The City Staff has reviewed the Spirit of Joy Lutheran Church, minor subdivi-
sion and has the following comments:
1. A 15' minimum easement is needed along the Harmony frontage and. along
the frontage of Lemay.
2. Mountain Bell requests a 8' utility easement around the perimeter.
I Water and sewer service is not readily available to this site. The developer's
engineer / architect should contact the water utility to determine the best
way to obtain water and sewer service.
4. Utility plans arc needed for the curb, gutter, and sidewalk.
5. Landscape maintenance along Harmony Road will not be done by the City
Parks and Recreation Department.
6. City maps show that there are existing drainage facilities on the southern
portion of the site. If there are drainage easements on the property they
should be shown.
7. A drainage report and grading and drainage plan (prepared by a licensed
engineer) must be submitted for review and approval prior to development
of this lot.
OFFICE OF DEVELOPMENT
SERVICES, PLANNING
300 LaPorte Ave. • P.O. Box 580 • Fort Collins, Colorado 80522 • (303) 221-6750
Page 2 • •
Response to these comments arc due by noon Wednesday, April 20. 1988. The
administrative hearing is scheduled for Thursday, April 21. at I: 30 in the
Planning Department conference room..
If you have any questions, please call nic at 221-6750.
Sincerely,
Debbie deBesche
City Planner