Erosion Control Report
for
Voice of Truth Tabernacle Subdivision
(Tract Two, Dix Amended Plat)
Fort Collins, Colorado
Prepared for:
Voice of Truth Tabernacle
P.O. Box 273491
Fort Collins, CO 80527
Attn: Tito Moreira
Prepared by:
SHEAR ENGINEERING CORPORATION
Project No: 2978-01-18
Date: April 2022
TABLE OF CONTENTS
Title Page
Vicinity Map
Table of Contents
I. PROJECT DESCRIPTION AND NATURE OF CONSTRUCTION ............................. 1
A. Site location and contact information .......................................................................... 1
B. Existing Site Condition .................................................................................................. 1
C. Proposed Construction Activities ................................................................................. 3
II. POTENTIAL POLLUTANT SOURCES…………………………………………………3
III. INSTALLATION AND REMOVAL SEQUENCE OF CONTROL MEASURES…….8
IV. FINAL VEGETATION AND STABILIZATION AND EROSION CONTROL
ESCROW………………………………………………………………………………….10
V. CONCLUSIONS ................................................................................................................. 10
A. Compliance with Standards ........................................................................................ 10
VI. REFERENCES………………………………………………………………………… …11
Project: Disturbed Acres:3.17
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
EA. 1 $825.00 $825.00
L.F. 1,140 $2.75 $3,135.00
EA. 6 $150.00 $900.00
EA. 1 $1,925.00 $1,925.00
Sub-Total: $6,785.00
1.5 x Sub-Total: $10,177.50
Amount of security: $10,177.50
Total Acres x Price/acre: 3106.6
$980.00 Sub-Total: $3,106.60
1.5 x Sub-Total: $4,659.90
Amount to Re-seed: $4,659.90
Minimum escrow amount: $3,000.00
Erosion Control Escrow:$10,177.50
Fields in yellow should be amended for this project.
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times
the cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid,
whichever is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three
thousand dollars ($3,000) for commercial development”
Vehicle Tracking Control (VTC)
Reseeding
Unit Price of Seeding per acre:
Minimum Escrow Amount
Final Escrow Amount
Erosion and Sediment Control Escrow/Security Calculation
for The City of Fort Collins
Voice of Truth Tabernacle Subdivision; Fort Collins, Colorado
BMP Amount
Concrete Washout (CW)
Wattle (W)
Rock Sock (CSP)
4/26/2022 9:02 AM\\server\Clients\V-Clients\Voice of Truth Tabernacle (Tito Moreira) - Copy\2978-01-18 Voice of Truth Tabernacle Sub\Documents\Drainage and floodplain\Erosion Control\Voice of Truth Escrow April 2022.xls