HomeMy WebLinkAboutTHE SAVOY - FDP230012 - SUBMITTAL DOCUMENTS - ROUND 1 - EROSION CONTROL LETTER/REPORTProject:Disturbed Acres:10.29
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
each 6 $250.00 $1,500.00
L.F.3,791 $1.10 $4,170.10
each 50 $125.00 $6,250.00
each 2 $1,700.00 $3,400.00
Outlet Protection each 0 $900.00 $0.00
each 1 $1,250.00 $1,250.00
Stabilized Staging Area S.Y.0 $4.75 $0.00
Sub-Total:$16,570.10
1.5 x Sub-Total:$24,855.15
Amount of security:$24,855.15
Minimum escrow amount:$3,000.00
Erosion Control Escrow:$24,855.15
Fields in yellow should be amended for this project.
Inital Erosion and Sediment Control Escrow/Security Calculation for
the City of Fort Collins
BMP Amount
Inlet Protection
Rock Socks
Miniumum Escrow Amount
The Savoy
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the
cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever
is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand
dollars ($3,000) for commercial development”
Silt Fence
Escrow Amount
Vehicle Tracking Control Pads
Concrete Washout Area
3/27/2023 4:19 PM P:\514-003\Drainage\Reports\SWMP Report\514-003-The Savoy-EC_Escrow.xls
Project:Disturbed Acres:10.29
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
each 97 $250.00 $24,250.00
Rock Socks each 16 $90.00 $1,440.00
each 6 $1,000.00 $6,000.00
Sub-Total:$31,690.00
1.5 x Sub-Total:$47,535.00
Amount of security:$47,535.00
Minimum escrow amount:$3,000.00
Erosion Control Escrow:$47,535.00
Fields in yellow should be amended for this project.
Escrow Amount
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the
cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever
is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand
dollars ($3,000) for commercial development”
Interim Erosion and Sediment Control Escrow/Security Calculation
for the City of Fort Collins
The Savoy
BMP Amount
Inlet Protection
Miniumum Escrow Amount
3/27/2023 4:19 PM P:\514-003\Drainage\Reports\SWMP Report\514-003-The Savoy-EC_Escrow.xls
Project:Disturbed Acres:10.29
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
acre 1.48 $1,000.00 $1,478.00
Sub-Total:$1,478.00
1.5 x Sub-Total:$2,217.00
Amount of security:$2,217.00
Total Acres x Price/acre:$10,290.00
$1,000.00 Sub-Total:$10,290.00
1.5 x Sub-Total:$15,435.00
Amount to Re-seed:$15,435.00
Minimum escrow amount:$3,000.00
Erosion Control Escrow:$15,435.00
Fields in yellow should be amended for this project.
Miniumum Escrow Amount
Escrow Amount
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the
cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever
is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand
dollars ($3,000) for commercial development”
Vegetate Landscaped Areas
Final Erosion and Sediment Control Escrow/Security Calculation for
the City of Fort Collins
The Savoy
BMP Amount
Reseeding Amount
Unit Price of Seeding per acre:
3/27/2023 4:19 PM P:\514-003\Drainage\Reports\SWMP Report\514-003-The Savoy-EC_Escrow.xls