April 05, 2023
Nichole Rex
HOUSING CATALYST
1715 W MOUNTAIN AVE
Fort Collins, CO 805212359
RE: Impala Redevelopment, FDP230001, Round Number 3
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Impala Redevelopment. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Brandy Bethurem Harras via phone at 970‑416‑2744 or
via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras, 970‑416‑2744, bbethuremharras@fcgov.com
Topic: General
Comment Number: 1
01/31/2023: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone conversations. Thank you!
Comment Number: 2
01/31/2023: SUBMITTAL:
As part of your resubmittal, you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a different font color.
When replying to the comment letter please be detailed in your responses, as
all comments should be thoroughly addressed. Comments requiring action
should NOT have a response such as noted or acknowledged. You will need to
provide references to specific project plans, pages, reports, or explanations of
why comments have not been addressed [when applicable].
Comment Number: 3
01/31/2023: SUBMITTAL:
Please follow the Electronic Submittal Requirements and File Naming
Standards found at https://www.fcgov.com/developmentreview/files/electronic
submittal requirements and file naming standards_v1_8 1 19.pdf?1566857888.
File names should begin with the file type, followed by the project information, and round number.
Example: UTILITY PLANS_PROJECT NAME_PDP_Rd2.pdf
File type acronyms maybe appropriate to avoid extremely long file names.
Example: TIS for Traffic Impact Study, ECS for Ecological Characterization Study.
Reach out to me if you would like a list of suggested names.
*Please disregard any references to paper copies, flash drives, or CDs.
Comment Number: 4
01/31/2023: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set, and these
must be removed prior to submittal as they can cause issues with the PDF file. The default setting
is "1" ("on") in AutoCAD. To change the setting and remove this feature, type "EPDFSHX"
(version 2016.1) or “PDFSHX (version 2017 and newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing‑text‑appears‑as‑Comments‑in‑a‑PDF‑created‑by‑Aut oCAD.html
Comment Number: 5
01/31/2023: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut‑off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced notice as possible.
Comment Number: 6
01/31/2023: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration of your project.
Comment Number: 8
01/31/2023: FOR FINAL APPROVAL:
All "For Final Approval / For Approval" comments need to be addressed and
resolved prior to moving forward with the final documents and recording of this
project. I will provide a recording checklist and process information when we are closer to this step.
Comment Number: 9
01/31/2023: INFORMATION:
LUC 2.211 Lapse, Term of Vested Right: Within a maximum of three (3) years
following the approval of a final plan or other site‑specific development plan, the
applicant must undertake, install and complete all engineering improvements
(water, sewer, streets, curb, gutter, streetlights, fire hydrants and storm
drainage) in accordance with city codes, rules and regulations. The period of
time shall constitute the "term of the vested property right." Failure to undertake
and complete such engineering improvements within the term of the vested
property right shall cause a forfeiture of the vested property right and shall
require resubmission of all materials and reapproval of the same to be
processed as required by this Code. All dedications as contained on the final
plat shall remain valid unless vacated in accordance with law.
Department: Engineering Development Review
Contact: Tim Dinger, , tdinger@fcgov.com
Topic: General
Comment Number: 1
02/27/2023: FOR DEVELOPMENT AGREEMENT ‑ UPDATED:
We need the lender information to complete the first draft of the development
agreement. Please provide that as soon as possible, and email to your DRC.
01/19/2023: FOR DEVELOPMENT AGREEMENT:
The Development Agreement information form has "Julie J. Brewen" listed as
the both the individual that is signing the DA for the developers, as well as in the
attest field. The person who is attesting to Julie's signature must be a different
person than Julie, who is signing the DA for the developer. Please revise the
DA info form to have a different person in the attest field.
In the meantime, we will begin drafting the development agreement. We intend
on providing the first draft of the DA around the same time as we provide FDP round 2 comments
Comment Number: 3
03/06/2023: FOR ROW VACATION ‑ UPDATED:
The ROW vacation forms are under review. We will update you as we start the
vacation process through City Council.
01/25/2023: FOR ROW VACATION:
The ROW Vacation forms should be accompanied by a letter of request. The
letter of request should include a short (1 paragraph) description about what you
are proposing to vacate, and justification as to why the vacation is necessary. It
should also include your contact information. Please visit
https://www.fcgov.com/engineering/files/row‑vacation‑process_2022.pdf?1646
783322 for more information on the ROW vacation process.
Department: Stormwater Engineering
Contact: Stephen Agenbroad, , sagenbroad@fcgov.com
Topic: General
Comment Number: 5
03/31/2023: FOR FINAL APPROVAL ‑ UPDATED:
Please show the irrigation lateral on the storm water profile for Storm Drain 1.
03/10/2023: FOR FINAL APPROVAL:
The irrigation lateral is being located on March 15th. Further information will be
included in the final draft letter.
01/31/2023: FOR FINAL APPROVAL:
The irrigation lateral on the southern portion needs further discussion.
Comment Number: 13
03/31/2023: FOR FINAL APPROVAL:
In the forebay detail, please show that the forebay has been moved out of the
rain garden media or that a stable soil (#57 rock or native soil) is located under
the forebay to prevent any possible settling from occurring. In addition, please
lower the relief notch so that it is flush with the curb of the forebay, and make
sure the curb is flush with the rain garden media.
Department: Water‑Wastewater Engineering
Contact: Stephen Agenbroad, , sagenbroad@fcgov.com
Topic: General
Comment Number: 1
03/31/2023: FOR FINAL APPROVAL ‑ UPDATED:
Please submit the AWWA Manual M22 calcs as PDFs for filing purposes.
03/10/2023: FOR FINAL APPROVAL‑UNRESOLVED:
01/31/2023: FOR FINAL APPROVAL:
Please also include AWWA M22 meter sizing calculations for additional
reference. The IPC calculations can also be included but the city requires
AWWA M22 calculations be used when determining meter sizing.
Comment Number: 6
03/31/2023: FOR FINAL APPROVAL:
Based on the AWWA water meter spreadsheets, it appears that Building A
requires at least a 1.5‑inch meter. The utility plans show building A only having a
1‑inch meter. Please update the utility plans to match the meter sizing. In
addition, please submit the water meter sizing tables as PDFs for the next submittal.
Comment Number: 7
04/03/2023: INFORMATION ONLY
The city would suggest that the fire line does not run under the stairs that lead up
to the concrete patio. This is to ensure clear access in the case that the fire line
ever needed maintenance in the future.
Department: Light And Power
Contact: Austin Kreager, 970‑224‑6152, akreager@fcgov.com
Topic: General
Comment Number: 1
04/05/2023: FOR DCP:
Thank you for submitting the revised C‑1 Forms. On Building D, the maximum
conductor size allowed for connection into our single‑phase transformer is 350
kcmil. Please revise the C‑1 Form and One‑Line Diagram accordingly.
03/14/2023: FOR APPROVAL:
Thank you for submitting the C‑1 forms. I can't seem to find the one‑line
diagrams in your submittal though. Can you please send those directly to me? Thank you
02/01/2023: FOR APPROVAL:
Multi family buildings and duplexes are treated as customer owned services;
therefore a C‑1 form and one line diagram must be filled out and submitted to
Light & Power Engineering for each NEW building. All secondary electric
service work is the responsibility of the developer and their electrical consultant
or contractor. A C‑1 form can be found here:
https://www.fcgov.com/utilities/business/builders‑and‑developers/development‑f
orms‑guidelines‑regulations
Comment Number: 2
02/01/2023: INFORMATION:
Light & Power will need AutoCAD files of the site plan, utility plans, and
landscape drawings once plans are approved.
Comment Number: 3
02/01/2023: INFORMATION:
Electric capacity fees, development fees, building site charges and any system
modification charges necessary to feed the site will apply to this development.
Please contact me to discuss development fees or visit the following website for
an estimate of charges and fees related to this project:
http://www.fcgov.com/utilities/business/builders‑and‑developers/plant‑investmen t‑development‑fees
Comment Number: 5
04/05/2023: FOR DCP:
Thank you for submitting the revised C‑1 Forms. On Building D, the maximum
conductor size allowed for connection into our single‑phase transformer is 350
kcmil. Please revise the C‑1 Form and One‑Line Diagram accordingly.
03/14/2023: FOR APPROVAL:
The submitted C‑1 form shows three phase power being required for Building
D. Three phase power will not be available for that building coming from the
power source that was discussed During PDP. please coordinate with me
offline so that I can better understand why your power needs are higher than I
had anticipated.
Department: Park Planning
Contact: Missy Nelson, , mnelson@fcgov.com
Topic: General
Comment Number: 1
01/18/2023: INFORMATION:
Both Park Planning & Development and Parks department comments will be
provided by Missy Nelson | mnelson@fcgov.com
Comment Number: 3
04/04/2023: FOR FINAL APPROVAL:
Thanks for the update, when information is available, please show pipeline
location on final plan sets.
03/14/2023: FOR HEARING ‑ UPDATED: There have been delays in locating
the pipe. New Crew Chief are scheduled to deploy camera truck to locate 8am
on 3/15/23. Once located, please show on landscape and utility plans.
02/03/2023: Pipe location will need to be established prior to approval of
proposed storm line easement. Parks has it scheduled for Tuesday 2/7 and I
will contact applicant with the information as soon as I get it.
Department: Technical Services
Contact: Jeff County, 970‑221‑6588, jcounty@fcgov.com
Topic: Building Elevations
Comment Number: 3
04/04/2023: FOR FINAL APPROVAL‑UNRESOLVED:
Please change the title to match the other plan sets.
Topic: Construction Drawings
Comment Number: 8
04/04/2023: FOR FINAL APPROVAL‑UNRESOLVED:
All Benchmark Statements must match on all sheets.
Topic: Plat
Comment Number: 1
04/04/2023: FOR FINAL APPROVAL‑UPDATED:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the redlines, please contact John
Von Nieda at 970‑221‑6565 or HYPERLINK "mailto:jvonnieda@fcgov.com" jvonnieda@fcgov.com
Department: Forestry
Contact: Carrie Tomlinson, , ctomlinson@fcgov.com
Topic: General
Comment Number: 4
04/03/2023: FOR RECORDING:
Please exchange the horse chestnut for another species from the
recommended list emailed to you. No resubmittal or quick check is necessary for this
Department: Historic Preservation
Contact: Jim Bertolini, 970‑416‑4250, jbertolini@fcgov.com
Topic: General
Comment Number: 1
02/06/2023: FOR BUILDING PERMIT:
Plan appears consistent with recommendations from PDP. As noted during
PDP, a Plan of Protection must be submitted along with the Building Permit
application for the six‑plex on Mulberry, documenting plan for protecting the
Landmark (Ricketts Farmhouse) at 2300 W Mulberry St. during construction,
including equipment plan, materials storage, and contact info for on‑site team.
Department: Environmental Planning
Contact: Scott Benton, (970)416‑4290, sbenton@fcgov.com
Topic: General
Comment Number: 5
04/04/2023: INFORMATION:
This project requires a substantial amount of tree removal, thus the songbird
nesting survey to satisfy Migratory Bird Treaty Act and City LUC requirements
will be a substantial effort if tree removal occurs during the nesting season (Feb
1 ‑ July 31). Depending on project timing, this survey could be tied to DCP.