March 21, 2018
iiI II J,'�1,II, I
iiil
�Il��i III 1 11
Angela Milewski
BHA Design 1i''; 11;' Illl'I
1603 Oakridge Dr ,u;;;11 ''! ' 1,
Fort Collins, CO 80525 ill"I ;'I
•I.; I �,
Iliilil i11111,, I'i�!,;1I illy
I�
l���,
11111,
RE: Pedersen Toyota Expansion,.'FDP180007, Round'Numtiler 1
Iilul; !1I1 I,
Please see the following summary of comments from City staff anal outside reviewing
agencies for your submittal of the above referenced'project., If you''filave!Iquestions about
any comments, you may contact the individual'commenter or.;direct your questions through
the Project Planner, Noah.Beals, at 970-416-2313 or nbeals @fcgov com.'"
Comment Summary:
I _
Department.'''' Engineering Development Review
Contactr Morgan Uhlman, 970-416-4344, muhlman@fcgov.com
Topic:''!iGeneral 4i ll'I
Comment Number 111 Comment Originated: 03/20/2018
03/20/2018 03/19/208:l1 From Tyler Siegmund's files,the utility providers were
fine with aireduced UE along College, 9' minimum. Please dedicate a 9' utility
easement lalong the College Ave frontage.
; II
08/19/2014: Per'current road standards for an arterial roadway,a 15ft utility
easement should be provided along the College Ave frontage of the property. If
this utility easement is not needed by utility providers the 15ft UE requirement
may be reduced in size or waived. Coordination with utility providers(COFC
Water, COFC Light and Power, COFC Storm water, Comcast, Century Link,
Public Service Company of Colorado) is needed to determine if this easement
is needed."
Comment Number: 4 Comment Originated: 03/20/2018
03/20/2018: The 15'utility easement behind College Ave was not needed, but
the utility providers want a standard 9' utility easement. Please show that on all
final plan documents.
Comment Number: 5 Comment Originated: 03/20/2018
03/20/2018: Please add cross slope and running slope labels and spot
elevations for curb ramps to show they are ADA compliant. ,t
;iil'ilr„
Comment Number: 6 , !,il Comment Originated: 03/20/2018
For the sidewalk widening along College Ave and Mason Street,there is some
work being proposed outside of the properties frontage'for,a transition. Is that
all in the right-of-way or is it on the adjacentilproperty? If it is ion the adjacent
property, a temporary construction easement,,will be needed between the two
owners before construction can begin, ";1�' �i,
Comment Number: 7 '1�i, Comment Originated: 03/20/2018
The next steps will include drafting and finalizing the Development Agreement
and issuing a Development Construction Permit?(D I,P'.!''The draft Agreement'''
will be assembled after comments have been resolved Iiby the other
departments, I have received their language for the Development Agreement,
and the Information for Development Agreementlsheet is returned to me from
the owner/developer For more information on the DCP, please','go to this
website httpadlioiww.'fCgtiv.com/engin'a'"arirvi'davrev.ph(i':
Comment Number: 8 .,,` Comment Originated: 03/20/2018
03/20/2018: Please see redlines for minor'comments.
Topic:1!'1IiSite Plan j1111
111 Comment Number: 2 Comment Originated: 03/20/2018
03/20/2018: Please depict the driveways off of Kensington Drive and Mason
Street as concrete in'the right-of-way.
Comment Number: 3' i Comment Originated: 03/20/2018
03/20/2018 ;! Add the fallowing note to the site plan:
illll i ull
Damaged curb,gutter„and sidewalk existing prior to construction, as well as
existing fences,trees, streets, sidewalks, curbs and gutters, landscaping,
structures,and improvements destroyed, damaged or removed due to
construction of this project,shall be replaced or restored in like kind at the
developer's expense, unless otherwise indicated on these plans, prior to the
acceptance of completed improvements and/or prior to the issuance of the first
Certificate of Occupancy. "
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak@fcgov.com
Topic: Landscape Plans
Comment Number: 1 Comment Originated:• 03/20/2018
03/20/2018: Clarify both "Dryland Seedmix" and "Wetland Seed Mix"called for
on plans.Will need: species list including scientific names, percent each
species contributes to mix in addition to pounds per acre and/or pounds per
square foot application rate for drill seed and broadcast seed. Recommend
using a mix containing both cool and warm season native and/or native-adapted
species. Minimum 15 lbs/acre drill seed rate and double that for broadcast rate.
List and mix options can be provided.
Comment Number: 2 Comment Originated: 03/20/2018
03/20/2018: Add NATIVE SEED MIX NOTES
1. PREPARE SOIL AS NECESSARY AND APPROPRIATE FOR NATIVE
SEED MIX SPECIES THROUGH AERATION AND ADDITION OF
AMENDMENTS, THEN SEED IN TWO DIRECTIONS TO DISTRIBUTE SEED
EVENLY OVER ENTIRE AREA. DRILL SEED ALL INDICATED AREAS AS
SOON AS POSSIBLE AFTER COMPLETION OF GRADING OPERATIONS.
2. IF CHANGES ARE TO BE MADE TO SEED MIX;''BASED ON SITE
CONDITIONS THEN APPROVAL MUST BE PROVIDED BY CITY
ENVIRONMENTAL PLANNER.
3.APPROPRIATE NATIVE SEEDING 4EQ'UIPMENT WILL BE USED
(STANDARD TURF SEEDING EQUIPMENT OR AGRICULTURE Eo'UIPMENT
SHALL NOT BE USED). ""'
it 4i1111 I i.
4. DRILL SEED APPLICATION RECOMMENDED PER;SPECIFIED lili;' ';1,
APPLICATION RATE TO NO MORE THAN/ INCHpEPTH. FOR
BROADCAST SEEDING INSTEAD OF DRILL SEEDING METHOD DOUBLE
SPECIFIED APPLICATION RATE;.REFER TO NATIVE MIX TABLE
FOR SPECIES, PERCENTAGES SAND APPLICATION RATES...
5. PREPARE A WEED MAN
AGEMENT PLAN TO ENSURE THAT WEEDS
ARE PROPERLY MANAGED BEFORE,DURING AND AFTER SEEDING
ACTIVITIES.`"
THE AREA SHALL 6. AFTER SEEDINGBE'COVERED WITH CRIMPED
STRAW,JUTE MESH 'OR OTHERIAPPROPRIATE METHODS
4 . iu
WHERE',NEEDED,TEMPORARY IRRIGATION SHOULD BE PROVIDED
'101C.UNTIL SEED IS ESTABLISHED. IF IRRIGATION IS USED,THE IRRIGATION
:'SYSTEM FOR SEEDED AREAS SHALL BE FULLY OPERATIONAL AT THE
TIMEOF SEEDING AND SHALL ENSURE 100% HEAD-TO-HEAD
COVERAGE OVER ALL AREAS. ALL METHODS AND
REQUIREMENTS IN THE APPROVED IRRIGATION PLAN SHALL BE
FOLLOWE'.
8. CONTRACTOR'pHALL MONITOR SEEDED AREA FOR PROPER
IRRIGATION, EROSION CONTROL, GERMINATION AND RESEEDING AS
NEEDED TO ESTABLISH COVER.
9. THE APPROVED SEED MIX AREA IS INTENDED TO BE MAINTAINED IN
A NATURAL LIKE LANDSCAPE AESTHETIC. IF AND WHEN MOWING
OCCURS IN NATIVE GRASS SEED MIX AREAS DO NOT MOW LOWER
THAN 6 TO 8 INCHES IN HEIGHT TO AVOID INHIBITING NATIVE PLANT
GROWTH.
10. NATIVE SEED AREA WILL BE CONSIDERED ESTABLISHED WHEN
SEVENTY PERCENT VEGETATIVE COVER IS REACHED WITH NO
LARGER THAN ONE FOOT SQUARE BARE SPOTS AND/OR UNTIL
DEEMED ESTABLISHED BY CITY PLANNING SERVICES AND EROSION
CONTROL.
11.THE DEVELOPER AND/OR LANDSCAPE CONTRACTOR IS
RESPONSIBLE FOR ADEQUATE SEEDLING COVERAGE AND GROWTH
AT THE TIME OF FINAL STABILIZATION, AS DEFINED BY STATE AND
LOCAL AGENCIES. IF FINAL STABILIZATION IS NOT ACHIEVED TO THE
SATISFACTION OF THE AGENCY,THE DEVELOPER AND/OR
LANDSCAPE CONTRACTOR SHALL BE RESPONSIBLE FOR ADDITIONAL
CORRECTIVE MEASURES TO SATISFY FINAL VEGETATIVE
REQUIREMENTS FOR CLOSEOUT.
Topic: Lighting Plan
Comment Number: 3 Comment Originated: 03/20/2018
03/20/2018: Lighting plan shows all 4000K CCT to be selected-please
update to warmer color temperatures (warm white).The American Medical
�I��,il� I�I�II�.
Association (AMA) and International Dark-Sky Association'(IDA) both
recommend using lighting that has a corrected color'temperature (CCT) of no
more than 3000 degrees Kelvin in order to limit the amountofAblue light in the
night environment. Cooler color temperatuiresilare harsher at night and cause
more disruption to circadian (biological) rhythms for both humansland wildlife
�Il��i ills �Illiill�ih
and blue light brightens the night sky andl,creates more glare than any,otlher
color of light. Both LED and metal halide fixtures contain large amountslof blue
� Ili I linl Ili, 4 iIIII,
light in their spectrum, and exposure to blue lighti;iat night h'as been shown to, ,,
harm human health and endanger wildlife. Therefore,use of warmer color
temperature(warm white, 3000K or less)for light fixtures is preferred in addition
to fixtures with motion-sensing or dimming cepabilities:''Site,light sources shall
be fully shielded and down-directional to minimize up light;'light spillage and
glare[see LUC 3.2:4(D)(3)]. '111I1''
Selecting 3000K or less luminaires supports City of Fort Collins Night Sky
Objectives. For further information regarding health effects please see:
httpJ ldarksky org/ama-report affirms-human health-impacts-from-leds/
i II �,li
Department: Forestry ;I'
Contact: Molly Roche, '111mroche@fcoov.com
l l ��III
Topic: Landscape Plans
Comment Number: III1 '.;I, Comment.Originated: 03/21/2018
3/20/2018: 'j;, i;', ju
Continued: 111 ,,,ji t,I'
Please address the!!status of this previous comment. I was not working for the
City of Fort Collins Forestry Division at this time and Tim Buchanan has since
retired, so I cannot ask him about the history of this specific question.
6/25/2014:
Thank you for arranging the first tree evaluation meeting. Please set up a
second onsite meeting with the City Forester to complete the tree inventory and
mitigation plan.As part of that meeting, some further review of the north-most
Ash on Mason can occur to consider desirability of removal or retention. Initial
discussion at the first meeting indicated the tree would be removed but some
further discussion could be beneficial in making a final determination.
Comment Number: 2 Comment Originated: 03/21/2018
3/20/2018:
Continued:
Please provide tree species diversity in the plant list and list percentages.
6/25/2014:
Provide tree species diversity on the final landscape plan and list percentages
in the plant list. Identify species on final landscape plan.
Comment Number: 5 Comment Originated: 03/21/2018
3/20/2018:
Continued:
8/19/2014:
Previous comment number two provided on 6/25/2014 is continu ed and still
active.
Comment Number: 7 G111 1 ;11 1' Comment Originated: 03/21/2018
3/20/2018: :•,.:;11111ipor
Continued: ,11
1li;1li1
�e
p g providing
g .. , G � Please
Thank you for 33 mitigation trees,to meett a re uirement
u size mitigation,trees as follows:
Canopy shade trees: 3.0"caliper balled'and;burlapped yl
Ornamental trees:2.5"caliper balled and burla'pped
Evergreen trees: 8' height bajject and burlapped'' ;;,1, 1111 11111 i'
In addition, please indicate mitigation trees with an'1"M";next to the trees on the
landscape plans. i
8/19/2014:
For final landscape plan,include 22 upsized•mitigation:trees Mitigation trees
should be'upsized as follows:
Canopy shade trees:3.0 inch caliper
Ornamental trees 25 inch caliper,,
Evergreen'trees 8 feet height
u II III' „
i11111 ' Comment Number: 8 Comment Originated; 03/21/2018
';3I20/2018: '1'1''
•Lindens do not typically,survive or thrive in parking lot islands and medians.
Please,use another species in places where Lindens are shown in the parking
lot, su6K,O,Kentucky Goffetree or Catalpa.
Comment Number „9'1 Comment Originated: 03/21/2018
3/20/2018: 'il y, "';�l'
Please use the most current City of Fort Collins General Landscape Notes,
Tree Protection Notes, and Street Tree notes on the plans, and show the street
tree permit note on all landscape sheets to emphasize importance.These notes
are available from Molly Roche in City Forestry(mroche@fcgov.com).
Comment Number: 10 Comment Originated: 03/21/2018
3/20/2018:
Show location of any stop signs and street lights. Identify these fixtures with a
distinct symbol. Space trees if needed as follows.
Stop Signs: 20 feet from sign
Street Light: 40 feet for canopy shade trees and 15 feet for ornamental trees
Department: Internal Services
Contact: Jonathon Nagel, , jnaoel@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 03/16/2018
03/16/2018: The Community Recycling Ordinance (No. 109 2016) requires that
all business and multifamily complexes subscribe to recycling service by the
end of 2020 that is at minimum 1/3 of their overall service capacity(total bin
capacity x number of weekly pickups, include both trash and recycling when
calculating overall service capacity). In general recycling containers must be at
least 50%the size of proposed trash containers to meet this requirement.
Please make sure proposed containers meet this requirement and that
adequate space is provided in all enclosures.
Comment Number: 2 ;'il'l!p; Comment Originated: 03/16/2018
03/16/2018: I see a plan enlargement for a proposed trash/recycling enclosure
on A4.3, but it doesn't appear to match either,enclosure on the site plan. Will
�III� unlit;'
both enclosures be identical? Please provideupdated elevations and plan
enlargements for all proposed trash/recycling'enclosure and include the overall
dimensions,widths of service gates andl��required pedestrian entrance,along
with proposed containers and their capacities on
U!i1;
Comment Number: 3 y , ;;! Comment Originated: 03/16/2018
03/16/2018: The enclosure located behind the existing structure is not
conducive to efficient pickup. Being locating at the end'of,a dead end the
collection truck will need to back into or Oit of the isle increasing the risk of
injury and property damage. ';!
Comment Number: 4 Comment Originated: 03/16/2018
03/16/2018: Curb cuts will need to be provided in front of all trash/recycling
enclosures to allow.containers to be wheeled in and out if not done so already.
•Comment Number:' 5 Comment Originated: 03/16/2018
03/16/2018:'11;!I;1The enclosure behind the parking structure will need a pedestrian
entrance that islseparate from the main service gates. Consider using a
e
oor-less entry which will provide safer and more efficient access.
Department: Light And Power �''�!"'
Contact: Rob Irish, ;'!970-224 61,67, rirish@fcgov.com
Topic: General .,0i1Fh;1l11
Comment Numb er: 1 Comment Originated: 03/19/2018
03/19/2018: Light& Power has existing streetlights adjacent to the site along
Mason St.that may be in conflict with the proposed entrance off of Mason St.
Please field locate and show these facilities on the plans.
Comment Number: 2 Comment Originated: 03/19/2018
03/19/2018: Please field locate and show the existing primary line from
College Ave.to the existing transformer on the plans. This line most likely runs
through the proposed LID area and may need to be potholed to determine if this
line will be in conflict.
Comment Number: 3 Comment Originated: 03/19/2018
03/19/2018: . Certain building materials and or building design may require
more clearance for the proposed transformer location. Please adhere to all
clearance requirements in the Electric Service Standards at the following link.
http://www.fcgov.com/utilities/business/builders-and-developers/development-fo
rms-guidelines-regulations
Comment Number: 4 Comment Originated: 03/19/2018
03/19/2018: A commercial service information form (C-1 form) and a one line
diagram will need to be submitted to Light& Power Engineering. A link to the
C-1 form is below:
http://www.fcgov.com/utilities/business/builders-and-developers/development=fo
rms-guidelines-regulations
Comment Number: 5 Comment Originated: 03/19/2018
03/19/2018: Electric Capacity Fee, Building Site charges, and any system
modification charges necessary will apply to this development. Please contact
Light& Power Engineering if you have any questions 1,at,970-221-6700. Please
reference our Electric Service Standards, developmenticharges and fee
estimator at the following link: �1,�';114,,, 1��1 I,�h' I,'h�
1;;,III'
http://www.fcgov.com/utilities/business/builders-and-developers
Comment Number: 6 ; Comment Originated: 03/19/2018
03/19/2018: What is the dark line shown;jin front of the proposed transformer
�l�l tl1,u I� III 1,
location?
1 .Ili •lil 1
Department: PFA
Contact: Andrew Rosen, , @f arosencgov com
Topic: General
Comment Number 1 111Comment Originated: 03/20/2018
03/19/2018:
Per the IFC•2015, the Emergency Access„Easement is now allowed to be 26ft
in width rather than the 30ft'shown but it cannot be located closer than 15ft to the
edge ofllthe building
•
Commenf�Nimber 2 Comment Originated: 03/20/2018
III I��I� illll�l{' II
11;,03/19/2018: dull
I111The,signage plan for the Fire Lanes should be available for review by PFA
b'efore.the FDP can be'approved ,
�I
Comment Number: 3' ; Comment Originated: 03/20/2018
03/20/2018: ! i!�
Cars are shown on the provided documents parked very closely in the new
structure. PFA re uests information on how the vehicles will be stored to allow
for access.
Department: Planning Services
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 03/20/2018
03/20/2018: On the Plat the signature block for Planning, "Director of" appears
twice, delete one. On the signature line edit to CDNS Director.
Comment Number: 2 Comment Originated: 03/20/2018
03/20/2018: Note 8 on the site plan should include all signs, not just monument
signs.
Comment Number: 3 Comment Originated: 03/20/2018
03/20/2018: On the site plan, the Handicap spaces on the north side of the
building, where is the sidewalk ramp connection for these spaces?
Comment Number: 4 Comment Originated: 03/20/2018
03/20/2018: Can there be wheels stops or something else to prevent cars
parked in the parallel spaces on the south parking area from encroaching into
the accessibility route to the entrance of the building?
Department: Stormwater Engineering ,;1,
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.co'�m I1i'i,.
Topic: Erosion Control hil�;li '';III,
P !I
1' Illi iii
1i;� I�III
03/12/2018: Please resubmit an Erosion Cnnfro' " Comment Originated: 03/12/2018
Comment Number: 1
VI l Report as the recently
received materials has comments andlllredlines that needed to be add.ressed to
meet City Criteria. Please resubmit an Erosion Control Plans as the recently
"�il� li ,Ir i1�4I'�i
received materials have comments and redlines that needed to be addressed
'I I '�Ill�ltl I" , '� °r,
to meet City Criteria. Please resubmit an Erosion'Control Escrow/Security �!;yu'
Calculation as the recently'received,materials has'comments and redlines,that
needed to be addressed to meet City Criteria and as a!result have changed the
Erosion Control Plans and would require°a recalculation'ot the Escrow. If you
need clarification concerning the Erosion Control Material Requirements or
Comments presented above please contact myself JesseSch'lam (970)
224-6015 jschlam@fcgov.com
q Contact: Wes Lamar ue, 970-416-2418, wlamarque@fcgov.com
Topic ,1'1General
11' !,Comment Number 2 Comment Originated: 03/20/2018
11 iO3/20/2018: The°void ratio the City has for criteria is 30%in the No.2 rock.
u u 'I
Please revise detention calculations.
Comment Number: '3;;i' Comment Originated: 03/20/2018
03/20/2018,I,,,,An overflow,inlet is required at the low point for all the porous
paver areasll ;This is,to'prevent standing water in the sump locations for the
paver areas.
Department: Technical Services
Contact Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations
Comment Number: 8 Comment Originated: 03/19/2018
03/19/2018: Please change the title as marked on all sheets to Pedersen
Toyota Expansion"to match the other plan sets. See redlines.
Comment Number: 9 Comment Originated: 03/19/2018
03/19/2018: There are line over text issues. See redlines.
Topic: Construction Drawings
Comment Number: 11 Comment Originated: 03/19/2018
03/19/2018: Please revise the sub-title as marked. See redlines.
Comment Number: 12 Comment Originated: 03/19/2018
03/19/2018: Please provide the following information in the EXACT format
shown.
PROJECT DATUM: NGVD29 UNADJUSTED (OLD CITY OF FORT COLLINS
DATUM)
BENCHMARK#w/DESCRIPTION
ELEVATION:
BENCHMARK#w/DESCRIPTION
ELEVATION:
NOTE: IF NAVD 88 DATUM IS REQUIRED FOR;ANYi�;PURPOSE,THE
FOLLOWING EQUATION SHOULD BE USED:' 'NAVD88 '�tNGVD29
UNADJUSTED+X.XX'.
Comment Number: 13 ,, ;;1!1 Comment Originated: 03/19/2018
03/19/2018: Some of the easement descriptions shown are incorrect. If they
are going to stay on the plan,they should match whatlis�1shown on the 'li�i Subdivision Plat. �� ;'�; 'i'
Comment Number: 14 H, Comment Originated: 03/19/2018
03/19/2018: Please tie the coordinate values�shown to;;the project boundary.
i hu�a,
We would prefer that this be done by adding property corn Ier,values to each
ing sheet, or show the property cornerlvalues on the horizontal'control plans and
adding a note.to each sheet with coordinate values.
Comment Number: 15 Comment Originated: 03/19/2018
03/19/2018: There is text that needs to be masked. Mask all text in hatched
, areasj;See,redlines:'
"1''; Comment Number: 16 Comment Originated: 03/20/2018
Please make'sure the right of way&easement descriptions
shown match what is;,shown on•the Subdivision Plat.
Topic: Landscape Plans 11,111,111
Comment;Number: 6I1i, Comment Originated: 03/19/2018
03/19/2018: There are;lline over text issues.See redlines.
Comment Number:''' 7 Comment Originated: 03/19/2018
03/19/2018: There are text over text issues. See redlines.
Topic: Lighting Plan
Comment Number: 10 Comment Originated: 03/19/2018
03/19/2018: Please change the title as marked on all sheets to °Pedersen
Toyota Expansion"to match the other plan sets.
Topic: Plat
Comment Number: 1 Comment Originated: 03/19/2018
03/19/2018: Please make changes as marked. If changes are not made or you
disagree with comments, please provide written response of why corrections
were not made. Please provide any responses on redlined sheets and/or in
response letter.
Topic: Site Plan
Comment Number: 2 Comment Originated: 03/19/2018
03/19/2018: Some of the sheet titles in the sheet index do not match the sheet
titles on the noted sheets. See redlines.
Comment Number: 3 Comment Originated: 03/19/2018
03/19/2018: Please revise the legal description as marked. See redlines.
Comment Number: 4 i';I;I Comment Originated: 03/19/2018
03/19/2018: There is text that needs to be masked. Mlasklall text in hatched
areas. See redlines. II;,, ,I1;li;l1!1
'IFII II 'll it
Comment Number: 5 'II''1� !ill'' III I,I, Comment Originated: 03/19/2018
03/19/2018: Some of the easement descnptio�ns shown are"incorrect. If they
m
Subdivision Plat plan,they I II itch what is shown on the are goingto stayon the should, I I
Ili ll I!��lil
I
� I
IIII III II,II IIIII
Department: Traffic Operation uIl l lll„
pli 'IIIII�I ,1Ilull" �I,1,1,.
Contact: .Tim Tuttle, TTUTTLE@.fcgov.com I,i
Topic: General
(i-ttal) Comment Number: 1 �'Ir1 ,i;l�; Comment Originated: 03/19/2018
Signing and striping
I Ill „ ,r
�; comments rf any w be provided at the
03/19/2018: •
Planning Review meeting;'i
Department: Water-Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcoov.com
,I, r �ii li III 1Iilk
Topic:'j General 'II'Ip "II,1,
''Comment Num b Iber 1 • Comment Originated: 03/20/2018
03/20/2018: There'are proposed'tress located along the northern property line
within the utility easemer t. Please remove all the trees within the easement.
See redlines. ,,I,
Ills
Comment Number: Ill2 Comment Originated: 03/20/2018
�i' II'lll 'lii ' ';,
03/20/2018: Pleasellshow the existing curb stops and meter pits for the existing
water services
Comment Number: 3 Comment Originated: 03/20/2018
03/20/2.018: Please label the existing water and sewer lines north of the site.