November 23, 1993
Cityscape Urban Design
3555 Stanford Road, Suite 105
Fort Collins, CO 80525
Dear Eldon:
For your information,_attached is a copy of the Staff's comments concerning
Miramont Preliminary P.U.D.] presented before the Conceptual Review Team on
Novem ear 2-2—I9 3.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely,
Ted Shepaitl, AICP
Project PT"anner
TS/gjd
Attachments
cc: Tom Peterson, Planning Director
Transportation Department
Stormwater Department
Project Planner
File
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750
0
CONCEPTUAL
MEETING DATE: November 22, 1993
COMMENTS
ITEM: Miramont Preliminary P.U.D.
APPLICANT: Nordick/Neal Partnership c/o Cityscape Urban
Design, 3555 Stanford Road, Suite 105, Fort
Collins, CO 80525.
LAND USE DATA: Request for two Preliminary P.U.D.Is on about 96
acres of the Miramont P.U.D./Oak-Cottonwood Farm O.D.P. The first
request includes three-story apartments (210 units) at the
southeast corner of Boardwalk and Oak Ridge Drive (14.43 acres).
In the southern portion of the O.D.P.,,south of Boardwalk Drive,
the request is for 246 single family lots on 82 acres. These two
areas may be submitted as two separate preliminary P.U.D.'s.
COMMENTS:
1. The City Light and Power Department will assess normal
development charges. Please contact Janet Perry, 221-6700,
for further information.
2. The City will provide water and sewer services north of Mail
Creek Ditch. The District provides services south. Both
water and sewer mains are available in both Boardwalk and Oak
Ridge Drives. These mains can serve the multi -family
property. Water lines should be looped. Please contact. Mark
Taylor, 221-6681, for further information..
3. The Poudre Fire Authority is concerned about both P.U.D.Is
meeting the fire access requirements. Temporary fire access
connections are allowed if accompanied by a logical phasing
plan that conforms to the O.D.P. Both sites must meet minimum
water supply requirements for fire fighting. If the
apartments are equipped with automatic fire extinguishing
systems, then the P.F.A. is willing to consider flexible site
design considerations.
4. Street widths are also a concern for the Poudre Fire
Authority. The primary issue is onstreet parking. For the
apartments, drive aisles and turning radii must be minimum
standards. A ladder truck may have to serve the three-story
apartments and may require special consideration. The single
family homes must provide a sufficient amount of off-street
COMMUNITY PLANNING &
ENVIRONMENTAL SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS; COLORADO 805224580 (M)221-6750
PLANNING DEPARTMENT
parking so that a 28 foot street does not become over -burdened
with parked cars which restricts lane width. For further
information, please contact Roger Frasco or Warren Jones, 221-
6570, at the Poudre Fire Authority.
5. The Parks and Recreation Department remains very interested in
acquiring the parcel west of the former Collinwood Hospital
facility for a neighborhood park. This park will be designed
to serve residents of both Oak-Cottonwood.Farm and Oak Ridge.
to the east. Please contact Leslie Bryson, 221-6640, for
further information regarding this potential acquisition.
6. The site is located in the McClellands-Mail Creek Drainage
Basin. The storm drainage fees in this basin are $3,-717 per
acre, subject to the amount of impervious surface and runoff
coefficient.
7. At the time of Preliminary submittal for either P.U.D., the
submittal must include a Drainage Report, Drainage and Grading
Plan, and Erosion Control Plan. These documents should
include all the field changes that have occurred to date.
8. The proposed drainage facilities must comply with the Oak -
Cottonwood O.D.P. master drainage study. Since Kate Malers
will be taking maternity leave, the new drainage engineer will
be Basil. Hamden.
9. The Transportation Department will require the Oak -Cottonwood
Farm street network to connect into the Huntington Hills
O.D.P. This connection needs to be more than a local street
due to the heavier anticipated traffic volumes. The collector
standard, however, may be excessive and a 50'foot wide street
could be reduced. The developer is encouraged to think- in
terms of a "hybrid collector" that can carry the volume but
remain a residential -looking street. Both the traffic
engineer and the land planner are encouraged to explore
possible street design options.
10. The connection into Huntington Hills should tie into the
planned extension of Fossil Creek Parkway. The future
extension of Fossil Creek Parkway will be a collector street
that intersects with Lemay Avenue south of Portner Reservoir.
11. The developers are encouraged to meet with the adjacent
developer of Huntington Hills and the City to discuss options
on providing the appropriate street connection to the south.
12. The developer is responsible for the "local street portion" of
a collector or "hybrid collector" street. This includes the
local street portion of any crossing of Mail Creek.
13. With frontage on. Lemay Avenue, the developers of the single
family P.U.D. are obligated to design the widening to the
arterial standard. Such design includes centerline profiles
4..
as well as cross-section profiles every 50 feet. There are.
new details regarding tieing the new portion into the existing
crown of the street.
14. If sub drains are needed for the single family homes, then a
hydrology study must be submitted at the time of Final P.U.D.
15. A Soils Report is required at the Preliminary P.U.D. stage.
16. The developer is.cautioned that landscape islands in the cul-
de-sacs may present a problem in accessing the sewer line. In
a recent development, served by the District, the sewer line
was not allowed to go under the island. This resulted in
three additional manholes. In addition, it was difficult to
get compaction and proper cross -slopes. The proposal to build
landscaped islands in the cul-de-sacs should be reviewed by
the District in advance of utility planning.
17. The Street Oversizing Fee is $584 per dwelling unit, payable
at the time of building permit issuance.
18. A neighborhood information meeting will be required. This
meeting could combine Preliminary P.U.D. Is, as well as the
office park area that was brought into Conceptual Review a few
weeks ago. Combining the Preliminary P.U.D.'s will result in
a larger notification area but will allow .the citizens to
comment on the big picture. The Planning Department will
determine the notification area.
19. As you are aware, the Neighborhood Compatibility Study
recommended amendments to the L. D. G. S . that are expected to be
implemented in 1994.