Planning Department
Ci of Fort
rt Collins
November 4, 1991.
Woodcraft Homes
c/o Eldon Ward, Cityscape Urban Design
3030 South College Avenue
Fort Collins, CO 80525
Dear Eldon:
For your information, attached is a copy of the Staff's comments concerning,
Woodridge P.U.D., that was presented before the Conceptual Review Team on
November 4, 1991.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely,
Tavt
Ted Shepard
Project Planner
TS/gjt
Attachment
cc: Tom Peterson, Planning Director
Kerrie Ashbeck, Civil Engineer
Project Planner
file
281 North College Avenue • P.O. Bo\ 580 • Fort Coilins, CO 80522-0380 • (303) 221-0730
o _..a
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: November 4, 1991
ITEM: Woodridge P.U.D.
APPLICANT: Woodcraft Homes c/o Eldon Ward, Cityscape Urban Design,
3030 South College Avenue, Fort Collins, CO. 80525
LAND USE DATA: Preliminary P.U.D. for 370 single family homes on
approximately 109 acres located north of Harmony Road, east of Taft
• Hill Road, and south of Imperial Estates. To be-- developed-In--
phases over approximately seven year period. The proposed layout
includes the realignment of Harmony Road.
COMMENTS:
1. Electrical power is available to the pump station along Taft
Hill Road. Power can also be brought from the southeast
progressively north into the project with each subsequent
filing. Power is also available in Seneca Street. Close
coordination will be required to keep deciduous street trees
40 fee away from future streetlights.
2. The Water and Wastewater Department approves the general
layout according to the Master Utility Plan that has been
submitted with the previous two filings.
3 . With two points of access, the Poudre Fire Authority has no
problems.
4. As long as the former landfill site remains undeveloped, the.
Natural Resources Department has no problems.
5. The Stormwater Utility is working to improve downstream
regional facilities. Coordination with the regional
improvements should be shown on the final design. Temporary
detention can be provided in the northeast corner until
downstream improvements are completed.
6. The project is located in the McClelland and Mail Creek
Drainage Basin. The fees in this basin are $3 ,232 per
developed acre.
7. Please keep in mind the direction of storm flows from the
commercial areas. If these areas drain through residential
areas, then certain measures may have to be taken. Also, an
erosion control plan must be submitted at the time of final
design.
4
8. The landscaped medians will not be maintained by the Parks and
Recreation Department. Please be aware that the medians may
also serve to restrict full turning movements into the
commercially designated parcels as well provide channelization
at the arterial intersections.
9. It is recommended that the central drainageway be landscaped
with moderate water consumptive materials, not irrigated blue
grass sod.
10. The City is very supportive of efforts to provide an underpass
for the bikeway/drainage channel at Harmony Road. The central
contact person for the City's interest in the underpass is
Rita Davis in the Transportation Department.
11. The Parkland Development Fee is presently $625 per unit.
12. The three non-vehicular connections into the two schools
should be constructed with a hard surface treatment.
13. At some point, the timing and the extent of the improvements
to Taft Hill Road will have to be discussed and documented in
the form of a development agreement.
14. The Street Oversizing Fee is presently $584 per unit.
15. The Street Oversizing Fund will: participate in the medians at
the arterial intersections. The typical length of the City's
participation on an arterial street is a distance of 300 feet.
If, for some reason, the realigned Harmony is not downgraded
from major arterial, then the possibility exists that the
entire length would have to be constructed with a median as
per the major arterial standard. If the realigned Harmony is
indeed downgraded to arterial, then the landscaped medians in
the center of the quarter section would be the sole
responsibility of the developer.
16. Since no local street connections are contemplated into
Imperial Estates of Westfield Subdivision, then the existing
local stubs (Royal, Lynda, Goodell) should be investigated for
vacation. Of these three, only Royal appears to serve as
sideyard access. Lynda and Goodell appear to serve as front
yard access and would, therefore, be more difficult to vacate.
Any vacation procedure would have to be administered through
the County.
•
17. It is recommended that street trees (parkway) along the
realigned Harmony be planted as early as possible to gain
maturity in advance of the homes. Similarly, where
opportunities exist to establish buffering of commercial
areas, materials should be planted to again gain maturity to
better serve the future residents.