January 28, 1994
Albrecht Homes
C/o Mr. Frank Vaught
Vaught -Frye Architects
1113 Stoney Hill Drive
Fort Collins, CO 80525
Dear Frank:
For your information, attached is a copy of the Staff's comments concerning
Courtyard Homes at Miramont (Tract Q of Oak Cottonwood Farm), presented before
the Conceptual Review Team on. January 24, 1994.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincere ,
Tea Sheppard. P
Senior Planner
TS/gjd
Attachments
cc: Transportation Department
Stormwater Department
Project Planner
File
281 North College Avenue - P.O. Box 580 - Fort. Collins, CO 80522-0580 - (303) 221-6750
a
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: January 24, 1994
ITEM: Courtyard Homes at Miramont (Tract Q of Oak
Cottonwood Farm)
APPLICANT: Albrecht Homes c/o Mr. Frank Vaught, Vaught -Frye
Architects, 1113 Stoney Hill Drive, Fort Collins,
CO. 80525.
LAND II811 DATA:
Request to 55 to 60 single family lots on about 11 acres located
south of the Oak Hill Apartments and east of Boardwalk Drive, on
Tract Q of the Oak -Cottonwood Farm O.D.P. The "Courtyards"
features single family lots with lot widths ranging from 46 to 48
feet.. Private streets .are proposed. The City is in .the process of
negotiating the acquisition of a neighborhood park just south of
the subject property.
COMMENTS
1. Electrical system will be brought in from Boardwalk Drive. If
28 foot wide streets are proposed, Light and Power needs a
minimum of 12 feet wide utility easements along the fronts of
,the units for the electrical system. If you have any
questions, please call Alan Rutz, 221-6700.
2. Both water and sewer mains are available in Boardwalk Drive.
The waterline should be connected to the existing water line
in Rule Drive that is planned to serve the Tennis and Fitness
Center. If you have any questions, please.call Mark Taylor,
221-6681.
3. The Poudre Fire Authority will now allow cul-de-sacs to attain
a length of 900 feet without a second point of access.. The
Code, however, has not yet been amended and the 660 foot rule
is still applicable. Therefore, a variance must be applied
for.
4. The private streets must have inside turning radii of 20 feet
and outside turning radii of 40 feet.
5. At the present time, the Parkland Development Fee is $779 per
dwelling unit.
COMMUNITY PLANNINU &
ENVIRONMENTAL SERVICES 281 NORTH COLLEGE P.O.BOX S80 FORT COLLINS, COLORADO 8052241580 (303)221-6750
PLANNING DEPARTMENT
i
11
6. Please be aware that the pond will be an irrigation pond for
watering both the proposed park and the Miramont greenbelt
areas. It will be feature a'pump house.
7. It is strongly recommended that irrigated blue grass sod not
be planted to the edge.of the pond. This will attract geese.
8. Staff applauds the placing of a path around _the pond. The
edge of the pond should not be privatized by individual lot
owners as is the case with Harmony Cove Reservoir. Fencing of
rear yards adjacent to the pond should be sensitively designed
and include a gate.
9. The site is located in the McClelland -Mail Creek Drainage
Basin. The Stormwater drainage fee in this basin is $3,717
per developed acre, subject to the amount of impervious
surface and stormwater detention. The Drainage Report and
.Drainage and Grading Plan must comply with the Oak -Cottonwood
O.D.P. Drainage Study. Release rates are very strictly
controlled in this area and must be adhered to. An Erosion
Control Plan must be submitted with any final phase.
10. The Engineering Department will require the standard submittal
for Utility Plans.
11. The Street Oversizing Fee is $584 per dwelling unit.
12. Why doesn't the northerly .cul-de-sac tie into Rule Drive?
This would allow easy access to Lemay Avenue and improve
circulation for residents of the project.
13. A variance request for the 28 foot street will be required.
14. Solar orientation will apply. If a variance is necessary, it
must be in written form and accompany the P.U.D. submittal.
15. The ,P.U.D. will be reviewed by the new, Neighborhood
Compatibility Criteria. Also, developers are now responsible
for posting signs on the property and paying for postage.
16. Is the area between Lots 49 and 50-designated for guest
parking? Is the guest parking property distributed?
17. As with the Courtyards at Stone Ridge, there should be one
street tree per lot.