Loading...
HomeMy WebLinkAboutMONTAVA - PHASE E - TOWN CENTER RESIDENTIAL - BDR220003 - MONTAVA SUBMITTAL DOCUMENTS - ROUND 2 - OTHER WATER AND OR SANITATION DISTRICTS3201 East Mulberry, Unit Q – P.O. Box 1518 • Fort Collins, Colorado 80522 Phone (970) 498-0604 •Fax (970) 498-0701 •www.boxeldersanitation.org September 9, 2022 Tenae Beane City of Fort Collins Planning P.O. Box 580 Fort Collins, CO 80522-0580 RE: Case Number: PDR210015 Title: Montava Phase E Engineering/Survey: TST Engineer Contact: Parcel Number(s): Boxelder Sanitation District (BSD) has reviewed the proposed project identified as: Montava Phase E Utility Plans The District hereby advises as follows:  There is no objection to this proposal.  Responses required to comments below.  The District will respond at the hearing date of ______________. Comments: 1) The sewer that is shown as existing installed by Phase G was not included in the Phase G plans by Martin and Martin and has not been reviewed. The design needs to be completed and submitted. The Sanitary Sewer Study completed by Martin and Martin calls out for a 15-inch sewer not a 10-inch. This line will need be located in a 30-foot dedicated easement, where it is not located in public ROW and will need to be shown on the plat and referenced as separate document. 2) Standalone easements will be required for all sewers not located in public ROW’s. Sewers in “Tracts” will require easements. 3) Does line SS-01(10-inch) need to extend north across Timberline? Provide information on where sewers are planned to be extended and provide information on proposed flows for those extensions. This line is only 11-feet deep. Provide information that it will be able to service Phase E and the future sewer extensions to the north. 4) Provide information on the line in Montava Drive on what it will serve and the capacities that will be generated. 5) Relocate any services that are shown connecting to manholes. All services need to connect the sewer. 6) Show dimensions between water and sewer to assure the 10-foot separation is achieved. 7) Include Boxelder Standard Construction notes on the plans. 8) On the grading plans the District’s existing 21-inch sewer is shown. In many areas new features will be construction adjacent to or on top of the sewer (Sheet 9). It will be necessary to provide information to show that we can get access to all manholes with the District’s equipment including large vac-truck and possible construction equipment. This access should allow for access in all weather conditions. 9) Provide Boxelder signature block on appropriate sewer sheets. 10) We will review additional information as it is made available. Please feel free to contact me if you have any questions. Sincerely, Brian Zick, P.E. District Manager