Dear Dave:
The purpose of this letter is to advise you of the status of The Overlook Convenience Center at
Arapahoe Farm, Preliminary P.U.D. The project was granted Preliminary approval on January
27, 1997. This approval contained two conditions regarding traffic safety and hours of operation.
As a requirement for approval, the Final Plan must be in substantial compliance with the
approved Preliminary Plan. Substantial compliance means that all conditions imposed by the
Planning and Zoning Board upon its approval of the Preliminary Plan have been met, and the
final plan does not:
1. Change the general use or character of the development.
2. Increase the number of residential dwelling units by more than one (1%)percent.
3. Contain changes which would normally cause the development to be disqualified
under the applicable criteria of the Land Development Guidance System.
•
If the Final Plan meets these criteria, it will be forwarded to the Planning and Zoning Board with
a Staff recommendation of approval. If you have any,questions, please feel free to call our office
at 221-6750.
Sincerel : -
Ted Shepard
Senior Planner
xc: Mike Coley, Civil Engineer
Steve Olt, City Planner
Craig Foreman, Parks Engineer
Tom Shoemaker,Director of Natural Resources
281 North College Avenue • P.O. Box 580 • Fort Collins,CO 80522-0580 • (970)221-6750 • FAX(970)416-2020