HomeMy WebLinkAboutGATEWAY AT PROSPECT - BDR200010 - CORRESPONDENCE - OTHER WATER AND OR SANITATION DISTRICTS (2)3201 East Mulberry, Unit Q – P.O. Box 1518 • Fort Collins, Colorado 80522
Phone (970) 498-0604 •Fax (970) 498-0701 •www.boxeldersanitation.org
February 1, 2021
City of Fort Collins Planning
P.O. Box 580
Fort Collins, CO 80522-0580
Attention: Todd Sullivan
RE: Case Number: BDR 2000010
Title: Gateway at Prospect
Owner/Applicant:
Owner Contact:
Parcel Number(s):
Boxelder Sanitation District (BSD), has reviewed the Gateway at Prospect:
1. Subdivision Plat – Dated 06/08/2020
2. Utility Plans - Dated 06/08/2020
The District hereby advises as follows:
There is no objection to this proposal.
Responses required to comments below.
The District will respond at the hearing date of ______________.
Comments:
The District has reviewed this submittal and has the following comments:
Plat
1. The existing easements within the property are currently 20 feet in width. As part
of this project the District would like to increase those easements to 30 feet in
width to provide better access and constructability should any maintenance be
required in the future.
2. Any location the where the sewers are not in public R.O.W will need easements
that are on separate documents from the standard utility and access easements.
The District can provide the template for the Easement Agreement.
Utility Plans
S:\DEVELOPMENT\Basins\East_Basin\Boxelder_Interceptor_Subbasin\Gateway at Prospect\Gateway at Prospect - Review 1 2-1-2021.docx
1. Sheet OU1 – In the area around the Lake Canal and Cache La Poudre Inlet Canal
Boxelder has several large sewers. This area also has ELCO and Greeley
waterlines and there has been discussion that NISP is looking at alternatives for a
large waterline and the City of Fort Collins has stormwater projects planned. We
require that communication and planning occur to discuss all future plans and
impacts on our sewers.
2. Sheet OU2
a. The 27- inch sewer in Street B will need to be 30-inch. The 10-inch line to
the west will be abandoned. The existing 10-inch line will need to connect
to the 30-inch at the northern terminal manhole.
b. The sewer in front of the Glanz property flows to the east and connects to
the 27-inch sewer.
c. Provide access for District maintenance equipment to existing sewer
manholes in open space areas.
Please let us know if you have any questions. We look forward to future submittals on
this project.
Sincerely,
Brian Zick, P.E.
District Manager