February 8, 1995
Steve Olt
Planning Department
City of Fort Collins
RE: Hugh M. Woods P.U.D.
Final Revisions
Dear Steve:
This letter is in response to staff comments of January 13, 1995,
regarding Hugh M. Woods P.U.D., Final. The response numbers
correspond to those of staff comments. Those not noted will be
addressed by the project engineer.
1. PSCo has been contacted for comments. Line is in north side of
Skyway.
2. U.S. West has no out standing issues.
4a. Required accessible parking (5 in front, 2 in rear) and routing
has been designated. Other
4b. A 100-foot access and drainage easement has been provided on
south side of building. Other comments will be addressed at
building permit application.
5a. JR Engineering has provided design for development on the east
side of College Ave.
5b. The owners on the northwest corner of College Ave. and
Skyway Dr. have reached an agreement with Hugh M. Woods
and the Transportation Department. This signed document will
be available.
5c. Matt Delich provided an Oct. 4 letter verifying left turn storage
capacity to Tom Vossberg and Steve Olt.
6a. Southerly street is Timan Drive.
6b. Skyway Drive ROW has been identified.
6c. Dimensions have been labeled.
Sell De��
in Ave- saw
117 E. ��plorado
(3Q 48 -1921
6d. Boundary description has been corrected.
8a. Construction has been clarified at SE access.
8b.. Boundary description has been corrected.
8c. Legal description has been submitted.
8d. Property lines, ROW's and easements have been identified.
8e. Site Plan has been separated from Landscape Plan.
9a. See 5a and 5b. New alignment is indicated on the Site Plan.
9b. Signed easements will be available at Feb. 24 work session.
9c. See RBD report.
9d. Southeast corner has been revised.
9e. Weight restrictions - per staff recommendation.
9f. East building wall includes 8-foot offset. Color pallet has been
submitted. Architectural detailing has been added to security
wall along Skyway Dr.
10a. All existing trees have been shown, with intent to save or
remove.
10b. Of 15 existing trees on the site, 5 will be removed. To mitigate
this loss, we have proposed to plant 60 trees in addition to the
street trees along College Avenue and Skyway Drive, and the
trees in the parking lot and retaining wall.
10c. Ash species has been changed to Manchurian.
10d. Evergreens have been substituted at the south access, as well as
the intersection of College Ave. and Skyway Dr. Plantings here
have been configured somewhat to accommodate the new
location for a ground sign.
11. Wetland impacts have been addressed in RBD's report to Rob
Wilkinson.
D12.Ditch Company signature block has been revi edlans sent
for comment. ����
>��
14. Parking and access at Hickory House has been reconfigured.
Patterned concrete will define pedestrian crossing areas to the
restaurant.
15. The offsite drainage easement will be resolved before this item
goes to the Planning and Zoning Board.
16. There is no exterior wall lighting on the building.
17. A monument sign has been located near the intersection of
College Ave. and Skyway Dr.
18. The "potential parking" has been deleted from plans.
We hope that these revisions address the concerns of the development
review staff.
Sincerely,
JIM SELL DESIGN INC.
� � Yce
Kay Force
xc: Barry Hilton