February 01, 2022
Russ Lee
Ripley Design, Inc
419 Canyon Ave.
Suite 200
Fort Collins, CO 80521
RE: Castle Ridge Group Home, PDP210012, Round Number 4
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Castle Ridge Group Home. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Brandy Bethurem Harras via phone at 970‑416‑2744 or
via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras, 970‑416‑2744, bbethuremharras@fcgov.com
Topic: General
Comment Number: 1
07/15/2021: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone conversations. Thank you!
Comment Number: 2
01/31/2022: FOR FINAL PLAN:
As part of your FDP submittal you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color. When replying to the comment letter please be detailed in
your responses, as all comments should be thoroughly addressed. Provide
reference to specific project plans or explanations of why comments have not
been addressed, when applicable, avoiding responses like noted or acknowledged.
Comment Number: 3
01/31/2022: FOR FINAL PLAN:
Please follow the Electronic Submittal Requirements and File Naming
Standards found at https://www.fcgov.com/developmentreview/files/electronic
submittal requirements and file naming standards_v1_8 1 19.pdf?1566857888.
File names should begin with the file type, followed by the project information,
and round number. Example: UTILITY PLANS_PROJECT NAME_PDP_Rd2.pdf
It may be appropriate to abbreviate some file types, such as Traffic Impact Study to TIS.
*Please disregard any references to paper copies, flash drives, or CDs.
Comment Number: 4
01/31/2022: FOR FINAL PLAN:
Submittals are accepted any day of the week, with Wednesday at noon being
the cut‑off for routing the same week. When you are ready to resubmit your
plans, please notify me advanced notice as possible.
Comment Number: 5
01/31/2022: FOR FINAL PLAN:
Temporary Service Changes ‑ City of Fort Collins Development Review
In order to continue providing thorough reviews and giving every project the
attention it deserves, the City of Fort Collins is implementing temporary
changes in how we serve our development customers. As you may be aware,
we are experiencing staff shortages in a number of key departments, which has
begun to impact the timeliness of our reviews. We recognize that development
and construction play a critical role in our community’s vibrancy and economic
recovery, and we have been exploring options for mitigating impacts to our
customers. As a result, we will be making some temporary service changes.
Beginning Monday May 10th one additional week of review time will be added
to all 1st and 2nd round submittals (increase from 3 weeks to 4 weeks).
Comment Number: 7
01/31/2022: FFOR HEARING ‑ UPDATED:
We are anticipating the project will be heard at the March 2022 Planning and
Zoning Commission. Final applicant materials are due 02/14/2022, the work
session is scheduled for 03/04/2022, and the hearing is scheduled for 03/10/2022.
I will send additional information about the work session and hearing once we
are closer to those dates.
07/15/2021: FOR HEARING:
This proposed project is processing as a Type 2 Development Plan. The
decision maker for Type 2 is the Planning and Zoning (P&Z) Commission. For
the hearing, we will formally notify surrounding property owners within 800 feet
(excluding public right‑of‑way and publicly owned open space). Staff would
need to be in agreement the project is ready for Hearing approximately 3‑5
weeks prior to the hearing. I have attached the P&Z schedule, which has key
dates leading up to the hearing.
Comment Number: 8
07/15/2021: FOR HEARING:
All "For Hearing" comments need to be addressed and resolved prior to
moving forward with scheduling the Hearing. Staff would need to be in
agreement the project is ready for Hearing approximately 3 to 5 weeks prior to the hearing.
Comment Number: 9
01/31/2022: FOR FINAL PLAN:
All plans should be saved as optimized/flattened PDFs to reduce file size and remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be
removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the
PDF file. The default setting is "1" ("on") in AutoCAD. To change the setting
and remove this feature, type "EPDFSHX" in the command line and enter "0".
Read this article at Autodesk.com for more tips on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing‑text‑appears‑as‑Comments‑in‑a‑PDF‑created‑by‑Aut oCAD.html
Comment Number: 10
01/31/2022: FOR FINAL PLAN:
The request will be subject to the Development Review Fee Schedule:
https://www.fcgov.com/developmentreview/fees.php
As noted in the comments, there are additional fees required by other
departments, and additional fees at the time of building permit. The City of Fort
Collins fee schedule is subject to change – please confirm fees before submitting.
Payments can be made by check or credit card.
If paying by check, make payable to City of Fort Collins. This is accepted at the
Development Review Center, 281 N College Ave, Fort Collins, CO 80524 by
mail or can be placed in the blue drop box located at the west side of the
building. Please mark it to my attention and reference the project it is
associated with.
If paying by credit card, I can process the payment over the phone with you.
Credit card payments include a convenience fee of 2% + $0.25 added to all
payments under $2,500.00, and 2.75% added to all payments over $2,500.00.
Comment Number: 11
01/05/2022: INFORMATION:
LUC 2.211(D) Project Development Plan and Plat. Following the approval of a
project development plan and upon the expiration of any right of appeal, or upon
the final decision of the City Council following appeal, if applicable, the
applicant must submit a final plan for all or part of the project development plan
within three (3) years... If such approval is not timely obtained, the project
development plan (or any portion thereof which has not received final approval)
shall automatically lapse and become null and void.
Department: Planning Services
Contact: Kai Kleer, 970‑416‑4284, kkleer@fcgov.com
Topic: General
Comment Number: 14
01/31/2022: FOR HEARING ‑ UPDATED:
Further discussion is needed to finalize the operational plan.
01/03/2022 FOR HEARING ‑ UNRESOLVED:
The operational plan has not been updated in accordance with the previous comment.
09/21/2021 FOR HEARING:
Regarding the Operation Plan, staff would only consider the operation of the facility
under its full occupancy and not a staged approach. The operational plan should really
describe each individual element of traffic (e.g., deliveries, trash, employee 1, 2, 3, mail, etc...).
I've asked Traffic Engineering to provide you with an example that would be appropriate.
From the initial review of the Operational Plan staff will be recommending the following conditions:
"Visiting hours shall be limited from 9AM to 6PM, 7‑days a week"
"Visitation shall be scheduled in a way that limits the impacts to on‑street
parking and staggers traffic in and out of the neighborhood."
"In an effort to mitigate overlap in the need for staff parking during shift changes,
the group home shall provide monetary incentives to encourage: 1) last mile
carpooling from Fossil Creek Park; 2) public transit 3) bicycle ridership"
"Supply, food, and medication delivery shall be limited to certain times of day
that do not overlap employee shift changes and should be limited to 9‑6PM, 7‑days a week"
We realize that these will require some tweaking based on how the Operation
Plan is updated, however, once finalized we will ask that the notes be added to the site plan.
Department: Traffic Operation
Contact: Steve Gilchrist, 970‑224‑6175, sgilchrist@fcgov.com
Topic: General
Comment Number: 2
02/01/2022: FOR HEARING ‑ UPDATED:
Staff will want to see a more detailed operational/parking plan that attempts to
provide a typical daily schedule for various services, deliveries, etc. that will
create site traffic. This should be the basis for an operational plan or standard
operating procedure, that will identify how site traffic will be scheduled/planned
and dictated to minimize traffic impacts and ensure that the number of on‑site
parking spaces is sufficient to prevent overflow parking into the adjacent private drive.
09/21/2021: FOR HEARING:
Thank you for providing the Operational Plan. We would like to get some
additional details with regard to how the facility will operate once it is at full
capacity, with Covid restrictions lifted in order to gauge the impacts of the peak
traffic times for this facility. More information about the staggering of shifts, i.e.
will you have six staff members on site during the shift change? Will deliveries,
doctors visits, be restricted to certain times outside of shift changes?