HomeMy WebLinkAboutTHE SAVOY - FDP230012 - DECISION - VARIANCE REQUEST (2)
FORT COLLINS: 301 North Howes Street, Suite 100, 80521 | 970.221.4158
GREELEY: 820 8th Street, 80631 | 970.395.9880 | WEB: www.northernengineering.com
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Administrative Engineering Variance Request Letter
Date: September 13, 2022
Project: The Savoy Project No. 514-003
Fort Collins, Colorado
Attn: Sophie Buckingham and Spencer Smith
Engineering Development Review
City of Fort Collins
281 North College Avenue
Fort Collins, Colorado 80524
RE: Precision Drive and Brookfield Drive Cross-Section
Dear Staff:
Public safety and convenience, maintaining public use, and optimizing the use of limited physical capacity of
right-of-way are among the objectives of the Larimer County Urban Area Street Standards (LCUASS) – Repealed
and Reenacted August, 2021. It is with those considerations in mind that this variance request letter has been
prepared. This letter is provided pursuant to Section 1.9.4 of LCUASS to document the site condition proposed
to deviate from the current standards.
The criteria in question are the cross-section components for a Residential Local Street Section, as prescribed in
Section 7.4 of LCUASS. Under current Section 7.3 of LCUASS Precision Drive and Brookfield Drive would now
be classified as Connector Local Streets because the surrounding developments are a combination of
commercial and multifamily parcels. However, when Precision Drive and Brookfield Drive were designed and
built, they were classified as Residential Local Streets with right-of-way widths of 51’. Prior to the July 2021
revisions to LCUASS Chapter 7 Figures 7.1F – 7.13F, the city requested that The Savoy redo Precision Drive
and Brookfield Drive to match the Connector Local Street (Figure 7-8F) standard from September 2016. The
city’s reasoning was that they were getting complaints from surrounding neighbors that the Precision Drive and
Brookfield Drive feel too packed, and vehicles were having a hard time safely navigating the congested
roadways. Additionally, the city expressed a desire to bring these streets up to current LUCASS standards.
Therefore, to alleviate congestion on the roadway The Savoy is proposing to install 7’ deep inset parking spots
along the north side of Precision Drive and west side of Brookfield Drive. By moving the on-street parking into
these inset spots the roadway will be increased by 7’ bring the total width of the travel lanes from 16’ to 23’.
The current Connector Local Streets travel lane is 20’. Therefore, Precision Drive and Brookfield Drive will be
exceeding the current travel lane standards while also still providing on-street parking. However, with this
revision it is imperative that The Savoy be allowed to use attached walks along Precision Drive and Brookfield
Drive because of existing electrical, gas, and storm infrastructure located along the north side of Precision Drive.
The variance requested in this letter will not be detrimental to public health, safety, or welfare. The variance
requested will help alleviate vehicular congestion without having to move centerlines or existing utility
infrastructure. The requested variance will not have an adverse impact on the City’s capital and maintenance
costs, nor are they expected to reduce the design life of the respective improvements.
The Savoy | Variance Request | 09.13.2022
P:\514-003\Admin\Variance Requests\VarianceRequest - Street Cross-Section - Precision and Brookfield.docx
Page 2 of 2
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Please feel free to contact me if you have any questions.
Sincerely,
Northern Engineering
Blaine Mathisen, PE
Project Engineer
Attachment:
Cross-Sections
Brookfield Utility Plans (Original Design)
Brookfield Second Replat Utility Plans (Original Design)
SheetTHE SAVOYThese drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETENGINEERNGIEHTRONRNFORT COLLINS: 301 North Howes Street, Suite 100, 80521GREELEY: 820 8th Street, 80631970.221.4158northernengineering.comof 12
CS1 COVER STEET1
Northern Engineering
Project No. 514-003
Date: July 28, 2021
APRIL 2022 CONTACT INFORMATION
PROJECT TEAM:
VICINITY MAP
NORTH
City of Fort Collins Benchmark 7-01
NORTH SIDE OF HARMONY ROAD ON AN IRRIGATION STRUCTURE APPROX 100 FT.
WEST OF THE WEST CURB LINE OF THE EAST ENTRANCE TO H.P.
ELEV.=4941.52
City of Fort Collins Benchmark 7-07
0.5 MILES SOUTH OF HARMONY RD. AND STRAUSS CABIN RD., ON THE WEST SIDE
OF STRAUSS CABIN RD., ON THE NORTHWEST WINGWALL OF THE BRIDGE OVER
AN IRRIGATION CANAL ON A LARIMER COUNTY CAP.
ELEV.=4879.16
Please Note: This plan set is using NAVD88 for a vertical datum. Surrounding
developments have used NGVD29 Unadjusted for their vertical datums.
If NGVD29 Unadjusted Datum is required for any purpose, the following equation should be
used: NGVD29 Unadjusted = NAVD88 - 3.18'
Basis of Bearings
The Basis of Bearings is the East line of Tract A, Brookfield First Replat as bearing South
01° 23' 27" West.
PROJECT BENCHMARKS:
THE SAVOY
PROJECT TEAM:
Steve Allen
Henry Design Group
1501 Wazee St. Suite 1C
Denver, Colorado 80202
(303) 446-2368
Milestone Development
Ken Kikenr
1225 17th St Unit 29
Denver, CO 80202
(303) 298-7270
Northern Engineering Services, Inc.
Blaine Mathisen, PE
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
(970) 221-4158
LANDSCAPE ARCHITECT
OWNER/APPLICANT
SITE ENGINEER
SHEET INDEX
A REPLAT OF TRACT A, BROOKFIELD FIRST REPLAT, LOCATED IN THE NORTHEAST QUARTER OF SECTION 4, TOWNSHIP 6 NORTH,
RANGE 68 WEST OF THE 6TH P.M., CITY OF FORT COLLINS, COUNTY OF LARIMER, STATE OF COLORADO
ORIGINAL FIELD SURVEY BY:
Northern Engineering Services, Inc.
Bob Tessely, PLS
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
(970) 221-4158
SITE SURVEYOR
1 CS1 COVER SHEET
2 CS2 GENERAL & CONSTRUCTION NOTES
3 CS3 EROSION CONTROL NOTES
3 EX1 EXISTING CONDITIONS & DEMOLITION PLAN
5 HC1 HORIZONTAL CONTROL PLAN
UTILITY SHEETS
6 U1 UTILITY PLAN
GRADING SHEETS
7-10 G1-G4 GRADING PLANS
ROADWAY SHEETS
11 R1 LE FEVER DRIVE PLAN & PROFILE
DRAINAGE SHEETS
12 DR1 DRAINAGE EXHIBIT
PRELIMINARY UTILITY PLANS FOR
Earth Engineering Consultants, LLC
"Geologic and Preliminary Geotechnical Investigation - The Savoy"
Fort Collins, Colorado
EEC Project No. = FC10152-115
Date: November 17, 2021
SUBSURFACE EXPLORATION BY:
E N G I N E E R N GI
EHTRON R N
E N G I N E E R N GI
EHTRON R N
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
City of Fort Collins, CO
UTILITY PLAN APPROVAL
APPROVED:
CITY ENGINEER,APPROVED SHEETS DATE
APPROVED:
WATER & WASTEWATER UTILITY,APPROVED SHEETS DATE
APPROVED:
STORMWATER UTILITY,APPROVED SHEETS DATE
APPROVED:
PARK PLANNING & DEVELOPMENT,APPROVED SHEETS DATE
APPROVED:
TRAFFIC OPERATIONS,APPROVED SHEETS DATE
APPROVED:
ENVIRONMENTAL PLANNER,APPROVED SHEETS DATE
GAS-----------------Xcel Energy-----------------------------Stephanie Rich (970) 225-7828
ELECTRIC--------City of Fort Collins Light & Power-- Rob Irish (970) 224-6167
CABLE-------------Xfinity--------------------------------------Don Kapperman (970) 567-0245
TELECOM.--------Centurylink-------------------------------Bill Johnson (970) 490-7501
WATER------------City of Fort Collins Utilities-----------Heidi Hansen (970) 221-6339
WASTEWATER-South Fort Collins Sanitation--------TBD
STORMWATER-City of Fort Collins Utilities-----------Heidi Hansen (970) 221-6339
UTILITY CONTACT LIST: *
UTILITY COMPANY
* This list is provided as a courtesy reference only. Northern Engineering Services assumes no responsibility for
the accuracy or completeness of this list. In no way shall this list relinquish the Contractor's responsibility for
locating all utilities prior to commencing any construction activity. Please contact the Utility Notification Center of
Colorado (UNCC) at 811 for additional information.
PHONE NUMBER
** The underground utility locates are based upon the best available information at the time of locating.
Contractor acknowledges that it is common for underground facility owner maps to have errors and omissions of
data shown. Consequently, it is the Contractor's sole responsibility to field verify the location of all utilities prior
to construction, and notify the Engineer of any discrepancies found.
I HEREBY AFFIRM THAT THESE FINAL CONSTRUCTION PLANS WERE PREPARED UNDER MY DIRECT SUPERVISION, IN
ACCORDANCE WITH ALL APPLICABLE CITY OF FORT COLLINS AND STATE OF COLORADO STANDARDS AND STATUTES,
RESPECTIVELY; AND THAT I AM FULLY RESPONSIBLE FOR THE ACCURACY OF ALL DESIGN. REVISIONS, AND RECORD
CONDITIONS THAT I HAVE NOTED ON THESE PLANS.
THESE PLANS HAVE BEEN REVIEWED BY THE CITY OF FORT COLLINS FOR CONCEPT ONLY. THE REVIEW DOES NOT IMPLY
RESPONSIBILITY BY THE REVIEWING DEPARTMENT, THE CITY OF FORT COLLINS ENGINEER, OR THE CITY OF FORT COLLINS
FOR ACCURACY AND CORRECTNESS OF THE CALCULATIONS. FURTHERMORE, THE REVIEW DOES NOT IMPLY THAT
QUANTITIES OF ITEMS ON THE PLANS ARE THE FINAL QUANTITIES REQUIRED. THE REVIEW SHALL NOT BE CONSTRUED FOR
ANY REASON AS ACCEPTANCE OF FINANCIAL RESPONSIBILITY BY THE CITY OF FORT COLLINS FOR ADDITIONAL QUANTITIES
OF ITEMS SHOWN THAT MAY BE REQUIRED DURING THE CONSTRUCTION PHASE.
DISCLAIMER STATEMENT:
CERTIFICATION STATEMENT:
SITE I-25HARMONY ROAD
ZIEGLER ROADKECHTER ROAD STRAUSS CABIN RD.Adam Kanto
Kephart
2555 Walnut St
Denver, Colorado 80205
(303) 832-4474
BUILDING ARCHITECT
7'7'
PARK
37' ROADWAY
53' ROW (MIN.)
UTIL.
ESMT.
9'
(MIN.)
PKWY6'
WALK
(MIN)
4.5'
INSET
PARK
9'
5.5'
WALK
FROM
UTIL.
ESMT.
8.5'PKWY
23'
TRAVEL
7'
PARK
7'BUMP-OUT
LANDSCAPE
30' ROADWAY
53' ROW (MIN.)
(MIN)
WALK
5.5'
UTIL.
ESMT.
9'
(MIN.)
PKWY6'
WALK
(MIN)
4.5'
9'
UTIL.
ESMT.
8.5'PKWY
30' SETBACK (MAX)
23'
TRAVEL
NOTE: NO MORE THAN 3 (23' X 7') PARKING SPACES
SHALL BE IN A ROW PRIOR TO LANDSCAPE BUMP-OUT
BROOKFIELD DRIVE AND PRECISION DRIVE AT
INSET PARKING
(53' ROW MIN)
BROOKFIELD DRIVE AND PRECISION DRIVE AT
LANDSCAPE BUMP-OUTS
(53' ROW MIN)
10'
TRAVEL
8'
PARK
8.5'(MIN.)
PKWY
36' ROADWAY
63' ROW (MIN.)
(MIN)
WALK
5'
UTIL.
ESMT.
9'
(MIN.)
PKWY13.5'
9'
UTIL.
ESMT.
CONNECTOR LOCAL STREET
(63' ROW)
CUSTOM TYPICAL SECTION WITH 4' OF
DEDICATED ROW
(73' ROW)
PRECISION DRIVE
BROOKFIELD DRIVE
PRECISION DRIVE
BROOKFIELD DRIVE
LE FEVER DRIVE
CINQUEFOIL LANE
7'
PARK
8'
48' FL TO FL
EX. 69' ROW
UTIL.
ESMT.
9'
(MIN.)
PKWY6'
WALK
(MIN)
4.5'
9'
UTIL.
ESMT.
5'
BIKE
7'
PARK
5'
BIKE
12'
TRAVEL
LANE
12'
TRAVEL
LANE
(MIN.)
PKWY
WALK
5'
DEDICATED ROW4'
10'
TRAVEL
8'
PARK
All changes, addendums, additions, deletions and
modifications to these drawings must be approved,
in writing, by the Fort Collins-Loveland
Water District and the South Fort Collins Sanitation District.
District Engineer Date
SOUTH FORT COLLINS
SANITATION DISTRICTCINQUEFOIL LANEROCK CREEK DR.
The following sheets show the original designs for
Precision Drive and Brookfield Drive.