall not be responsible for the maintenance of storm drainage facilities located on private property. Maintenance of onsite
drainage facilities shall be the responsibility of the property owner(s).
2.All recommendations of the Final Drainage Report, dated March 1, 2023 by Northern Engineering shall be followed and implemented.
3.Prior to final inspection and acceptance by the City of Fort Collins, certification of the drainage facilities, by a registered engineer, must by
submitted to and approved by the Stormwater Utility Department. Certification shall be submitted to the Stormwater Utility Department at least two
weeks prior to the release of a certificate of occupancy for single family units. For commercial properties, certification shall by submitted to the
Stormwater Utility Department at least two weeks prior to the release of any building permits in excess of those allowed prior to certification per the
Development Agreement.
E. Utility Notes
1.All waterline and sanitary sewer construction shall conform to the City of Fort Collins Utility standards and specifications current to date of
construction.
2.The minimum cover over water lines is 4.5 feet and the maximum cover is 5.5 feet unless otherwise noted in the plans and approved by the water
utility.
3.Water mains shall be poly-wrapped D.I.P, or PVC with tracer wire.
4.HDPE pipe may be used for 1-1/2 and 2 inch water services. The pipe shall meet the standards of AWWA 901, NSF Standard 61 and ASTM. The
HDPE pipe shall be SDR 9 having a pressure rating of 200 psi. Stiffeners shall be used at all fittings and connections. Tracer wire shall be
installed with the HDPE service, and shall extend up the curb stop. The curb stop shall be covered with a metal valve box and "water" lid per City
Water Detail 11A.
INFILL AND REDEVELOPMENT NOTE
A.Despite everyone's best efforts, it is impossible to fully display subsurface information prior to excavation. This is especially true in areas of infill and
redevelopment. Unknown subsurface conditions can have cost and schedule implications. Prior to finalizing contract terms, it is strongly
recommended that the Owner and General Contractor have a candid discussion to formulate a strategy for dealing with such circumstances when
they arise. The process and procures should be in place prior to excavation. Allowances and contingencies can address the cost implications, but
additional measures are required to deal with scheduling and factors impacting sequence of work. The Architect, Engineer(s), and Construction
Surveyor should be made aware of the protocol for dealing with such unknown subsurface conditions prior to starting work.
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
3/28/2023
Does not match the most current format. See written comments.
LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LOD LOD
LODLOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD
LOD LOD LODLODLODLODLOD LODLODLODLODLODLODLODLODLODS
S
S
S
SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SSSSSS SSSSSSSSSSSSSSS
VAULT
ELEC
GGGSSSSSSSS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS SSSSSSSSSSVAULT
ELEC
VAULT
ELEC
VAULT
ELEC
VAULT
ELEC
ELEC
T
VAULT
F.O.F.O.
D
CONTROL
IRR
CONTROL
IRR
GAS
ELEC
BRKR
T SGGGGGGGG
GGGGGGGGGGGGGGGXSSS
SSSSSSSSSSSSSSSSSSSSS
SSSSSSSSSSOHUOHUD FE
SGGGG
G/ / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / /
/
/
// / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /FE
S
FE
S
FE
SST
STST
STST
STFESFESFES
VAULT
ELEC
GASSSSS
/ / / / / / / /S
D GCTV CTV CTV CTV CTVGGGGG
CTV CTV CTV CTV CTV CTV CTV
CTV
VAULT
CABLE
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRRSFSFSFSFSFSFSFSFSFSFSFSFSFSFSFSFSFSFSFSF SF SF SFSFSFSFSF
SF
SF
SF SF
SF
SF
SF
S
F
SF SF
SF
SF
SF
SF
SF
SF
SF
SF
SFCF
CF
CF
CF CF
CF
CF
CF
C
F
CF CF
CF
CF
CF
CF
CF
CF
CF
CF
EAST VINE DRIVECOLLEGE AVENUEJEROME STREETLAKE
C
A
N
A
L
JEROME STREET LLC,
216 E OAK ST
JEROME STREET STATION LLC,
742 N COLLEGE AVE
LMC VENTURES LLC,
742 N COLLEGE AVE
CITY OF FORT COLLINS
405 N COLLEGE AVE
MORAK KAREN LLC
622 N COLLEGE AVE
CITY OF FORT COLLINS,
740 N COLLEGE AVE
SF
SF
SF
SF
SF
SF
SF
SF
SF
SFCF
CF
CF
CF
CF
CF
SF
SFNORTH
( IN FEET )
0
1 INCH = 40 FEET
40 40 80 120
PROPOSED CONTOUR
PROPOSED STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
PROPOSED CURB & GUTTER
LEGEND:
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
EC1INITIAL EROSION CONTROL PLAN37
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION
Project: POWERHOUSE 2
CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING
BEST MANAGEMENT PRACTICES (BMPS)
STRUCTURAL "INSTALLATION"
Silt Fence Barriers *
Flow Barriers (Wattles) *
Inlet Filter Bags *
Vegetative
Temporary Seeding Planting
Mulching / Sealant
Permanent Seeding Planting
Sod Installation
Rolled Products : Netting / Blankets / Mats
Contour Furrows (Ripping / Disking)
Rock Bags *
UTILITIES
INSTALLATION
FLAT WORK
INSTALLATION
VERTICAL
INSTALLATION LANDSCAPE DEMOBILIZATION
Vehicle Tracking Pad *
* All Temporary BMPs to be Removed once Construction is Complete
Any prior inlets that
could use protecting
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Riprap
Construction Fence*
EROSION CONTROL NOTES:
1.IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR.
STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT
BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE
CONDITIONS OR AS REQUIRED BY LOCAL AUTHORITIES.
2.THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR
ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND
COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT
HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED.
4.CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE
CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, UNTIL SITE IS
FULLY STABILIZED.
6.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM
DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT.
7.INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e.,
STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8.CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP
MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING
MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE.
9.CONTRACTOR IS RESPONSIBLE FOR PREVENTING SEDIMENT FROM UNSTABILIZED LANDSCAPE AREAS FROM
MIGRATING ONTO AND ENTERING THE RAIN GARDEN SYSTEMS UNTIL UPGRADIENT TRIBUTARY AREAS ARE FULLY
STABILIZED.
10.ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO ENSURE THE BUILDING PAD IS
STABILIZED THROUGHOUT CONSTRUCTION. WATTLES SHALL BE PROVIDED AROUND THE BUILDING PAD SIDES TO
ENSURE AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
11.CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE.
PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION
(i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
12.FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER,
WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET
IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED
INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY.
13.CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL
BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES
MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR
BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE
GROUND, AND CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
14.THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY
CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE
INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE.
15.WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING
OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS
APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
16.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER
PERMANENT SITE STABILIZATION METHODS.
17.DIRT AND DEBRIS FROM CONSTRUCTION ACTIVITIES TRACKED ON CITY STREETS SHALL BE KEPT TO A MINIMUM AND
CLEANED IMMEDIATELY OR AT THE SUGGESTION OF THE CITY'S EROSION CONTROL INSPECTOR.
18.CONTRACTOR SHALL KEEP CONSTRUCTION VEHICLES ENTERING AND EXITING SITE TO A MINIMUM.
19.THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM INSTALLATION, PREVENT SEDIMENT, DEBRIS, AND
DIRT FROM ANY SOURCE FROM ENTERING THE RAIN GARDEN SYSTEM. LOOSE MATERIALS SHALL NOT BE STORED ON
THE RAIN GARDEN AREA. MUD AND SEDIMENT-LADEN RUNOFF SHOULD BE KEPT AWAY FROM THE RAIN GARDEN AREA.
TEMPORARILY DIVERT RUNOFF OR INSTALL SEDIMENT CONTROL MEASURES AS NECESSARY TO REDUCE THE AMOUNT
OF SEDIMENT RUN-ON TO THE RAIN GARDEN.
LIMITS OF DISTURBANCE
ROCK SOCK
SCOUR-STOP
WATTLE DIKE
CONCRETE WASH AREA
BALE OUTLET PROTECTION
INLET PROTECTION
VEHICLE TRACKING CONTROL PAD
LOD
AREA INLET PROTECTION
CONSTRUCTION FENCE CF
STAGING AREA
BENCHMARK/BASIS OF BEARING:
1.CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY
CRIMP MULCHING OR SIMILAR METHODS.
2.SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone ________________________________
3.CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
4.REFER TO THE FINAL DRAINAGE REPORT BY NORTHERN ENGINEERING FOR
ADDITIONAL INFORMATION.
5.THE NATURAL HABITAT BUFFER ZONE IS INTENDED TO BE MAINTAINED IN A
NATIVE LANDSCAPE. PLEASE SEE SECTION 3.4.1 OF THE LAND USE CODE
FOR ALLOWABLE USES WITHIN THE NATURAL HABITAT BUFFER ZONE.
GENERAL NOTES:
BENCHMARK: #1
CITY OF FORT COLLINS BENCHMARK 1-00
Elevation=4968.74
BENCHMARK: #2
CITY OF FORT COLLINS BENCHMARK 3-13
Elevation=4962.27
Basis of Bearings
The Basis of Bearings is the West line line of the Southwest Quarter of
Section 1-7-69 as bearing South 00° 38' 34" West (assumed bearing)
and monumented as shown on Plat.
IRRIGATED TURF
NATIVE SEED
SILT FENCE SF
3/28/2023
Does not match the required format.
See written comments.
Incorrect Sheet Numbering
G UGEUGE UGE UGE
UGES UD
UD
UD
UD UD
UD UDUDUDUD
UD
UD
UD
UD
UD
UD
UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGEVAULT
ELEC
GGGVAULT
ELEC
VAULT
ELEC
VAULT
ELEC
VAULT
ELEC
ELEC
T
VAULT
F.O.F.O.
D
CONTROL
IRR
CONTROL
IRR
GAS
ELEC
BRKR
T SGGGGGGGG
GGGGGGGGGGGGGGGXOHUOHUD FE
SGGGG
G/ / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / /
/
/
// / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /FE
S
FE
S
FE
SST
STST
STST
STFESFESFES
VAULT
ELEC
GAS
/ / / / / / / /D GCTV CTV CTV CTV CTVGGGGG
CTV CTV CTV CTV CTV CTV CTV
CTV
VAULT
CABLE
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
EM
GMTFTF
SFSFSFSFSFSFSF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SFSFSFEAST VINE DRIVECOLLEGE AVENUEJEROME STREETLAKE
C
A
N
A
L
JEROME STREET LLC,
216 E OAK ST
JEROME STREET STATION LLC,
742 N COLLEGE AVE
LMC VENTURES LLC,
742 N COLLEGE AVE
CITY OF FORT COLLINS
405 N COLLEGE AVE
MORAK KAREN LLC
622 N COLLEGE AVE
CITY OF FORT COLLINS,
740 N COLLEGE AVE
DETENTION
POND
25:17:18:127:142:138:166:145:135:173:174:177:
1
29:1
48:149:14:16:122:124:1
17:1
21:1 11:16:11
1
2
:
15:165:152:1SF
SFRAIN GARDEN 1
SEE SHEET RG1
SOUTH RAIN GARDEN 1
SEE SHEET RG2
SOUTH RAIN GARDEN 2
SEE SHEET RG2
SOUTH RAIN GARDEN 3
SEE SHEET RG2SFSF
SF
SF
SF SF
SF
SF
SF
SF SF SF
SF
SF
SF
SF
SF
SF
SF
SF
SFCF
CF
CF
CF CF
CF
CF
CF
C
F
CF CF
CF
CF
CF
CF
CF
CF
CF
CF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SFCF
CF
CF
CF
CF
CF
LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LOD LOD
LODLOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD
LOD LOD LODLODLODLODLOD LODLODLODLODLODLODLODLODLODNORTH
( IN FEET )
0
1 INCH = 40 FEET
40 40 80 120
PROPOSED CONTOUR
PROPOSED STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
PROPOSED CURB & GUTTER
ROCK SOCK
SCOUR-STOP
WATTLE DIKE
CONCRETE WASH AREA
BALE OUTLET PROTECTION
LEGEND:
INLET PROTECTION
VEHICLE TRACKING CONTROL PAD
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
EC2INTERIM EROSION CONTROL PLAN37
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
AREA INLET PROTECTION
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION
Project: POWERHOUSE 2
CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING
BEST MANAGEMENT PRACTICES (BMPS)
STRUCTURAL "INSTALLATION"
Silt Fence Barriers *
Flow Barriers (Wattles) *
Inlet Filter Bags *
Vegetative
Temporary Seeding Planting
Mulching / Sealant
Permanent Seeding Planting
Sod Installation
Rolled Products : Netting / Blankets / Mats
Contour Furrows (Ripping / Disking)
Rock Bags *
UTILITIES
INSTALLATION
FLAT WORK
INSTALLATION
VERTICAL
INSTALLATION LANDSCAPE DEMOBILIZATION
Vehicle Tracking Pad *
* All Temporary BMPs to be Removed once Construction is Complete
Any prior inlets that
could use protecting
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Riprap
Construction Fence*
EROSION CONTROL NOTES:
1.IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR.
STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT
BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE
CONDITIONS OR AS REQUIRED BY LOCAL AUTHORITIES.
2.THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR
ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND
COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT
HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED.
4.CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE
CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, UNTIL SITE IS
FULLY STABILIZED.
6.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM
DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT.
7.INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e.,
STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8.CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP
MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING
MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE.
9.CONTRACTOR IS RESPONSIBLE FOR PREVENTING SEDIMENT FROM UNSTABILIZED LANDSCAPE AREAS FROM
MIGRATING ONTO AND ENTERING THE RAIN GARDEN SYSTEMS UNTIL UPGRADIENT TRIBUTARY AREAS ARE FULLY
STABILIZED.
10.ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO ENSURE THE BUILDING PAD IS
STABILIZED THROUGHOUT CONSTRUCTION. WATTLES SHALL BE PROVIDED AROUND THE BUILDING PAD SIDES TO
ENSURE AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
11.CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE.
PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION
(i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
12.FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER,
WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET
IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED
INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY.
13.CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL
BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES
MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR
BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE
GROUND, AND CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
14.THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY
CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE
INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE.
15.WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING
OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS
APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
16.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER
PERMANENT SITE STABILIZATION METHODS.
17.DIRT AND DEBRIS FROM CONSTRUCTION ACTIVITIES TRACKED ON CITY STREETS SHALL BE KEPT TO A MINIMUM AND
CLEANED IMMEDIATELY OR AT THE SUGGESTION OF THE CITY'S EROSION CONTROL INSPECTOR.
18.CONTRACTOR SHALL KEEP CONSTRUCTION VEHICLES ENTERING AND EXITING SITE TO A MINIMUM.
19.THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM INSTALLATION, PREVENT SEDIMENT, DEBRIS, AND
DIRT FROM ANY SOURCE FROM ENTERING THE RAIN GARDEN SYSTEM. LOOSE MATERIALS SHALL NOT BE STORED ON
THE RAIN GARDEN AREA. MUD AND SEDIMENT-LADEN RUNOFF SHOULD BE KEPT AWAY FROM THE RAIN GARDEN AREA.
TEMPORARILY DIVERT RUNOFF OR INSTALL SEDIMENT CONTROL MEASURES AS NECESSARY TO REDUCE THE AMOUNT
OF SEDIMENT RUN-ON TO THE RAIN GARDEN.
CONSTRUCTION FENCE CF
STAGING AREA
BENCHMARK/BASIS OF BEARING:
1.CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY
CRIMP MULCHING OR SIMILAR METHODS.
2.SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone ________________________________
3.CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
4.REFER TO THE FINAL DRAINAGE REPORT BY NORTHERN ENGINEERING FOR
ADDITIONAL INFORMATION.
5.THE NATURAL HABITAT BUFFER ZONE IS INTENDED TO BE MAINTAINED IN A
NATIVE LANDSCAPE. PLEASE SEE SECTION 3.4.1 OF THE LAND USE CODE
FOR ALLOWABLE USES WITHIN THE NATURAL HABITAT BUFFER ZONE.
GENERAL NOTES:
BENCHMARK: #1
CITY OF FORT COLLINS BENCHMARK 1-00
Elevation=4968.74
BENCHMARK: #2
CITY OF FORT COLLINS BENCHMARK 3-13
Elevation=4962.27
Basis of Bearings
The Basis of Bearings is the West line line of the Southwest Quarter of
Section 1-7-69 as bearing South 00° 38' 34" West (assumed bearing)
and monumented as shown on Plat.
IRRIGATED TURF
NATIVE SEED
LIMITS OF DISTURBANCE LOD
SILT FENCE SF
3/28/2023
Does not match the required format.
See written comments.
Incorrect Sheet Numbering
G UGEUGE UGE UGE
UGES UD
UD
UD
UD UD
UD UDUDUDUD
UD
UD
UD
UD
UD
UD
UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGE UGEVAULT
ELEC
GGGVAULT
ELEC
VAULT
ELEC
VAULT
ELEC
VAULT
ELEC
ELEC
T
VAULT
F.O.F.O.
D
CONTROL
IRR
CONTROL
IRR
GAS
ELEC
BRKR
T SGGGGGGGG
GGGGGGGGGGGGGGGXOHUOHUD FE
SGGGG
G/ / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / /
/
/
// / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /FE
S
FE
S
FE
SST
STST
STST
STFESFESFES
VAULT
ELEC
GAS
/ / / / / / / /D GCTV CTV CTV CTV CTVGGGGG
CTV CTV CTV CTV CTV CTV CTV
CTV
VAULT
CABLE
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
EM
GMTFTF
EAST VINE DRIVECOLLEGE AVENUEJEROME STREETLAKE
C
A
N
A
L
JEROME STREET LLC,
216 E OAK ST
JEROME STREET STATION LLC,
742 N COLLEGE AVE
LMC VENTURES LLC,
742 N COLLEGE AVE
CITY OF FORT COLLINS
405 N COLLEGE AVE
MORAK KAREN LLC
622 N COLLEGE AVE
CITY OF FORT COLLINS,
740 N COLLEGE AVE
24:1 9:16:131:111:129:144:138:1122:157:153:144:155:16
8
:
174:136:1
65
:
1
46:15:145:124:1
87:15
0
:
1
19:15:15:111:124:1
17:1
21:1
12:1 5:16:11
1
2
:
1
POND OUTLET
STRUCTURE A
TYPE D INLET
TYPE R INLET
COMBINATION INLET
RAIN GARDEN
EMERGENCY SPILLWAY
RAIN GARDEN
EMERGENCY SPILLWAY
RAIN GARDEN
EMERGENCY SPILLWAYRAIN GARDEN
EMERGENCY SPILLWAY LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LOD LOD
LODLOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD
LOD LOD LODLODLODLODLOD LODLODLODLODLODLODLODLODLODDETENTION
POND
RAIN GARDEN 1
SEE SHEET RG1
SOUTH RAIN GARDEN 1
SEE SHEET RG2
SOUTH RAIN GARDEN 2
SEE SHEET RG2
SOUTH RAIN GARDEN 3
SEE SHEET RG2
NORTH
( IN FEET )
0
1 INCH = 40 FEET
40 40 80 120
PROPOSED CONTOUR
PROPOSED STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
PROPOSED CURB & GUTTER
LEGEND:
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
EC3FINAL EROSION CONTROL PLAN37
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION
Project: POWERHOUSE 2
CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING
BEST MANAGEMENT PRACTICES (BMPS)
STRUCTURAL "INSTALLATION"
Silt Fence Barriers *
Flow Barriers (Wattles) *
Inlet Filter Bags *
Vegetative
Temporary Seeding Planting
Mulching / Sealant
Permanent Seeding Planting
Sod Installation
Rolled Products : Netting / Blankets / Mats
Contour Furrows (Ripping / Disking)
Rock Bags *
UTILITIES
INSTALLATION
FLAT WORK
INSTALLATION
VERTICAL
INSTALLATION LANDSCAPE DEMOBILIZATION
Vehicle Tracking Pad *
* All Temporary BMPs to be Removed once Construction is Complete
Any prior inlets that
could use protecting
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Riprap
Construction Fence*
EROSION CONTROL NOTES:
1.IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR.
STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT
BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE
CONDITIONS OR AS REQUIRED BY LOCAL AUTHORITIES.
2.THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR
ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND
COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT
HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED.
4.CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE
CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, UNTIL SITE IS
FULLY STABILIZED.
6.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM
DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT.
7.INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e.,
STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8.CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP
MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING
MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE.
9.CONTRACTOR IS RESPONSIBLE FOR PREVENTING SEDIMENT FROM UNSTABILIZED LANDSCAPE AREAS FROM
MIGRATING ONTO AND ENTERING THE RAIN GARDEN SYSTEMS UNTIL UPGRADIENT TRIBUTARY AREAS ARE FULLY
STABILIZED.
10.ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO ENSURE THE BUILDING PAD IS
STABILIZED THROUGHOUT CONSTRUCTION. WATTLES SHALL BE PROVIDED AROUND THE BUILDING PAD SIDES TO
ENSURE AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
11.CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE.
PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION
(i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
12.FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER,
WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET
IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED
INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY.
13.CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL
BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES
MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR
BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE
GROUND, AND CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
14.THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY
CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE
INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE.
15.WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING
OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS
APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
16.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER
PERMANENT SITE STABILIZATION METHODS.
17.DIRT AND DEBRIS FROM CONSTRUCTION ACTIVITIES TRACKED ON CITY STREETS SHALL BE KEPT TO A MINIMUM AND
CLEANED IMMEDIATELY OR AT THE SUGGESTION OF THE CITY'S EROSION CONTROL INSPECTOR.
18.CONTRACTOR SHALL KEEP CONSTRUCTION VEHICLES ENTERING AND EXITING SITE TO A MINIMUM.
19.THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM INSTALLATION, PREVENT SEDIMENT, DEBRIS, AND
DIRT FROM ANY SOURCE FROM ENTERING THE RAIN GARDEN SYSTEM. LOOSE MATERIALS SHALL NOT BE STORED ON
THE RAIN GARDEN AREA. MUD AND SEDIMENT-LADEN RUNOFF SHOULD BE KEPT AWAY FROM THE RAIN GARDEN AREA.
TEMPORARILY DIVERT RUNOFF OR INSTALL SEDIMENT CONTROL MEASURES AS NECESSARY TO REDUCE THE AMOUNT
OF SEDIMENT RUN-ON TO THE RAIN GARDEN.
ROCK SOCK
SCOUR-STOP
WATTLE DIKE
CONCRETE WASH AREA
BALE OUTLET PROTECTION
INLET PROTECTION
VEHICLE TRACKING CONTROL PAD
AREA INLET PROTECTION
CONSTRUCTION FENCE CF
STAGING AREA
BENCHMARK/BASIS OF BEARING:
1.CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY
CRIMP MULCHING OR SIMILAR METHODS.
2.SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone ________________________________
3.CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
4.REFER TO THE FINAL DRAINAGE REPORT BY NORTHERN ENGINEERING FOR
ADDITIONAL INFORMATION.
5.THE NATURAL HABITAT BUFFER ZONE IS INTENDED TO BE MAINTAINED IN A
NATIVE LANDSCAPE. PLEASE SEE SECTION 3.4.1 OF THE LAND USE CODE
FOR ALLOWABLE USES WITHIN THE NATURAL HABITAT BUFFER ZONE.
GENERAL NOTES:
BENCHMARK: #1
CITY OF FORT COLLINS BENCHMARK 1-00
Elevation=4968.74
BENCHMARK: #2
CITY OF FORT COLLINS BENCHMARK 3-13
Elevation=4962.27
Basis of Bearings
The Basis of Bearings is the West line line of the Southwest Quarter of
Section 1-7-69 as bearing South 00° 38' 34" West (assumed bearing)
and monumented as shown on Plat.
IRRIGATED TURF
NATIVE SEED
LIMITS OF DISTURBANCE LOD
SILT FENCE SF
3/28/2023
Does not match the required format.
See written comments.
Incorrect Sheet Numbering
Line Over Text
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
EC4EROSION CONTROL DETAILS37
VTC
ROCK SOCK SECTION ROCK SOCK PLAN
ROCK SOCK JOINTING
GRADATION TABLE
SIEVE SIZE
MASS PERCENT
PASSING SQUARE
MESH SIEVES
NO. 4
2"100
1-1/2"90-100
1"20-55
3/4"0-15
3/8"0-5
MATCHES SPECIFICATIONS FOR NO. 4 COARSE AGGREGATE FOR
CONCRETE PER AASHTO M43. ALL ROCK SHALL BE FRACTURED FACE,
ALL SIDES
RS
001 CONCRETE WASHOUT AREA 002 ROCK SOCK 003 VEHICLE TRACKING PAD
004 SILT FENCE
SF
CWA
005 CURB INLET PROTECTION
IP
POSTS
PREASSEMBLED SILT FENCE POSTS SHALL OVERLAP
AT JOINTS SO THAT NO
GAPS EXIST IN SILT FENCE.
NOTE:
THICKNESS OF GEOTEXTILE
HAS BEEN EXAGGERATED.POST SHALL BE JOINED AS SHOWN, THEN
ROTATED 180° IN DIRECTION SHOWN AND
DRIVEN INTO THE GROUND.
SILT FENCE JOINTS
DRIVE POSTS VERTICALLY INTO THE GROUND TO A MINIMUM DEPTH OF 18".
EXCAVATE A TRENCH APPROXIMATELY 4" WIDE AND 4" DEEP ALONG THE
LINE OF POSTS AND UPSLOPE FROM THE BARRIER.
ANCHOR TRENCH SHALL BE EXCAVATED BY HAND, WITH TRENCHER, OR
WITH SILT FENCE INSTALLATION MACHINE. NO ROAD GRADERS, BACKHOES,
ETC. SHALL BE USED.
NOT LESS THAN THE BOTTOM 1' OF THE SILT FENCE FABRIC SHALL BE
BURIED IN THE TRENCH.
THE TRENCH SHALL BE COMPACTED BY HAND, WITH "JUMPING JACK" OR BY
WHEEL ROLLING. COMPACTION SHALL BE SUCH THAT THE SILT FENCE
RESISTS BEING PULLED OUT OF ANCHOR TRENCH BY HAND.
SILT FENCE INDICATED IN THE PLANS SHALL BE INSTALLED PRIOR TO ANY
LAND-DISTURBING ACTIVITIES.
USE WOOD POSTS OR OTHER MATERIAL AS ACCEPTED BY THE CITY.
INSTALLATION NOTES:
1.
2.
3.
4.
5.
6.
7.
THE CONTRACTOR SHALL INSPECT SILT FENCE EVERY TWO WEEKS AND
AFTER SIGNIFICANT STORM EVENTS AND MAKE REPAIRS OR CLEAN OUT
UPSTREAM SEDIMENT AS NECESSARY.
SEDIMENT ACCUMULATED UPSTREAM OF SILT FENCE SHALL BE REMOVED
WHEN THE UPSTREAM SEDIMENT REACHES A DEPTH OF 6".
SILT FENCE SHALL BE REMOVED WHEN THE UPSTREAM DISTURBED AREA IS
STABILIZED AND GRASS COVER IS ACCEPTED BY THE CITY. IF ANY
DISTURBED AREA EXISTS AFTER REMOVAL, IT SHALL BE SEEDED AND
MULCHED OR OTHERWISE STABILIZED IN A MANNER ACCEPTED BY THE CITY.
MAINTENANCE NOTES:
1.
2.
3.
4" MIN.
4" MIN.
1 12" x 1 12" WOODEN FENCE POSTS
SF
006 SWALE WATTLE DIKE 007
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
WITH NO GAPS (TYP.)
TIGHTLY ABUTTING
ENTRENCH 3"FLOWFLOWNOTE:
ENTRENCH WATTLE 3" INTO
NATURAL GROUND AT THE OUTSIDE
EDGE OF CONCRETE APRON
WATTLE
WATTLE
OR
NOTE:
INSTALLATION OF WATTLE STAKES
MAY VARY
(10" MIN. DIAMETER)
IPA
DROP INLET WATTLE FILTER
008 CALCULATION TABLE PER FCSCM CH. 2, SEC. 6.1.3.1
Description Estimated Quantity Units
Total Disturbed Project Area 5.6 Acre
Total "Onsite" Area of Disturbance 4.73 Acre
Total "Offsite" Area of Disturbance 0.87 Acre
Total Storage/Staging Area 1 Acre
Total Haul Roads Area N/A
Construction vehicle traffic Area N/A
Est. Percent of Project Area Exposed 100 %
Est. Percent Vegetation Cover 5 %
Existing Soil Type B Table Mountain loam, 0 to 1% slopes
Groundwater Depth 8 Feet
Number of Phases w/Project N/A
Total volume of imported (+) / exported (-) materials 8,900 Cubic Yds.
Total area of stockpilling of fill or borrow areas off site 0 Sq. feet
Steepest Slope 8:1 H:V
Distance from riparian area or sensitive area 0 Feet
3/28/2023
Incorrect Sheet Numbering
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
EC5EROSION CONTROL DETAILS37
001
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
SECTION G-G
G
PLAN
G
BOP
BALE OUTLET PROTECTION
3/28/2023
Incorrect Sheet Numbering
D
STT
VAULT
F.O.F.O.
D
CONTROL
IRR
CONTROL
IRR
GAS
XOHUOHUOHUD FE
S/ / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / /
/
/
// / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /FE
S
FE
SFE
SST
STST
STST
ST
F E
SFE
SFE
SGAS
/ / / / / / / /D
CTV CTV CTV CTV CTV
CTV CTV CTV CTV CTV CTV CTV
CTV
VAULT
CABLE
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRRFLOODWAY ZONE AE
930
72312351341
4964.34966.04967.64964.2
FFE=69.00
JEROME STREET LLC, 216
E OAK ST FORT COLLINS
JEROME STREET STATION LLC,
742 N COLLEGE AVE
LMC VENTURES LLC,
742 N COLLEGE AVE
CITY OF FORT COLLINS
405 N COLLEGE AVE
MORAK KAREN LLC
622 N COLLEGE AVE
CITY OF FORT COLLINS,
740 N COLLEGE AVE
EM
GMTFTF
68.8968.85JEROME STREETCOLLEGE AVENUEVINE DRIVE
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
500 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
500 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
500 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
500 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
100 YR FLOOD PLAIN
(CURRENT EFFECTIVE)
SheetPOWERHOUSE 2These drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETof 37
( IN FEET )
1 inch = ft.
Feet04040
40
80 120
FP1FLOODPLAIN EXHIBIT37
NORTH
LEGEND:
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
PROPOSED CURB & GUTTER
PROPOSED STORM INLET
PROPOSED CONCRETE
CROSS PAN (TYP.)
PEDESTRIAN ACCESS RAMPS
PROPERTY BOUNDARY
CROSS-SECTION (CSU CLOMR) 2446
NOTES:
1.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS, UTILITY
EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION
2.THIS PROJECT IS LOCATED WITHIN A FEMA DESIGNATED 100-YEAR FLOODPLAIN FRINGE AND MUST
COMPLY WITH CHAPTER 10 OF THE CITY CODE.
3.ALL ELEVATIONS DEPICTED IN PLAN VIEW AND BENCHMARKS LISTED HEREON ARE PER THE CITY OF
FORT COLLINS VERTICAL CONTROL DATUM (NAVD 88).
4.ANY ITEMS LOCATED IN THE FLOODPLAIN ON THE POUDRE RIVER THAT CAN FLOAT (E.G., PICNIC
TABLES, BIKE RACKS, ETC.) MUST BE ANCHORED.
5.A FLOODPLAIN USE PERMIT SHALL BE REQUIRED FOR EACH SITE CONSTRUCTION ELEMENT IN THE
FLOODPLAIN, INCLUDING BUILDING. THE FLOODPLAIN USE PERMIT FOR THE BUILDING WILL BE
APPROVED AT THE TIME OF BUILDING PERMIT APPLICATION.
6.A FLOODPLAIN USE PERMIT AND NO RISE CERTIFICATION IS REQUIRED PRIOR TO PERFORMING ANY
WORK WITHIN THE FLOODPLAIN (I.E., CURB CUT REMOVAL, LANDSCAPING).
7.NO OVERNIGHT STORAGE OF MATERIALS OR EQUIPMENT SHALL BE ALLOWED IN THE FLOODPLAIN,
WHETHER TEMPORARY (DURING CONSTRUCTION) OR PERMANENT. LANDSCAPING SHALL ALSO
MEET THE REQUIREMENTS FOR NO RISE IN THE FLOODPLAIN.
8.REFER TO THE FINAL DRAINAGE REPORT, DATED MARCH 1, 2023 FOR ADDITIONAL INFORMATION.
9.A POST-CONSTRUCTION ELEVATION CERTIFICATE INCLUDING COMPONENTS LIKE TRANSFORMER,
YARDS, EV CHARGING STATIONS, SOLAR PANEL COMPONENTS, ELEVATOR, HVAC EQUIPMENT,
EMERGENCY VEHICLE ACCESS GATE, OTHER ELECTRICAL AND MECHANICAL SYSTEMS, ETC. MUST
BE APPROVED BEFORE A CERTIFICATE OF OCCUPANCY WILL BE ISSUED.
10.TRANSFORMER, YARDS, EV CHARGING STATIONS, SOLAR PANEL COMPONENTS, ELEVATOR, HVAC
EQUIPMENT, EMERGENCY VEHICLE ACCESS GATE, OTHER ELECTRICAL AND MECHANICAL SYSTEMS
ARE TO BE PLACED AT OR ABOVE THE REGULATORY FLOOD PROTECTION ELEVATION.
11.FURNITURE OR SITE COMPONENTS WILL BE SECURELY ANCHORED TO GRADE WITH A SYSTEM TO BE
4" LAGS BOLTS EPOXIED INTO GROUND BASE CONCRETE OR STONE WITH STRAPS AND/OR CHAINS
SECURED TO ELEMENTS TO PREVENT FLOTATION. ANCHORING DETAILS WILL BE SUPPLIED AT THE
TIME OF THE FLOODPLAIN USE PERMIT.
12.ALL ELEVATORS INSTALLED BELOW THE RFPE IN THE PROJECT WILL COMPLY WITH FEMA NFIP
TECHNICAL BULLETIN 4 JUNE, 2019 AND THE 2021 IBC.
13.HORIZONTAL CONTROL: CITY OF FORT COLLINS GROUND MASTER CONTROL.
14.CRITICAL FACILITIES ARE PROHIBITED IN THE FLOODPLAIN, INCLUDING HAZARDOUS MATERIAL,
GOVERNMENT SERVICES, ESSENTIAL SERVICES AND AT-RISK POPULATION CRITICAL FACILITIES.
THIS INCLUDES SCHOOLS AND AFTER SCHOOL PROGRAMS/DAY CAMPS FOR GRADES K-12.
15.AN EMERGENCY RESPONSE AND PREPAREDNESS PLAN (ERPP) WILL BE REQUIRED BY THE CITY OF
FORT COLLINS PRIOR TO A FLOODPLAIN OR BUILDING PERMIT BEING ISSUED.
16.OUTDOOR CLASSROOM AS AN INFORMAL OUTDOOR GATHERING SPACE TO BE USED FOR SITE
TOURS AND OUTDOOR LEARNING. THESE SPACES WILL BE CONSTRUCTED USING LARGE BOULDERS
AND CRUSHED-FINE SURFACING.
17.THE QUANTITIES LISTED BELOW AND THE REMOVAL OF HYDROGEN STORAGE FROM THE SITE, WILL
REMOVE THE DESIGNATION OF A “CRITICAL FACILITY', AS PER DEFINED BY CHAPTER 10 OF CITY
CODE, FROM THE PROJECT. MATERIAL STORAGE RESTRICTIONS WILL BE REMOVED WITH THE
APPROVAL OF THE LOMR.
THE FOLLOWING OUTLINES THE HANDLING AND STORAGE PROCESSES OF HYDROGEN FOR
RESEARCH PROCEDURES ANTICIPATED AT THE PROPOSED POWERHOUSE II FACILITY:
·HYDROGEN PRODUCED BY HYDROLYSIS OR SIMILAR METHOD WILL BE DISPOSED OF AS PRODUCED
VIA VENTING OUTDOORS (AS PER ANY CODE REQUIREMENTS), BURNED IN OUTDOORS IN A
NON-VISIBLE FLARE, CONSUMED BY FUEL CELL OR SIMILAR DEVICE.
·ONSITE STORAGE OF HYDROGEN WILL REMAIN AT OR BELOW QUANTITIES REGULATED BY
INTERNATIONAL FIRE SAFETY CODE OR “HOUSEHOLD LEVELS”
·HYDROGEN FUELED VEHICLES, SUCH AS AUTOMOBILES, LIGHT AND MEDIUM DUTY TRUCKS, AND
TRANSIT BUSES WILL BE TESTED ONSITE AND ADHERE TO ALL FIRE SAFETY CODES AND DOT
REGULATIONS REGARDING HYDROGEN FUELED VEHICLES. NO VEHICLES WILL BE STORED
OUTSIDE OVERNIGHT PER THE FLOATABLE MATERIALS REQUIREMENTS IN CHAPTER 10 OF CITY
CODE.
·H2 STORAGE TANKS WILL REMAIN AT POWERHOUSE I UNTIL APPROVAL OF THE LOMR.
FLAMMABLE MATERIALS:
·ACETYLENE : 1 COMMERCIAL CYLINDER AT 300 OR LESS STD. CU. FT. VOLUME.
·OXYGEN : 1 COMMERCIAL CYLINDER AT 300 OR LESS STD. CU. FT. VOLUME.
NON-REACTIVE GASES:
·COMPRESSED AIR : 500 GAL. TANK
·COMPRESSED NITROGEN : 2000 L. CRYOGENIC TANK, LIQUID
·COMPRESSED ARGON : 2000 L. CRYOGENIC TANK, LIQUID
·COMPRESSED HELIUM : <20 - 300 STD. CU FT, STEEL CYLINDERS
·COMPRESSED ARGON : <20 - 300 STD. CU FT, STEEL CYLINDERS
·COMPRESSED CO2 : <20 - 300 STD. CU FT, STEEL CYLINDERS
18.THE PROPOSED POWERHOUSE II BUILDING IS PROJECTED TO HOUSE SEVERAL TYPES OF
ORGANIZATIONS: RETAIL, PRIVATE COMPANIES WORKING IN ENERGY INDUSTRY, AND COLORADO
STATE UNIVERSITY (CSU) FUNCTIONS RELATING TO SPONSORED RESEARCH. THE CSU SPACE WILL
BE ASSIGNED TO RESEARCHERS TO CONDUCT SPONSORED RESEARCH FOR INDUSTRY AND
GOVERNMENT (LOCAL, CITY, STATE AND FEDERAL) SPONSORS. THESE SPACES WILL NOT BE USED
FOR TRADITIONAL EDUCATIONAL FUNCTIONS SUCH AS CLASSROOM INSTRUCTION OR LABORATORY
INSTRUCTION. WHILE UNIVERSITY EMPLOYEES (RESEARCHERS, STAFF, AND STUDENT EMPLOYEES)
WILL BE USING THE SPACE THEY WILL NOT BE ENGAGED IN INSTRUCTIONAL ACTIVITIES.
GOVERNMENT SERVICES FACILITIES INCLUDE ESSENTIAL STRUCTURES SUCH AS DORMITORIES,
OFFICES, CLASSROOMS, AND LABORATORIES FOR PUBLIC HIGHER EDUCATION FACILITIES.
POWERHOUSE II WILL NOT BE USED FOR DORMITORY HOUSING. NOR WILL IT HAVE INSTRUCTIONAL
CLASSROOMS AND THE LABORATORY AND OFFICE SPACES WILL BE USED SOLELY FOR SPONSORED
RESEARCH ACTIVITIES. GIVEN THIS DEFINITION AND PURPOSES, POWERHOUSE II SHOULD NOT BE
CLASSIFIED AS A GOVERNMENT SERVICES FACILITY PER CHAPTER 10 OF CITY CODE AND THE
RESTRICTIONS ASSOCIATED WITH THIS DESIGNATION.
BENCHMARKS:
5000ELEVATION NGVD 88
100-YR FLOODPLAIN - (PER CSU CLOMR)
PROJECT DATUM: NAVD88
CITY OF FORT COLLINS BENCHMARK 1-00
ON A CATCH BASIN AT THE SOUTHEAST CORNER OF VINE DR. AND COLLEGE AVE.
ELEV.=4968.74
CITY OF FORT COLLINS BENCHMARK 3-13
APPROX.40 FT SOUTH OF THE LINDEN ST. BRIDGE OVER THE POUDRE RIVER, ON THE WEST SIDE OF
LINDEN ST. , ON A STORM INLET.
ELEV.=4962.27
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATION SHOULD
BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.18'
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE LINE OF THE SOUTHWEST QUARTER OF SECTION 1-7-69 AS
BEARING SOUTH 00° 38' 34" WEST (ASSUMED BEARING) AND MONUMENTED AS SHOWN ON PLAT.
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
MINIMUM FINISHED FLOOR ELEVATION (RFPE)
ELEVATION = C
BASE FLOOD ELEVATION
(BFE) = A
MINIMUM MECH./ELEC. EQUIPMENT
ELEVATION = B (RFPE)
BASE FLOOD ELEVATION
(BFE) = A
MECH. /
ELEC.
EQUIPMENT
FLOOD ELEVATION DETAIL
NTS
SLAB-ON-GRADE
BUILDING SUMMARY
ELEV. DESIGNATION PROJECT ELEV.
(NAVD 88)
A 4966.44 FT
B 4968.44 FT
C 4968.44 FT
FINISHED FLOOR
ELEVATION 4969.00 FT
FIELD SURVEY BY:
NORTHERN ENGINEERING
DATED: OCTOBER 25, 2019
3/28/2023
Does not match the required format. See written comments.