HomeMy WebLinkAboutPOWERHOUSE 2 - PDP220006 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORT400 North Link Lane | Fort Collins, Colorado 80524
Telephone: 970-206-9455 Fax: 970-206-9441
GEOTECHNICAL INVESTIGATION
PROPOSED POWERHOUSE 2
NE CORNER EAST VINE DRIVE
AND COLLEGE AVENUE
FORT COLLINS, COLORADO
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
320 East Vine Drive, Suite 101
Fort Collins, Colorado 80524
Attention: Bryan Wilson
Project No. FC10223-125
March 14, 2022
TABLE OF CONTENTS
SCOPE 1
SUMMARY OF CONCLUSIONS 1
SITE CONDITIONS AND PROPOSED CONSTRUCTION 2
INVESTIGATION 4
SUBSURFACE CONDITIONS 4
Groundwater 5
GEOLOGIC HAZARDS 5
Shallow Groundwater 5
Expansive Soils 6
Seismicity 6
SITE DEVELOPMENT 6
Excavations 7
Dewatering 7
Fill Placement 8
SUBSURFACE IMPROVEMENT 10
Chemical Grouting 10
Compaction Grouting 10
Vibropiers and Grouted Aggregate Piers 11
FOUNDATIONS 11
Spread Footings 12
Reinforced Concrete Mat 13
Drilled Piers Bottomed in Bedrock 14
Franki Piles 15
Augercast Piles 15
Helical Piers 15
Driven H-Piles 16
Laterally Loaded Piers 17
Closely Spaced Pier Reduction Factors 17
RETAINING WALLS 18
SETTLEMENT 19
LATERAL EARTH PRESSURES 19
BELOW GRADE AREAS 20
FLOOR SYSTEMS 21
Exterior Flatwork 22
PAVEMENTS 23
Pavement Selection 24
Subgrade and Pavement Materials and Construction 24
Pavement Maintenance 24
WATER-SOLUBLE SULFATES 25
SURFACE DRAINAGE 25
CONSTRUCTION OBSERVATIONS 26
GEOTECHNICAL RISK 26
LIMITATIONS 26
FIGURE 1 – LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2 – SUMMARY LOGS OF EXPLORATORY BORINGS
APPENDIX A – RESULTS OF LABORATORY TESTING
APPENDIX B – SAMPLE SITE GRADING SPECIFICATIONS
APPENDIX C – PAVEMENT CONSTRUCTION RECOMMENDATIONS
APPENDIX D – PAVEMENT MAINTENANCE PROGRAM
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
1
SCOPE
This report presents the results of our Geotechnical Investigation for the proposed
Powerhouse 2 facility in Fort Collins, Colorado. The purpose of the investigation was to
evaluate the subsurface conditions and provide foundation recommendations and
geotechnical design criteria for the project. The scope was described in our Service
Agreement (Proposal No. FC-21-0545) dated October 15, 2021.
The report was prepared from data developed during field exploration, laboratory
testing, engineering analysis, and experience with similar conditions. The report includes a
description of subsurface conditions found in our exploratory borings and discussions of site
development as influenced by geotechnical considerations. Our opinions and
recommendations regarding design criteria and construction details for site development,
foundations, floor systems, slabs-on-grade, lateral earth loads, pavements and drainage are
provided. The report was prepared for the exclusive use of Powerhouse 2 Development
Company, LLC in design and construction of the proposed improvements. If the proposed
construction differs from descriptions herein, we should be requested to review our
recommendations. Our conclusions are summarized in the following paragraphs.
SUMMARY OF CONCLUSIONS
1. Subsurface conditions encountered in our borings generally consisted of 4 to
7 feet of clayey sand or sandy clay fill over clean to clayey sand and gravel,
underlain by sandstone bedrock to the depths explored. Three of the borings
were overlain by 4 to 6 inches of asphaltic concrete. All of the soils encountered
are considered non-swelling to low swelling.
2. Groundwater was encountered in six borings during drilling at depths of 8 to 11
feet. When measured several days later, groundwater was at depths of 5 to 10
feet in four borings. Existing groundwater levels may affect proposed
construction. We recommend a minimum 3-foot separation between foundation
elements and groundwater. Groundwater will likely be encountered during
construction of below grade areas and deeper utilities unless final grade is
raised. Dewatering should be anticipated.
3. Existing fill was encountered in four borings to depths of 4 to 6 feet. The fill
was likely placed during previous site grading activities. It is of unknown age
and origin and should not support foundations or floor slabs. We recommend
removal and recompaction of the existing fill beneath the building. The fill is
likely acceptable below pavements provided it can pass proof roll.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
2
4. We understand that multiple foundation options are being considered, with a
focus on reducing the use of cement. Drilled piers socketed into the sandstone
bedrock, helical piers, driven H-piles, and aggregate piers are acceptable for
the proposed structure and discussed in this report. Casing and pumped
concrete methods for drilled piers will likely be required because borings will
be advanced through groundwater and caving granular soils. The displaced
water may need to be filtered, treated, or disposed of.
We believe it is also possible to use a shallow foundation system such as
footings and/or reinforced concrete slabs (mat) with tolerable movements. The
founding soils can be improved by vibropier (stone column) or compaction
grouting techniques to reduce potential settlement. A specialty contractor
should evaluate the feasibility and maximum allowable soil pressures for these
ground improvement methods. Design and construction criteria for these
options are presented in the report.
5. Site grading is expected to be raised with imported fill. If deep foundations are
used, the building floors should be structurally supported. We believe slab-on-
grade floors, placed on approved fill are also appropriate for this site. Some
movement of slab-on-grade floors should be anticipated. We expect
movements will be minor, on the order of 1-inch or less if compacted properly.
If movement is unacceptable, structural floors should be used.
6. Surface drainage should be designed, constructed and maintained to provide
rapid removal of surface runoff away from the proposed structure.
Conservative irrigation practices should be followed to avoid excessive wetting.
7. Samples of the subgrade soils generally classified as AASHTO A-6 soils. We
anticipate that the parking lot will have semi -frequent heavy truck traffic for
deliveries and waste removal. For heavy traffic areas and parking, we
recommend 6 inches of asphaltic concrete over 6 inches of aggregate base
course. Some areas of the site will be predominantly for pedestrian traffic but
may also take vehicular traffic. We understand brick or concrete pavers may
be used in these areas. Where pavers will receive vehicular traffic , we
recommend that they be placed over 5 inches of rigid pavement.
SITE CONDITIONS AND PROPOSED CONSTRUCTION
The site is located at the northeast corner of the intersection of East Vine Drive and
College Avenue, north of East Vine Drive, between College Avenue and Jerome Street in
Fort Collins, Colorado (Figure 1). The property is currently occupied by a vehicle repair shop,
and a semi-truck service yard. Some areas are paved in asphalt and the rest of the property
is gravel paved. The Lake Canal (aka Josh Ames Ditch) irrigation ditch is directly north of the
site. It was dry during our investigation.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
3
Figure A: Google Earth Aerial of Site
Only preliminary plans were available at the time of this report, structural details and
construction plans were not provided. We understand that an approximately 153,260 square
foot, 5-story building is to be constructed at this site. Based on cut/fill plans provided by the
client we understand that fill will be imported to raise the grade of the area around the building
by 2 to 7 feet (Figure B). The only below grade construction planned is an elevator pit. The
property will have paved parking and access drives connecting to East Vi ne Drive and College
Avenue. An approximately 3-foot-deep detention pond is planned in the southeast corner of
the property.
Figure B: Cut/Fill Map by Connell Resources
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
4
INVESTIGATION
The field investigation included drilling seven exploratory borings at the locations
presented on Figure 1. The borings were drilled to depths of approximately 10 to 3 0 feet
using 4-inch diameter, continuous-flight augers, and a truck-mounted drill. Drilling was
observed by our field representative who logged the soils and bedrock. Summary logs of the
borings, including results of field penetration resistance tests, are presented on Figure 2.
Soil and bedrock samples obtained during drilling were returned to our laboratory and
visually examined by our geotechnical engineer. Laboratory testing was assigned and
included moisture content, dry density, swell -consolidation, particle-size analysis, Atterberg
limits and water-soluble sulfate tests. Swell-consolidation test samples were wetted at a
confining pressure which approximated the pressure exerted by the overburden soils
(overburden pressures). Results of the laboratory tests are presented in Appendix A and
summarized in Table A-I.
SUBSURFACE CONDITIONS
Subsurface conditions encountered in our borings generally consisted of 4 to 7 feet of
clayey sand or sandy clay fill over clean to clayey sand and gravel. Three of the borings were
overlain by 4 to 6 inches of asphaltic concrete . Samples of the soils from the upper 5 feet
exhibited low plasticity and nil to low-swell potential. The clean to clayey sands and gravel
were loose to very dense according to standard penetration testing. Very hard sandstone
bedrock was encountered in four borings at 16 to 19½ feet to the depths explored. Further
descriptions of the subsurface conditions are presented on our boring logs and in our
laboratory test results.
Existing fill, comprised of clayey, gravelly sand, was encountered in the upper 4 to 6
feet in four borings during this investigation. Fill is likely present in other places and at greater
depths not explored by our borings. The fill presents risk of settl ement. We recommend
removing, moisture treating and re-compacting any existing fill below structures.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
5
Groundwater
Groundwater was encountered in six borings during drilling at depths of 8 to 11 feet.
When measured several days later, groundwater was at depths of 5 to 10 feet in four borings.
Groundwater will fluctuate seasonally and will be affected by water levels in nearby irrigation
ditches, if present. Groundwater may develop on or near the bedrock surface or other low
permeable soil or bedrock when a source of water not presently contributing becomes
available. We recommend a minimum 3 -foot separation between foundation elements and
groundwater. Existing groundwater levels may affect proposed construction unless final
grade is raised.
GEOLOGIC HAZARDS
Our investigation addressed potential geologic hazards, including shallow
groundwater, expansive soils, and seismicity that should be considered during planning and
construction. None of these hazards considered will preclude proposed construction. The
following sections discuss each of these geologic hazards and associated development
concerns.
Shallow Groundwater
Shallow groundwater was encountered at depths of 5 to 10 feet in four borings.
Groundwater will likely be encountered during construction of below grade areas such as the
elevator pit and deeper utilities. Groundwater levels fluctuate seasonally and may rise during
the wet season from March to September. Dewatering should be anticipated and is discussed
in SITE DEVELOPMENT. We understand that fill may be imported to raise the grade up to 7
feet above current elevation in the area of the planned structure. If that is the case,
groundwater may be less of a concern unless excavations will exceed approximately 12 feet.
Other options to control groundwater could be lining or piping the nearby irrigation ditches.
Groundwater control recommendations are outside of the scope of this investigation but
should be considered prior to construction. Additional investigation would be required.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
6
Expansive Soils
Expansive soils are present at the site. The presence of expansive soils constitutes a
geologic hazard. There is a risk that ground heave will damage slabs -on-grade and
foundations. We believe that risk to be low at this si te and mitigation is not required for the
proposed construction. The risks associated with swelling soils can be mitigated, but not
eliminated, by careful design, construction, and maintenance procedures. We believe the
recommendations in this report will help control risk of foundations and/or slab damage; they
will not eliminate that risk.
Seismicity
This area, like most of central Colorado, is subject to a low degree of seismic risk. As
in most areas of recognized low seismicity, the record of the past earthquake activity in
Colorado is incomplete. According to the 2021 International Building Code and the
subsurface conditions encountered in our borings, this site probably classifies as a Site Class
D. Only minor damage to relatively new, properly designed and built buildings would be
expected. Wind loads, not seismic considerations, typically govern dynamic structural design
for the structures planned in this area.
SITE DEVELOPMENT
Site development will be primarily impacted by shallow groundwater and
undocumented fill. The fill presents risk of settlement and is not recommended for structural
support unless it is removed and recompacted. Groundwater and/or saturated conditions will
likely be encountered in below grade excavations that approach or exceed 4 feet below
existing grades. Groundwater and caving soils will likely affect utility and deep foundation
installation. Ground improvement could be employed to achieve greater bearing capacity
and to reduce settlement. There are many different options for ground improvement. We
believe the most feasible options include chemical grouting, vibropiers, and rigid inclusions.
These as well as other site development considerations are described in detail in the following
sections.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
7
Excavations
We believe the materials found in our borings can be excavated using conventional
heavy-duty excavation equipment. Excavations should be sloped or shored to meet local,
State, and Federal safety regulations. Based on our investigation and OSHA standards, we
believe the granular soils classify as Type C soils. Type C soils require a maximum slope
inclination of 1.5:1 in dry conditions. Excavation slopes specified by OSHA are dependent
upon types of soil and groundwater conditions encountered. The contractor’s “competent
person” should identify the soils and/or rock encountered in the excavation and refer to OSHA
standards to determine appropriate slopes. Stockpiles of soils, rock, equipment, or other
items should not be placed within a horizontal distance equal to one -half the excavation
depth, from the edge of excavation. Excavations deeper than 20 feet should be braced or a
professional engineer should design the slopes.
Dewatering
Groundwater was encountered in six borings at depths of approximately 5 to 10 feet.
The elevator pit is anticipated to be near, or below, current groundwater depths, at existing
grade. Our experience in this area suggests that gro undwater depths can vary with season,
precipitation, and depending on the time of construction, could be higher than measured in
our borings. If grade is raised according to the cut and fill plans provided, groundwater may
not be a concern. If not, excavation near groundwater depths should consider temporary
dewatering prior to and/or during construction. Buoyant forces may need to be considered in
the design if a structure is planned below groundwater.
The predominantly granular material at this site is expected to have a fairly rapid
hydraulic conductivity. Dewatering can likely be maintained using trench drains and pumps.
The sumps should be several feet below the bottom of excavations to pump water d own
through the soil rather than up through the bottom of the excavation. Pumping water up
through the base of the excavation will likely result in destabilization of the base of the
excavation. If destabilization of the soil becomes a problem, a system of well points should
be considered. Discharge volumes and the outfall will need to be considered. Additionally,
dewatering efforts need to be monitored to avoid conditions where exit velocities could
destabilize the soil surface. Also, adjacent areas s hould be sloped to avoid runoff into the
excavation.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
8
The contractor should anticipate extensive dewatering and possibly caving soils in
excavations below the water table. The design of a well point system will require further
exploratory drilling to deeper depth and permeability tests, both of which were not in the scope
of this study. Planning construction to avoid seasonal high groundwater, which is typically
March to September, should be considered to reduce the need for dewatering.
Fill Placement
Existing fill was encountered in four borings to depths of up to 6 feet. Deeper fill areas
may be encountered during site development. The fill is of unknown origin and age , and
presents risk of settlement to improvements constructed on it. It also has a relatively low
bearing capacity. We recommend the fill be removed, moisture treated and recompacted in
the building area or load bearing structures. Clean portions of the fill can be reworked and
reused as new, moisture conditioned, compacted fill. Unsuitable material, if present, may
need to be removed, handled and disposed properly.
The fill removal area should extend beyond the building footprint at least one footing
width. If the excavations to remove existing fill are deeper than about 10 feet in the planned
building area, additional measures should be considered to reduce the potential settlement
of backfill. We should be advised if any of the excavations are deeper than 10 feet below the
proposed floor. The excavation can be filled with on-site soils, moisture-conditioned and
compacted as described above. This procedure should remove the existing fill and provide
more uniform support for improvements.
We understand that imported fill is planned. Import material should be tested and
approved as acceptable fill by CTL Thompson. In general, import fill should meet or exceed
the engineering qualities of the onsite soils. Imported fill should have a maximum particle size
of 3 inches, less than 50 percent passing a No. 200 sieve, a liquid limit less than 30 and a
plasticity index of less than 15. CDOT Class 5 or 6 materials or clean recycled concrete may
also be considered. The existing onsite soils are suitable for re-use as fill material provided
debris or deleterious organic materials are removed. Areas to receive fill should be scarified,
moisture-conditioned and compacted to at least 95 percent of standard Proctor maximum dry
density (ASTM D698, AASHTO T99). If soft or loose soils are encountered, stabilization can
likely be achieved by crowding 1½ to 3-inch nominal size crushed rock into the subsoils until
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
9
the base of the excavation does not deform by more than about 1 -inch when compactive
effort is applied. Sand soils used as fill should be moistened to within 2 percent of optimum
moisture content. Clay soils should be moistened between optimum and 3 percent above
optimum moisture content. The fill should be moisture-conditioned, placed in thin, loose lifts
(8 inches or less) and compacted as described above. We should observe placement and
compaction of fill during construction. Fill placement and compaction should not be conducted
when the fill material is frozen.
Backfill behind retaining walls is discussed in the RETAINING WALL section of this
report. Our experience indicates that fill and backfill can settle even if properly compacted to
criteria specified above. Factors that influence the amount of settlement are depth of fill, soil
type, degree of compaction and time. The length of time for the compression to occur can be
a few weeks to several years. The degree of compression of the recommend fill , under its
own weight, will likely be about 1 percent of the fill depth. Any improvements placed over
backfill should be designed to accommodate movement. Increased compaction criteria can
be employed to reduce the potential compression risk.
The existing fill can also affect pavements and exterior flatwork. We believe the fill has
been in place long enough that it will most likely perform adequately as pavement subgrade
as long as it passes proof roll. However, the lowest risk alternative for exterior pavement and
flatwork would also be complete removal and recompaction. The cost could be significant. If
the owner can accept a risk of some movement and distress in these areas, then partial depth
removal is an alternative. We suggest removal of the existing fill to a depth of 1 to 2 feet
below existing grade, proof rolling the exposed subgrade, and additional removal or
stabilization of areas where soft, yielding or organic soils or debris is encountered. After this,
fill placement can proceed to construction grades.
Water and sewer lines are often constructed beneath slabs and pavements.
Compaction of utility trench backfill can have a significant effect on the life and serviceability
of floor slabs, exterior flatwork and pavements. We recommend utility trench backfill be placed
in thin loose lifts and moisture conditioned and compacted according to the specifica tions
presented previously. The placement and compaction of utility trench backfill should be
observed and tested by a representative of our firm during construction.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
10
Site grading in areas of landscaping where no future improvements are planned can
be placed at a dry density of at least 90 percent of standard Proctor maximum dry density
(ASTM D 698, AASHTO T 99). Example site grading specifications are presented in
Appendix B.
SUBSURFACE IMPROVEMENT
The bearing support characteristics at this site could be improved to increase bearing
capacity or reduce potential settlements. A variety of options could be considered and are
discussed below.
Chemical Grouting
Chemical grouting involves injecting a cement slurry to permeate granular soils to
increase strength and reduce permeability. It permeates the soils, binding them together
which can stop water movement in granular soil and/or rock while improving bearing capacity.
The grouting is typically injected in a grid pattern to depths that would be determined by the
contractor.
Compaction Grouting
Compaction grouting techniques can be employed to densify the fill and/or granular
soils in place and enhance performance of shallow foundations and floors. Compaction
grouting involves pumping a low-mobility, aggregate grout to displace and densify the
surrounding soils. This approach is best suited for soils that are soft to medium stiff or very
loose to medium dense, such as the majority of the upper soils at this site. Injection points
should be located within improvement areas and spaced at 8 feet on -center. The extent of
the grouting will depend on the grout volume and pressure. Based on our investigation, we
anticipate grouting to depths of about 15 to 20 feet, will be required.
To provide a guide specification, the grout should have a maximum slump of 1 -inch
and should be injected at a volume between 4 to 6 cubic feet per foot. Inject ion pressures
should not exceed 250 psi. We typically prefer a bottom-up grouting procedure. Adjustments
may be needed in the field as grouting progresses, depending on actual conditions
encountered.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
11
The top of the compaction grout bulbs will be at vario us elevations relative to
foundations and finished floor grades in the building. Generally, they are terminated about
1.5 to 3 feet below the footing, slab elevations. We recommend installation of a minimum 12-
inch-thick layer of ¾-inch crushed rock below the foundations and floor slabs. A geogrid
should be installed below the base of the gravel layer, along the tops of the compaction grout
bulbs, to help the floor span and bridge the improved ground. The below -slab gravel layer
can also serve as the vapor mitigation system in some cases.
Vibropiers and Grouted Aggregate Piers
Vibropiers, also known as aggregate piers or stone columns, may also be considered,
where a grid of large-diameter holes is drilled, or vibrated, and gravel aggregate is rammed
or vibrated into each hole, densifying surrounding soils and creating stiff columns of gravel to
reduce differential and total settlement by increasing the overall stiffness of the treated mass.
We believe these piers can be grouted to help transmit loads to deeper, denser materials
below the building foundation. The vibratory energy densifies the aggregate and any
surrounding soil. The dense aggregate interlocks to form a stiff pier that engages the
surrounding soil to provide reinforcement and increased shear resistance. If this technique is
selected, we recommend installation of a layer of ¾-inch crushed rock and geogrid below the
floor slab, along the tops of the stone columns, to help span the improved ground. Vibropiers
are believed to be difficult to install at this site because holes could cave in before aggregate
can be placed.
FOUNDATIONS
We understand that different foundation options are being examined. Considering the
anticipated loads and height of the proposed construction, deep foundations are judged to be
the safest foundation system for the structure. However, drilled piers , augercast piles and
franki piles will be challenging to install because of possible cobble, caving material and
shallow groundwater. Other deep foundation options such as large diameter helical piers and
driven H-pile can also be considered. The use of shallow footings or reinforced mat
foundations can be considered. if the available bearing capacity of the site soils are
insufficient, existing ground is improved by methods discussed in the previous section. Most
of the ground improvement options will generally be hampered by the water, caving, and
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
12
cobbles in a similar manner to some of the deep foundations. We recommend considering
simple re-compaction (over-excavation and replacement) of the near surface sandy fill which
should improve bearing capacities and reduce potential settlement of shallow foundations
provided higher compaction criteria is employed. Design criteria for footings, mats and deep
foundations developed from analysis of field and laboratory data and our experience are
presented below.
Spread Footings
1. Footings should be constructed on properly compacted fill or ground
improvement described in the SITE DEVELOPMENT section of this report.
Ground improvement methods previously discussed will increase net allowable
bearing capacity to a degree that would be determined by the method selected.
This will be determined by the specialty contractor selected for the desired
ground improvement method. All existing, uncontrolled fill should be removed
from under footings and within one footing width around footings and replaced
with properly compacted fill as discussed in the Fill Placement section. Where
soil is loosened during excavation, it should be removed and replaced with
compacted fill.
2. Footings placed on properly compacted fill can be designed for a net allowable
soil pressure of 3,000 psf. The soil pressure can be increased 33 percent for
transient loads such as wind or seismic loads. We recommend a minimum 3-
foot separation between foundation elements and groundwater.
3. We anticipate footings designed using the soil pressure recommended above
could experience 1-inch of movement. Differential movement of ½- inch should
be considered in the design.
4. Footings should have a minimum width of at least 18 inches. Foundations for
isolated columns should have minimum dimensions of 24 inches by 24 inches.
Larger sizes may be required depending on loads and the structural system
used.
5. The soils beneath footing pads can be assigned an ultimate coefficient of
friction of 0.3 to resist lateral loads. The ability of grade beam or footing backfill
to resist lateral loads can be calculated using a passive equivalent fluid
pressure of 250 pcf for the upper clayey, sand and 300 pcf for granular
materials. This assumes the backfill is densely compacted and will not be
removed. Deflection of grade beams is necessary to mobilize passive earth
pressure; we recommend a factor of safety of 2 for this condition. Backfill
should be placed and compacted to the criteria in the Fill Placement section of
this report.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
13
6. Exterior footings should be protected from frost action. We believe 30 inche s
of frost cover is appropriate for this site.
7. Foundation walls and grade beams should be well reinforced , both top and
bottom. We recommend reinforcement sufficient to simply span 10 feet. The
reinforcement should be designed by a structural engineer.
8. We should observe completed footing excavations to confirm whether the
subsurface conditions are similar to those found in our borings.
Reinforced Concrete Mat
1. Reinforced concrete mat foundations should be constructed on properly
compacted fill or ground improvement as described in the SITE
DEVELOPMENT section of this report. The reinforced concrete mat foundation
should be designed for a net allowable soil pressure of 3,000 psf if constructed
on properly compacted fill. The soil pressure can be increased 33 percent for
transient loads such as wind or seismic loads. If other ground improvement
methods are used, bearing capacity will be determined by the installing
contractor.
2. Reinforced slabs are typically designed using a modulus of subgrade reaction.
We recommend use of a modulus of 100 pounds per square inch per inch of
deflection (pci).
3. The soils beneath mat foundations can be assigned an ultimate coefficient of
friction of 0.5 to resist lateral loads. The ability of foundation backfill to resist
lateral loads can be calculated using a passive equivalent fluid pressure of 300
pcf. This assumes the backfill is densely compacted and will not be removed.
Backfill should be placed and compacted to the criteria in the Fill Placement
section of the report. A moist unit weight of 120 pcf can be assumed for natural
soils and compacted fill. These values are considered ultimate values and
appropriate factors of safety should be used. Typically, a factor of safety of 1.5
is used for sliding and 1.6 for lateral earth pressure.
4. The edges of the mats should be thickened or turned down for structural
strength.
5. Materials beneath the mat foundation should be protected from frost action.
We believe 30 inches of frost cover is appropriate for this site.
6. We should be retained to observe the completed excavations for mats to
confirm that the subsurface conditions are similar to those found in our
borings.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
14
Drilled Piers Bottomed in Bedrock
1. Piers should be designed for a maximum allowable end pressure of 50,000 psf
and an allowable skin friction of 5,000 psf for the portion of pier in bedrock.
Skin friction should be neglected for the upper 3 feet of pier below grade
beams. Pier end pressure can be increased 30 percent for short duration live
loads such as wind loads.
2. Piers should penetrate at least 5 feet into the comparatively fresh sandstone
bedrock. Based on our boring data, piers could have a total length of 20 to 25
feet. Longer piers may be necessary to achieve proper bedrock penetration.
3. Uplift due to swelling soils is expected to be negligible.
4. There should be a 6-inch (or thicker) continuous void beneath all grade beams
and foundation walls, between piers, to concentrate the dead load of the
structure onto the piers.
5. Foundation walls and grade beams should be well reinforced. A qualified
structural engineer should design the reinforcement. Lateral earth pressures
and the effects of large openings within below grade walls should be
considered.
6. Pier borings should be drilled to a plumb tolerance of 1.5 percent relative to the
pier length.
7. Groundwater was encountered during this investigation and will affect pier
installation. Casing may be required because of groundwater, and also
because of granular caving soils. Piers should be carefully cleaned prior to
placement of concrete. We recommend a “drill-and-pour” procedure for pier
installation. Concrete should be on site and placed in the pier holes
immediately after the holes are drilled, cleaned, and observed by our
representative to avoid collecting water and possible contamination of open
pier holes. We anticipate tremie equipment and/or pumping may be necessary
for proper cleaning, dewatering, and concrete placement. Concrete should not
be placed by free fall if there is more than about 3 inches of wate r at the bottom
of the hole.
8. Concrete placed by the free fall method should have a slump between 5 inches
and 7 inches. Concrete placed by pump, tremie or when temporarily cased
should have a slump between 6 inches and 8 inches.
9. Formation of “mushrooms” or enlargements at the top of piers should be
avoided during pier drilling and subsequent construction operations.
10. We should observe installation of drilled piers to confirm the subsurface
conditions are those we anticipated from our borings.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
15
Franki Piles
Franki piles are constructed by driving a casing to the desired depth, then driving or
pressurizing a dry concrete mix into the area directly below the casing. Additional concrete
and reinforcement are then placed as the casing is removed. This technique creates
significant additional end bearing capacity as the grouting densifies a larger area directly
under the tip. While this option could be used at this site, it will require specialty equipment
and contractors to install and will require contractor involvement in the design as the method
is proprietary. Additionally, because the support resistance of the pile tip depends greatly on
the site soil type, density, ground water and more, the complex interaction of the parts with
the freshly cast concrete can vary, requiring a more comprehensive load testing program to
verify capacity.
Augercast Piles
Augercast piles were considered for this site as a means to provide foundation
support. Our experience with the gravelly sand layer above the bedrock has shown it often
contains cobbles which will significantly hamper the construction of augercast foundations. It
is our opinion that other foundation systems will have greater success of installation at this
site.
Helical Piers
1. Contractor shall use the number and size of helical blades required to achieve
the required depth and capacity. However, the ratio of design bearing capacity
specified by the structural engineer and the total area of helical blades used by
the contractor shall not exceed 15,000 pounds per square foot (psf).
2. The bottom helix should be installed to bedrock. Piers will likely have a total
length of at least 16 to 20 feet. Helical piles should be placed as close to vertical
as possible.
3. The diameter and blade strength of the helical piles should be appropriate to
accommodate the penetration counts of approximately 30/12 as shown on the
boring logs.
4. At a minimum, helical piles should be spaced apart a distance equal to three
times the average helix diameter to avoid group efficiency effects.
5. Installation of helical piles should be observed by a representative of our firm
to confirm the depth and installation torque of the helical piles are adequate.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
16
Driven H-Piles
1. Piles should be designed for an ultimate end bearing capacity (q p) of 15,000
psf and an ultimate skin friction capacity (qs) of 1,500 psf required for the LRFD
method for the portion in the overburden soils. These values correspond to a
maximum allowable end pressure of 5,000 psf and an allowable skin friction of
500 psf for the portion of the pier in the overburden soils using the ASD method.
Piles should be designed for an ultimate end bearing capacity (q p) of 150,000
psf and an ultimate skin friction capacity (qs) of 15,000 psf required for the
LRFD method for the portion in bedrock. These values correspond to a
maximum allowable end pressure of 50,000 psf and an allowable skin friction
of 5,000 psf for the portion of the pier in bedrock using the ASD method. Skin
friction of the portion of a pier contained within a casing should be neglected.
The ultimate capacities using LRFD method assumes a weighted load factor
of 1.35 and a resistance factor (Φ) of 0.45 for end bearing and side shear
values.
2. The piles will need to be designed to resist lateral loading. The Laterally
Loaded Piers section gives soil data input for LPILE software.
3. We estimate the pile tip elevations will be near the bedrock surface. Based on
our borings, bedrock was encountered at approximately 16 to 1 9 feet below
current grade. We should be notified if practical refusal occurs shallower than
the estimated depth. We define “practical” refusal at this site as an average
penetration of 0.25 inch per blow for the final 1-foot of pile penetration with a
hammer delivering at least 20,000-foot pounds of energy per blow. The
manufacturer's rated energy output of the hammer should be between 1,000
and 2,000 foot-pounds per square inch of steel section. The hammer for pile
driving should be operated at manufacturers recommended stroke and speed
when "practical refusal" is measured.
4. The maximum allowable pile capacity should not exceed the rated working
stress for the chosen steel H-pile section.
5. The efficiency of the hammer and impact should be monitored during driving.
The contractor should select a driving hammer and cushion combination which
is capable of installing the selected piles without over -stressing the pile. The
contractor should submit the pile driving plan and the pile hammer/cushion
combination to the engineer for evaluation of the driving stress in advance of
the pile installation.
6. Piles should be driven plumb to within plan tolerance or battered as detailed by
the structural engineer.
7. Groups of piles required to support concentrated loads will require an
appropriate reduction of the estimated bearing capacity based on the effective
envelope area of the pile group. This reduction can be avoided by spacing piles
a distance of at least 3 widths center-to-center. The Closely Spaced Pile
Reduction Factors section contains detailed discussion of this issue.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
17
8. We are available to assist with or advise on settlement calculations for service
limit states in LRFD once a preliminary layout and anticipated loading of the
foundation are defined.
9. CTL Thompson should observe pile driving and keep the records of driving
penetration resistance, pile length, and other factors that affect the
performance of a pile foundation. This will permit us to confirm the piles are
driving as anticipated from our boring information.
Laterally Loaded Piers
Several methods are available to analyze laterally loaded piers and piles. With a pier
length to diameter ratio of 7 or greater, we believe the method of analysis developed by
Matlock and Reese is most appropriate. The method is an iterative procedure using applied
loading and soil profile to develop deflection and moment versus depth curves. The computer
programs LPILE and COM624 were developed to perform this procedure. Suggested criteria
for LPILE analysis are presented in the following table.
TABLE 1
SOIL INPUT DATA FOR LPILE or COM624
Clay Soils or
Clay Fill Granular Soils Bedrock
Soil Type Stiff Clay w/o
Free Water
Sand and Gravel
(below water/above water) Weak Rock
Effective Unit
Weight (pci) 0.06 0.07 0.07
Cohesive Strength,
c (psi) 13 - 100
Friction Angle
Degrees - 35 -
Soil Strain, ε50 (in/in) 0.007 - 0.003
RQD (%) - - 80
p-y Modulus ks (pci) 500 60/90 2,000
The ε50 represents the strain corresponding to 50 percent of the maximum principle stress difference.
Closely Spaced Pier Reduction Factors
For axial loading, a minimum spacing of three diameters is recommended. At one
diameter (piers touching) the skin friction reduction factor for both piers would be 0.5. End
bearing values would not be reduced provided the bases of the piers are at similar elevations.
Linear interpolation can be used between one and three diameters.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
18
Piers in-line with the direction of the lateral load should have a minimum spacing of
six diameters (center-to-center) based upon the larger pier. If a closer spacing is required,
the modulus of subgrade reaction for initial and trailing piers should be reduced. At a spacing
of three diameters, the effective modulus of subgrade reaction of the first pier can be
estimated by multiplying the given modulus by 0.6. For trailing piers in a line at three
diameters spacing, the factor is 0.4. Linear interpolation can be used for spacing between
three and six diameters.
Reductions to the modulus of subgrade reaction can be accomplished in LPILE by
inputting the appropriate modification factors for the p -y curves. Reducing the modulus of
subgrade reaction in trailing piers will result in greater comp uted deflections on these piers.
In practice, the grade beam can force deflections of piers to be equal. Load -deflection graphs
can be generated for each pier in the group using the appropriate p -multiplier values. The
sum of the piers’ lateral load resistance at selected deflections can be used to develop a total
lateral load versus deflection relationship for the system of piers.
For lateral loads perpendicular to the line of piers a minimum spacing of three
diameters can be used with no capacity reduction. At one diameter (piers touching) the piers
can be analyzed as a single unit. Linear interpolation can be used for intermediate conditions.
RETAINING WALLS
Site retaining walls can be constructed on footing foundations placed on properly
compacted fill. For mechanically stabilized earth (MSE) wall design, we recommend using a
friction angle of 25 degrees and no cohesion for the retained soil. We recommend an imported
granular soil be used as backfill within the reinforced zone behind the walls. Table 2 provides
a typical gradation specification for wall backfill. CDOT Class 6 aggregate base course is also
acceptable. The top 2 feet of exterior backfill behind walls should be clayey soils to reduce
water infiltration. Backfill behind retaining walls should be placed in thin, loose lifts; moisture
conditioned and compacted. Settlement on the order of 1 to 2 percent of the backfill depth
may occur; improvements constructed over backfill should be designed to perform
considering anticipated settlements.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
19
Table 2: Typical Gradation Specification for Wall Backfill Soil
Sieve Size Percent Passing
2-inch 100
No. 4 30-100
No. 50 10-60
No. 200 5-10
Some walls may be subjected to lateral loading. Lateral loads are dependent on the
height and type of wall, backfill configuration, and backfill type. For purposes of design, we
have assumed backfill will consist of on-site sands and gravels. For walls that are free to
rotate, we recommend walls be designed to resist an “active” earth pressure using an
equivalent fluid density of 30 pcf without hydrostatic pressure. These values are for dry
conditions. We recommend appropriate hydrostatic pre ssure be included in the design.
Drains should be installed to help control hydrostatic pressures. The drain should lead to a
positive gravity outlet, or the wall could be provided with weep holes. A “passive” resistance
calculated using 300 pcf equivalent fluid density can be used for walls subject to lateral loads.
The recommended “passive” pressure assumes fill placed in front of walls will be densely
compacted and will not be removed. The friction coefficient for concrete sliding on the site
soil can be taken to be 0.45.
SETTLEMENT
We understand that anticipated column loads for the 5-story structure will be 400 kips.
Based on these load conditions, the subsurface conditions encountered and our experience,
we expect the proposed structure could experience up to 1-inch of vertical movement.
Differential movement of ½-inch over a 50-foot horizontal distance should be considered in
the design. The majority of movement will occur during construction. Construction of
structures on the existing fill will likely experience additional settlement.
LATERAL EARTH PRESSURES
Below grade walls should be designed to withstand lateral earth pressures. Table 3
provides anticipated equivalent fluid density values for native soils or backfill soils composed
of onsite materials. These are considered ultimate values and appropriate factors of safety
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
20
should be applied in design. For native material and dense ly compacted backfill made from
on-site materials, a friction coefficient of 0.4 and a moist unit weight of 1 10 pounds per cubic
foot (pcf) can be assumed. For medium dense compacted granular fill, a friction coefficient of
0.5 and a moist unit weight of 120 pounds per cubic foot (pcf) can be assumed.
Table 3: Lateral Earth Pressure Design Parameters
Loading Condition
Equivalent Fluid
Density (𝜸)
Clayey Sand
Equivalent
Fluid Density
(𝜸)
Sand/Gravel
Active (𝜸A) psf 50 30
At-Rest (𝜸o) psf 65 45
Passive (𝜸p) psf 200 575
The appropriate load distribution to apply for design depends not only on the soil type,
but also on the wall type and restraint. For walls that are restrained from rotation, the walls
should be designed to resist the “at rest” earth pressure. Walls which are free to rotate to
develop the shear strength of the retained soils should be designed to resist the “active” earth
pressure. Resistance to lateral loads can be provided by friction between concrete and soil
and/or by “passive” earth pressure. Passive earth pressure should be ignored for the top 1-
foot of soil against the structure since it can be removed easily with time. The proper
application of these loading conditions is the responsibility of the wall designer. Wall backfill
should be placed according to the Backfill Placement section of this report.
BELOW GRADE AREAS
No below grade areas are planned for the buildings with the exception of an elevator
pit. For this condition, perimeter drains are not usually necessary. Lateral earth pressure on
the pit walls can be calculated using an equivalent fluid density of 45 pcf. This value is for
horizontal backfill conditions and does not include pressure due to surcharge or hydrostatic
pressure. We should be contacted to provide foundation drain recommendations if plans
change to include below grade areas.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
21
FLOOR SYSTEMS
In our opinion, it is reasonable to use slab -on-grade floors for the proposed
construction if placed on improved ground. Any fill placed for the floor subgrade should be
built with densely compacted, engineered fill or an elected ground improvement method as
discussed in the SITE DEVELOPMENT section of this report. The existing fill is not an
acceptable subgrade for a slab-on-grade floor and should be completely removed from the
subgrade under a floor.
It is impossible to construct slab-on-grade floors with no risk of movement. We believe
movements due to swell are not likely and settlement on improved ground should be less
than 1-inch. If movement cannot be tolerated, structural floors should be used. Structural
floors will be used with pier foundations and can be considered for specific areas that are
particularly sensitive to movement or where equipment on the floor is sensitive to movement.
Where structurally supported floors are selected, we recommend a minimum void
between the ground surface and the underside of the floor system of 6 inches. The
minimum void should be constructed below beams and utilities that penetrate the floor .
The floor may be cast over void form. Void form should be chosen to break down quickly
after the slab is placed. We recommend against the use of wax or plastic -coated void
boxes.
Slabs may be subject to heavy point loads. The structural engineer should design
floor slab reinforcement. For design of slabs-on-grade, we recommend a modulus of
subgrade reaction of 100 pci for anticipated soils.
If the owner elects to use slab-on-grade construction and accepts the risk of movement
and associated damage, we recommend the following precautions for slab -on-grade
construction at this site. These precaution s can help reduce, but not eliminate, damage or
distress due to slab movement.
1. Slabs should be separated from exterior walls and interior bearing members
with a slip joint that allows free vertical movement of the slabs. This can reduce
cracking if some movement of the slab occurs.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
22
2. Slabs should be placed directly on exposed soils or properly moisture
conditioned, compacted fill. The 2021 International Building Code (IBC)
requires a vapor retarder be placed between the base course or subgrade soils
and the concrete slab-on-grade floor. The merits of installation of a vapor
retarder below floor slabs depend on the sensitivity of floor cove rings and
building use to moisture. A properly installed vapor retarder (minimum 6-mil;
10-mil recommended) is more beneficial below concrete slab-on-grade floors
where floor coverings, painted floor surfaces or products stored on the floor will
be sensitive to moisture. The vapor retarder is most effective when concrete
is placed directly on top of it, rather than placing a sand or gravel leveling
course between the vapor retarder and the floor slab. The placement of
concrete on the vapor retarder may increase the risk of shrinkage cracking and
curling. Use of concrete with reduced shrinkage characteristics including
minimized water content, maximized coarse aggregate content, and
reasonably low slump will reduce the risk of shrinkage cracking and curling.
Considerations and recommendations for the installation of vapor retarders
below concrete slabs are outlined in Section 3.2.3 of the 2006 report of
American Concrete Institute (ACI) Committee 302, “Guide for Concrete Floor
and Slab Construction (ACI 302.R1-04)”.
3. Underslab plumbing should be eliminated where feasible. Where such
plumbing is unavoidable it should be thoroughly pressure tested for leaks prior
to slab construction and be provided with flexible couplings. Pressurized water
supply lines should be brought above the floors as quickly as possible.
4. Plumbing and utilities that pass through the slabs should be isolated from the
slabs and constructed with flexible couplings. Where water and gas lines are
connected to furnaces or heaters, the lines should be constructed with
sufficient flexibility to allow for movement.
5. HVAC equipment supported on the slab should be provided with a collapsible
connection between the furnace and the ductwork, with allowance for at least
1-inch of vertical movement.
6. The American Concrete Institute (ACI) recommends frequent control joints be
provided in slabs to reduce problems associated with shrinkage cracking and
curling. To reduce curling, the concrete mix should have a high aggregate
content and a low slump. If desired, a shrinkage compensating admixture
could be added to the concrete to reduce the risk of shrinkage cracking. We
can perform a mix design or assist the design team in selecting a pre -existing
mix.
Exterior Flatwork
We recommend exterior flatwork and sidewalks be isolated from foundations to reduce
the risk of transferring heave, settlement, or freeze-thaw movement to the structure. One
alternative would be to construct the inner edges of the flatwork on haunches or steel angles
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
23
bolted to the foundation walls and detailing the connections such that movement will cause
less distress to the building, rather than tying the slabs directly into the building foundation.
Construction on haunches or steel angles and reinforcing the sidewalks and other exterior
flatwork will reduce the potential for differential settlement and better allow them to span
across wall backfill. Frequent control joints should be provided to reduce problems associated
with shrinkage. Panels that are approximately square perform better than rectangular areas.
PAVEMENTS
The project will include various paved surfaces. This report addresses paved parking
and access drives in anticipation of vehicular traffic. Semi-frequent, heavy truck traffic is
expected. The performance of pavements is dependent upon the characteristics of the
subgrade soil, traffic loading and frequency, climatic conditions, drainage and pavement
materials. We drilled three exploratory borings and conducted laboratory tests to characterize
the subgrade soils, which consisted of clayey, gravelly fill and clayey sand. The subgrade
soils classified as A-6 soils in accordance with AASHTO procedures. The subgrade soil will
likely provide fair to poor support for new pavement. The existing fill is considered acceptable
as long as it passes proof rolling. If imported fill is needed, we have assumed it will be soils
with similar or better characteristics.
Flexible hot mix asphalt (HMA) over aggregate base course (ABC) is appropriate for
pavement areas. We understand that pavers are desired in some areas currently designated
for pedestrian and light vehicle traffic. Where pavers will be subject to heavy vehicle traffic,
we recommend using rigid pavement below the pavers , as conventional pavers tend to
transmit heavy wheel loads to the subgrade and cause bearing failure . Rigid Portland cement
concrete (PCC) pavement should be used for trash enclosure areas and where the pavement
will be subjected to frequent turning of heavy vehicles. Our designs are based on the
AASHTO design method and our experience. Using the criteria discu ssed above we
recommend the minimum pavement sections provided in Table 4.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
24
TABLE 4
RECOMMENDED PAVEMENT SECTIONS
Classification
Hot Mix Asphalt
(HMA) + Aggregate
Base Course (ABC)
Portland Cement
Concrete (PCC)
Commercial Grade
Paver + Aggregate
Base Course (ABC)
Pedestrian/Light
Vehicle Area
5" HMA +
6" ABC 5" PCC Paver +
5" PCC
Parking Area 5" HMA +
6" ABC 5" PCC -
Access Drives /
Heavy Traffic
Areas
6" HMA +
6" ABC 6" PCC -
Trash
Enclosures - 6" PCC -
Pavement Selection
Composite HMA/ABC pavement over a stable subgrade is expected to perform well
at this site based on the recommendations provided. HMA provides a stiff, stable pavement
to withstand heavy loading and will provide a good fatigue resistant pavement. However ,
HMA does not perform well when subjected to point loads in areas where heavy trucks turn
and maneuver at slow speeds. PCC pavement is expected to perform well in this area; PCC
pavement has better performance in freeze-thaw conditions and should require less long-
term maintenance than HMA pavement. The PCC pavement for trash enclosures should
extend out to areas where trash trucks park to lift and empty dumpsters.
Subgrade and Pavement Materials and Construction
The design of a pavement system is as much a function of the quality of the paving
materials and construction as the support characteristics of the subgrade. The construction
materials are assumed to possess sufficient quality as reflected by the strength factors used
in our design calculations. Moisture treatment criteria and additional criteria for materials and
construction requirements are presented in Appendix C of this report.
Pavement Maintenance
Routine maintenance, such as sealing and repair of cracks, is necessary to achieve
the long-term life of a pavement system. We recommend a preventive maintenance program
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
25
be developed and followed for all pavement systems to assure the design life can be realized.
Choosing to defer maintenance usually results in accelerated deterioration leading to higher
future maintenance costs, and/or repair. A recommended maintenance program is outlined
in Appendix D.
Excavation of completed pavement for utility construction or repair can destroy the
integrity of the pavement and result in a severe decrease in serviceability. To restore the
pavement top original serviceability, careful backfill compaction before repaving is necessary.
WATER-SOLUBLE SULFATES
Concrete that comes into contact with soils can be subject to sulfate attack. We
measured water-soluble sulfate concentrations in two samples from this site. Concentrations
were from below measurable limits to 0.06 percent. Sulfate concentrations less than 0.1
percent indicate Class 0 exposure to sulfate attack for concrete that comes into contact with
the subsoils, according to the American Concrete Institute (ACI). For this level of sulfate
concentration, ACI indicates there are no special requirements for sulfate resistance.
Superficial damage may occur to the exposed surfaces of highly permeable concrete,
even though sulfate levels are relatively low. To control this risk and to resist freeze -thaw
deterioration, the water-to-cementitious materials ratio should not exceed 0.50 for concrete
in contact with soils that are likely to stay moist due to surface drainage or high -water tables.
Concrete should have a total air content of 6 percent ± 1.5 percent. We advocate all
foundation walls and grade beams in contact with the soil (including the i nside and outside
faces of garage and crawl space grade beams) be damp-proofed.
SURFACE DRAINAGE
Performance of foundations, flatwork and pavements are influenced by changes in
subgrade moisture conditions. Carefully planned and maintained surface grading can reduce
the risk of wetting of the foundation soils and pavement subgrade. We recommend a
minimum slope of 5 percent in the first ten feet outside foundations in landscaped areas.
Backfill around foundations should be moisture treated and compacted as described in Fill
Placement. Roof drains should be directed away from buildings. Downspout extensions and
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
26
splash blocks should be provided at discharge points, or roof drains should be connected to
solid pipe discharge systems. We do not recommend directing roof drains under buildings.
CONSTRUCTION OBSERVATIONS
We recommend that CTL Thompson, Inc. provide construction observation services
to allow us the opportunity to verify whether soil conditions are consistent with those found
during this investigation. Other observations are recommended to review general
conformance with design plans. If others perform these observations, they must accept
responsibility to judge whether the recommendations in this report remain appropriate.
GEOTECHNICAL RISK
The concept of risk is an important aspect with any geotechnical evaluation primarily
because the methods used to develop geotechnical recommendations do not comprise an
exact science. We never have complete knowledge of subsurface conditions. Our analysis
must be tempered with engineering judgment and experience. Therefore, the
recommendations presented in any geotechnical evaluation should not be considered risk -
free. Our recommendations represent our judgment of those measures that are necessary to
increase the chances that the structures will perform satisfactorily. It is critical that all
recommendations in this report are followed during construction. Owners must assume
responsibility for maintaining the structures and use appropriate practices regarding drainage
and landscaping. Improvements performed by owners after construction, such as
construction of additions, retaining walls, landscaping , and exterior flatwork, should be
completed in accordance with recommendations in this report.
LIMITATIONS
This report has been prepared for the exclusive use of Powerhouse 2 Development
Company, LLC for the purpose of providing geotechnical design and construction criteria for
the proposed project. The information, conclusions, and recommendations presented herein
are based upon consideration of many factors including, but not limited to, the type of
construction proposed, the geologic setting, and the subsurface conditions encountered. The
conclusions and recommendations contained in the report are not valid for use by others.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
27
Standards of practice evolve in the area of geotechnical engineering. The recommendations
provided are appropriate for about three years. If the proposed construction is not constructed
within about three years, we should be contacted to determine if we should update this report.
Seven borings were drilled during this investigation to obtain a reasonably accurate
picture of the subsurface conditions. Variations in the subsurface conditions not indicated by
our borings are possible. A representative of our firm should observe foundatio n excavations
to confirm the exposed materials are as anticipated from our borings. We should also test
compaction of fill if over-excavation is used.
We believe this investigation was conducted with that level of skill and care ordinarily
used by geotechnical engineers practicing under similar conditions. No warranty, express or
implied, is made. If we can be of further service in discussing the contents of this report or in
the analysis of the influence of subsurface conditions on design of the structures, please call.
CTLTHOMPSON, INC.
Trace Krausse, EI R.B. “Chip” Leadbetter, III, PE
Project Geotechnical Engineer Senior Geotechnical Engineer
TH-1
TH-7
TH-6TH-5TH-4
TH-3 TH-2
E VINE DRHWY 287HWY 287REDWOOD STCONIFER ST
E. VINE DR.
SITE
LEGEND:
INDICATES APPROXIMATE
LOCATION OF EXPLORATORY
BORING
TH-1
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTL I T PROJECT NO. FC10223-125
FIGURE 1
Locations of
Exploratory
Borings
VICINITY MAP
(FORT COLLINS, CO)
NOT TO SCALE
120'60'
APPROXIMATE
SCALE: 1" = 120'
0'
0
5
10
15
20
25
30
35
40
0
5
10
15
20
25
30
35
40
24/12
50/11
47/12
TH-1
7/12
21/12
WC=16.9LL=30 PI=12-200=49
WC=10.1-200=23SS=0.060
TH-2
8/12
50/2
50/2
WC=14.4-200=36
TH-3
6/12
32/12
14/12
50/3
50/3
50/3
WC=8.0-200=5
WC=9.3-200=6
TH-4
9/12
WC=21.2LL=34 PI=13-200=65
TH-5
39/12
50/2
50/1
TH-6
10/12
9/12
24/12
WC=22.2DD=98SW=0.5SS=<0.01
WC=15.6-200=65
TH-7
DEPTH - FEETDRIVE SAMPLE. THE SYMBOL 24/12 INDICATES 24 BLOWS OF A 140-POUND HAMMER FALLING
30 INCHES WERE REQUIRED TO DRIVE A 2.5-INCH O.D. SAMPLER 12 INCHES.
ASPHALTIC CONCRETE (AC)
1.
NOTES:
THESE LOGS ARE SUBJECT TO THE EXPLANATIONS, LIMITATIONS AND CONCLUSIONS IN THIS
REPORT.
WATER LEVEL MEASURED SEVERAL DAYS AFTER DRILLING.
FILL, SAND, GRAVELLY, CLAYEY, MOIST, MEDIUM DENSE, DARK BROWN, TAN
3.
LEGEND:
SAND, CLAYEY, MOIST, LOOSE TO MEDIUM DENSE, BROWN (SC)
SAND AND GRAVEL, CLEAN TO CLAYEY, MOIST TO WET, MEDIUM DENSE TO VERY DENSE,
BROWN, DARK GRAY, TAN (SP, SP-SC, GC)
SANDSTONE, CLAYEY, MOIST, VERY HARD, GRAY
DEPTH - FEETWATER LEVEL MEASURED AT TIME OF DRILLING.
Summary Logs of
Exploratory Borings
THE BORINGS WERE DRILLED ON JANUARY 12, 2022, USING 4-INCH DIAMETER
CONTINUOUS-FLIGHT AUGERS AND A TRUCK-MOUNTED DRILL RIG.
FIGURE 2
WC
DD
SW
-200
LL
PI
SS
-
-
-
-
-
-
-
INDICATES MOISTURE CONTENT (%).
INDICATES DRY DENSITY (PCF).
INDICATES SWELL WHEN WETTED UNDER OVERBURDEN PRESSURE (%).
INDICATES PASSING NO. 200 SIEVE (%).
INDICATES LIQUID LIMIT.
INDICATES PLASTICITY INDEX.
INDICATES SOLUBLE SULFATE CONTENT (%).
2.
POWERHOUSE 2 DEVELOMPMENT COMPANY, LLC
POWERHOUSE 2
CTL | T PROJECT NO. FC10223-125
APPENDIX A
RESULTS OF LABORATORY TESTING
Sample of FILL, CLAY, SANDY (CL) DRY UNIT WEIGHT=98 PCF
From TH - 7 AT 2 FEET MOISTURE CONTENT=22.2 %
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTL | T PROJECT NO. FC10223-125
APPLIED PRESSURE -KSFCOMPRESSION % EXPANSIONSwell Consolidation
Test Results FIGURE A-1
-8
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
0.1 1.0 10 100
Sample of SAND, CLAYEY (SC)GRAVEL 0 %SAND 64 %
From TH - 3 AT 4 FEET SILT & CLAY 36 %LIQUID LIMIT %
PLASTICITY INDEX %
Sample of SAND, GRAVELLY, SLIGHTLY CLAYEY (SP-SC)GRAVEL 36 %SAND 59 %
From TH - 4 AT 14 FEET SILT & CLAY 5 %LIQUID LIMIT %
PLASTICITY INDEX %
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTL | T PROJECT NO. FC10223-125 FIGURE A-2
Gradation
Test Results
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR.7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSING0
10
20
30
50
60
70
80
90
100 PERCENT RETAINED40
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR.7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSINGPERCENT RETAINED0
10
20
30
40
50
60
70
80
90
100
Sample of SAND, SLIGHTLY CLAYEY (SP-SC)GRAVEL 11 %SAND 83 %
From TH - 4 AT 19 FEET SILT & CLAY 6 %LIQUID LIMIT %
PLASTICITY INDEX %
Sample of FILL, CLAY, SANDY (CL)GRAVEL 0 %SAND 35 %
From TH - 7 AT 4 FEET SILT & CLAY 65 %LIQUID LIMIT %
PLASTICITY INDEX %
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTL | T PROJECT NO. FC10223-125 FIGURE A-3
Gradation
Test Results
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR.7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSING0
10
20
30
50
60
70
80
90
100 PERCENT RETAINED40
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR.7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSINGPERCENT RETAINED0
10
20
30
40
50
60
70
80
90
100
PASSING WATER-
MOISTURE DRY LIQUID PLASTICITY APPLIED NO. 200 SOLUBLE
DEPTH CONTENT DENSITY LIMIT INDEX SWELL*PRESSURE SIEVE SULFATES
BORING (FEET)(%)(PCF)(%)(PSF)(%)(%)DESCRIPTION
TH-2 2 16.9 30 12 49 SAND, CLAYEY (SC)
TH-2 4 10.1 23 0.06 SAND, CLAYEY (SC)
TH-3 4 14.4 36 SAND, CLAYEY (SC)
TH-4 14 8.0 5 SAND, SLIGHTLY CLAYEY (SP-SC)
TH-4 19 9.3 6 SAND, SLIGHTLY CLAYEY (SP-SC)
TH-5 2 21.2 34 13 65 FILL, CLAY, SANDY (CL)
TH-7 2 22.2 98 0.5 200 <0.01 FILL, CLAY, SANDY (CL)
TH-7 4 15.6 65 FILL, CLAY, SANDY (CL)
SWELL TEST RESULTS*
TABLE A-I
SUMMARY OF LABORATORY TESTING
ATTERBERG LIMITS
Page 1 of 1
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTL|T PROJECT NO. FC10223-125
APPENDIX B
SAMPLE SITE GRADING SPECIFICATIONS
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
B-1
SAMPLE SITE GRADING SPECIFICATIONS
1. DESCRIPTION
This item shall consist of the excavation, transportation, placement and
compaction of materials from locations indicated on the plans, or staked by the
Engineer, as necessary to achieve building site elevations.
2. GENERAL
The Geotechnical Engineer shall be the Owner's representative. The
Geotechnical Engineer shall approve fill materials, method of placement, moisture
contents and percent compaction, and shall give written approval of the completed
fill.
3. CLEARING JOB SITE
The Contractor shall remove all trees, br ush and rubbish before excavation or fill
placement is begun. The Contractor shall dispose of the cleared material to
provide the Owner with a clean, neat appearing job site. Cleared material shall not
be placed in areas to receive fill or where the mate rial will support structures of any
kind.
4. SCARIFYING AREA TO BE FILLED
All topsoil and vegetable matter shall be removed from the ground surface upon
which fill is to be placed. The surface shall then be plowed or scarified to a depth
of 8 inches until the surface is free from ruts, hummocks or other uneven features,
which would prevent uniform compaction by the equipment to be used.
5. COMPACTING AREA TO BE FILLED
After the foundation for the fill has been cleared and scarified, it shall be disked or
bladed until it is free from large clods, brought to the proper moisture content and
compacted to not less than 95 percent of maximum dry density as determined in
accordance with ASTM D 698 or AASHTO T 99.
6. FILL MATERIALS
On-site materials classifying as CL, SC, SM, SW, SP, GP, GC, and GM are
acceptable. Fill soils shall be free from organic matter, debris, or other deleterious
substances, and shall not contain rocks or lumps having a diameter greater than
three (3) inches. Fill materials shall be obtained from the existing fill and other
approved sources.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
B-2
7. MOISTURE CONTENT
Fill materials shall be moisture treated. Clay soils placed below the building
envelope should be moisture-treated to between optimum and 3 percent above
optimum moisture content as determined from Standard Proctor compaction tests.
Clay soil placed exterior to the building should be moisture treated between
optimum and 3 percent above optimum moisture content. Sand soils can be
moistened to within 2 percent of optimum moisture content. Sufficient laboratory
compaction tests shall be performed to determ ine the optimum moisture content
for the various soils encountered in borrow areas.
The Contractor may be required to add moisture to the excavation materials in the
borrow area if, in the opinion of the Geotechnical Engineer, it is not possible to
obtain uniform moisture content by adding water on the fill surface. The Contractor
may be required to rake or disk the fill soils to provide uniform moisture content
through the soils.
The application of water to embankment materials shall be made with any ty pe of
watering equipment approved by the Geotechnical Engineer, which will give the
desired results. Water jets from the spreader shall not be directed at the
embankment with such force that fill materials are washed out.
Should too much water be added to any part of the fill, such that the material is too
wet to permit the desired compaction from being obtained, rolling and all work on
that section of the fill shall be delayed until the material has been allowed to dry to
the required moisture content. The Contractor will be permitted to rework wet
material in an approved manner to hasten its drying.
8. COMPACTION OF FILL AREAS
Selected fill material shall be placed and mixed in evenly spread layers. After each
fill layer has been placed, it shall be uniformly compacted to not less than the
specified percentage of maximum dry density. Fill materials shall be placed such
that the thickness of loose material does not exceed 8 inches and the compacted
lift thickness does not exceed 6 inches. Fill placed under foundations, exterior
flatwork and pavements should be compacted to a minimum of 95 percent of
maximum standard Proctor dry density (ASTM D698).
Compaction, as specified above, shall be obtained by the use of sheepsfoot rollers,
multiple-wheel pneumatic-tired rollers, or other equipment approved by the
Engineer. Compaction shall be accomplished while the fill material is at the
specified moisture content. Compaction of each layer shall be continuous over the
entire area. Compaction equipment shall make sufficient trips to ensure that the
required dry density is obtained.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
B-3
9. COMPACTION OF SLOPES
Fill slopes shall be compacted by means of sheepsfoot rollers or other suitable
equipment. Compaction operations shall be continued until slopes are stable, but
not too dense for planting, and there is no appreciable amount of loose soil on the
slopes. Compaction of slopes may be done progressively in increments of three
to five feet (3' to 5') in height or after the fill is brought to its total height. Permanent
fill slopes shall not exceed 3:1 (horizontal to vertical).
10. DENSITY TESTS
Field density tests shall be made by the Geotechnical Engineer at locations and
depths of his choosing. Where sheepsfoot rollers are used, the soil ma y be
disturbed to a depth of several inches. Density tests shall be taken in compacted
material below the disturbed surface. When density tests indicate that the dry
density or moisture content of any layer of fill or portion thereof is below that
required, the particular layer or portion shall be reworked until the required dry
density or moisture content has been achieved.
11. SEASONAL LIMITS
No fill material shall be placed, spread or rolled while it is frozen, thawing, or during
unfavorable weather conditions. When work is interrupted by heavy precipitation,
fill operations shall not be resumed until the Geotechnical Engineer indicates that
the moisture content and dry density of previously placed materials are as
specified.
12. NOTICE REGARDING START OF GRADING
The contractor shall submit notification to the Geotechnical Engineer and Owner
advising them of the start of grading operations a t least three (3) days in advance
of the starting date. Notification shall also be submitted at least 3 days in advance
of any resumption dates when grad ing operations have been stopped for any
reason other than adverse weather conditions.
13. REPORTING OF FIELD DENSITY TESTS
Density tests performed by the Geotechnical Engineer, as specified under "Density
Tests" above, shall be submitted progressively to the Owner. Dry density, moisture
content and percent compaction shall be reported for each test ta ken.
APPENDIX C
PAVEMENT CONSTRUCTION RECOMMENDATIONS
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
C-1
SUBGRADE PREPARATION
Moisture Treated Subgrade (MTS)
1. The subgrade should be stripped of organic matter, scarified,
moisture treated and compacted to the specifications stated below in
Item 2. The compacted subgrade should extend at least 3 feet
beyond the edge of the pavement where no edge support, such as
curb and gutter, are to be constructed.
2. Sandy and gravelly soils (A-1-a, A-1-b, A-3, A-2-4, A-2-5, A-2-6, A-
2-7) should be moisture conditioned near optimum moisture content
and compacted to at least 95 percent of standard Proctor maximum
dry density (ASTM D 698, AASHTO T 99). Clayey soils (A-6, A-7-5,
A-7-6) should be moisture conditioned between optimum and 3
percent above optimum moisture content and compacted to at least
95 percent of standard Proctor maximum dry density (ASTM D 698,
AASHTO T 99).
3. Utility trenches and all subsequently placed fill should be properly
compacted and tested prior to paving. As a minimum, fill should be
compacted to 95 percent of standard Proctor maximum dry density.
4. Final grading of the subgrade should be carefully controlled so the
design cross-slope is maintained and low spots in the subgrade that
could trap water are eliminated.
5. Once final subgrade elevation has been compacted and tested to
compliance and shaped to the required cross-section, the area
should be proof-rolled using a minimum axle load of 18 kips per axle.
The proof-roll should be performed while moisture contents of the
subgrade are still within the recommended limits. Drying of the
subgrade prior to proof-roll or paving should be avoided.
6. Areas that are observed by the Engineer that have soft spots in the
subgrade, or where deflection is not uniform of soft or wet subgrade
shall be ripped, scarified, dried or wetted as necessary and
recompacted to the requirements for the density and moisture. As
an alternative, those areas may be sub-excavated and replaced with
properly compacted structural backfill. Where extensively soft,
yielding subgrade is encountered; we recommend a representative
of our office observe the excavation.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
C-2
PAVEMENT MATERIALS AND CONSTRUCTION
Aggregate Base Course (ABC)
1. A Class 5 or 6 Colorado Department of Transportation (CDOT)
specified ABC should be used. A reclaimed concrete pavement
(RCP) alternative which meets the Class 5 or 6 designation and
design R-value/strength coefficient is also acceptable. Blending of
recycled products with ABC may be considered.
2. Bases should have a minimum Hveem stabilometer value of 72, or
greater. ABC, RAP, RCP, or blended materials must be moisture
stable. The change in R-value from 300-psi to 100-psi exudation
pressure should be 12 points or less.
3. ABC or RCP bases should be placed in thin lifts not to exceed 6
inches and moisture treated to near optimum moisture content.
Bases should be moisture treated to near optimum moisture content,
and compacted to at least 95 percent of standard Proctor maximum
dry density (ASTM D 698, AASHTO T 99).
4. Placement and compaction of ABC or RCP should be observed and
tested by a representative of our firm. Placement should not
commence until the underlying subgrade is properly prepared and
tested.
Hot Mix Asphalt (HMA)
1. HMA should be composed of a mixture of aggregate, filler, hydrated
lime, and asphalt cement. Some mixes may require polymer
modified asphalt cement, or make use of up to 20 percent reclaimed
asphalt pavement (RAP). A job mix design is recommended and
periodic checks on the job site should be made to verify compliance
with specifications.
2. HMA should be relatively impermeable to moisture and should be
designed with crushed aggregates that have a minimum of 80
percent of the aggregate retained on the No. 4 sieve with two
mechanically fractured faces.
3. Gradations that approach the maximum density line (within 5 percent
between the No. 4 and 50 sieves) should be avoided. A gradation
with a nominal maximum size of 1 or 2 inches developed on the fine
side of the maximum density line should be used.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
C-3
4. Total void content, voids in the mineral aggregate (VMA) and voids
filled should be considered in the selection of the optimum asphalt
cement content. The optimum asphalt content should be selected at
a total air void content of approximately 4 percent. The mixture
should have a minimum VMA of 14 percent and between 65 percent
and 80 percent of voids filled.
5. Asphalt cement should meet the requirements of the Superpave
Performance Graded (PG) Binders. The min imum performing
asphalt cement should conform to the requirements of the governing
agency.
6. Hydrated lime should be added at the rate of 1 percent by dry weight
of the aggregate and should be included in the amount passing the
No. 200 sieve. Hydrated lime for aggregate pretreatment should
conform to the requirements of ASTM C 207, Type N.
7. Paving should be performed on properly prepared, unfrozen
surfaces that are free of water, snow and ice. Paving should only be
performed when both air and surface temperatures equal, or exceed,
the temperatures specified in Table 401-3 of the 2006 Colorado
Department of Transportation Standard Specifications for Road and
Bridge Construction.
8. HMA should not be placed at a temperature lower than 245 oF for
mixes containing PG 64-22 asphalt, and 290oF for mixes containing
polymer-modified asphalt. The breakdown compaction should be
completed before the HMA temperature drops 20 oF.
9. Wearing surface course shall be Grading S or SX for residential
roadway classifications and Grading S for collector, arterial,
industrial, and commercial roadway classifications.
10. The minimum/maximum lift thicknesses for Grade SX shall be 1½
inches/2½ inches. The minimum/maximum lift thicknesses for Grade
S shall be 2 inches/3½ inches. The minimum/maximum lift
thicknesses for Grade SG shall be 3 inches/5 inches.
11. Joints should be staggered. No joints should be placed within wheel
paths.
12. HMA should be compacted to between 92 and 96 percent of
Maximum Theoretical Density. The surface shall be s ealed with a
finish roller prior to the mix cooling to 185oF.
13. Placement and compaction of HMA should be observed and tested
by a representative of our firm. Placement should not commence
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
C-4
until approval of the proof rolling as discussed in the Subgrade
Preparation section of this report. Subbase, base course or init ial
pavement course shall be placed within 48 hours of approval of the
proof rolling. If the Contractor fails to place the subbase, base course
or initial pavement course within 48 hours or the condition of the
subgrade changes due to weather or other con ditions, proof rolling
and correction shall be performed again.
Portland Cement Concrete (PCC)
1. Portland cement concrete should consist of Class P of the 2011
CDOT - Standard Specifications for Road and Bridge Construction
specifications for normal placement or Class E for fast-track projects.
PCC should have a minimum compressive strength of 4,200 psi at
28 days and a minimum modulus of rupture (flexural strength) of 6 50
psi. Job mix designs are recommended and periodic checks on the
job site should be made to verify compliance with specifications.
2. Portland cement should be Type II “low alkali” and should conform
to ASTM C 150.
3. Portland cement concrete should not be placed when the subgrade
or air temperature is below 40°F.
4. Concrete should not be placed during warm weather if the mixed
concrete has a temperature of 90°F, or higher.
5. Mixed concrete temperature placed during cold weather should have
a temperature between 50°F and 90°F.
6. Free water should not be finished into the concrete surface.
Atomizing nozzle pressure sprayers for applying finishing
compounds are recommended whenever the concrete surface
becomes difficult to finish.
7. Curing of the Portland cement concrete should be accomplished by
the use of a curing compound. The curing compound should be
applied in accordance with manufacturer recommendations.
8. Curing procedures should be implemented, as necessary, to protect
the pavement against moisture loss, rapid temperature change,
freezing, and mechanical injury.
9. Construction joints, including longitudinal joints and transverse joints,
should be formed during construction or sawed after the concrete
has begun to set, but prior to uncontrolled cracking.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
C-5
10. All joints should be properly sealed using a ro d back-up and
approved epoxy sealant.
11. Traffic should not be allowed on the pavement until it has properly
cured and achieved at least 80 percent of the design strength, with
saw joints already cut.
12. Placement of Portland cement concrete should be observed and
tested by a representative of our firm. Placement should not
commence until the subgrade is properly prepared and tested.
APPENDIX D
PAVEMENT MAINTENANCE PROGRAM
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
D-1
MAINTENANCE RECOMMENDATIONS FOR FLEXIBLE PAVEMENTS
A primary cause for deterioration of pavements is oxidative aging resulting
in brittle pavements. Tire loads from traffic are necessary to "work" or knead the
asphalt concrete to keep it flexible and rejuvenated. Preventive maintenance
treatments will typically preserve the original or existing pavement by providing a
protective seal or rejuvenating the asphalt binder to extend pavement life.
1. Annual Preventive Maintenance
a. Visual pavement evaluations should be performed each spring or
fall.
b. Reports documenting the progress of distress should be kept
current to provide information on effective times to apply
preventive maintenance treatments.
c. Crack sealing should be performed annually as new cracks
appear.
2. 3 to 5 Year Preventive Maintenance
a. The owner should budget for a preventive treatment at
approximate intervals of 3 to 5 years to reduce oxidative
embrittlement problems.
b. Typical preventive maintenance treatments include chip seals,
fog seals, slurry seals and crack sealing.
3. 5 to 10 Year Corrective Maintenance
a. Corrective maintenance may be necessary, as dictated by the
pavement condition, to correct rutting, cracking and structurally
failed areas.
b. Corrective maintenance may include full depth patching, milling
and overlays.
c. In order for the pavement to provide a 20-year service life, at least
one major corrective overlay should be expected.
POWERHOUSE 2 DEVELOPMENT COMPANY, LLC
POWERHOUSE 2
CTLT PROJECT NO. FC10223-125
D-2
MAINTENANCE RECOMMENDATIONS FOR RIGID PAVEMENTS
High traffic volumes create pavement rutting and smooth polished surfaces.
Preventive maintenance treatments will typically preserve the original or existing
pavement by providing a protective seal and improving skid resistance through a
new wearing course.
1. Annual Preventive Maintenance
a. Visual pavement evaluations should be performed each spring or
fall.
b. Reports documenting the progress of distress should be kept
current to provide information of effective times to apply
preventive maintenance.
c. Crack sealing should be performed annually as new cracks
appear.
2. 4 to 8 Year Preventive Maintenance
a. The owner should budget for a preventive treatment at
approximate intervals of 4 to 8 years to reduce joint deterioration.
b. Typical preventive maintenance for rigid pavements includes
patching, crack sealing and joint cleaning and sealing.
c. Where joint sealants are missing or distressed, resealing is
mandatory.
3. 15 to 20 Year Corrective Maintenance
a. Corrective maintenance for rigid pavements includes patching
and slab replacement to correct subgrade failures, edge damage,
and material failure.
b. Asphalt concrete overlays may be required at 15 to 20 year
intervals to improve the structural capacity o f the pavement.