HomeMy WebLinkAboutTHE OVERLOOK AT WOODRIDGE PUD - FINAL - 55-87D - CORRESPONDENCE - CITY COUNCIL 1'P ri
Al
MEMORANDUM lit"
r50
Date: August 1, 1991.
To: The Honorable Mayor and City Council Members
From: Matt Baker, SID Coordinator
Thru: Gary Diede, Director of Engineering
RE: Harmony Road Realignment
Council has raised several issues regarding the purchase of right
of wayfor the realignment of HarmonyRoad. `1'g The �oll;;wi;.y
information will detail the analysis and staff's recommendation on
the alignment of Harmony Road.
HARMONY ROAD REALIGNMENT:
Harmony Road was planned to be realigned in 1980 when the Master
Street Plan was developed. Staff recognized that the property
immediately to the west of Taft Hill Road on the Harmony Road
alignment had been platted in the county for single family
lots without a right of way dedicated for the extension of Harmony
Road or Overland Trail and, therefore, thought to be disruptive and
expensive to extend Harmony Road on a -straight alignment to
possibly connect to Overland Trail.
Staff also recognized that topography was a factor that would
require expensive construction due to the steep hills. Several
alignment options for Harmony Road have been revisited as follows:
Option 1 e Retain the present alignment of Harmony Road at Taft
Hill.
The present alignment of Harmony Road stays on the section line and
intersects Taft Hill. The north side of the road has a steep hill
which was an old Larimer County Landfill. The south side of the
roadway drops steeply approximately 40 ' in height. Taft Hill Road
was built on fill material and has drop offs of 30 - 40 feet on
each side. The street grades on these roads are much steeper than
city standards for safety.
CONS:
O Difficult and costly ($1.9 million) project with
massive earthmoving required. The roadway could not
be built to provide direct access to the adjoining
property.
O Old county landfill would require excavation and
removal of contaminated material to new county
landfill.
O Extension of Harmony Road west of Taft Hill blocked
by county development.
O Leaves a jog in the east - west arterial road
connection.
PROS:
O Straight road alignment is consistent with city
street grid system.
Option 2 - Curve Harmony Road to meet Taft Hill south of the
present alignment.
CONS:
O Costly project ($1.4 million) with massive
earthmoving required. The street would have to be
elevated on high fill material. The roadway could
not be built to provide direct access to the
adjoining property.
O Extension of Harmony Road west of Taft Hill blocked
by county development.
O Environmental impacts to wetlands and wildlife
areas would have to be mitigated.
O Leaves a jog in the east - west arterial road
connection.
PROS:
O Avoids old county landfill from east Ft. Collins.
O Favors route to county landfill site.
4
Option 3 - Curve Harmony Road to meet Taft Hill just north of the
present alignment.
CONS:
O Extension of Harmony Road west of Taft Hill blocked
by county development.
O Creates an offset arterial hampering traffic flows.
PROS:
O Less earthmoving required than previous options.
Construction costs moderate ($950, 000) .
O Avoids old county landfill.
Option 4 - Curve Harmony Road north to connect with Taft Hill at
the intersection of CR 38E.
CONS:
O Bi-sects property which makes development more
difficult.
O Curved road varies from the city's grid street
system.
PROS:
O Least expensive construction costs, estimated at
$750, 000.
O CR 38E provides arterial extension west of Taft Hill
to (future) Overland Trail.
O Avoids offset arterial intersections.
O Can be built safely to meet arterial design
standards.
The Harmony Road realignment has been re-analyzed since its
original adoption in 1980. The City's Transportation Department
has looked at Harmony Road in this part of the city at various
times to determine if the concepts that were analyzed in 1980 are
still valid and still meet the needs of the city's transportation
system. We have two specific work efforts in which we have looked
at the city wide street system: one, as a part of the
Transportation Plan development and second, the Colorado Highway 14
review performed in conjunction with the Ad Hoc Transportation
Committee. In both cases we used the transportation model to
analyze traffic flow/capacity and air quality. The results of both
efforts indicate that the Master Street Plan System and the
recommended realignment of Harmony Road (option 4) , continues to
provide for an acceptable traffic flow.
Staff has also looked at traffic impact in this area on a more site
specific basis. As PUD's are submitted to the city a traffic impact
study is required for Transportation Department review. Over the
years there have been a number of traffic impact studies that have
looked at this area and the impact of development of the street
system. In the case of the Arapahoe Farms Master Plan, which is
the project that included the realignment of Harmony Road, a
traffic study was completed. We looked, at the traffic impact
numbers and their relationship to the proposed street system.
Staff believes that the realignment of Harmony Road to connect with.
CR 38E (option 4) is still the preferred option of the arterial
street network in this area, providing both efficient traffic flows
and reasonable construction costs.
OTHER ISSUES:
Citizen Involvement:
Since 1987 there have been 12 development projects in the immediate
area that have gone through the development review process. In
addition to the formal P & Z meeting, five were subject to
neighborhood meetings. All meetings had mailed notification of
affected property owners within a minimum of 500 feet of the
project. These neighborhood meetings included the development
projects of the PR-1 Southwest Elementary School, Clarendon Hills
Master Plan, Clarendon Hills PUD, Arapahoe Farms Master Plan, and
Arapahoe Farms Amended Master Plan. Maps, planning material, and
project information at all of these forums clearly indicated the
realignment of Harmony Road. There were no negative comments about
the realignment and several that were positive.
Garbage Trucks:
Taft Hill Road is the major haul route to the County Landfill. In
�n i n r+ntheir
talking to the. waste d�..posal companies in town and comparing
numbers and routes, it appears that approximately 75% (172 trucks
per day) of the truck traffic uses Taft Hill Road and 25% (58
trucks per day) use Harmony Road in this location.
•
Arterial roads are designed to carry trucks and higher speed
traffic. For this reason, single family developments are designed
to avoid facing or having access onto an arterial street. Usually,
the backs of the lots are found along arterial frontages and
provided with a buffer by using setbacks and landscaping.
Current Status of Development:
The developer of Arapahoe Farms on the north side of Harmony Road
has received Planning and Zoning Board approval of 28 homes on the
curved. Harmony Road alignment in option four above. The developer
of Arapahoe Farms is planning to build the remainder of the
development in phases. Each phase will construct a portion of the
realignment for site access. Harmony Road will continue in its
present straight alignment until the development of Arapahoe Farms
progresses to the point where the connection can be made at Taft
Hill and CR 38E. This is projected to be in five to seven years.
Future Access to South.:
Seneca will eventually function as a collector from Horsetooth to
Harmony serving this square mile. It is also planned for Seneca to
serve future development south of Harmony and east of Taft Hill.
The actual alignment of this facility will need to be sensitive to
any wildlife habitat in this area, but until development is
proposed this actual alignment is uncertain. It could be designed
to encourage or discourage truck usage depending on the land use.
Other Arterial Street Improvements in the Area:
There are no immediate plans for improving Taft Hill to the north
and Harmony Road east. As the Transportation staff implements the
action plans in the Transportation Plan, gaps in the
pedestrian/bike system will be identified and funding methods will
be explored. Current city policy is to require developing
properties to improve their adjacent street frontage plus
improvements to mitigate their traffic impacts, whether on or of.f
site. If there are properties that have previously developed
without improving the streets (such as, the Harmony Mobile Home
Park, Imperial Estates County Subdivision, or the Ridge County
Subdivision) then improvements to these frontages fall back upon
the city to complete as a Capital Improvement project.
Recommendation:
Staff recommends that realigning Harmony Road to connect with CR
38E (option 4) is the most desirable option.
Staff also recommends that the city purchase the entire right-of-
way from a single property owner at this time. This would be
advantageous for three reasons:
1. ) Undeveloped land prices are lower cost.
2. ) The recommended realignment of Harmony Road would be in place
with one negotiation.
3 . ) The eventual timing of the connection of the realignment would
be more under the city's control. Rather than wait for
development to construct the last portions of the realignment
before connection is made, the city would be in a position to
initiate or delay the connection as future traffic conditions
warrant.