HomeMy WebLinkAboutMIRAMONT TENNIS AND FITNESS CENTER PUD - PRELIMINARY - 54-87K - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTGEOTECHNICAL INVESTIGATION REPORT
FOR
THE MIRAMONT TENNIS AND FITNESS CENTER
FORT COLLINS, COLORADO
WATER
WASTE
& LAND
INC.
GEOTECHNICAL INVESTIGATION REPORT
FOR
THE MIRAMONT TENNIS AND FITNESS CENTER
FORT COLLINS, COLORADO
Mr. Clifford Buchholz, DBA
Fort Collins Tennis Center, Ltd.
1800 Heath Parkway
Fort Collins, CO 80525
Water, Waste & Land, Inc.
2629 Redwing Road, Suite 200
Fort Collins, Colorado 80526
*,.�tutu�atttt►ui1
'LOUISST��ii���i
.o,1,93UZ 4wu?
%P g:
OF CO ,"
O````
Septe if0ltiv�'l993
v
Geotechnical Engineering Report WWL #402
Miramont Fitness and Tennis Center i September 27, 1993
TABLE OF CONTENTS
1.0
INTRODUCTION ................................................. 1
1.1 Site Location .............................................. 1
2.0
SITE INVESTIGATION ............................................. 1
3.0
SOILS TESTING .................................................. 1
4.0
OVERVIEW OF SOILS AND GROUND WATER CONDITIONS ................... 2
5.0
RECOMMENDATIONS AND DISCUSSION ................................ 4
5.1 Site Grading, Excavation, and Utilities ............................. 4
5.2 Building Foundation .......................................... 5
5.3 Slab on Grade ............................................. 5
5.4 Backfill and Lighting Foundations ................................ 6
5.5 Pavement Design Recommendations .............................. 6
5.6 Erosion Control ............................................. 8
6.0 GENERAL RECOMMENDATIONS ...................................... 9
APPENDIX A ........................................ Boring Logs and Field Logs
APPENDIX B......................................... Soil Lab Testing Results
Geotechnical Engineering Report WWL #402
Miramont Fitness and Tennis Center 1 September 27, 1993
1.0 INTRODUCTION
This report details the results of the geotechnical soil survey conducted for the Miramont
Tennis and Fitness Center at its proposed location on the south side of Oakridge Drive south of the
Builder's Square Building in southeast Fort Collins, Colorado.
The survey was conducted to determine the suitability of the site soils for construction of the
proposed facility and to make recommendations regarding foundation structures and pavement design.
Additionally, precautions were outlined for adverse soil and/or ground water conditions and measures
which should be followed to address wind and water erosion of soils from the site during construction
prior to vegetation.
1.1 Site Location
The proposed location for the Miramont Tennis and Fitness Center is south of Oakridge Drive
directly south of Builder's Square and west of the Evangelical Covenant Church which is located on
the southwest corner the intersection of Oakridge and Lemay. The proposed property is located within
the Southwest % of the Northeast % of Section 1, Township 6 North, Range 69 West of the Sixth
P.M., City of Fort Collins, Larimer County, Colorado.
2.0 SITE INVESTIGATION
Field exploration at the proposed Miramont Tennis and Fitness Center property was conducted
in two events. A geotechnical engineer from Water, Waste & Land, Inc. (WWL) was present during
the drilling of six borings on August 24, 1993 and again during the collection of soil samples from four
backhoe pits on August 31, 1993. Borings were advanced with a CME 55 drill rig using 3.25 inch
inside diameter, hollow stem flight augers. Backhoe pits were excavated using a t/4 cubic yard
backhoe to approximately 3 feet depth.
Borings and backhoe pits were drilled and excavated within the footprint of the proposed
building foundation and in areas to be paved. Borings were located by WWL with conventional
surveying techniques from points of known location. Boring and backhoe pit locations are shown on
Figure 1 (Appendix A) along with the boring logs and the field logs. Samples collected for testing
purposes were assigned sample identification numbers for ease of reference.
' 3.0 SOILS TESTING
Soil testing was conducted on selected samples from the borings and backhoe pits to estimate
t the physical properties of the soils encountered. A summary of the samples tested and the testing
conducted is provided in Table 1. The results of the soils testing are presented in Appendix B.
Geotechnical Engineering Report
' Miramont Fitness and Tennis Center
2
WWL 1402
September 27, 1993
TABLE 1
SUMMARY OF GEOTECHNICAL TESTS CONDUCTED FOR
MIRAMONT TENNIS AND FITNESS CENTER
LABORATORY TESTING
SAMPLE
ID
BORE
HOLE
TYPE
DEPTH
FIELD
DESCRIPTION
USCS
200
HYDTs
-C
ATT
S.S.
S.P.
2
BH-1
BAG
4.6-9.5
LOW PLASTICITY SILT,
TRACE SAND
ML
1
1
6
BH-2
CAL
3.5-4
LOW PLASTICITY SILT
ML
1
1
9
BH-3
CAL
6.5-7
LOW PLASTICITY SILT
ML
1
1
19
SH-5
CAL
3.5-4
LOW PLASTICITY
CLAYEY SILT
ML
1
1
27
TP-1
5-GAL
3
LOW PLASTICITY SILT
ML
1
28
TP-2
5-GAL
3
LOW PLASTICITY SILT
ML
1
1
1
1
29
TP-3
5-GAL
3
LOW PLASTICITY SILT
ML
1
1
1
1
30
TP-4
5-GAL
3
LOW PLASTICITY SILT
ML
1
1
1
TOTALS
5
4
2
4
1
4
200-200 Wash, Hydr-Hydrometer, S-C-Swell Consolidation, ATT-Atterberg, S.S.-Soluble Sulfates, S.P.-Standard Proctor
4.0 OVERVIEW OF SOILS AND GROUND WATER CONDITIONS
Site soils generally consisted of fine grained soils deposited by both wind and water overlaying
weathered sandstone. Exploration generally encountered five distinct material horizons. These
horizons may vary in color or composition but are distinct from each other. The five soil horizons are
described below and are depicted on the boring logs in Appendix A.
' Silty Topsoil: The site is overlain by a 6 inch horizon of clayey silt topsoil with a moderate
organic content. The topsoil originates from the overconsolidated aeolian or wind deposited
soils in the next horizon. The soils have been penetrated by root growth and organic matter
and should not be used as a bearing soil or as a fill and/or backfill.
Aeolian Clayey Silt: A layer of clayey silt or silty clay underlies the topsoil across the entire
site extending to a depth of 4 to 9.5 feet below the surface. This material contains 50 to 70
percent fines with approximately equal proportion of clay and silt. The soil contains no medium
or coarse sands, is deposited without alluvial features and can vary in color from a deep brown
to a tan/yellow or white. The horizon is typically stiff to hard, having an in -situ unit weight of
115 to 130 pounds per cubic foot and shows signs of overconsolidation. (See Section 6.0)
The soil exhibits the plasticity characteristics of a low -plasticity clay, plotting just above the
"A line" with plastic indices between 16 and 19 percent. When wetted, the clay stratum
Geotechnical Engineering Report
Miramont Fitness and Tennis Center
3
WWL 1402
September 27, 1993
exhibits moderate swell potential, and when loaded the soil exhibits minor amounts of
settlement.
' Alluvial Sandy Silt or Sandy Clay: A layer of brown to pink sandy silt or sandy clay of alluvial
origins underlies the aeolian clayey silt horizon in all borings except BH-1. This material
' contains fine to coarse sand and fine gravel bedded in well graded to poorly graded alluvial
outwash deposits. This material exhibits moderate bearing capacity characteristics.
Silty Sand and Gravels: A lense of alluvial silty sand and gravel intrudes into the clayey silt and
silty Sand materials in borings BH-4 and BH-5 at depths of 12 to 15 feet and 7 to 1 1.5 feet,
respectively. The felsic and mafic sands and gravels are sub -angular and range in size from
fine sand to coarse gravel. The material is well graded and is loose to medium dense. This
alluvial lense was most pronounced in BH-4 and seemed to pinch out in BH-5 or to be
discontinuous with the silty sand and gravel material in boring BH-5. Previous soils
' investigations at Steele's Market and at the Evangelical Covenant Church (ECC) to the north
and east of the proposed property, respectively, encountered a similar alluvial material at
depths ranging from 7 to 15 feet below the surface.
Clayey Sand: Below the above stratum a tan to yellow uncemented clayey or silty sand was
' encountered in borings BH-1, BH-2, BH-4 and BH-6. This material is an alluvial or shoreline
deposit and can have interbedded layers of relatively clean sands or fines. The material is of
1 low plasticity, stiff to hard or dense with medium to fine sand and exhibits moderate bearing
capacity characteristics.
Ground Water: A free ground water surface was encountered in boring BH-4 at 12.5 feet at
the time of the investigation. Additionally, a free water surface was noted in the Builder's
Square stormwater detention pond approximately 200 feet north of BH-4. The ground water
table to the north of the proposed property, as detailed in the Steele's Market soils
investigation, was located at approximately 10 feet below the ground surface and 3 to 5 feet
above the alluvial gravel tense. The ground water table to the east of the proposed property
as detailed in the ECC soils investigation was located at approximately 6 feet below the ground
surface and 1 to 2 feet above the alluvial gravel lense. The Steele's Market and ECC soils
investigations were conducted on July 11, 1990 and August 30, 1985, respectively. The
water table in the area of the proposed property is variable due to annual and seasonal
precipitation and is most likely affected by irrigation of adjacent properties.
Geotechnical Engineering Report WWL 1402
' Miramont Fitness and Tennis Center 4 September 27, 1993
5.0 RECOMMENDATIONS AND DISCUSSION
' WWL has been informed by the project architect that at this point in planning, the fitness
center building will consist of a single story, slab -on -grade structure with load -bearing cinder block
' walls and long -span, steel joist with steel column supports where necessary. The indoor tennis facility
will consist of a rigid steel frame with a fabric cover. The building will be founded near the existing
grade minus the topsoil horizon with proposed maximum cuts and fills of less than 2 feet. The
proposed parking and drive areas are located to the north and east of the buildings and the outdoor
tennis facility and pool are located to the southwest and west of the fitness center building,
respectively. Some stormwater is proposed to be detained in a depression created by lowering the four
tennis courts south of the fitness center below the existing ground surface.
5.1 Site Grading, Excavation, and Utilities
WWL recommends removal and stockpiling of the upper 6 inches of topsoil containing organic
material beneath all buildings, fill areas and paved areas. This material could be reused in planting
areas. Any fill material or soils containing debris or significant organic material encountered during site
excavation should be removed from proposed building areas and stockpiled for reuse or disposed of
off -site. Exposed natural foundation and subgrade materials below buildings, fill and paved areas
should be scarified and recompacted between optimum and 2 percent wet of optimum moisture
content to at least 95 percent of Standard Proctor Density (SPD) (ASTM D 698-78). Soils to be used
1 for fill should be on -site soils devoid of debris, or imported granular materials approved by the
geotechnical engineer. Fill soils should be placed in uniform 6 to 8 inch lifts and compacted between
' optimum and 2 percent wet of optimum moisture content to at least 95 percent of SPD (ASTM D
698-78).
' All excavations greater than 4 feet depth should have side slopes which comply with OSHA
regulations 29 CFR 1926.650 or local codes pertaining to the required slope setback. Where such
' slope setbacks are not possible or practical, sheeting, bracing or shoring or a combination thereof will
be required to comply with OSHA regulations. These measures will prevent sliding or caving of the
excavation walls. The proper side slope or sheeting, bracing or shoring of the excavation should be
' maintained under safe conditions and heavy construction equipment should be kept at a safe distance
from the edge of the excavation until completion of backfilling.
' Any subsurface piping should be adequately bedded for proper load distribution. Backfill placed
in utility trenches in open and planted areas should be compacted in uniform lifts at optimum moisture
' to at least 90 percent of SPD (ASTM D 698-78) for the entire depth of fill. The upper 4 feet of backfill
placed in utility trenches under buildings or paved areas should be compacted at or near optimum
moisture content to at least 95 percent of SPD (ASTM D 698-78). Moisture adjustment of subsurface
or fill soils may be necessary to achieve proper compaction.
LJ
Geotechnical Engineering Report WWL 1402
' Miramont Fitness and Tennis Center 5 September 27, 1993
Stripping, grubbing, grading, subgrade preparation, and fill and backfill placement should be
conducted under continuous observation of the geotechnical engineer. Field density tests should be
taken daily in the compacted subgrade, fill and backfill under the direction of the geotechnical engineer.
5.2 Building Foundation
WWL recommends all structures be supported by grade beams and/or conventional spread
footings. All footings and/or grade beams should be founded on the original, undisturbed soil or on
structural fill extended to the undisturbed soil. All exterior footings susceptible to freezing soils should
be founded at a minimum depth of 30 inches below the final grade for frost protection. Structural fill
should be constructed in accordance with the recommendations discussed in Section 5.1. The
geotechnical engineer should identify undisturbed natural soils or verify the integrity of structural fill
prior to placement of concrete foundations. Grade beams and/or spread footings founded on properly
prepared soils at minimum depth of 30 inches may be designed for a maximum allowable bearing
capacity of 2,500 pounds per square foot (dead load plus maximum live load). A minimum dead load
of 1,000 pounds per square foot should be maintained on all foundation grade beams or footings to
counteract any swelling pressures which may develop if the subsoils become wetted.
The predicted settlement under the maximum design load should be less than 0.75 inch,
generally considered to be within acceptable tolerances for building construction. Efforts should be
made to equalize the unit loads applied to the soil by the foundations to minimize differential
settlement.
5.3 Slab on Grade
In view of the swell -consolidation test results from sample number 5, it is WWL's opinion that
a structural floor with a void beneath it is the only definite means to eliminate the risk of floor
movement. The cost associated with this type of flooring system may be unreasonable. Therefore,
if the owner is willing to assume the risk of future slab movement and related structural damage, a
floating floor slab may be a reasonable alternative to the expense of a structural floor. Slab movement
and structural damage can be limited if certain precautions are taken to reduce slab movement and its
adverse effects.
Subgrade below slabs on grade should be prepared in accordance with the recommendations
discussed in Section 5.1. If the subgrade below slabs on grade is allowed to dry below the required
moisture content, the subgrade should be rescarified and recompacted at 2 percent wet of optimum
moisture content to the required density just prior to placement of underslab gravel and concrete.
Slabs on grade supporting light floor loads should be underlain by a minimum of 4 inches of clean,
graded gravel or crushed rock devoid of fines. Slabs on grade supporting heavy loads should be
underlain by a minimum of 6 inches of crushed aggregate base course meeting Colorado Department
of Highways Class 5 or 6 specifications. The base course should be compacted at 0 to 2 percent wet
Geotechnical Engineering Report WWL 9402
Miramont Fitness and Tennis Center B September 27, 1993
of optimum moisture content to a minimum of 95 percent of SPD (ASTM D 698-78). Slabs on grade
should be designed and constructed structurally independent of bearing members. '
5.4 Backfill and Lighting Foundations
Backfill placed adjacent to the foundation structures should consist of the on -site silty or silty
clay soils or off -site granular material approved by the geotechnical engineer. The backfill should be
mechanically compacted in uniform 6 to 8 inch lifts between optimum and 2 percent wet of optimum
moisture content to a minimum of 95 percent of SPD (ASTM D 4253, D 4254). Foundation walls
which are backfilled with on -site silty or clayey soils on one side should be designed using a hydrostatic
pressure distribution and equivalent fluid pressure of 55 pounds per cubic foot per foot of depth of
backfill.
It is recommended that all light standards be founded on drilled pier type foundations. The
passive pressure Fp which can be developed in the upper clay soils at the site at a depth D in feet
below the surface may be expressed by the following equation in pounds per square foot.
Fp (psf) = 200 x D + 3,000
This equation may be used in the design criteria for resisting lateral loads and overturning moment
forces developed on the foundation. A factor of safety of 3 should be used in conjunction with the
above equation. All lighting foundation piers should extend a minimum of 30 inches below finished
grade for frost protection. Piers should be founded on the original, undisturbed soil or properly placed
fill that has been compacted to a minimum of 95 percent of SPD ASTM D 698-78 in accordance with
Section 5.1.
5.5 Pavement Design Recommendations
WWL used the AASHTO pavement design method to estimate required pavement thickness.
The required pavement and base coarse structure at proposed property is a function of the foundation
or subgrade soils and the estimated soil conditions. Average test values for the percent passing the
number 200 sieve, the liquid limit and the plasticity index for the near -surface samples collected from
backhoe pits TP-1 through TP-4 were used to develop the group index of the subgrade soils. These
values are 68, 36 and 15, respectively. The calculated group index was 2.7 which corresponds to a
Soil Support Value, S, equal to 5.7. An Equivalent Daily 18 kip Load Application for residential streets
of 15 was used with a conservative Regional Factor of 4.0 to estimate a required Weighted Structural
Number for the pavement of 2.4. Based on these factors, the following minimum pavement thickness
should be provided for the pavement structure.
Geotechnical Engineering Report
Miramont Fitness and Tennis Center 7
1
Passenger Car Parking
Alternative #1
Asphalt Concrete 2.5 inches
I Crushed Aggregate Base Course 10.0 inches
Total Pavement Thickness 12.5 inches
Alternative #2
Asphalt Concrete 2.5 inches
Plant mix Bituminous Base Course 4.0 inches
Total Pavement Thickness 6.5 inches
Circular Drivewav and Entrance Areas
Alternative #1
Asphalt Concrete 3.0 inches
Crushed Aggregate Base Course 10.0 inches
Total Pavement Thickness 13.0 inches
Alternative #2
Asphalt Concrete 2.5 inches
Plant mix Bituminous Base Course 4.5 inches
Total Pavement Thickness 7.0 inches
WWL 1402
September 27, 1993
Subgrade below proposed paved areas should be prepared in accordance with the
recommendations discussed in Section 5.1. The surface of the subgrade should be hard, uniform,
smooth, and true to grade. Excessive weed growth should be prevented by treating all subgrade under
parking areas be treated with a soil sterilant.
The base course overlying the subgrade should consist of a hard, durable, crushed rock or
stone and filler and should have a minimum "R" value of 80. Composite base course material should
be free from organic matter and lumps or balls of clay and should meet the City of Fort collins and/or
Colorado Department of Highways Specification Class 5 or 6 Aggregate Base Course. Base course
material should be placed on the subgrade at or near optimum moisture content and compacted to at
least 95 percent of SPD ASTM D-698-78. It is important that the base course be shaped to grade so
' that proper drainage of the parking area is obtained.
All asphaltic concrete shall meet City of Fort Collins and/or Colorado Department of Highways
specifications and shall be placed in accordance with these specifications.
' A reasonable pavement alternate would be nonreinforced concrete pavement. Using a modulus
of subgrade reaction of 110 pounds per square inch per inch, a design life of 20 years, and concrete
Geotechnical Engineering Report WWL #402
Miramont Fitness and Tennis Center 8 September 27, 1993
with a modulus of rupture of 600 pounds per square inch, the following pavement thicknesses are
recommended:
Passenger Car Parking
Nonreinforced Concrete - 5"
Circular Driveway, Concrete Pans & Main Entrance Areas
Nonreinforced Concrete - 5"
Subgrade below the proposed pavement should be prepared in accordance with the recommendations
discussed in Section 5.1.
Concrete used in the pavement should meet ASTM specifications, and aggregate should
conform to ASTM C-33 specifications. Concrete should be designed with a minimum modulus of
rupture of 200 pounds per square inch in 28 days. It is suggested that a minimum cement content of
6.5 sacks be used for this mix. It is further recommended that laboratory mix designs be done to
determine the proper proportions of aggregate, cement, and water to meet this requirement. It is
essential that the concrete mix have a low water -cement ratio, an adequate cement factor, and
sufficient quantities of entrained air. It is recommended that the subgrade be in a moist condition at
the time the concrete is placed. the pavement surface should be free of depressions in which water
may stand.
Catch basins and manhole casting should be separated from the pavement with expansion joint
material. The jointing plan should be prepared by the contractor and/or architect and approved by the
geotechnical engineer prior to pavement. Longitudinal and transverse joint spacing should be at regular
10 to 13 foot intervals. Longitudinal and transverse contraction joints should have a depth
approximately equivalent to one-fourth the pavement thickness. The joints should be cut within 24
hours of pouring. Expansion joints should be full -depth and should only be used to isolate fixed objects
abutting or within the pavement area. Joint openings wider than one-fourth inch should be cleaned
and sealed before opening to traffic. A uniform, gritty final surface texture should be provided. Curing
should be obtained with uniform coverage with white membrane curing compound or by seven-day
coverage with white polyethylene or waterproof paper. The completed pavement should be closed to
automobile traffic for three days and to truck traffic for seven days. If paving is done during cold
weather, cold weather procedures should be used. The concrete should be protected from freezing
temperatures until it is at least 10 days old.
5.6 Erosion Control
According to the SCS Soil Survey of Larimer County, issued December 1980, the hazards of
wind and water erosion of the native soils at the site of the Tennis and Fitness Center are slight to
moderate. The Wind Erodibility Map, furnished as a part of the Storm Drainage Division's Design
Criteria and Construction Standards, indicates that the site lies in a moderate Erodibility Zone.
Geotechnical Engineering Report WWL 1402
Miramont Fitness and Tennis Center 9 September 27, 1993
Since construction of the Center may start before the end of the wind erosion season and
continue into the rainfall erosion season, both seasons as defined by the above mentioned division
standards, both conditions should be addressed. Prior to construction, a silt fence should be located
just outside the property lines on the west, south and east sides of the property. A swale and ditch
system should be installed at the southeast corner of the site to confine and convey runoff to an
adjacent point where sediment can be trapped upstream of a straw bale dike. Appropriate erosion
control measures should be planned for the completed site.
1 6.0 GENERAL RECOMMENDATIONS
(11 A swell -consolidation test on a sample of material from the southern portion of the property
(BH-2) revealed the presence of soils with swell potential at a depth of approximately 3.5 to
4 feet. These soils appear to be over -consolidated clays and their swelling potential is a
function of high in -situ density and low moisture content. These soils will likely impact the
outdoor tennis court area for several reasons. First, the design grade of these facilities is lower
than the existing grade (final grade will be closer to the material with swell potential) and the
excavation will relieve some of the confining overburden pressure. Second, these soils will
swell when their moisture contents are increased. A portion of the outdoor tennis court area
is currently designed to be utilized as a storm water detention facility which would tend to
contribute to the problem. It is recommended that during construction, several test pits be
excavated in the area of concern, samples collected at the proposed subgrade and 2 to 3 feet
' below the proposed subgrade. This would allow examination of the variability in layering and
extent of potential problem materials. This inspection would determine if 3 feet of
overexcavation for the entire area is required, or if a smaller area or lesser depth of
overexcavation would be suitable. If test pits are not excavated and samples collected for
verification purposes, then a conservative approach dictates that the entire area under the
courts be excavated to an elevation of approximately 4982, the material at that point should
' be reworked, moisture conditioned to within plus or minus 1 percent of optimum, and
recompacted in place to 95 percent of SPD (ASTM D 698-78). Select backfill should then be
placed in accordance with Section 5.1 Without a proper solution to the apparent problem,
there is significant potential for adverse movement of the tennis courts.
(2) Laboratory test results indicate that water soluble sulfates in the soil are negligible, and a Type
' 1-II cement may be used in concrete exposed to subsoils. Slabs on grade subjected to de-icing
chemicals should be composed of a more durable concrete with low water -cement ratios and
higher air contents.
' (3) Finished grade should be sloped away from the structure on all sides to give positive drainage.
Five percent for the first 10 feet away from the structure is the suggested slope.
I(4) Gutters and downspouts should be designed to carry roof runoff water well beyond the backfill
area.
(5) Underground sprinkling systems should be designed such that piping is placed a minimum of
5 feet outside the backfill of the structure. Heads should be designed so that irrigation water
is not sprayed onto the foundation walls. These recommendations should be taken into
account in the landscape planning.
(6) Plumbing under slabs should be eliminated wherever possible since plumbing failures are quite
frequently the source of free water which may cause slab heave.
Geotechnical Engineering Report WWL #402
Miramont Fitness and Tennis Center 10 September 27, 1993
(7) Footing and/or grade beam sizes should be proportioned to equalize the unit loads applied to
the soil and thus minimize differential settlements.
(8) It is recommended that compaction requirements in the project specifications be verified in the
field with density tests performed under the direction of the geotechnical engineer.
(9) It is recommended that a registered professional structural engineer design the substructure
and that he take into account the findings and recommendations of this report.
J
APPENDIX A
BORING LOGS AND FIELD LOGS
LEGEND
■ BACKHOE PIT LOCATION
• BOREHOLE LOCATION
BUILDER'S SQUARE
DETENTION POND
-r
BH-4
�r TP-2 0
I
i
II
I
:I
I
BH-5
r LFUTURE INDOOR TENNIS
NG 0 BH-3 I III I I W�
1 Y
a J II I <
FITNESS CENTER 1 II P 3 0
.III
I ,<
=1 FUTURE BUILDING INDOOR TENNIS
i m I EXPANSIONCD
I III I I'
----J III � ; :I
BH-6 I <
J
' OUTDOOR TENNIS FUTURE UTDOOR III
FF j Nrf 71T�...j T III 1
II+u III+II
I I I I III I
I LL _u I LL _u III i �ITP-4 RULE DRIVE
II IL ------------------
I I I
_ 1-J
SCALE IN FEET
0 160 200
n
WATER FIGURE A-1 Date:
SEP 1993
WASTE BOREHOLE AND
IV& LAND BACKHOE TRENCH LOCATIONS Project:
wc.
402
o
\ a w
N
a ; E
LLJ O
o cocn cn SYMBOLS
�Q
-15
A
BORING LOG LEGEND
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION Ft. MSLD
TOTAL DEPTH OF HOLE 20 Feet
MATERIALS DESCRIPTION
Topsoil
Clayey SILT
Hill,
rr
r
Sandy SILT or Sandy CLAY
Silty SAND and GRAVEL
J
Clayey SANO
.J
Ground water Surface
California Split Spoon Sampler, D = 2.0"
Standard Split Spoon Sampler, D = 1.5"
Bulk Sample From Cutt,ngs
T
JOB NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
0
o to
x a
a. 3 E E
LU O
a m cn Ln SYMBOLS
-�0
-15
20
i
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION Ft. MSLD
TOTAL DEPTH OF HOLE 20 Feet
MATERIALS DESCRIPTION
To;jsoil
rr
r
Clayey SILT
rr
rr
rr
r
i�
r
Sandy SILT or Sandy CLAY
Silty SAND and GRAVEL
f
Clayey SAND
J.
j.
Ground Water Surface
California Split Spoon Sampler, D = 2.0"
Standard Split Spoon Sampler, D = 1.5''
Bulk Sample From Cuttings
1
J08 NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
o to
_ LLI
N Q
d ; E f
o m co uai SYMBOLS
22
1
2
25 3
-10
37 4
_�5
I
BORING BH-1 (Page 1 of 1)
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4986.6 Ft. MSLD
TOTAL DEPTH OF HOLE 16.0 Feet Feet
MATERIALS DESCRIPTION
ML
TOPSOIL, Silt, Brown, Dry, Loose
rr
ML
Sandy SILT, Brown, SI. Moist
r
rr
rr
rr
rr
r
rr
rr
rr
rr
r
rr
rr
rr
rr
rr
rr
Fine Sandy SILT, Yellow to Tan, Dry to SI. Moist, Very Stiff
rr
rr
rr
SILT, Brown to Yellow Brown, Dry to SL Moist
rr
rr
rr
rr
rr
rr
rr
rr
rr
rr
rr
rr
rr
r
rr
f
SP
Fine Silty SAND, SI. Moist to Moist, Hard/Dense,
f.
SP
Very Fine SAND, Sandstone Stringer??, Orange -Brown
SP
Silty SAND, Brown, Moist
J .
f.
SP
Interbedded Fine SAND and SILT, Orange -Brown, SI. Moist, Hard
JOB NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
v
o �
u` v
d
W
; E
o M
0
m cn
-1 0
I
13 5
39 6
42 7
u�
w
a
f
uu) SYMBOLS MATERIALS DESCRIPTION
ML TOPSOIL, Silt, Brown, Dry, Loose
ML I Clayey SILT, Brown, Dry to SI. Moist,
BORING BH-2 (Page 1 of V
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8124/93
SURFACE ELEVATION 4988.5 Ft. MSLD
TOTAL DEPTH OF HOLE 11.5 Feet Feet
r r ML Clayey SILT, Brown to Pink, Mottled, Dry, Loose
rr
Clayey SILT, Brown to Yellow, Dry, Hard
rr
rr
r
ML I Mixture Fine SAND and SILT, Some Clay, Brown, Dry
J
Sp
Silty Very Fine SAND, Tan to Orange, St. Moist
Hard/Very Dense, Possible Bedrock
JOB NUMBER: 402.1
LOCATION: Fort Collins, Colorado
Water, Waste & Land, Inc.
Consulting Engineers and Scientists
v
o
x
L w
r
a
N Q
; E
W
O m
o
m cn
-10
20
19 8
28 9
22 10
U)
w
a
x
BORING BH-3 (Page ! of o
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4989.9 Ft. MSLD
TOTAL DEPTH OF HOLE 11.5 Feet Feet
can SYMBOLS MATERIALS DESCRIPTION
FAML TOPSOIL, Silt, Brown, Dry, Loose
IM ML I Clayey SILT, Brown, Dry to SI. Moist,
rr SILT, Brown, SI. Moist, V. Stiff
rr
rr
rr
rr
rr
rr
Sandy SILT , Brown, Dry to SI. Moist
SILT, Brown to Pink, Mottled, SI. Moist, V. Stiff
J rr
r
rr
Sandy SILT, Brown, SI. Moist
x�
i CL Sandy CLAY, Brown, SI. Moist, V. Stiff
r
1" Fine Sand and Silt Layer
i
JOB NUMBER: 402.1
LOCATION: Fort Collins, Colorado
Water, Waste & Land, Inc.
Consulting Engineers and Scientists
o [n
LL 2 LL v LLj
N a
a Y E f
o Coto tan SYMBOLS
a 11
7 12
� o 13
10 14
15
4 16
BORING BH-4 (Page 1 of 2)
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4989.5 Ft. MSLD
TOTAL DEPTH OF HOLE 26.0 Feet Feet
MATERIALS DESCRIPTION
ML
TOPSOIL, Silt, Brown, Dry, Loose
rr
ML
SILT, Brown, Dry to SI. Moist, Loose
r
rr
rr
rr
rr
r
rr
rr
rr
rr
r
rr
rr
rr
rr
rr
rr
i
ML
Sandy SILT, Brown to Pink, Mottled, Dry to SI. Moist, Firm
Xi
Increasing Clay Content
/Z
/ter
Sandy SILT, Brown, Moist to V. Moist, Firm
i�
Increasing Sand Content
iX
i
SW
Silty SAND and GRAVEL, Wet to Saturated, Loose
ML
Interbedded Clayey SILT and Silty SAND, yl/Gray, Moist to Wet, Stiff
%
Clayey SILT, Brown, Wet
J .
J .
y.
y .
SP
Silty Fine SAND, Brown, Wet, Loose
1
JOB NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
BORING BH-4 (Page 2 of 2) 11
0 M
L w w
y Q d
a ; E
o Coin (n SYMBOLS
22 17
5
0.
30
5
F1
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4989.5 Ft. MSLD
TOTAL DEPTH OF HOLE 26.0 Feet Feet
MATERIALS DESCRIPTION
Sp
SW
Silty SAND, Brown, Wet
y .
'
SAND, Medium to Coarse, Rounded, Brown, Wet, Weathered
SP
Sandstone BEDROCK, Silty Fine SAND, Brown to Gray, V. Dense
JOB NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
BORING BH-5 (Page l of l) 1
_ o
o cn
_ L J
N
i
m GOrn cn SYMBOLS
-10
-� 5
20
20 19
30 20
21
29 22
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4988.8 Ft. MSLD
TOTAL DEPTH OF HOLE 11.5 Feet Feet
MATERIALS DESCRIPTION
ML
TOPSOIL, Silt, Brown, Dry, Loose
rr
ML
Clayey SILT, Brown, Dry to SI. Moist,
r
rr
rr
rr
rr
rr
rr
White Hard Layer
i�
ML
Clayey SILT, Brown to Pink, Mottled, Dry, V. Stiff
No Recovery
i;
ML
SILT, Pink to Brown, Dry, Hard
Sandy SILT, Brown, Dry, Hard
/X/
/��
Silty Fine SAND and GRAVEL, White to Brown, Dry
S P
i
Gravel Layer @ 8.5 feet
SW
Silty SAND and GRAVEL, White to Brown, Dry, Dense
Increasing Silt to base
JOB NUMBER: 402.1 Water, Waste & Land, Inc.
LOCATION: Fort Collins, Colorado Consulting Engineers and Scientists
BORING BH-6 (Page l of 1)
CLIENT NAME Miramont Tennis and Fitness Center
DATE DRILLED 8/24/93
SURFACE ELEVATION 4987.6 Ft. MSLD
U
0
W
TOTAL DEPTH OF HOLE 115 Feet Feet
a
H
Z
E
J
o
O
Cocn
u)SYMBOLS
MATERIALS DESCRIPTION
5
23
6
24
0
15
25
26
5
20
Water, Waste & Land, Inc.
JOB NUMBER:
402.t
LOCATION: Fort Collins, Colorado
Consulting Engineers and Scientists
ML
TOPSOIL, Silt, Brown, SI. Moist, Loose
rr
rr
ML
Sandy SILT, Brown, 51. Moist to Moist
rr
rr
rr
rr
rr
rr
rr
rr
rr
rr
Clayey SILT, Brown, SI. Moist to Moist, Firm
rr
rr
rr
No Recovery
i/
ML
Sandy SILT, Brown, St. Moist, V. Stiff
Sandy SILT, Brown, SI. Moist
/ter
y
Sandy SILT, Brown, Dry to 51. Moist, Stiff
�,
ML
Silty SANG, Rust to Brown, Dry to St. Moist, Stiff
1
I
ii
L1
1
1
DRILLING LOCI
DRILL HOLE Btf-t DATE S Zy PACE( CF I
PROJECT I". cTe. DRILLER 6N& WEATHER SvV
CLIENT " RIG TYPE CME7 55 DRILLING METHCD
LOCATION 5. o� ma's SAMPLERS
H6uow s Ian
WATER
WASTE
& aN D
OEPTH (ft) RUN OR
oatvE
LENGTH
t•KCM io (ft)
S.wrt-
INc
METHOD
'
BLOW COUNT
OR
1ENETRAri ON
RE 3ISTANCE
Lu+►LE
RE[ v_
ERY
(ttJ
S.wrLE
co
Nom
OESCRI►-
rtaN
OEPTH
(ft)
MATERIAL DUaIPTICN ANO CRILLING NO) v**
0 —o. 5
o.5-y.5
7DPSorz �1 S Lo05j5' CAA L
src� T2. ce.ky L.P. B2N. St-. Mos3'r rml
-�•�trs 5 �-►.t 0 I
�. S
5.5
1.0
��
�•Ft
q - 13
ven�Y tl F
1.0
Gkc
skwo
NLo33T
q.5
5.0
C
—
—
b
ys '9 5
S'SZT L • P. M � LT. j5 7D w-z&i fit.
Y -ra sL_MOz3-FM--5?E797xokcc
ssMt o I
� QD ppu
I�.o
y, F. 5r-MD 69?-' -BeN 55 Bt Dktg ? P
5. o
C
-
-
-
M033 r xl� O ML
/'�{. S
r6.D
�. 5
'>�r
/Z-ZS-3o
t 5
1
BfFb
14.5-
t7�Y g. F. elkN D 4 SZZr SP-ML
6 -BW AAf7ZEV 5. �c,�015T
I
I
- -D 16.0,
DV-Y f0Lt;
D2Y PA R-i of F:r�
I
I
I
I
I
I
I
I
I
I
"S,*—V ` ABBPF/!AT:CNS: S?T - I'4" SPL 7 SPCCV. ST - Sr -=Y TLBE. DC - ryf CyE C - C171,1CS. C?T - Z'�' SrL'T SrxXN II
""^C,f iTDT?!'� �itC;f r..�T�i.;4�• Sr= SQt' ^Gf TDT'CN _"CTI II
J
zY
m
I
IJ
1
1
i
DRILLING LOG
DRILL HOLE'�3N-2 DATE S 2y q3 PAGE Or-
. f
PROJECT am
,c, DRILLER p2 �N6WEATHER �N,vy
CLIENT ,. �, RIG TYPE 6ME 55 DRILLING METHOD
LOCATION 5• of S7n-ZE 5 SAMPLERS Dub SSA
WATER
WASTE
& LAND
y' 5.5. k
OE►TN (ft) AU N as
DRIVE
F..,� TO LENGTH
(ft)
swr�_
ING
MET= 00
SLOW CUNT
OR
PENETRATION
AESISTA 4CE
SAMPLE
RECCV_
ERY
(ft)
IAMILE
CLLEC-
TION
aEscat._
rION
DEPTH
(ft)
PATERIAL DE MIPTICN AND GRILLING NO
3
3
C
—
,-
—
0 — 0. 5
0.5-3.o
g ao4. 5=ZT Qom' c005E L
LT. OAV. sc..
M 0r-f i -ri2 . sA,,4 D
z
S-S
I.0
3_5_y
- y
Ssz-r w sow M)L Fop >n w
D4 YomEO
3
3
�
7
�
Z„
�.T
w�u►c
!1- z8
�. 0
(r
6.s-�
�
7
SSLT Cd 5ontE Ntc. 13R-N. Qe.i I
I
6TL,T'Y F. ,A-m o BeN 091",
6 -to
IJ1lwruiLE of 4 5A-�4 SP
IMF CLAYsue. oeX
ID
I(.�
l.5
f• $"
sPT-
ly-Zg-3o
),5
y
10-11.5
�-��� Sera Y Esr3-r
I
I
D2V 1•ioc.E
i
I
DAY PH-�T or- ernD
I
I
I-T
I
tSAPPL ET- ASSREWATTCNS: SPT - I'.4" LPL ?T SPCCN. ST - SrF SY TLEE. DC - DRY MZE. C - CTTTNGS. CPT - 2,{' Sr! r- cZN it
*'^cSC.<IorrC{� _p6 crr,�T'SV� r= SCi
1
1
1
1
DRILLING LOG
DRILL HOLE 13r4 - 3 DATE zy q3 PAGE 1 OF
PROJECT -�� ( DRILLER fj sxl6, WEATHER S�,vNy
CLIENT r RIG TYPE C 55 DRILLING METHOD
LOCATION S,oF 5rcrLpS SAMPLERS Doh �lA SsA
NVWATER
WASTE
& LAND
S�ro s-r kvcc
DEPTH (ft)
RUN OR
Cs -DRIVE
LENGTH
I�ti
SAMPt-
ING
ME T:OD
&LOW COUNT
OR
PENETRATION
RESISTANCE
SAMPLE
RECOV-
ERT
SAMPLE
COLLSC-
TION
OESCAIP-
TION
DEPTH
µgj'QIAL DESCRIPTION AND GRILLING NOT -
FROM
TO
U
3
3
C
-
-
-
b - 0. 5
0.5 -3.v
7Df5olL &44 ST3 T ,vtr, Loos,-
ya !9 ZT --T BP-�
'0 ORV To sC-Tyf-l-rcy L'. P.
wGRz
V . SIT; F
I. 3
3.5 -y
G�-t
w 50 L. P. `;ake
1'. SfA-r-t !C. gr2N . 5L. MOS3-r
# F- 5A-,4D Mc SP
LT. f3rz�. CRY70
1
Z"
w�
12 - J
I . D
-
6 - 7
�z.T Mi_ I .P. M�rrL�D gW
IvMal-3T
ma7vey 6T LT F 5A-0 D LLk �T
jr7
! I.5
f 5
SP'r
Io-l2-I5
V . S7I�F
13
�BAs
51-Z-rY GLky Cc L.P. oeP. 6t-.77
Moi�T I-
I
I
02t� FFac.E I
i
*SAWL ING ASSREVIATICNS: SPT - IW' SPLIT SPOCN. ST - S-iELSY TLEE. DC - DRY CORE. C - CJTTTNGS CPT - 21�" SPLIT SPOON
*'^ESCRTPTTCN aSSREVTATTCNS: Sc- SOTL DESCRT?T'^N cr'911
DRILLING LOG
DRILL HOLE 1 4-14 DATE 8 2 43 PAGE 1 OF r
PROI ECT -TEW Gam. DRILLER Dew. Olb. WEATHER SiNuy
RIG TYPE GME SS DRILLING METHOD
LOCATION $. aF SIZE'S SAMPLERS &6, 6�5,4.
1%to.40r WATER
WASTE
& LAND
{uow srE
DEPTH (ft) RUM OR
ORIVE
�� TO LENGTH
(ft)
SAING
ING
METHOD
6LO�l COUNT
OR
PENETRATION
RESISTANCE
SAMPLE
REM-
ERY
(ft)
SAMPLE
COLLEC-
TION
DETION
iION
DEPTH
(}t)
HA tMIAL DESCRIPTION AND DRILLING NOTES"
—
—
D -OS
0.5-q.s
�PSaTZ gam• SRT fl�f LooSE
Cc.AYE+� s�z-r 7a SZLT -TR. SMtD
BRaJ. l-o�.�E G1C�' 7b SL. NLb T I
15"
y-3
�^
C).5
y
BAG
q,5-5
y. s-s
29-4-1 -7b Lu
2Y 5L . -�
'
<i.5
9.5
r7
C
N 5-1. 5
p y Cc,Q u, -11 cc, -Mc Cq1, f
'
9.5
10.5
1
Z"
wSPr
shy
y- 3
films
1.0
y
l0-10,5 8.
5 -locks
9.5-10
10-ro, 5
5Z1.r Ul sra A-m0 Mt Mc.13TV. W13T
P. .
6¢-A oY BBM
'
VELD SA-mo y 51Z.T cal 50
1.0 ET I Z o' RA-tl EZ I Z.o'
t
Sr1�F
8.
IS-rb a.
15 -16$
svr M CuFf'E4' �iT ML
M
yt�ow bEA� oir Ta WE-T d
1`l,s-lq 5
� co-yAkTREV w F. kmD ur, Bk�ll
i
-17
� 5
Y
p. s - ��
�'lY � 5� D � GT_ BP-�1. cvr✓T
Y 4TTTZE 4EZo vEfY
'
1.5 "
2-3$
H�/V.
I.
667
Y
zyszs6�-zbo
zsG-zc*
zy s -zr, 6
M-G SA-�I 0 Scv rznL 0 �t WET i
s �' -mow wrm�
�S. Bf--VacC4( MgZ3" V. DEY C
Z 5.0'
*SAMPLING ABBREVTATTCNS: SPT - lu" SPLIT SPCCN, ST - Sn'EL3Y TIRE. OC - DRY CORE. C - =T%S, CPT - 2u" SPLIT SPO N
I **^ESCfZTP77CN -lBBRT/TAT?CNS: SE SOIL -IESCRTPTTGN FORM
urr
1
11
1
1
1
1
1
DRILLING LOG
DRILL HOLE �90- 5 DATE 8 Zy 93 PAGE_L OF I
PROJECT -WW. M. DRILLER � . WEATHER 5a"A&
CLIENT " " RIG TYPE CGUE 55 DRILLING METHOD
LOCATION 5. or. jmnE's SAMPLERS 5, A.
'
WATER
WASTE
,�Xrv& LAND
rao c.Sro ST�1
OEPTM (!t)
RUN OR
DRIVE
LENGTH
(tt)
SAMPL-
ING
MET-OO
SLOW COUNT
OR
PENETRATION
RESISTANCE
SAMPLE
RECCV-
ERY
(it)
SAMPLE
COLL°C-
TION
oEscRTv-
TION
OEPTN
(ft)
MATERIAL DESCRIPTION AND DRILLING NOTES"
F,.,�
I TO
D
3
3
'�
-
—
o ' ��•
0.5-3
TbP5a1Z SILT �R" 1-0o sE �- I
c�kv�Y C•P. LT. (39:. DRY
iz-�+
v- l
3
b
(o
%
I
1:7pr
13-17
tL1 Sor�E 5� }tD D2Y 6�
-
► 0
-3
—
—
—
7 -1 0
S�-T M F, 5A44J 0 P w ScMC
EL w -ra be-,,J oey
1.5"
�N-15-I$
DE,usE-
y
BAt
►o-tl.5
5�T`f SA --up w 6-2kvEL �
rLE- �.-r �� bdr-ra�n I
i�.o'
I +4.p LC
I
I
*SAMPLING ASSREVIATTCNS: SPT - IW" SPLIT SPOON, ST - SrEL3Y TLBE. DC - DRY Ca?E. C - CUTTINGS. CPT - N' SPLIT SPOCW
**" ESCRTPTTC-N ASSREVTATTONS: SE SOIL nEMZTPTICf4 -Mj
11
1
1
DRILLING LOG
DRILL HOLE Sg_� DATE B Zy 93 PAGE ( OF 1
PROJECT -F-t7 . L-Tt. DRILLER �. WEATHER 5�NNy
CLIENT RIG TYPE C,ME 55 DRILLING METHOD
LOCATION__5. of f SAMPLERS Qb6 Z4 55.A
NVWATER
WASTE
& LAND
-mqr-
DEPTH (rt)
RUN on
DRIVE
-ENGTH
(}t)
SAMPL-
ING
METHOD
SLOW COUNT
OR
PENETRATION
MESISTANCE
SAMPLE
RECOV-
ERY
(}t)
SAJAPLE
COLLEC-
TION
DESCAIP-
TION
DEPTH
(}t)
MATERIAL DESCRIPTION AND DRILLING NOTES**
FROM
TO
O
3
3
C
—
_
—
(5 -o. s
o, s - 3
-� Psorz ben! T- y toast
'SSLT µ� C . P. a" Sc MdI3i -ra
z- 3
. c)
3.55--44
..4. 5o µE 5A-m D GrNE M-L I
-3
3
C
I
(o
-7
I
APT
7- q
(. 0
6 s- 7
MD-B� S o ME- 5/+-N D
6 - 10
A -A, mi7t-0 4r - i
SOIL LAB TESTING RESULTS
i
w
q Q
g
U U U
U
..1
a-1
00 00 CO) Q)
(V •--�
q
[ra.1
�WF
7N
�n�nOM
zb�
C- oo
O U
X U2
o o 0
�< o
zz
Z $
U N
h
z-3
U W�
00 'IT
Mu 3
N O
W rn
a
MV)
oz
orn
w
0
—4 N
zZ
o0 N
Z.
.+ ..
Ll
La
a z
o
M r+
zoo
� U
•r
O� O O O C
lr') Wi r Iq M M M M
00
W
�.l
C.
Q\ 1` 00 (0n O
N .. N N N M
W)
fr
W
H
z
W
U
u1
z
F•
LL
0
z
Q
z
z
w
F-
H
z
O
Q
Ln
N
L.
V1
r
D
0
In
C
a
CL
J
Iq
0
N
0
0 0 0 0 0 0 0 0 0 0
0
O N 17 V .1 CO
I 1 1 1 I 1 I 1
113MS/Nouvc 10SN00 1N3043d
Q'
L.J
Z
W
I U
(n
rM W
Z
In N ~
m c� o
Z z
W ofQ
� O
m (n
� I Z
Z
In W
W
J Z
0- O
V
in
N
n
a
N
O
0
0
- O N IA v m
1 I I 1 I 1 I I
T)3MS/Noiiy(i lOSN0:) 1N33S3d
w
W
Z
W
I U
�n L/)
cf)
co W
z
cfl M ~
m CD o
Z Z
W C:� Q
O
m (1)
(.L I
Z
W
Q�
W
J Z
O
a a
V
0
0
o
}
V)
}
J
Q
Z
Q
x
W
H
W
_
�
O
O
O
J
O
V)
}
S
o-
------
------
-----
------
-----
----
------
------
------
N
o U)
o
------
------
------
------
------
------
------
------
------
------
W
F-
o-
l+J
W
�
J
� _
______
______
______
______
_______
______
______
______
______
______
_J
Z
------
-
-----
------
------
------
W
v
�
O
Z
Z
N
Q
�
N
------
------
------
------
------
o
O C�
W
N
V)
W
O
>
W
N
U
O
U
Q
C
Z
__
____
______
______
_
Q
------------------------------
F-
cn
vi
Z
Z\m_
______
______
______
______
______
_
____
_____-
______
O
n
J
W
_
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
Ul
Q
N -
Q
O O O O O O O O O O
O CD 00 N (U L ff) N
1HO13M 1,8 a3N13 1N3383d
CY
W
L H
� Z
W
I u
f/I
M ul
W
Z
I � W
m o
W Z Z
CY - Q
Z O
Z
1 Z
WI
N ~
W ~
J Z
O
(n [If
0
0
o
g
V7
V
J
Q
Z
Q
Of
W
H
W
�
O
�
p
�
J
O
V)
2
0
--
----
------
------
------
N
O V)
Of
o
o-
------
------
----
---
------
------
--- ---------
------------
W
w
w
�
z
�
J
�_
______
______
______
______
_______
______
______
______
______
______
_J
Z
�-
------
------
------
------
-------
------
------
------
------
------
W
(n
�
Z
Z
V
Q
o
�-
N
------
------
------
------
------
------
------
------
------
------
c
w
O C�
W
N
W
O
LJ
ui
0
�
V
Q
O
Q
(/7
V)
�
Z
Z-
------
------
------
------
-------
---
---
----
-
O
J
W
�a
Q
• -
------
------
------
------
------
------
------
------
------
------
w
_
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
U
N-
-______
______
______
______
______
______
______
O
O
O O O O O O O O O O
O O) co (D to d r) N
1HO13M XG 83N13 1N33d3d
M
N
0
W
tz
W
Z
W
U
M N
W
_ Z
N M ~
1 �
m Z 0
1..j W' Z
Q� o a
:D M N
� I Z
Z
cn W
H
W ~
J Z
a O
a a
c
0
CD
U
J
Q
Z
Q
0'
w
H
W
_
:
O
O
O
J
O
Ul
•
0
o-
------
------
------
----
-------
---
-
--------
----
------
N
O cn
o
------------------------------------------------------------------------
w
w
w
J
J
w
O
Z
o-
______
______
______
______
_______
______
______
______
______
______
LLJ
v
N
N
z
Z
Z
V
j
0-
------
------
------
------
------
------
------
------
------
Of
o
O C)
m
w
N
w o
> —
w
w
N
0
�
U
Of
Q
F—
(N
w
uj
Zgym-
---
-
------
------
------
------
------
------
------
------
O
'�
J
w
--
___
______
______
______
______
______
______
______
______
Q
_ _
______
______
--- _----------------------------------------
______
0
w
_ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ _ _ _ _
_ _ __ _ _
Q
U
N -
______
______
______
___-.___
__-___
__--__
_-____
-------------
O
O
O O O O O O O O O O
O C) 00 r� c0 Ln d N
1HO13M X8 63N13 1N3083d
LL,
LLJ
Z
W
M U
M N
� W
� Z
M ~
m W C)
Q
D
U 0
Z
N Z
W W
J ~
W �
Z
Q O
Q
Of
0
0
o }
L
cn
J
Q
Z
Q
0'
W
H
W
_
�
O
0
c
O
J_
O
}
Vl
o-
------
------
------
----
-------
------
---
-
N
O U)
0_
o
o-
------
------
------
------
------
------
------
------
------
------
w
F-
W
w
�
z
�
J
O_
______
______
______
______
_______
______
______
____
_J
Z
�-
------
------
------
------
------
------
------
------
-
----
W
v
N
N
O
Z
z
<
m
o
�-
------
------
------
------
-------
------
------
------
------
------
O C)
W
N
LEI
W
w
O
Q
Q
0
Zv_
______
______
______
______
_______
______
______
______
______
______
H
w
Vi
Z
J
W
.�
• -
------
------
------
------
------
------
------
------
------
------
w
a
U
N -
n_
______
______
______
______
______
______
--- ___
______
O
O
O O O O O O O O O O
O O) 00 n (0 d rn CV
1HO13M A8 83N13 1N3083d
U
CD m
0
W
H i
Z
W
M U
� t17
Ln
� W
� Z
m W
W H Z
cy- Q
D
CD N
U Z
M Z
I W W
J ~
Q O
Q
2'
TERRACHEM LABORATORIES, INC. LAB LAB NO.
12860 W. Cedar Drive, Spite 208 WENT w� rFrC <��+rr� I`1Gatip PROJECT
Lakewood, Colorado 80228 FEATURE PROJEcr-No.
SAMPLE NO. GATE TESTED
Phone (303) 989-5159 Par (3(13) 98"157
�.✓�r wE.�yrr ;
war
vENr.ry C/�cF)
1
;Guyer
p/,yL
9�A�
Re Hom/C
C "Ywwe E
Ci1./cH�=r)
C�n�eNfr�
O
p.sov�
4
o, v0I
10 —
0,o/a0
I:
Y..D
d —
D.
h''L') /. j ;Z.o/ f4o//o.v
�f}'' S�� SAp7ALC
h� S4
• 0�D
CH.9iV6 t
f v•9S
7'
L
/leie'lyl— = /, D i vcfi
TERRACHEM LABORATORIES, INC.
12860 W. Cedar Drive, Suite 208
Lakewood, Colorado 80228
Phoac (303) 989LS159 Far (303) 980-6157
' u�lOi✓c rceac-Ale- < <K/f I) -
!� r Ox:VS,r ?% /pe f) '
Q/ZV 1pe'r) =
0
p,svuc
6./
0//v Z.
c dy"We`
C"Va.-S
Ao
p,sp73
_ 'D.vo7S
b
o. uv75
$e. O
6
0.5/xS,
5S
b
- 0. 0/Aj
�D. U
o. 7b
I
LAB LAB NO.
CLIENT /�.,rre,� G�,rJ�E !'L�uro PROJECT 72WAIir CsNTcf
FEATURE Sa"L JWi"PZf S PROJECT NO. 240 �•
SAMPLE NO. -/ �%�iY' 3� OATS TESTED ?
//' ; f, %/ y, v/ /Z). Z)
vyy
C j/,y v,C C
— 47S
0.3s
s
TERRACHEM LABORATORIES, INC. LAB LAB No.
12860 W. Cedar Drive, Suite 208 CLIENT wR% QJTL ('29A9 PROJECT 7&WNl1
Lakewood, Colorado 80228 FEATURE o �� S i'�i�l�i PROJECT NO.
I SAMPLE NO. 7 �TP-DATE TESTED �o
Phonc: (303) 989-5159 Pas (303) 980-6157
MOISTURE -DENSITY RELATIONSHIPS
PROCTOR COMPACTION TEST
ASTM DESIGNATION:—'0 69 9 — i / METHOD: A
130.0
125.0
•A
t 110.0
Z
95.0
90.0
0.0
i+gtnvcc rno irnno/ CATIIDAT�f�N FOR
0:
5.0 10.0 15.0 20.0 25.0
MOISTURE CONTENT
IY DENSITY
PCF
OISTURE CONTENT
CRIPTION
RTIES:
No, 200 U.S. SIEVE
_PSIS REFERENCE
1
30.0
FIGURE NO.
TERRACHEM LABORATORIES, INC. LAB LAB NO. 0//6 9
1
12860 W. Cedar Drive, Suite 208 CLIENT ����t�Jrz &q PROJECTTG✓Nis e4A6 IL -
Lakewood, Colorado 80228 FEATURE L//- ��"PROJECT NO. f"'-
Phoac: (303) 989-5159 Pat (303) 980-6157 I SAMPLE N0. a (T)'��� DATE TESTED 3
MOISTURE -DENSITY RELATIONSHIPS
PROCTOR COMPACTION TEST
ASTM DESIGNATION: '0 6 �?J / / METHOD:
130.0
125.0
120.0
115.0
U
d
•• W
95.0
90.0
C
rM IO%/LLn rno IM o/ CATI ID ATI r)►I CnD
TERRACHEM LABORATORIES, INC. LAB LAB NO.
1-7860 W. Cedar Drive, Suite 208 CLIENT "-`r /"N 2 rGam PROJECT T'N/V)r
Lakewood, Colorado 80228 FEATURE
PROJECT NO. �L/ar�Lc S
I SAMPLE NO. DATE TESTED 3
Phoac_ (303) 989-5159 Par (303) 980-6157
MOISTURE -DENSITY RELATIONSHIPS
PROCTOR COMPACTION TEST
ASTM DESIGNATION:-- 'r '� % $- 9 / METHOD
130.0
125.0
120.0
t I10.0
U)
z
r
of
0 105.0
95.0
90.0
0.0
rtrovccc cno iMo/ CATHDATirW FOR
D:
5.0 10.0 15.0 20.0 25.0
MOISTURE CONTENT
�
IY DENSITY
PCF
OISTURE CONTENT
46
CRIPTION
RTIES:
No. 200 U.S. SIEVE
_YSIS REFERENCE
�g
t
R
FIGURE NO.
TERRACHEM LABORATORIES, INC. LAB LAB NO. 211� 0 /
12860 W. Cedar Drive, Suite 208 CLIENT 1-dS7— IIZWWo� PROJECT T ✓��s C17•✓%c�L
Lakewood, Colorado 80228 FEATURE 14- /S��r/ tpt�, PROJECT NO.
Phoac: (303) 989-5159 Paic (303) 9W 6L57 I SAMPLE N0. ? tJ ( �T OATS TESTED
MOISTURE- DENSITY RELATIONSHIPS
PROCTOR COMPACTION TEST
ASTM DESIGNATION IJ d 9 g - l / METHOD:
130.0
125.0
120.0
t 110.0
z
95.0
90.0
0.0
r*^n i.,,NOI cATi io nTiON FOR
0.
5.0 10.0 15.0 20.0 25.0
MOISTURE CONTENT
tY DENSITY
PCF
OISTURE CONTENT
;CRIPTION
RTIES;
No. 200 U.S. SIEVE
YSIS REFERENCE I
30.0
FIGURE NO.
TTA Colorado Engineering
& Instrumentation, Inc.
I
r
s���
r 3
BY ---------------- DATE --------- SHEETNO------------ OF-------
CHKD. BY --------- DATE --------- JOBNO -------------------------
SUBJECT --- r1_�J�1S-- j�/U j � ----
r j /o7� /07,5- /os"/Df�,/
1
1
1
1
9
r
1
1
1'
1
1
1
1
Jam-
300
ova 3-
1 S-co V,41�
Soy �r �.T.��, 'MS��
��sao��\ ` Go �K5
3oa �.�J