HomeMy WebLinkAboutPOLESTAR VILLAGE - PDP220010 - SUBMITTAL DOCUMENTS - ROUND 1 - PROJECT NARRATIVEDEVELOPMENT CONSTRUCTION STATEMENT
Development of Polestar Gardens is expected to begin in the 2nd quarter of 2023.
Polestar Gardens will be constructed as two sequences of development. Sequence
1 will beginning in the 2nd Quarter of 2023 and Sequence 2 beginning in the second
half of 2024. Each of the sequences of construction shall include the following:
The First Sequence of Construction will include of extending Orchard Place and its
associated utilities from the eastern terminus of Orchard Place to the western
boundary of the subject property. Also included will be the extension of Locust
Grove Drive to intersect Orchard Place, overlot grading of the entire 20.5 acres site
area, pedestrian sidewalks, tree lawn and street tree plantings, as well as the
construction of the on-site Detention and Water Quality Pond. The development
of this critical first sequence of infrastructure construction will allow for the
development of 19 Single Family Detached Homes that will front onto Orchard
Place.
The Second Sequence of Construction will likely begin in late 2023 or early 2024
and will include the extension of West Plum Street and its associated utilities from
the eastern boundary of the property to the intersection of Orchard Place. Also
included will be pedestrian sidewalks, tree lawns and street tree plantings, as well
as the construction of several private drives and alley’s, storm drainage
infrastructure, Low Impact Design (LID) water quality features, reclamation and
landscape construction of the 50’ wide Natural Area Habitat Buffer and soft trail
and the landscape of the common area open space tracts. The completion of this
sequence of construction will allowing for the development of all other proposed
housing products, neighborhood activity center and other community buildings
and amenities.