HomeMy WebLinkAboutHUGH M WOODS PUD - PRELIMINARY - 26-88D - CORRESPONDENCE - DRAINAGE RELATED DOCUMENT09-23-1994 03:42PM FROM Jim Sell Design TO 2216378 P.01
0 0
MEMO
TO: Barry Hilton, Hugh M. Woods
FROM: Jim Sell, Jim Sell Design 3(t
DATE: September 23, 1994
SUBJECT: Hugh M. Woods PUD: Storm Draingage
The following three items must be responded to no later than 5:00 pm October 5, 1994.
1. Identify where surface water is going after it leaves the H.M. Woods site.
2. Find out if there are any existing drainage easements on that location.
3. Identify the impacts that will occur when the H.M. Woods site is developed as proposed.
Steve Olt will give us further clarification on what is desired at this stage in the way
pertaining to impact.
These issues are urgent and very important, therefore requiring immediate attention primarily
by RBD engineers. However, I will do my best to obtain further details from Steve Olt and
Torn Shoemaker pertaining to item number three and specifically what is needed to address
that issue.
cc Stan Meyers, R13D
Steve Fister, Realtec
Steve Olt, City of Ft. Collins Planning
Glen Schlueter, City of Ft. Collins Storm Drainage
TOTAL P.01