HomeMy WebLinkAboutSTITCH-TECH WAREHOUSE - EXPANSION OF A NON-CONFORMING USE - 16-88B - CORRESPONDENCE - RESPONSE TO APPLICANT0 0
CITY OF FORT COLLINS
OFFICE OF DEVELOPMENT SERVICES, PLANNING DEPARTMENT
May 9, 1988
Charles Lockman
1409 Longs Peak Drive
Fort Collins, CO 80524
Dear Mr. Lockman:
As you are aware, the proposed non -conforming use expansion for Stitch Tech,
Inc. is scheduled for the May 23, 1988 Planning and Zoning Board meeting. I
have been working with Dick Rutherford of Stewart and Associates regarding
the specific requirements that must be addressed so that we may review and
evaluate the proposed expansion.
In a letter to Mr. Rutherford, dated April 26, 1988, I indicated that a storm
drainage report and plan must be submitted for review by the city's Storm
Drainage Utility, as required by city code. To date, Mr. Rutherford has not
provided us with any storm drainage information, since he has not been
authorized by his client (Stitch Tech, Inc.) to do any further work on this
project. Storm drainage, as well as concerns regarding the buffering of resi-
dences to the east of the proposed building expansion, were among the issues
raised at the May 5 neighborhood meeting by area residents and propertyown-
ers. In addition to the need for a storm drainage report and plan, I am also
asking that additional landscaping be provided along the east propertyline of
this site and be identified on the proposed site plan to address concerns raised
at the neighborhood meeting.
Since Stitch Tech, Inc. has not provided a satisfactory response regarding storm
drainage and has indicated that no additional work would be done on the pro-
ject, I am asking that as building owners, you clarify your intent regarding
this project and its present status. If the project is to remain on the May 23,
1988 agenda for the Planning and Zoning Board, a storm drainage report and
plan must be submitted to the Planning Office by Monday, Mav 16, 1988. The
91
SERVICES, PLANNING
Stitch Tech
Page 2
0
provision of additional landscaping along
be addressed prior to the Board meeting.
contact Tom Peterson (Planning Director) o
Sincerely,
jk( j
Sherry Alb rson-Clark
Senior City lanncr
the eastern propertyline should also
If you have any questions, please
r myself, at 221-6750.
cc: Tom Peterson, Director of Planning
Linda Hopkins, Economic Opportunity Administrator
Dick Rutherford, Stewart and Associates
Paul Gage, Union Pacific Railroad
Stitch Tech, Inc., 1800 E. Harmony Rd., Fort Collins, CO 80525
CITY OF FORT COLLINS
OFFICE OF DEVELOPMENT SERVICES, PLANNING DEPARTMENT
May 9, 1988
Arlo Deines
3024 Wakonda Drive
Fort Collins, CO 80525
Dear Mr. Deines:
As you are aware, the proposed non -conforming use expansion for Stitch Tech,
Inc. is scheduled for the May 23, 1988 Planning and Zoning Board meeting. I
have been working with Dick Rutherford of Stewart and Associates regarding
the specific requirements that must be addressed so that we may review and
evaluate the proposed expansion.
In a letter to Mr. Rutherford, dated April 26, 1988, I indicated that a storm
drainage report and plan must be submitted for review by the city's Storm
Drainage Utility, as required by city code. To date, Mr. Rutherford has not
provided us with any storm drainage information, since he has not been
authorized by his client (Stitch Tech, Inc.) to do any further work on this
project. Storm drainage, as well as concerns regarding the buffering of resi-
dences to the east of the proposed building expansion, were among the issues
raised at the May 5 neighborhood meeting by area residents and propertyown-
ers. In addition to the need for a storm drainage report and plan, I am also
asking that additional landscaping be provided along the east propertyline of
this site and be identified on the proposed site plan to address concerns raised
at the neighborhood meeting.
Since Stitch Tech, Inc. has not provided a satisfactory response regarding storm
drainage and has indicated that no additional work would be done on the pro-
ject, I am asking that as building owners, you clarify your intent regarding
this project and its present status. If the project is to remain on the May 23,
1988 agenda for the Planning and Zoning Board, a storm drainage report and
plan must be submitted to the Planning Office by Monday, May 16, 1988. The
OFFICE OF DEVELOPMENT
SERVICES, PLANNING
• P.O. Box 580 • Fort Collins, Colorado 80522 • (303) 221.6750
Stitch Tech •
Page 2
provision of additional landscaping along the eastern propertyline should also
be addressed prior to the Board meeting. If you have any questions, please
contact Tom Peterson (Planning Director) or myself, at 221-6750.
Sincerely,
Sherry Alb
tson-Clark
Senior City
lanner
cc: Tom Peterson, Director of Planning
Linda Hopkins, Economic Opportunity Administrator
Dick Rutherford, Stewart and Associates
Paul Gage, Union Pacific Railroad
Stitch Tech, Inc., 1800 E. Harmony Rd., Fort Collins, CO 80525