HomeMy WebLinkAbout4518 INNOVATION DR WIRELESS TELECOMMUNICATIONS - FDP220006 - SUBMITTAL DOCUMENTS - ROUND 1 - DESIGN NARRATIVE          VERTICAL BRIDGE / T‐MOBILE            APPLICATION FOR PROJECT DEVELOPMENT PLAN APPROVAL   THE PROPOSED NEW TOWER   AT      4518 INNOVATION DRIVE,   FORT COLLINS, CO  80525      VERTICAL BRIDGE SITE # US‐CO‐5082  PROJECT NAME: 4518 INNOVATION DR CELL TOWER     Table  of Contents  1. Letter of Application  2. Application Materials  3. Site Data Sheet  4. Legal Description  5. Narrative Overview  6. Project Development Plan Submittal Requirements  7. Review Comment Responses  8. Zoning Approval Letter  9. Fall Zone Letter  10. Photo Simulations  11. Propagation Maps  12. Site Plans   Letter of Application    March 23, 2022    Tenae Beane  Development Review Coordinator  Community Development & Neighborhood Services  City of Fort Collins  281 N. College  Fort Collins, CO  80524    RE: Project Development Plan  Project Name: 4518 Innovation Dr Cell Tower  Vertical Bridge Site Number: US‐CO‐5082  4518 Innovation Drive  Fort Collins, CO  80524    Dear Ms. Beane:    Vertical Bridge, on behalf of T‐Mobile has finalized a lease agreement with the landowners of  the site referenced above to construct a wireless telecommunications service facility.  The  proposed facility is designed to house the equipment necessary to provide the technology  needed to provide clear and uninterrupted wireless telecommunications services to the  residents of City of Fort Collins.    The proposed wireless telecommunications facility will consist of an 80’‐0” monopine tower  with a 5’‐0” lightning rod along with support equipment to be located on a 10’‐0” x 15’‐0”  raised platform within an 11’‐0” x 20’‐0” lease parcel.  The proposed tower will be erected,  owned and managed by Vertical Bridge and upon construction; T‐Mobile will locate its  antennas on the tower.  The proposed tower is being built for T‐Mobile to improve coverage in  the area.  The facility is unstaffed and will only require service technicians, in a pick‐up/van  sized vehicle, to visit the site approximately once per month.    On behalf of Vertical Bridge and T‐Mobile, LCC Telecom Services has submitted all required  documentation for the proposed tower in accordance with the City of Fort Collins Zoning  Ordinance.  Should you have any questions please feel free to contact me.  I look forward to  working with you during the approval process in order to provide the residents of City of Fort  Collins the best possible PCS coverage.    Sincerely,    Michael Bieniek, AICP  Zoning Director       '(9(/230(175(9,(: $33/,&$7,21)250 &RPPXQLW\'HYHORSPHQW 1HLJKERUKRRG6HUYLFHV±1&ROOHJH$YH±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Ö &(57,),&$7,210867 %(6,*1('Õ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nnovation Drive 11' x 20' = 120 Vertical Bridge is proposing to erect an 85'-0" monopine tower with a 5'-0" lightning rod for a total height of 90' along with support equipment to be located on a 10'x15' raised platform within ab 11' x 20' lease parcel. 0.00275 The proposed tower is to be located on the southeast corner of the building behind the existing Rocky Mountain Archery building. E. Harmony Road and Monte Carlo Avenue on Innovation Drive NC, Neighborhood Commercial District 87314-06-010 10' x 15' = 150' sq ft (raised platform) 750 Park of Commerce Drive Vertical Bridge - Lessee Suite 200 Boca Raton Florida 33487 561-948-6367 Mike Bieniek, AICP - Agent on behalf of Vertical Bridge LCC Telecom Services Mike Bieniek, AICP 10700 W. Higgins Road, Suite 240 5/30/21 and 9/22/21 Rosemont IL 60018 847-287-1156 mbieniek@lcctelecom.com phone or e-mail None required Type 1 - Hearing Officer Lori B. Strand Michael Bieniek, AICP 10700 W. Higgins Road, Suite 240, Rosemont, IL 60018 847-287-1156 5HYLVHG'HFHPEHU 7\SHRI5HTXHVW 3OHDVHLQGLFDWHWKHW\SHRIDSSOLFDWLRQVXEPLWWHGE\FKHFNLQJWKHER[SUHFHGLQJWKHDSSURSULDWHUHTXHVW V  $GGLWLRQDOKDQGRXWVDUHDYDLODEOHH[SODLQLQJWKHVXEPLWWDOUHTXLUHPHQWVIRUHDFKRIWKHIROORZLQJUHYLHZ SURFHVVHV ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ ‰ $QQH[DWLRQ3HWLWLRQZLWK,QLWLDO=RQLQJ5(48(67('=21(BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB )HH 5H]RQLQJ3HWLWLRQ5(48(67('=21(BBBBBBBBBBBBBBBBBBBBBBBBBBBBB )HH 3ODQQHG8QLW'HYHORSPHQW 38' )HH 2YHUDOO'HYHORSPHQW3ODQ 2'3  )HH 3URMHFW'HYHORSPHQW3ODQ 3'3  )HH )LQDO'HYHORSPHQW3ODQ )'3 )HH 0RGLILFDWLRQRI6WDQGDUGV )HH %DVLF'HYHORSPHQW5HYLHZ %'5 )HH 0DMRU$PHQGPHQW 0-$ )HH 0LQRU$PHQGPHQW&KDQJHRI8VH )HH 0LQRU6XEGLYLVLRQ )HHVXEGLYLVLRQRQO\QRODQGXVHDSSURYDOV ,QIUDVWUXFWXUH3URMHFW )HH ([WUD2FFXSDQF\8QLW )HHSHUXQLW $GGLWLRQRI3HUPLWWHG8VH $38 )HH 6LWH3ODQ$GYLVRU\5HYLHZ 12)(( $GGLWLRQDOURXQGVRI5HYLHZ )HHFKDUJHGRQFHIRUSURMHFWVWKDWUHTXLUHRUPRUHURXQGVRIUHYLHZ &LW\RI)RUW&ROOLQV'HYHORSPHQW5HYLHZFROOHFWV3RXGUH)LUH$XWKRULW\'HYHORSPHQW5HYLHZ)HHVIRUWKH DERYHUHTXHVWV$SSOLFDEOH3RXGUH)LUH$XWKRULW\)HHVZRXOGDSSO\DWWLPHRIDSSOLFDWLRQ 33D\PHQWVFDQEHPDGHE\FKHFNRUFUHGLWFDUG &KHFN0DNHSD\DEOHWR&LW\RI)RUW&ROOLQV0DLOWRWKH'HYHORSPHQW5HYLHZ&HQWHU1&ROOHJH$YH)RUW&ROOLQV&225SODFHLQWKHEOXHGURSER[ORFDWHGDWWKHZHVWVLGHRIWKHEXLOGLQJ &UHGLW&DUG:RXOGEHSURFHVVHGRYHUWKHSKRQH&UHGLWFDUGSD\PHQWVLQFOXGHDFRQYHQLHQFHIHHRIDGGHGWRDOOSD\PHQWVXQGHUDQGDGGHGWRDOOSD\PHQWVRYHU ‰ Development Application Complete Submittal Checklist Development Review Center | 281 N College Ave | Fort Collins CO 80522 | 970.221.6689 | DRCoord@fcgov.com Submittal Instructions • A City Development Review Coordinator will be assigned to all projects - Your Development Review Coordinator is available to assist you with the review process. If you do not have a review coordinator assigned to your project, please contact us at 970-221-6689 or DRCoord@fcgov.com for assistance. • Advanced notice of Submittal and resubmittals is appreciated - A completed copy of this checklist, all submittal materials and fee payments are due at the time of project submittal. Please contact your Development Review Coordinator at 970-221-6689 or DRCoord@fcgov.com for more submittal details including turn around times and next steps. • Only complete submittals are accepted - The submittal may be returned to the applicant if any required materials or application fees are missing or insufficient. Submittals received Monday morning through Wednesday noon will be routed for review the same week and submittals received after Wednesday noon will be held and routed the following week. • This checklist shall be used in tandem with the Submittal Requirements Document. The applicant must complete this checklist and acknowledgement of the Submittal Requirements Document. • The applicant shall be the designated contact person who will receive correspondence from city staff and referral agencies. Additional Resources • Development Review Guide and Flowchart: https://www.fcgov.com/drg/ • Development Review Applications and Submittal Requirements Main Page: https://www.fcgov.com/developmentreview/applications.php • City Land Use Code: https://library.municode.com/co/fort_collins/codes/land_use • City Utilities: Development Forms, Guidelines & Regulations • City Engineering main page: https://www.fcgov.com/engineering/ • The City’s Comprehensive Plans: City Plan and Transportation Master Plan • Online City Map Resources: https://www.fcgov.com/gis/maps.php • Larimer County Urban Area Street Standards: https://www.larimer.org/engineering/standards-and-guides/urban-area-street-standards 1/4/2022 2 FDP/BDR Development Application Submittal Checklist Office Use Only: Project Type: Project Number (if assigned):BBBBBBBBBBBBBB New Submittal Revision -- Review Round: Submittal Date:BBBBBBBBBBBB Complete Submittal Checklist: Final Development Plan (FDP) · Basic Development Review (BDR) Project Name: Applicant Name: 3URMHFWReview Meeting Date:BBBBBBBBBBB Development Review Coordinator: BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB This checklist is for the Final Review phase for all development projects (see Step 7 of the process flowchart). This includes final detail required for Project Development Plans (PDP). The checklist shall also be used for Basic Development Reviews (BDR) or plan amendments including Major Amendments (MJA) and Minor Amendments (MA) as determined by staff. All checklist items are required unless city staff indicates an item is (W)aived, (D)eferred, (N/A) Not Applicable or already (R)eceived. If the staff code is blank, then the item is required. This checklist must be reviewed, completed and accepted by staff prior to project routing. Additional information may be requested from the applicant during the review process, if necessary, to address specific issues that arise. Please note that all application materials, once submitted, become a matter of public record. Checklist, Submittal Forms and Fees: Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ One copy of this checklist, completed and signed by applicant Development Review Coordination DRCoord@fcgov.com 970-221-6689܆One signed copy of Development Application Form ܆ Payment for the above application form Payments can be made by check or credit card. Check: Make payable to City of Fort Collins. Mail to the Development Review Center, 281 N College Ave, Fort Collins, CO 80524, OR place in the blue drop box located at the west side of the building. Credit Card: Would be processed over the phone. Credit card payments include a convenience fee of 2% + $0.25 added to all payments under $2,500.00, and 2.75% added to all payments over $2,500.00. 4518 Innovation Dr Cell Tower Mike Bieniek ✔ ✔ REQUIRED REQUIRED REQUIRED ✔ Tenae Beane, tbeane@fcgov.com FDP 1/4/2022 3 FDP/BDR Development Application Submittal Checklist Electronic Copies* All copies must be provided per City file naming standards and submitted electronically. All copies must be prepared per city PDF formatting standards. See: Submittal Requirements Section M – File Naming Standards & PDF formatting standards *Paper copies of plans and reports are not required during development review. See Submittal Requirements, Section D for drawing format guidelines. All plan elements shall be clearly drawn and labelled. A scale bar must be provided on all scaled drawings. Paper copies of plan sheets may be requested in order to complete a time- ly review, including instances when the drawing scale is not accurately depicted. 1) General Information: Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ A comment response letter from the project's Conceptual Review or Preliminary Development Review staff meeting; for 1st round FDP include response from the last round PDP; or for resubmittals include a comment response letter from the prior round of review. To receive a final copy of the staff comment letter, contact your Development Review Coordinator Section C Development Review Coordination DRCoord@fcgov.com 970-221-6689 ܆ Project Information and Design Narrative 2) Planning Submittal Package: Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ Title Block information on all plan sheets Section D ܆ Cover Page, including: ܆ Title Block ܆ Land Use Table Section E ܆ Sheet Index Section D ܆ Signature Blocks ܆ Site Plan Notes Standard Notes (also available in Word format at the Submittal Requirements web page) ܆ Site Location Map Section D ܆ Legal Description Title Block information on all plan sheets Cover Page, including: Title Block Land Use Table Sheet Index Signature Blocks Site Location Map Legal Description Site Plan Notes ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ REQUIRED REQUIRED REQUIRED REQUIRED REQUIRED REQUIRED REQUIRED REQUIRED 1/4/2022 4 FDP/BDR Development Application Submittal Checklist ܆ Final Site Plan Sheet(s) (and related hardscape design detail sheets, See Section I for Requirements) Section F ܆ Final Architectural Elevation Sheet(s), Materials and other Detail Sheets (color elevations recommended) Section G ܆ Final Landscape Plan Sheet(s) Standard city landscape notes, and related planting detail sheets (See Section I for planting detail requirements) Section H and I Standard Notes (also available in Word format at the Submittal Requirements web page) ܆ Preliminary Irrigation Plan Section H (also available on the Water Conservation web page). ܆ Final Lighting Plan, Photometric Plan and Lighting Detail Sheets Section I ܆ Final Trash and Recycling Enclosure Details (include these details with the site plan sheets or elevation sheets) ܆ Confirmation that all Sheets provided incorporate City drafting and format standards Section D ܆ Staff Comments: Final Site Plan Sheet(s) (and related hardscape design()( p detail sheets, See Section I for Requirements) Preliminary Irrigation Plan Final Lighting Plan, Photometric Plan and Lighting Detail Sheets Final Trash and Recycling Enclosure Details (include these yg ( details with the site plan sheets or elevation sheets) Confirmation that all Sheets provided incorporate Cityp drafting and format standards Final Landscape Plan Sheet(s)p() Standard city landscape notes, and related planting detail yp, pg sheets (See Section I for planting detail requirements) REQUIRED REQUIRED REQUIRED NA NA NA REQUIRED ✔ ✔ ✔ ✔ ✔ ✔ ✔ REQUIRED 1/4/2022 5 FDP/BDR Development Application Submittal Checklist 3) Final Subdivision Plat: Staff Code Applicant Validation Item Description Submittal Requirement Resources A final subdivision plat of the site. This plat must conform to the subdivision requirements of the City. The subdivision Section J plat shall contain proper designations for public streets, easements, flood plains, floodways with base flood elevations if required and all other public rights-of-way. Approval by the Director for Type I Administrative Review, LUC Division 3.3 – Engineering Standards and approval by the Planning and Zoning Board for Type II Review by the Planning and Zoning Board, of the final plan and subdivision plat, and complete execution, together with all necessary certifications, shall be required before filing of the subdivision plat or issuance of building permits. Each residential lot on the subdivision plat shall identify if the garage door(s) is recessed behind the front face of the building, located on one of the other sides of the building, detached from the building or located to the front of the front face of the building. Please note that, with the Recording submittal, the subdivision plat is required to be provided in CAD format at time of recordation. The CAD file for plat must be set up to be in conformance with GIS's Subdivision Plat Digital Submittal Standards. Refer to the Recording Submittal Checklist which will be provided by your Development Review Coordinator. NA ✔ 1/4/2022 6 FDP/BDR Development Application Submittal Checklist 4) Final Civil Construction Plans (Utility Plans): Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ Cover Sheet Utility Plans Checklist.pdf City Contact: Engineering Development Review EngDevRev@fcgov.com 970-221-6605 ܆ Standard Notes Sheet ܆ Existing Conditions and/or Demolition Plan (if required) ܆ Overall Grading Plan (if required) ܆ Detailed Grading Plan Sheets ܆ Overall Utility Plan Sheet (if required) ܆ Detailed Utility Plan Sheets ܆ Sanitary Sewer Plan and Profile Sheets ܆ Storm Sewer Plan and Profile Sheets ܆ Water Plan and Profile Sheets (if required) ܆ Street Plan and Profile Sheets (if required) ܆ Street Cross-sections (if required) ܆ City of Fort Collins Standard Construction Details Cover Sheet Existing Conditions and/or Demolition Plan (if required) OOverall Grading Plan (if required) Detailed Grading Plan Sheets Overall Utility Plan Sheet (if required) Detailed Utility Plan Sheets anitary Sewer Plan and Profile SheetsSSa SStorm Sewer Plan and Profile Sheets Water Plan and Profile Sheets (if required) Street Plan and Profile Sheets (if required) SStreet Cross-sections (if required) City of Fort Collins Standard Construction Details Standard Notes Sheet ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ NA NA NA NA NA REQUIRED REQUIRED NA NA NA ✔ REQUIRED REQUIRED NA ✔ 1/4/2022 7 FDP/BDR Development Application Submittal Checklist 5) Final Drainage and Erosion Control Report: Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ Final Drainage and Erosion Control Report may include the following: Items from the PDP Checklist: Detention Requirements and Calculations Offsite Flows (if required) Floodplain Zone (if required) -- Contact Floodplain Administration staff at 970-416-2632 for questions Hydraulic Calculations Detention Basin Calculations Standard Water Quality and LID Calculations Include Drainage Plan or Exhibit in the report Additional Final Items: Hydraulic Calculations Four Step Process SDI Data Spreadsheet (if required) Erosion Control Materials Note: All items shown above are components that may be necessary with a drainage report analysis. Not all components may be necessary. The drainage report analysis must be prepared by a professional engineer. Stormwater Criteria Manual Resource Page Stormwater Criteria Manual Appendices: A. Required Submittal Content B. Stormwater Facilities Landscape Standards C. LID Implementation D. Erosion Control Guidance E. Erosion Control Construction Measures Fact Sheets F. Erosion Control Construction Measures Standard Notes City Utilities: Development Forms, Guidelines & Regulations For Stormwater or Floodplain questions, contact: waterutilitieseng@ fcgov.com 970-221-6689 Erosion Control Information: www.fcgov.com/erosion Detention Requirements and Calculations Offsite Flows (if required) p (q)p Administration staff at 970-416-2632 for questions draulic CalculationsHHyd Detention Basin Calculations Standard Water Quality and LID Calculations Include Drainage Plan or Exhibit in the report REQUIRED ✔ 1/4/2022 8 FDP/BDR Development Application Submittal Checklist 6) Final Reports and Supporting Documents: Staff Code Applicant Validation Item Description Submittal Requirement Resources Meeting Date: (mm/dd/yy) REQUIRED PRIOR TO FDP SUBMITTAL Building Services Presubmittal Meeting: Confirmation of completed Pre-Submittal Code Feasibility Meeting with Building Services. New Commercial Projects require a pre-submittal meeting for building code feasibility. This typically takes place when drawings are 50% complete and in the mid phases of the Development Review Process, and prior to Building Permit Submittal. Applicants are encouraged to review building requirements as early as possible in the process. For questions or to schedule this meeting please reach out to your Development Review Coordinator. Please Note: Building Permits will not be reviewed until Development Plan review process is completed and recorded. Building Codes and Standards Building Permit Fees ܆ Planning Services: Perspective views of the Building Exterior (Incorporated into the building elevation sheets) Section G ܆ Building Material Sample Board ܆ Neighborhood Context Plan (Overall site plan diagram indicating surrounding neighborhood features, to be incorporated into Site Plan sheets or cover page) Section C ܆ Land Use Code Modification and Alternative Compliance Requests; staff review, and approval required prior to Development Review Completion (if required) LUC Division 2.8 City Contact: Planning Services planning@fcgov.com 970-416-4311 ܆ Parking Alternative Compliance Studies Guidelines for these studies are held by the Director Parking Impact Study Guidelines (ifrequired) LUC Section 3.2.2(K) City Contact: Planning Services planning@fcgov.com 970-416-4311 ܆ Certification of Notice to Mineral Owner(s) (if required) Mineral Rights Certificate.pdf Perspective views of the Building Exterior (Incorporated into the building elevation sheets) Land Use Code Requests; staff q Development Review f required) Modification and Alternative Compliancep review,and approval required prior to Parking Alternative Compliance Studies Guidelines for these studies are held by the Director Parking Impact Study Guidelinesgp (if required) CCertification of Notice to Mineral Owner(s) (if required) REQUIRED REQUIRED NA REQUIRED NA NA NA ✔ ✔ ✔ ✔ ✔ 1/4/2022 9 FDP/BDR Development Application Submittal Checklist Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ Development Review Engineering: Soils Report In conformance with the Larimer County Urban Area Street Standards Larimer County Urban Area Street Standards ܆ Subsurface Hydrologic Study ܆ Development Agreement Information Form Engineering Main Page City Contact: Engineering Development Review EngDevRev@fcgov.com 970-221-6605 ܆ Final legal descriptions for accompanying deeds of dedication by separate document Easement and Right-of-Way Dedication Process ܆ Final legal descriptions for accompanying easement vacation request by separate document Vacation of Easements Process ܆ Approved and Signed Engineering or Utility Variance Requests Larimer County Urban Area Street Standards ܆ Traffic Operations: Transportation Impact Study (TIS) OR waiver indicated from Traffic Operations staff (Waiver indication to be provided with initial submittal) Traffic Operations Resource Page City Contact: Traffic Operations 970-221-6630 ܆ Utilities – Environmental Engineering: Erosion Control Cost Estimate City Utilities: Development Forms, Guidelines & Regulations ܆ Utilities – Electric Systems Engineering: Electric Utility Service C-1 Form City Utilities: Development Forms, Guidelines & Regulations ܆ Utilities – Water Development Fees: Water Fee Form City Utilities: Water development fees page Subsurface Hydrologic Study Final legal descriptions Final legal descriptions NA NA REQUIRED REQUIRED ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ NA REQUIRED NA NA REQUIRED NA ✔ 1/4/2022 10 FDP/BDR Development Application Submittal Checklist Staff Code Applicant Validation Item Description Submittal Requirement Resources ܆ Environmental Planning: Ecological Characterization Study (ECS) If an ECS is required, this must be submitted at least ten days prior to the development review application. A copy shall also be submitted at the time of the application with this checklist. Section J Section H LUC Section 3.4.1 City Contact: Environmental Planning 970-416-4311 ܆ Phase 1 Environmental Site Assessment To be provided by qualified third-party consultant ܆ City Forestry: Existing Tree Inventory Plan Prior to the review submittal, the applicant must schedule an on- site meeting with City Forestry to obtain tree inventory information for all existing trees within the development area. The meeting is also intended to discuss any proposed tree removal. PLEASE NOTE THAT EXISTING TREES SHOULD NOT BE REMOVED OR DAMAGED PRIOR TO SUBMITTAL, REVIEW AND APPROVAL OF THE PROPOSED DEVELOPMENT. See Submittal Requirements Sections H and L for more information regarding documentation of existing and proposed trees on landscape plans City Contact: City Forestry forestry@fcgov.com 970.221.6660 City Forestry Resources: www.fcgov.com/forestry Land Use Code Section: 3.2.1(F) Tree Protection and Replacement ܆ Existing Tree Removal Feasibility Request Provide a letter to City Forestry outlining the justification for the removal of any existing trees, if proposed. ܆ Existing Tree Mitigation Plan At your site meeting, City Forestry will determine the characteristics and mitigation requirements for all existing trees within the project's proposed Limits of Disturbance. (if required). REQUIRED ✔ ✔ ✔ ✔ ✔ NA NA REQUIRED REQUIRED 1/4/2022 11 FDP/BDR Development Application Submittal Checklist ܆ Other information and data as required for the full and complete consideration of the development (to be completed by City staff): Hazardous Materials Impact Analysis (if required). Any special wildlife, wetland, natural habitats and features, ecological or environmental study or mapping pursuant to Section 3.3 and 3.4 of the Land Use Code as requested by the Director. Other items required: City Contact: Development Review Coordination DRCoord@fcgov.com 970-221-6689 Applicant Acknowledgement: I have reviewed the Development Application Submittal Requirements, Sections A – M. All documents submitted are complete and the Development Application Submittal Requirements have been incorporated into the plans (See Development Application Submittal Requirements for detailed description of requirements). All documents submitted have been compared and consistent design information is shown on all plan sheets and reports. I understand that submittal requirements not sufficiently addressed or deferred may result in added review time. Applicant Signature: ______________________________________________________ Date: ______________________________ Phone: ______________________________________ Email: ________________________________________________________ (See Development Application Submittal Requirements for detailed description of requirements) 03/23/2022 847-287-1156 mbieniek@lcctelecom.com Outside Agencies to be Routed by the City of Fort Collins* (to be completed by staff): Comcast Cable Century Link Xcel Energy East Larimer County Water District Fort Collins-Loveland Water District South Fort Collins Sanitation District Platte River Power Authority Poudre Valley REA Boxelder Sanitation District Cherry Hills Sanitation Colorado Department of Transportation Greeley Water Line Railroad: Ditch Company: Larimer County Planning Poudre School District Thompson School District Other: Other: Other: Other: * Notice: The City of Fort Collins routes the project application materials to the specified outside agencies and requests a review of the materials and comments to the project’s applicant by the specified comment due date, but cannot guarantee that the agencies will provide comments by the date requested or certify acceptance of the routed project. Site Data Sheet  Applicant: Vertical Bridge  750 Park of Commerce Drive  Suite 200  Boca Raton, FL  33487    T‐Mobile  8000 W. 78th Street  Suite 400  Edina, MN  55439    Agent: Michael Bieniek, AICP  LCC Telecom Services  10700 Higgins Road  Suite 240  Rosemont, IL  60018    Tower Owner: Vertical Bridge  750 Park of Commerce Drive  Suite 200  Boca Raton, FL  33487    Applicant’s Interest in the  Property:  Leasehold    Project Title: 4518 Innovation Dr Cell Tower     Property Owner: Stewart King – Rocky Mountain Archery  4518 Innovation Drive  Fort Collins, CO  80525    Address of Property: 4518 Innovation Drive  Fort Collins, CO  80525    Entitlements Sought: Application for a Project Development Plan and any other  approvals necessary to erect an 80’‐0” monopine tower within  an 11’‐0” x 20’‐0” lease area.       Legal Description  Lot 10, except the North 10 feet, thereof, Golden Meadows Business Park, County of Larimer,  State of Colorado.    Tax Parcel No. 87314‐06‐010     Narrative Overview  Vertical Bridge Development LLC, (“Vertical Bridge”) and T‐Mobile, seek Development  Plan Approval, and any other necessary approvals in order to install a wireless  telecommunications facility on property located at 4518 Innovation Drive, Fort Collins, Colorado   80525.  Vertical Bridge and its affiliates have acquired the necessary licenses from the Federal  Communications Commission (“FCC”) to provide Personal Communications Services (“PCS”)  coverage throughout the United States.  These licenses include Fort Collins, CO.  The monopine tower which Vertical Bridge is proposing to install on behalf of T‐Mobile  on the property is necessary in order to provide uninterrupted PCS services to the residents of  Fort Collins, including wireless telephone service, voice paging, messaging and wireless internet  and broadband data transmission.  All registered wireless provider’s technology operates at  various radio frequency bands allocated by the FCC as part of their license.  PCS systems operate on a grid system with overlapping cells mesh together, forming a  seamless network.  No one site can function as a stand‐alone entity as each site is  interconnected, forming the network.  The technical criteria for establishing cell sites are very  exacting as to the location and height.  Within the Fort Collins area, cell sites are generally  located approximately one (1) to three (3) miles apart.  Vertical Bridge is proposing to erect a  80’‐0” monopine tower along with support equipment within an 11’‐0” x 20’‐0” lease area.  The  proposed site at 4518 Innovation Drive, Fort Collins, CO  50525 is within the geographic area  deemed necessary for T‐Mobile and various other wireless telecommunications providers in  order to provide uninterrupted services.   In accordance with the City of Fort Collins Zoning Ordinance, Vertical Bridge has made  application to install a wireless telecommunications facility. The proposed new tower is being  erected to allow T‐Mobile to provide the necessary coverage for residents in the Fort Collins  area.  T‐Mobile is currently on an existing facility in the area that will be removed on or before  construction of the proposed facility.  The facility is unstaffed and will only require service technicians, in a pick‐up/van sized  vehicle, to visit the site approximately once per month.  Access will be provided via an  easement and the proposed property entry at 4518 Innovation Drive, Fort Collins, CO  50525.   The site is entirely self‐monitored through a sophisticated alarm system which is connected to a  main switch station.  The system alerts personnel to any equipment malfunction or breach of  security.  Additionally, there is no impact on any city services such as water, sanitation, police  and fire.  The only services used in connect with the wireless telecommunications facility are  power and fiber / land‐line telephone.  In accordance with FCC regulations, the wireless telecommunications facility will not  interfere with any form of communications, including but not limited to, land‐line phones, cable  and satellite television and radio broadcasts.  PCS technology has become a vital part of  emergency services, aiding local residents and motorists in a variety of situations, thus helping  to protect the general public’s health, safety and welfare.  The proposed wireless  telecommunications facility at this site will further enhance T‐Mobile’s goals of providing the  most reliable network possible in this area.  The proposed stealth wireless telecommunications facility will be designed and  constructed to meet all applicable governmental and industry safety standards.  Specifically,  Vertical Bridge and T‐Mobile will comply with all FCC and FAA rules and regulations regarding  construction requirements and technical standards.  Any and all RF emissions are subject to the  exclusive jurisdiction of the FCC.  Any height, lighting or marking issues are subject to the  exclusive jurisdiction of the FAA.  LCC Telecom Services, on behalf of Vertical Bridge and T‐Mobile, looks forward to  working with the City of Fort Collins to bring the benefits of the proposed service to the entire  Fort Collins area.  The addition of the wireless telecommunications facility will ensure the best  uninterrupted wireless services for the citizens of Fort Collins.   Project Development Plan Submittal Requirements  In considering a Project Development Plan application, the City Staff shall review the particular  circumstances of the Project Development Plan request. As part of the Project Development  Plan submittal, the applicant is required to submit the following information:  1) Project title: Name of the development project as well as any previous name the project may  have had during Conceptual Review. Please provide a consistent project title on all documents.    4518 Innovation Drive Cell Tower    2) Past Meeting Dates: Provide dates of any CR, PDR, and neighborhood meeting held.    A Zoom meeting was held on April 29, 2020 at 2:00 mst with Matt Grugan and Johnnie  Whitfield, Vertical Bridge; Tenae Beane and Clark Mapes, City of Fort Collins and Michael  Bieniek, LCC Telecom Services.    A Zoom meeting was held on June 15, 2020 at 2:00 mst with Matt Grugan and Johnnie  Whitfield, Vertical Bridge; Matt Simpson, City of Fort Collins and Michael Bieniek, LCC  Telecom Services.    A Zoom meeting was held on May 30, 2021 at 8:30 mst with the City of Fort Collins Staff and  representatives for Vertical Bridge, T‐Mobile, Kimley‐Horn and Michael Bieniek, LCC Telecom  Services.  This was the first project review.     A Zoom meeting was held on September 22, 2021 at 8:30 mst with the City of Fort Collins  Staff and representatives for Vertical Bridge, T‐Mobile, Kimley‐Horn and Michael Bieniek, LCC  Telecom Services.  This was the second project review.    No neighborhood meetings are required for this project.    3) General Information: The information provided is used to describe the project in the City’s  online review database. General information includes the following (as applicable): project  location, overall size of the development in acres, existing zoning, proposed zoning, number of  dwellings, amount and type of commercial space, number of off‐street parking spaces provided,  number of building stories proposed, description of any Land Use Code Modifications proposed.      Project location – 4518 Innovation Drive, Fort Collins, CO  80525   Overall size of the development in acres – 220 square feet (.0051 acres)   Existing zoning – NC, Neighborhood Commercial District   Proposed zoning – No change to zoning designation   Number of dwellings – None, however T‐Mobile will be placing equipment cabinets on  a steel platform   Amount and type of commercial space – None   Number of off‐street parking spaces provided – None needed, existing parking will be  used   Number of building stories proposed – N/a   Description of any Land Use Code Modifications proposed – None    4) Proposed Owners: A list of names of all general and/or limited partners (if a partnership)  managers and directors (if a limited liability company) and/or officers and directors of the  corporation (if a corporation) involved as either applicants or owners of the development.    Stewart King – privately owned business     5) Existing Owners: The name and address of each existing owner of property within the  boundaries of the development plan area.    Stewart King  4518 Innovation Drive  Fort Collins, CO  80525     Other optional items that may be included with the narrative as applicable. The topics below  should also be addressed when designing the project:    6) Transportation Improvements: Summary of any proposed on and off‐site improvements  identified with the Traffic Impact Study (if applicable).    There will be no impact in traffic off‐site and no additional traffic.  A cell site is unstaffed and  will only require service technicians, in a pick‐up/van sized vehicle, to visit the site  approximately once per month.  The utility and access will be through an existing entrance.   An extension of the existing pavement will consist of a 14’ wide access and utility easement  on the north side of the property back to the site.     7) Written narrative addressing each concern/issue raised at the neighborhood meeting(s), if a  meeting has been held. Please contact a Development Review Coordinator (or Planning Services  main number) to receive a copy of the neighborhood meeting minutes in Word format. Please  note that neighborhood meetings are required for all Type 2 projects, and if a neighborhood  meeting is required, a ten‐day waiting period is required prior to submitting a Development  Application.    No neighborhood meetings are required for this project.    8) Narrative description of the site design including building placement, vehicular and  pedestrian circulation, landscaping, proposed open space and treatments of wetlands, natural  habitats and features on site and in the general vicinity of the project.     Building placement – the proposed tower is to be located at the southeast corner of  the property, immediately behind the existing building.   Vehicular and pedestrian circulation ‐ utility and access will be through an existing  entrance.  An extension of the existing pavement will consist of a 14’ wide access and  utility easement on the north side of the property back to the site.   Landscaping – A row of eight (8) – five (5) gallon Viburnum Lentago (Nannyberry) will  be located on the north side of the property and ten (10) – five (5) gallon Viburnum  Lentago (Nannyberry) will be located on the south side of the property.   Proposed open space and treatments of wetlands – The proposed platform will extend  in the existing detention area.  Vertical Bridge has worked closely with Matthew  Simpson, City Engineer to come up with a solution.  The steel platform will be elevated  with a non‐solid surface to minimize impact on the detention.  An easement  agreement has been signed and provided for the encroachment into the detention  pond.    Natural habitats and features on site and in the general vicinity of the project – The  proposed site is located in an industrial park; no natural features will be impacted.     9) Narrative description of how disturbances to wetlands, natural habitats and features and/or  wildlife are being avoided to the maximum extent feasible.     There are no wetlands on the property, however there is a detention pond on the east  side of the property.  The proposed tower is being located on a mesh steel platform on  the southwest corner of the detention area.  The only penetrations in the detention  pond will be two steel piers to hold up the platform.   Natural habitats and features on site and in the general vicinity of the project – The  proposed site is located in an industrial park; no natural features will be impacted.    10) Narrative description of transition techniques, associated buffering and how conflicts  between existing and proposed land uses are mitigated.    The proposed monopine tower is being located on the rear of the property which is located  immediately adjacent to an electric substation.  The tower is designed to blend in with the  existing towers located to the east.    11) Narrative description of the architectural design including general description of how  Building Standards are met (Sections 3.5.1 and other applicable Sections in 3.5). Depending on  the nature of the project, the narrative provided may be one page or multiple pages.  Description should also include information regarding the design approach used to satisfy any  applicable historic preservation considerations, as required in Section 3.4.7 ‐‐ Historic and  Cultural Resources, and should also include a discussion of the design approach used to satisfy  the recommendations from the Landmark Preservation Commission (LPC), if applicable.    There are no historic or cultural resources which are being considered in the design.  The  property is in an industrial area.  As stated above, the proposed monopine tower is being  located on the rear of the property which is located immediately adjacent to an electric  substation.  The tower is designed to blend in with the existing towers located to the east.    12) Development Phasing Schedule (if applicable). This shall include a development schedule  with anticipated start dates, completion dates and descriptions for each development phase  proposed. Schedule shall include the proposed phasing of construction of public improvements  and recreational and common space areas. Projects with multiple parcels and/or property  owners should review and refine shared phased elements such as streets, walkways/trails,  grading, walls and utilities and incorporate construction phasing by development parcel, if  applicable. Larger or more complex projects should include a phasing plan and supplemental  tables and notations as a plan sheet.     Narrative may be divided into topics for clarity. Topics included with the narrative may vary  and may include a justification of choices made with the project including the configuration of:  parking areas, walkways, trail connections, new tree stocking, landscape bed areas, existing  trees, site circulation and access, transition areas, buffering from incompatible uses and  adjacent features, location and design of parks and open space, configuration of trash and  recycling service areas and loading zones, preservation and enhancement of natural habitats  and features, easements needed/provided, provisions for emergency access, ADA accessibility  considerations, lighting considerations, notable utility and drainage constraints or  considerations, description of the exterior building design and articulation, interior and exterior  amenities provided that support the proposed uses, project information such as the intended  users, number of employees, or other relevant information.     With more complex projects that touch on many of the subjects described above, please  use multiple headings to organize the information provided. The narrative can be an effective  tool to communicate to all stakeholders or parties‐in‐interest how the project meets the  developer/applicant’s objectives while mitigating project impacts in accordance with code  requirements, subarea plans and City Plan. The narrative may also include and reference how  goals and objectives of City Plan and subarea plans are satisfied. If references to City goals and  objectives are provided, it is recommended that the references include all relevant  development, neighborhood character and mitigation objectives.    There is no development phasing for this project.  A typical installation takes approximately  3‐4 weeks to erect the proposed tower.  Once that is complete T‐Mobile will install their  equipment.     Review  Comment Responses     1 Community Development and Neighborhood Services 281 North College Avenue PO Box 580 Fort Collins, CO 80522 970.221.6689 970.224.6134 - fax fcgov.com/developmentreview March 23, 2022 Mike Bieniek LCC Telecom Services 10700 W Higgins Rd Suite 240 Rosemont, IL 60018 RE: 4518 Innovation Dr Wireless Telecommunications, PDP210010, Round Number 2 Please see the following summary of comments from City staff and outside reviewing agencies for your submittal of 4518 Innovation Dr Wireless Telecommunications. If you have questions about any comments, you may contact the individual commenter or direct your questions through your Development Review Coordinator, Tenae Beane via phone at 970-224-6119 or via email at tbeane@fcgov.com. Comment Summary: Department: Development Review Coordinator Contact: Tenae Beane, 970-224-6119, tbeane@fcgov.com Topic: General Comment Number: 1 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: I will be your primary point of contact throughout the development review and permitting process. If you have any questions, need additional meetings with the project reviewers, or need assistance throughout the process, please let me know and I can assist you and your team. Please include me in all email correspondence with other reviewers and keep me informed of any phone conversations. Thank you! Comment Number: 2 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: As part of your resubmittal you will respond to the comments provided in this letter. This letter is provided to you in Microsoft Word format. Please use this document to insert responses to each comment for your submittal, using a different font color. When replying to the comment letter please be detailed in your responses, as all comments should be thoroughly addressed. Provide 2 reference to specific project plans or explanations of why comments have not been addressed, when applicable, avoiding responses like noted or acknowledged. Comment Number: 3 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: Please follow the Electronic Submittal Requirements and File Naming Standards found at https://www.fcgov.com/developmentreview/files/electronic submittal requirements and file naming standards_v1_8 1 19.pdf?1566857888. File names should begin with the file type, followed by the project information, and round number. Example: UTILITY PLANS_PROJECT NAME_PDP_Rd2.pdf Comment Number: 4 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: Resubmittals are accepted any day of the week, with Wednesday at noon being the cut-off for routing the same week. When you are ready to resubmit your plans, please notify me advanced notice as possible. Comment Number: 5 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: Temporary Service Changes - City of Fort Collins Development Review In order to continue providing thorough reviews and giving every project the attention it deserves, the City of Fort Collins is implementing temporary changes in how we serve our development customers. As you may be aware, we are experiencing staff shortages in a number of key departments, which has begun to impact the timeliness of our reviews. We recognize that development and construction play a critical role in our community’s vibrancy and economic recovery, and we have been exploring options for mitigating impacts to our customers. As a result, we will be making some temporary service changes. Beginning Monday May 10th one additional week of review time will be added to all 1st and 2nd round submittals (increase from 3 weeks to 4 weeks). Comment Number: 6 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: LUC 2.211 Lapse, Rounds of Review: Applicants, within one hundred eighty (180) days of receipt of written comments and notice to respond from the City on any submittal (or subsequent revision to a submittal) of an application for approval of a development plan, shall file such additional or revised submittal documents as are necessary to address such comments from the City. If the additional submittal information or revised submittal is not filed within said period of time, the development application shall automatically lapse and become null and void. Comment Number: 7 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: LUC 2.211(D) Project Development Plan and Plat. Following the approval of a project development plan and upon the expiration of any right of appeal, or upon the final decision of the City Council following appeal, if applicable, the applicant must submit a final plan for all or part of the project development plan within three (3) years... If such approval is not timely obtained, the project 3 development plan (or any portion thereof which has not received final approval) shall automatically lapse and become null and void. Comment Number: 8 Comment Originated: 06/29/2021 All of the above comments are for information only, no action is necessary 06/29/2021: FOR HEARING: The proposed development project is subject to a Type 1 Review. The decision maker for your project will be an Administrative Hearing Officer at a public hearing. For the hearing, we will formally notify surrounding property owners within 800 feet (excluding public right-of-way and publicly owned open space). As your Development Review Coordinator, I will assist with preparing the mailing and coordinating the hearing date with your team. Comment Number: 9 Comment Originated: 06/29/2021 06/29/2021: FOR HEARING: All "For Hearing" comments need to be addressed and resolved prior to moving forward with scheduling the Hearing. Staff would need to be in agreement the project is ready for Hearing approximately 3 5 weeks prior to the hearing. Hearing has been completed, no action is necessary Department: Planning Services Contact: Clark Mapes, 970-221-6225, cmapes@fcgov.com Topic: General Comment Number: 1 Comment Originated: 06/29/2021 06/29/2021: It will be helpful for you to be familiar with Land Use Code Section 3.8.13, easily found online. Comment Number: 2 Comment Originated: 06/29/2021 06/29/2021: FOR HEARING: Staff is assuming that this is a collapsing telescoping pole design as required under Land Use Code Section 3.8.13(C) (1), Setbacks. Such a pole design must be stamped by a licensed structural engineer. Here's that standard: With respect to a monopole, the setback of the facility from the property lines shall be one (1) foot for every foot of height. However, to the extent that it can be demonstrated that the structure will collapse rather than topple, this requirement can be waived by the Director. In addition, the setbacks for ground-mounted wireless telecommunication equipment shall be governed by the setback criteria established in Articles 3 and/or 4. Comment Number: 3 Comment Originated: 06/30/2021 06/30/2021: FOR HEARING: Please provide a context diagram or explanation of other structures in the vicinity that have been considered for colocation, which have led to the conclusion that a new structure is necessary. Comment Number: 5 Comment Originated: 06/30/2021 06/30/2021: For discussion at the 9.22 meeting: It appears that the proposed 4 location may has intrinsic problems of access and existing stormwater detention pond constraints, however, if the proposal were to go forward, an important next step would be to explore possibilities for the design of the facility. A slimline pole would seem to be most compatible with the context, which includes a number of other poles for the abutting electric substation and the transmission line poles along the railroad to the east. To fit into the context the pole should not exceed the height of the tallest existing poles – 75 feet in the case of the transmission line poles. Comment Number: 6 Comment Originated: 06/30/2021 06/30/2021: For the meeting: A photo rendering(s) is needed to illustrate the visual effect of the new pole in the context. Question for the meeting: did we see illustrations in a previous inquiry about this location? I don’t see anything in the 2.6.2020 conceptual review materials. Comment Number: 8 Comment Originated: 09/29/2021 09/29/2021: FOR HEARING: The switch from a monopole being feasible, to now being no longer feasible, results in a pole with maximum visual impact. The industrial and substation context is understood as far as helping to justify the utilitarian design. See #9 below. Comment Number: 9 Comment Originated: 09/29/2021 09/29/2021: FOR HEARING: We should have an updated narrative description of the project. Include: Mention your search for feasible locations and the lack of any others, such as on buildings or other existing structures. Include the explanation you gave at the 9.22 meeting as to why a slimline monopole is no longer feasible following previous agreement to use that design. The previous iteration of this facility was to be a monopole, and we do see monopoles being installed elsewhere in the city? Has it really become impossible? -- the narrative should explain this. Also, include what you said about the height in relation to the PRPA transmission line to the east - did you say that those poles are 104' tall? Anyway, include the explanation you gave at the meeting. (Staff had the idea that the tallest poles in the area, the transmission poles, were 75'.) Include explanation of whether the proposed pole can accommodate colocation of any additional equipment by any other wireless telecommunication provider? A local code standard requires that any application for the approval of a plan for the installation of wireless telecommunication facilities or equipment shall include documentation of the applicant's good faith efforts toward such cooperation. All of the above items were addressed in the Public Hearing, a copy of the approval letter is attached to the narrative. Department: Engineering Development Review Contact: Dave Betley, 970-221-6573, dbetley@fcgov.com Topic: General Comment Number: 20 Comment Originated: 09/19/2021 5 09/19/2021: FOR APPROVAL: The proposed easements did not appear to be submitted. Will the applicant be recording these easements or does the applicant want the City to help record the documents. The easements will need to be recorded before the plans can be signed. The easement will be recorded, this item was waiting for zoning approval to ensure the easement did not change. Since there were no changes to the easement, we will proceed, and any help will be appreciated. Department: Traffic Operation Contact: Steve Gilchrist, 970-224-6175, sgilchrist@fcgov.com Topic: General Comment Number: 1 Comment Originated: 06/28/2021 06/28/2021: FOR INFORMATION: The addition of a wireless telecommunications facility on this site is not anticipated to generate traffic or trips. The Traffic Impact Study is waived. This is for information, no action is necessary. Department: Stormwater Engineering Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com Topic: General Comment Number: 7 Comment Originated: 06/29/2021 09/21/2021: FOR FINAL PLAN: The drainage easement will need to encompass full detention area within the 100-yr water surface. Any piers within this area will need to be removed from easement and the platform over the detention pond will require a maximum vertical elevation for the drainage easement. 06/29/2021: The drainage easement exhibit is missing from the PDF file: “Dedication of Easement Agreement.pdf”. Please submit the drainage easement exhibit for our review and comment. (Thank you for dedicating this easement that was not recorded previously!) The revised survey will provide this information. Upon approval of the plans, this will be dedicated. Comment Number: 8 Comment Originated: 06/29/2021 09/21/2021: FOR INFORMATION ONLY: The pond volume will need to be re-certified post construction. This will be in the form of a Site and Drainage Certification form by a Colorado PE. This will need to be supported by ground survey. This is for information; no action is necessary. Comment Number: 11 Comment Originated: 09/21/2021 09/21/2021: FOR FINAL PLAN: Since there will be construction in the detention area, this project will require a 6 formal Utility Plan set meeting City and LCUASS requirements and stamped by a Colorado PE. Please review the requirements in appendix E here: https://www.larimer.org/urban-area-street-standards-2021 The plans will be sent to Larimer County as part of a separate review process, we will submit once the easement issues have been resolved. Comment Number: 12 Comment Originated: 09/21/2021 09/21/2021: FOR INFORMATION ONLY: Please do not lock or password protect the submitted PDF files. This is for information, no action is necessary. Comment Number: 13 Comment Originated: 09/22/2021 09/22/2021: FOR FINAL PLAN: See redlines on drainage report and utility plans. Department: Light And Power Contact: Austin Kreager, 970-224-6152, akreager@fcgov.com Topic: General Comment Number: 2 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: The additional load proposed on the transformer will require the transformer to be upgraded to a 150kVA transformer at the project's expense. Comment Number: 3 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: Please be aware of our capacity fees as it relates to the addition of two new meters onto our system. The capacity fee calculator can be found at: https://www.fcgov.com/utilities/business/builders-and-developers/plant-investme nt-development-fees/electric-development-fee-estimator?id=3 Comment Number: 4 Comment Originated: 06/29/2021 06/29/2021: INFORMATION: You may contact Austin Kreager, project engineering if you have questions. (970) 224-6152. You may reference Light & Power’s Electric Service Standards at http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar ds_FINAL_18November2016_Amendment.pdf You may reference our policies, development charge processes, and use our fee estimator at http://www.fcgov.com/utilities/business/builders-and-developers This is for information, no action is necessary. Department: PFA Contact: Marcus Glasgow, 970-416-2869, marcus.glasgow@poudre-fire.org Topic: General Comment Number: 4 Comment Originated: 09/17/2021 09/17/2021: FOR FINAL: There is an inconsistency with the proposed EAE. 7 C1 shows 14 feet and C1.1 shows 20 feet. The scaled measurements do not reflect what is noted on either plan. The Land Survey sheets also show the West EAE stopping midway through the parking lot. This must extend to the south of the parking lot and align with civil set. This has been corrected and included in the final survey. Department: Building Services Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com Topic: Building Insp Plan Review Comment Number: 1 Comment Originated: 06/28/2021 06/28/2021: Construction shall comply with adopted codes as amended. Current adopted codes are: 2018 International Building Code (IBC) with local amendments 2018 International Existing Building Code (IEBC) with local amendments 2018 International Energy Conservation Code (IECC) with local amendments 2018 International Mechanical Code (IMC) with local amendments 2018 International Fuel Gas Code (IFGC) with local amendments 2018 International Swimming Pool and Spa Code (ISPSC) with local amendments 2018 International Plumbing Code (IPC) as amended by the State of Colorado 2020 National Electrical Code (NEC) as amended by the State of Colorado Copies of current City of Fort Collins code amendments can be found at fcgov.com/building. Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017. Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF. Frost Depth: 30 inches. Wind Loads: Risk Category II (most structures): · 140mph (Ultimate) exposure B or · Front Range Gust Map published by The Structural Engineer's Association of Seismic Design: Category B. Climate Zone: Zone 5 Energy Code: 2018 IECC commercial chapter. INFORMATIONAL ITEMS: · Commercial occupancies must provide 10ft setback from property line and 20 feet between other buildings or provide fire rated walls and openings per chapter 6 and 7 of the IBC. · City of Fort Collins amendments to the 2018 IBC require a full NFPA-13 sprinkler system per IBC chapter 9 or when building exceeds 5000 sq.ft. (or meet fire containment requirements). · Prescriptive energy compliance with increased insulation values is required for buildings using electric heat. · A City licensed commercial general contractor is required to construct any new commercial structure. Building Permit Pre-Submittal Meeting: Please schedule a pre-submittal meeting with Building Services for this project. 8 Pre-Submittal meetings assist the designer/builder by assuring, early on in the design, that the new projects are on track to complying with all of the adopted City codes and Standards listed below. The proposed project should be in the early to mid-design stage for this meeting to be effective. Applicants of new projects should email rhovland@fcgov.com to schedule a pre-submittal meeting. Applicants should be prepared to present site plans, floor plans, and elevations and be able to discuss code issues of occupancy, square footage, type of construction, and energy compliance method being proposed. Comment Number: 2 Comment Originated: 06/28/2021 06/28/2021: Telecommunications tower must meet IBC section 3108 and TIA-222. All pertinent building codes will be adhered to on the final building plans. Department: Technical Services Contact: Jeff County, 970-221-6588, jcounty@fcgov.com Topic: General Comment Number: 1 Comment Originated: 06/29/2021 09/20/2021: INFORMATION ONLY: Unless required during PDP, a complete review of all plans will be done at FDP. 06/29/2021: INFORMATION ONLY: Unless required during PDP, a complete review of all plans will be done at FDP. This is for information, no action is necessary. Zoning Approval Letter     1 CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION HEARING DATE: January 24, 2022 PROJECT NAME: 4518 Innovation Drive Wireless Telecommunications Facility CASE NUMBER: PDP 210010 LESSEE/APPLICANT: Vertical Bridge 750 Park of Commerce Drive, Ste. 200 Boca Raton, FL 33487 APPLICANT REPRESENTATIVE: Mike Bieniek, AICP LCC Telecom Services 10700 W. Higgins Rd., Ste. 240 Rosemont, Illinois 60018 HEARING OFFICER: Lori B. Strand PROJECT DESCRIPTION AND BACKGROUND: This is a request for approval of a Project Development Plan for an 85-foot tall cell tower to be built at the rear southeast corner of 4518 Innovation Drive, Fort Collins (Parcel No. 8731406010) (the “Application”). The Application proposes to build the cell tower and accessory equipment adjacent to the existing Rocky Mountain Archery building and within an approximately 565 square foot leased area as more particularly shown in the site plan set included with the Application (the “Subject Property”). The Application provides that access to and utilities for the Subject Property will be provided in easements. The Subject Property is zoned Harmony Corridor (HC) Division 4.26 of the City of Fort Collins Land Use Code (“LUC”), within the Basic Industrial Non-Retail Activity Center land use designation. Wireless telecommunications facilities are permitted by zoning, subject to administrative review. No requests for modifications of standards or for alternative compliance are requested as part of the Application. Development Review Staff recommends approval of the Application with conditions. 2 The Subject Property is located within the Golden Meadows Business Park. The zoning and land uses surrounding the Subject Property are: North South East West Zoning HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center HC, Harmony Corridor, Basic Industrial Non-Retail HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center Land Use Supply/distribution warehouse/office next door, and a converted large light industrial building now used for a charter school Supply/distribution warehouse/office Electric substation Supply/distribution warehouse/office Additional background information and analysis of LUC compliance are detailed in the Development Review Staff Report, as revised for the public hearing, attached to this decision as ATTACHMENT A (the “Staff Report”) and incorporated herein by reference. SUMMARY OF DECISION: Approved with conditions. ZONE DISTRICT: Harmony Corridor (HC), within the Basic Industrial Non- Retail Activity Center land use designation. HEARING: The Hearing Officer opened the virtual public hearing on January 24, 2022 at approximately 6:00 PM. At the public hearing, the Hearing Officer reviewed the Order of Proceedings and Rules of Conduct for Administrative Hearings with the Applicant and members of the public present. EVIDENCE: Prior to or at the hearing, the Hearing Officer accepted the following documents as part of the record of this proceeding: 1. Staff Report 2. Applicant Narrative 3. Applicant Explanation of Infeasibility of Slim Pole 4. Site Plan Set 5. Photo Simulations Excerpted from Narrative 6. Fall Zone Collapse Letter 7. Photo Simulations Revised for Hearing with Monopine 8. Staff Presentation for Hearing 3 9. Copy of written notice of virtual public hearing, dated January 7, 2022, and excel list of recipients 10. Order confirmation and affidavit of publication of notice in the Coloradoan, confirming published notice occurred on January 7, 2022. 11. Rules of Conduct for Administrative Hearings 12. The City’s Comprehensive Plan, the City’s Wireless Telecommunications Master Plan, the LUC, and the formally promulgated polices of the City are all considered part of the record considered by the Hearing Officer. TESTIMONY: The following persons testified at the virtual public hearing: From the City: Clark Mapes, City Planner From the Applicant: Mike Bieniek, LCC Telecom Services Tim Keyser, T-Mobile radio frequency engineer From the public: None. Mr. Mapes and representatives for the Applicant testified during the hearing that the proposed cell tower will replace an antennae array previously located on a Platte River Power Authority utility pole and provide service to residents and businesses in the area of the tower as well as to those traveling through the area. Mr. Mapes and representatives of the Applicant testified that the Applicant sought, but was unsuccessful, in finding an alternative location where the cell tower or antennae array could be stealthily incorporated into an existing building or structure. Testimony was also provided regarding the City’s and Applicant’s consideration of alternative designs for the cell tower including a slim-pole form, a monopine, and a monopole. The plan set included in the Application includes a monopole design for the cell tower. However, Mr. Mapes and Mr. Bieniek testified at the hearing that said parties had agreed shortly before the hearing that the monopole cell tower should be redesigned as, and the plan set should be amended to provide for, a monopine cell tower in order to improve the cell tower’s compatibility with the surrounding environment (consistent with the requirements of LUC §3.8.13(C)(2)). To this end, said parties testified to their agreement that a condition be imposed on the approval of the Application that the plan set be revised to provide for an 85-foot monopine cell tower with antennae array(s) that meet the design details of the monopine and antennae array(s) recently approved by the City for location at Summit View Church on West Drake Road. Mr. Mapes testified that the 85-foot height limitation for the cell tower was critical to City staff’s recommendation of approval (with conditions) of the Application. Mr. Mapes emphasized that the 85-foot height is warranted only due to the industrial setting with nearby electric poles of similar height and is not warranted by consistency with nearby trees, and that any greater height would defeat the purpose of the monopine concealment. In response to Hearing Officer questions, said parties confirmed that, except for replacement of the tower from an 85-foot monopole to an 85-foot monopine and minor changes to the plan set that may 4 be necessary to accommodate the same, the plan set presented to the Hearing Officer in the Application would remain the same, including the site plan, the platform design and location, the design and location of the paved accessway, and required access and utility easement locations. Mr. Bieniek confirmed in his testimony that while the cell tower will initially include an antennae array for T-Mobile, the cell tower will have the capacity for co-location of other facilities and equipment.   The public hearing was closed at approximately 6:50 P.M. on January 24, 2022. FINDINGS 1. The preceding summary of the testimony of Mr. Mapes and representatives of the Applicant are incorporated as findings of the Hearing Officer. 2. Evidence presented to the Hearing Officer established the fact that notice of the public hearing was properly posted, mailed and published. 3. As required by City Council Ordinance 079, Series 2020 (the "City Ordinance"), the Hearing Officer, in consultation with City staff, determined that it was desirable to conduct the hearing on the Application by remote technology so as to provide reasonably available participation by parties-in-interest and by the public, consistent with the requirements of the City Ordinance, because meeting in person would not be prudent for some or all persons due to a public health emergency. 4. Based on testimony provided at the public hearing and a review of the materials in the record of this case, the Hearing Officer concludes as follows: A. The Application complies with the applicable procedural and administrative requirements of Article 2 of the LUC. B. The Application complies with the applicable General Development Standards contained in Article 3 of the LUC provided that the Applicant complies with: 1. Condition 1 set forth in the Decision below to satisfy the standard set forth in Section 3.8.13(C)(1) of the LUC. 2. Condition 2 set forth in the Decision to satisfy the standard set forth in Section 3.8.13(C)(2) of the LUC. C. The Application complies with HC zoning and the applicable standards in Division 4.26 of the LUC. 5. The Application’s satisfaction of the applicable Article 2, 3 and 4 requirements of the LUC is sufficiently detailed in the Staff Report and the testimony and materials in the record. 5 DECISION Based on the findings set forth above, the Hearing Officer approves the 4518 Innovation Drive Wireless Telecommunication Facility PDP 210010, subject to the Applicant’s compliance with the following conditions: Condition 1: Prior to final plan approval, the Applicant shall provide a fall zone letter from the monopine manufacturer, signed by a licensed engineer, confirming to City staff’s satisfaction that there is either no threat that the monopine cell tower will topple or collapse or that the tower will collapse rather than topple consistent with LUC Section 3.8.13(C)(1). Condition 2: Prior to final plan approval, the Applicant shall redesign the cell tower in the Application from an 85-foot monopole design to an 85-foot monopine design using the design details approved by the City for the monopine located at Summit View Church on West Drake Road. Such design details shall include branch density, tufting, bark texture, pole color, and color and texture on the antennas. DATED this 4th day of February, 2022. ___________________________________ Lori B. Strand Hearing Officer 6 ATTACHMENT A Staff Report 4518 Innovation Drive Wireless Telecommunication Facility (PDP 210010) Development Review Staff Report Planning Services Fort Collins, Colorado 80521 p. 970-416-4311 f. 970.224.6134 www.fcgov.com Administrative Hearing: January 24, 2022 4518 Innovation Drive Wireless Telecommunication Facility #PDP210010 Summary of Request This is a request for a Project Development Plan (PDP) for an 85- foot cell tower on a lot within an existing business park along Harmony Road. Zoning Map Next Steps If approved by the Hearing Officer, the applicant will be eligible to proceed to filing of final plans and then to a building permit. Site Location 4518 Innovation Dr., on the second lot north of Harmony Road, in the Golden Meadows Business Park subdivision Parcel ##8731406010 Zoning Harmony Corridor (HC) zone district, within the Basic Industrial Non-Retail Employment Activity Center land use designation in the HC zone Owner Vertical Bridge - Lessee 750 Park of Commerce Drive Ste. 200 Boca Raton, FL 33487 Applicant/Representative Mike Bieniek, AICP LCC Telecom Services 10700 W. Higgins Rd., Ste. 240 Rosemont, Illinois, 60018 Staff Clark Mapes, City Planner p. (970) 221-6225 e. cmapes@fcgov.com Contents 1. Project Introduction .................................... 2 2. Land Use Code Article 2 Procedural Requirements ............................................ 4 3. Land Use Code Article 3 - Applicable Standards .................................................. 4 4. Land Use Code Article 4 – Applicable Standards .................................................. 7 5. Findings of Fact/Conclusion ...................... 7 6. Recommendation ....................................... 8 7. Attachments ............................................... 8 Staff Recommendation Approval of the PDP, with a condition. . Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 2 of 8 Back to Top 1. Project Introduction PROJECT DESCRIPTION • This is a request for a Project Development Plan (PDP) to construct an 85-foot tall wireless monopole facility (cell tower) for use by T-Mobile at the rear southeast corner of the Rocky Mountain Archery building which exists on the subject lot. • The antenna array is a typical 3-axis triangular array approximately 17 feet wide, with no concealment or “stealth” design. • The location is adjacent to an electric substation and a large power transmission line. Those adjacent facilities create a setting that is already characterized by an assortment of similar-height poles. The image below is from the applicants’ narrative and shows the public view with the highest visibility of adjacent poles, on westbound Harmony Road. The antennas atop the powerline pole on the left are no longer there; the proposal is related to replacing lost coverage due to their removal. Westbound Harmony Road View with Proposed Facility • The subject lot is in a business park with supply/distribution /light industrial buildings. • The specific location in the rear of the lot is an existing stormwater detention area. A raised platform has been designed to accommodate equipment and walkway access through design iterations with stormwater utility staff to accommodate the facility without harm to the detention function. • Needed access easements are shown on the plans. Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 3 of 8 Back to Top SITE CHARACTERISTICS 1. Surrounding Zoning and Land Use North South East West Zoning HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center HC, Harmony Corridor, Basic Industrial Non- Retail Activity Center HC, Harmony Corridor, Basic Industrial Non-Retail Activity Center Land Use Supply/distribution warehouse/office next door, and a converted large light industrial building now used for a charter school Supply/distribution warehouse/office Electric substation Supply/distribution warehouse/office 2. Site History The land was annexed in 1977 as part of the Harmony Annexation. The site is within the Golden Meadows Business Park approved in 2003. OVERVIEW OF MAIN CONSIDERATIONS IN STAFF’S REVIEW Location. This was the first consideration starting about two years ago. Staff encouraged the applicants to seek a different location that could possibly offer more opportunity for a “stealth” facility to be incorporated into an existing structure. Staff’s understanding is that applicants have explored other potential alternatives for a year or more. No other property owners in the area have been interested according to the applicants. Furthermore, few buildings in the adjacent area are more than a single story, so suitable architectural opportunities appear to be very limited. The specific location on the lot involved technical issues of vehicle access, utility easements and a platform for ground equipment over an existing stormwater detention area on the lot. Those engineering issues were resolved with staff support. Appearance. After the question of location was resolved, the next fundamental consideration has been consistency with the surrounding “architectural character” and “natural environment” as required by a standard, subsection 3.8.13(C)(2). This is a basic consideration that is not resolved with staff support at the time of hearing. It is the primary consideration for the City in its local government role. For the hearing, staff is recommending a condition of approval for this aspect of the facility. Staff initially commented that a pole-form antenna array should be used because of the opportunity for such a facility to be consistent and blend with the numerous metal poles in the adjacent substation and transmission line. Staff sees numerous examples of this approach to cell tower facilities with ‘unipoles’, cylinder shaped canisters, or slimline arrays with antennas tucked tight to the pole. Also, staff has spoken with a concealment engineering firm that provides these kinds of solutions. A recently adopted Wireless Telecommunications Master Plan for the City calls fo r concealment or semi- concealment of antenna arrays; and it includes a variety of example solutions that could comply with code standards. That plan document is attached. Page 5, 10, page 32, page 59, and pages 67 -129 are notably pertinent to the issue. The applicants have stated a slim pole-form approach is no longer feasible in a situation like this because of increasing demands from smartphones. They explain that corresponding increases in equipment are needed to maintain reliable service, and this generates more heat, which makes the slim configurations unworkable. Page 16 of the Applicants Narrative, and the 2-page Explanation of Infeasibility (attachments 1 and 2) summarize the applicants’ contentions. The applicants also contend that the proposed facility is consistent with the character of the area given the prominence of the abutting electric substation and powerline with metal poles and large equipment. Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 4 of 8 Back to Top Staff acknowledges this contention. However, the simulations show how the array is visually appar ent and staff was not able to find that a complete lack of stealth/concealment is warranted by the industrial setting. Staff is not able to confirm or deny the applicants’ contentions from a wireless engineering standpoint. However, because of this specific location, in a business park, abutting a large electric substation with poles of similar height, staff finds that the visual sensitivity of this proposal is relatively low, and because of that, staff finds that an alternative to the pole-form approach using a monopine is supportable to provide concealment. The applicants do not object, and the monopine allows for the array(s) as desired from an RF engineering standpoint. For the hearing, staff recommends approval of the proposed facility with a condition that prior to Final Plan approval, the tower will be redesigned as a monopine for concealment of the antenna array(s), using the design details used on the most recent monopine installation in the City, including branch density, tufting, and color and on the pole and antennas. Lack of Setback. A basic consideration has been a requirement that a tower be engineered to collapse rather than topple in an unlikely catastrophic event, if the tower is not set back from property lines by a distance equal to the height. The applicants are providing documentation signed by a licensed engineer regarding this issue. Access. A technical consideration has involved confirmation of necessary access and utility easements across the existing development. 2. Land Use Code Article 2 Procedural Requirements PROJECT DEVELOPMENT PLAN PROCEDURAL OVERVIEW 1. Conceptual Review – CDR 200009 A conceptual review meeting was held on February 6, 2020. 2. Neighborhood Meeting A neighborhood meeting was not required, nor held, for this Type 1 review process. 3. Submittal The project was submitted on June 4, 2021. The project was routed to all reviewing departments with two rounds of review conducted to reach the proposed plan. 4. Notice (Posted, Written and Published) Posted notice: June 16, 2021, Sign #640 Written notice: September 15, 2021, 283 letters sent. Published Notice: October 22, 2021, Confirmation #4966214. 3. Land Use Code Article 3 - Applicable Standards Because the plan involves a facility on an existing fully developed property in a fully developed business park, the only applicable development standards in Land Use Code are those in Section 3.8.13 as reviewed below. SECTION 3.8.13 – WIRELESS TELECOMMUNICATION Applicable Code Standard Summary of Code Requirement and Analysis Staff Findings Co-location This standard requires that a facility or owner or lessee must not attempt to exclude any other wireless telecommunication provider from using the same Complies Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 5 of 8 Back to Top 3.8.13(B) structure or location. Applicants shall cooperate in good faith to achieve co- location of wireless telecommunication facilities and equipment. Any application for the approval of a plan for the installation of wireless telecommunication facilities or equipment shall include documentation of the applicant's good faith efforts toward such cooperation. • The plans indicate space for potential future antennas by others; and the applicants narrative acknowledeges this requirement. Staff finds that if an alternative stealth design is proposed in Final Plans in response to the proposed condition of approval, and the alternative precludes this co-location, this documentation fulfills the requirement. Setbacks 3.8.13(C)(1) This subsection requires towers to be set back from property lines by one foot for every foot of height unless it can be demonstrated that the structure will collapse rather than topple, in which case this requirement can be waived by the Director. • A fall zone letter from the pole manufacturer, signed by a licensed engineer, is attached and explains that there is no threat of collapse due to engineering of the pole. It states that in the unlikely event of failure, the monopole is designed to buckle at a designated point rather than collapse or fall. The top portion would bend down onto the bottom portion of the tower and the cabling inside the tower would act like a hinge to hold the upper portion in place until it could be repaired. The foundation is designed based on the existing soil conditions for the site. A geotechnical study determines the type of footing and how deep it must go into the ground. Staff interprets this to indicate no threat to the abutting electric substation or the property next door to the south. Complies Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 6 of 8 Back to Top • At ground level, all fencing and equipment is set back from the side lot line further than the existing building, with six feet of landscape area for shrub screening. Wireless Telecomm Facilities Subsection 3.8.13(C)(2) This subsection requires wireless telecommunication facilities to be “consistent with the architectural style of the surrounding architectural environment”. Considerations are to include “materials, roof form, scale, mass, color, texture and character”. Facilities must also be “compatible with the surrounding natural environment.” Staff interprets the standard to invoke the built environment in its totality inclusive of building architecture, landscape architecture, and infrastructure design, with the purpose to mitigate visual impact on the cityscape and skyline. In this particular case, the adjacent electric substation and power transmission line to the east comprise an assortment of steel poles similar in height to the proposed tower, as well as other large equipment within the substation . The site is within the Golden Meadows Business Park in which t he architectural environment comprises light industrial and supply/distribution buildings. A number of trees including pines exist in the landscaped setback along Harmony Road, and a few trees exist on nearby properties in the business park. The applicants contend that the proposed steel tower and antenna array is consistent with the assortment of poles and equipment in the abutting electric substation and the nearby power transmission line to the east. However, staff finds that the contrast in form of the high antenna array prevents it from blending with the linear form of the poles in the substation and the adjacent power transmission line. • The applicants and staff have agree to revise the tower to a monopine tower to provide concealment of the antennas and associated equipment. Staff recommends a condition of approval as explained in other sections of this report. Complies With a Condition Landscaping subsection 3.8.13(C)(4) This standard requires landscaping based on the unique nature of wireless telecommunication facilities. Landscaping may be required to achieve a total screening effect at the base of such facilities to screen the mechanical characteristics. A heavy emphasis on coniferous plants for year-round screening may be required. • The location is a rear area with very low public visibility between commercial/light industrial buildings in the business park. Nevertheless, shrub plantings are provided to as a buffer along the ground equipment. Complies Stealth Technology subsection 3.8.13(C)(15) This standard requires that to the extent reasonably feasible, the applicant shall employ "stealth technology" so as to convert the wireless telecommunication tower into wireless telecommunication equipment integrated into an existing structure, as the best method by which to mitigate and/or camouflage visual impacts. The standard mentions examples such as using grain bins, silos or elevators, church steeples, water towers, clock towers, bell towers, false penthouses or other similar "mimic" structures. Complies Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 7 of 8 Back to Top • As explained previously in discussion of main considerations, a search of possible suitable structures found none. DIVISION 3.3 - ENGINEERING Applicable Code Standard Summary of Code Requirement and Analysis Staff Findings Plats and Easements Section 3.3.1 This Section requires dedication of easements as necessary for drainage, utilities, and access as needed to serve the development. A number of easements are needed on for access, drainage, and temporary construction access on abutting property. • The plan set shows necessary easements, with the easement documents to be recorded in conjunction with approval of Final Plans. Complies 4. Land Use Code Article 4 – Applicable Standard Article 4 of the Land Use Code contains standards for the various zoning districts throughout the City. The subject lot is zoned Harmony Corridor (HC) Division 4.26 of the Land Use Code, within the Basic Industrial Non-Retail Activity Center land use designation. The purpose of the zone is to implement the design concepts and land use vision of the Harmony Corridor Plan -- that of creating an attractive and complete mixed-use area with a major employment base. The proposed wireless telecommunication facility is permitted subject to review by a Hearing Officer at a public hearing (Type 1 review). No other zone district standards pertain to the facility. 5. Findings of Fact/Conclusion In evaluating the request for the 4518 Innovation Drive Wireless Telecommunication Facility #PDP210010, staff makes the following findings of fact: 1. The PDP complies with process requirements located in Division 2.2 – Common Development Review Procedures for Development Applications of Article 2 – Administration. 2. The PDP complies with pertinent standards located in Article 3 – General Development Standards, with the exception of subsection 3.8.13(C)(2), which is addressed in the conditional recommendation by staff. 3. The proposed Wireless Telecommunication Facility is a permitted use subject to Type 1 review and hearing in the Harmony Corridor Zone District in Article 4 – Districts. 4. The 85-foot height is the absolute maximum permissible height; the 85-foot monopine will stand out in contrast to the surrounding environment but staff finds that it is warranted only due to the industrial setting with nearby electric poles of similar height and not warranted by consistency with nearby trees; and any greater height would defeat the purpose of the monopine concealment. Administrative Hearing 4518 Innovation Drive WTF | PDP210010 Monday, January 24, 2022 | Page 8 of 8 Back to Top 6. Recommendation Staff recommends that the Hearing Officer approve the 4518 Innovation Drive Wireless Telecommunication Facility Project Development Plan #PDP210010 based on the Findings of Fact and supporting explanations found in the staff report with the following condition: Prior to Final Plan approval, the tower will be redesigned as a monopine for concealment of the antenna array(s), using the design details that were used on the most recent monopine installation in the City, including branch density, tufting, and color on the pole and color and texture on the antennas. 7. Attachments 1. Applicants Narrative 2. Applicants Explanation of Infeasibility of Slim Pole 3. Site Plan set 4. Photo Simulations – Original Proposal 5. Photo Simulations – Revised for Hearing with Monopine 6. Fall Zone Collapse Letter Fall  Zone Letter       1426 North Marvin Street #101 ‐ Gilbert, AZ 85233  480‐664‐9588 Phone ‐ 480‐664‐9850 Fax    March 14, 2022    Steven Gosnell . Vertical Bridge 750 Park of Commerce Dr. Boca Raton, FL 33487 (770) 331-7524   Subject:    Telecommunication Tower Fall Zone Letter    Tower Owner:    Vertical Bridge       Site Name:     Rocky Mountain Archery  Site Number:          US‐CO‐5082  Larson Number:  544732    Engineering Firm Designation:  Pinnacle Consulting, Inc.      Site Data:    4518 Innovation Dr., Fort Collins, CO 80525       Larimer County       40° 31' 27.76” N, 105° 02' 43.65" W       ± 85’ Monopine Tower w/ a 20’ Ext.    Dear Steven,     This letter is intended to address the 50’ Fall Zone Requirement for the proposed monopine  telecommunications tower at the above noted site.     The tower was designed in accordance with the 2018 International Building Code and the adopted by  reference standard TIA‐222‐H, Structural Standard for Antenna Supporting Structures and Antennas.    The following structural design criteria were used in analysis:   Wind Speed: 140 mph (Ultimate – 3 second gust)   Service Wind Speed: 60 mph (Ultimate – 3 second gust – Deflection limits only)   Structure Class II   Exposure B   Topographic Category 1   Ice: 0.25” w/ 50 mph wind gust speed (Ignored per TIA‐222‐H 2.6.4)    At your request, we have designed the tower for a fall zone radius of 50 feet.  Our approach to this  request was to ensure that the point of maximum stress in the tower occur in the upper 50’ of the  structure.  In this case, the maximum demand to capacity ratio of 96.8% in the upper pole section which  has a length of 25’ and a 20’ Future Extension. The remaining structure is designed with a maximum  demand to capacity ratio at or below 80%.  In the improbable event of a failure, it is likely to occur in the  top 45’ of the structure thereby satisfying request of a 50’ fall zone radius.          March 14, 2022  85’ Monopine Tower w/ 20’ Future Ext. Fall Zone Letter Larson #544732  Page 2  1426 North Marvin Street #101 / Gilbert, AZ 85233 / 480‐664‐9588  Please note that our approach to the fall zone request is not codified in the references above nor is the  phrase ‘fall zone’ itself a codified term.  While we believe that our approach is a rational attempt to  address this request, building codes do not address failure mechanics and it is difficult to predict the  behavior of failing structures.  A failing or falling tower sections could detach and be impacted by wind  forces causing bouncing or rolling and pushing the section outside the fall zone.  Non‐structural  components attached to the pole structure are outside the scope of our design.  If not properly designed  and attached, these components could detach and fall outside the fall zone at or below code specified  design criteria.    We appreciate the opportunity to provide these services.  Please let us know if you have any questions  or comments.  Respectfully submitted by:  John S. Weaver, P.E.  Colorado License No. PE.0055672 Pinnacle Consulting, Inc.  john.weaver@pinnacleco.net  602‐418‐6802  3/14/22 Photo Simulations     ROCKY MOUNTAIN ARCHERY SITE SIMULATION MAP Site Photograph # Site 12 3 4 US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPOLESIMULATION View #2 from East Harmony Roadapprox. 350ft. south-southeast of site Existing View US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPINESIMULATION View #2 from East Harmony Roadapprox. 350ft. south-southeast of site Existing View US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPOLESIMULATION View #3 from Innovation Driveapproximately 225ft. west of site Existing View US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPINESIMULATION View #3 from Innovation Driveapproximately 225ft. west of site Existing View US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPOLESIMULATION View #4 from Innovation Driveapprox. 350ft. north-northwest of site Existing View US-CO-5082ROCKY MOUNTAIN ARCHERY85FT. MONOPINESIMULATION View #4 from Innovation Driveapprox. 350ft. north-northwest of site Existing View Propagation Maps     Existing Indoor Residential Coverage1 MileLTE 2100 MHz -100dBm RSRP Coverage Proposed Indoor Residential Coverage@80’LTE 2100 MHz -100dBm RSRP Coverage1 Mile Site Plans