HomeMy WebLinkAboutFORT COLLINS NISSAN-KIA - FDP220011 - SUBMITTAL DOCUMENTS - ROUND 1 - WILDLIFE DOCUMENTSITEM QTY UNIT COST TOTAL NOTES/COMMENTS
Deciduous Trees 8 EA 450.00$ 3,600.00$
Evergreen Trees 6 EA 450.00$ 2,700.00$
Shrubs 0 EA 50.00$ -$
Native Seed 53,887 SF 0.15$ 8,083.05$
Crimped Straw 0 AC 0.02$ -$
Wetland Restoration 0 AC -$
Wood Mulch 0 CY 0.85$ -$
Rock Mulch 0 CY 0.95$ -$
Boulders 60 Each 450.00$ 27,000.00$
Installation LS -$ Above Units Costs Include Install
Temp Irrigation System 53,887 SF 0.85$ 45,803.95$
Perm Irrigation System LS -$
Installation LS -$ Above Units Costs Include Install
Weed Treatment LS -$ This number is still pending
Monitoring and Reporting (3YR) 53,887 SF 0.30$ 16,166.10$
103,353.10$
129,191.38$ 125% of Subtotal
Notes:
1 - General conditions / insurance / bonding and mobilization are assumed in unit costs.
2 - All unit prices include labor, materials and machinery used to properly stock, prepare, install and maintain the work.
3 - This is an estimate to be used for preliminary budgetary considerations only.
4 -TB Group, LLC is not held responsible for any discrepancies of actual quantities, fees or construction costs.
WEED MANAGEMENT
MONITORING AND REPORTING (3YR)
SUBTOTAL
TOTAL ESCROW
Natural Habitat Buffer Zone Escrow Calculation
The purpose of this form is to help the applicant estimate the required Natural Habitat Buffer Zone Escrow/Security for a project. Provide details in all
highlighted fields.
LANDSCAPE
IRRIGATION