HomeMy WebLinkAboutFORTY-THREE PRIME - FDP210019 - DOCUMENT MARKUPS - ROUND 2 - UTILITY PLANS (2)COLLEGEAVE. (
U.S.
287)SOUTH LEMAY AVENUECARPENTER ROADAUTUMN RIDGE
ROADBRITTANY DRIVEJULY 2021 I
hereby affirm that these final
construction plans were prepared under
my direct supervision, in accordance with
all applicable City of
Fort Collins and State of Colorado
standards and statutes,respectively; and that
I am fully responsible
for the accuracy of all design.
revisions, and
record conditions that I have noted on these plans.These plans have been reviewed by the City of Fort Collins
for concept only. The review does not imply responsibility by the reviewing department, the City of Fort Collins Engineer, or
the City of Fort Collins for accuracy and correctness of the calculations. Furthermore, the review does not imply that quantities
of items on the plans are the final quantities required. The review shall not be construed for any reason as
acceptance of financial responsibility by the City of Fort Collins for additional quantities of items
shown that
may be
required during
the
construction phase.DISCLAIMER
STATEMENT:CERTIFICATION STATEMENT:VICINITY MAP NORTH PROJECT
DATUM: NAVD88 City of Fort Collins Benchmark 24-94 Northeast corner of East Trilby Rd and Portner Dr., on
top of the
West end of a concrete headwall.ELEV.=
4960.69 City of Fort Collins Benchmark 25-94 Northwest corner of East Trilby Rd. and South Lemay
Ave, on top of the Southeast
edge of the
concrete ring to an electric manhole.ELEV.= 4913.16 Please Note: This plan set is using
NAVD88 for a vertical datum. Surrounding
developments have used NGVD29 Unadjusted for their vertical datums.If NGVD29 Unadjusted Datum is required
for any purpose, the following
equation should be
used:NGVD29 Unadjusted = NAVD88 - 3.19'Basis of Bearings The Basis of Bearings is the North line of the Northeast
Quarter of Section 13-6-69
as bearing
North 88° 11' 32"
West (assumed bearing).
Northern Engineering Project No.
1328-101
Date: August 2018 ORIGINAL FIELD SURVEY BY:PROJECT
BENCHMARKS:CALL 2 BUSINESS DAYS IN ADVANCE BEFORE
YOU DIG, GRADE,
OR EXCAVATE FOR THE MARKING
OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATIONCENTER
OF
COLORADO Know what'sbelow.before you dig.Call R BEING A REPLAT OF LOT 1, PROVINCETOWNE FILING
THREE, LOCATED IN THE NORTHEAST QUARTER OF SECTION 13,TOWNSHIP 6 NORTH, RANGE 69 WEST OF THE 6TH
PRINCIPAL MERIDIAN, CITY
OF FORT
COLLINS, COUNTY
OF LARIMER,
STATE OF COLORADO OWNER/
APPLICANT PROJECT
TEAM:SITE ENGINEER Northern Engineering Services,
Inc.Andy Reese 301
North Howes Street,
Suite
100 Fort
Collins, Colorado
80521 970)
221-4158 SURVEYOR CONTACT INFORMATION PROJECT TEAM:SHEET INDEXE
N G I
N E E R
N GI EHTRON
R N
FINAL UTILITY PLANS FOR UTILITY CONTACT LIST: *UTILITY COMPANY This list is provided as a courtesy
reference only. Northern Engineering Services assumes no responsibility for the accuracy or completeness of this list. In no way
shall this list relinquish the Contractor's responsibility for locating all utilities prior to commencing any
construction activity. Please contact the Utility Notification
Center of
Colorado (UNCC) at 811 for additional information.PHONE
NUMBER GAS-----------------Xcel Energy-----------------------------------Pat Kreager (970) 225-7840 ELECTRIC--------City of
Fort Collins Light & Power-------Austin Kreager (970)
224-6152 CABLE-------------Comcast---------------------------------------Don Kapperman (970)
567-0245 TELECOM.--------CenturyLink-----------------------------------William Johnson (970) 377-6401 WATER------------Fort
Collins-Loveland Water District----Terry Farrill (970) 226-3104 WASTEWATER--South
Fort Collins Sanitation District---Terry Farrill (970) 226-3104 STORMWATER-City
of Fort
Collins Utilities----------------
Dan Mogen (970)
305-5989 LANDSCAPE ARCHITECT
GEOTECHNICAL ENGINEER FORTY-
THREE PRIME Northern Engineering Services, Inc.
Bob Tessely, PLS 301
North Howes Street,
Suite 100 Fort Collins, Colorado 80521 970) 221-4158E
N G I
N E E
R N GI
EHTRON R N Terracon Consultants,
Inc.Geotechnical Engineering Report
St. Peter's
Anglican Church 6608 Autumn
Ridge Road Fort Collins,
Colorado Terracon Project
No.
20155045
Date: November 6, 2015 SUBSURFACE
EXPLORATION BY:PROJECT LOCATION Blue
Mountain Environmental Consulting,
LLC Matt Tobler, Natural
Resource Specialist 937
Mallard Drive
Fort Collins, Colorado
80521 970)
224-0851 ENVIRONMENTAL ENGINEER Ripley
Design, Inc.Russell Lee
419 Canyon Avenue,
Suite 200 Fort Collins,
Colorado 80521 970)
224-
5828
land
planning landscape
architecture urban design entitlement
CS1 COVER SHEET1 SheetFORTY-
THREE PRIMEThese drawings areinstruments of serviceprovided
by NorthernEngineering Services, Inc.
and are not to be used forany type of
constructionunless signed and sealed bya Professional Engineer
inthe employ of NorthernEngineering Services,
Inc.NOT FOR CONSTRUCTIONREVIEW SETENGINEERNGIEHTRONRNFORT COLLINS:
301 North Howes Street, Suite
100, 80521GREELEY: 820 8th Street, 80631970.
221.4158northernengineering.comof 31 1
CS1 COVER SHEET 2 CS2
GENERAL NOTES 3 EX1 EXISTING
CONDITIONS & DEMOLITION PLAN 4 PV1
PAVING PLAN 8 - 12 SD1 -
SD5 STORM DRAIN PLAN AND
PROFILES 13 SD6 UNDER DRAIN PLAN
AND PROFILE 5 OU1 OVERALL UTILITY PLAN 6 -
7 U1 - U2 UTILITY PLAN 14 OG1
OVERALL GRADING PLAN
15 - 20
G1 - G6 GRADING PLAN
21 EC1 EROSION
CONTROL PLAN 22
EC2 EROSION CONTROL
DETAILS 23 EC3 EROSION
CONTROL NOTES 24 DR1
HISTORIC DRAINAGE EXHIBIT 25
DR2 DEVELOPED DRAINAGE
EXHIBIT 26 DT1 STREET CONSTRUCTION DETAILS
27 DT2 WATER & SANITARY CONSTRUCTION DETAILS 28 -
29 DT3 - DT4 STORM & DRAINAGE CONSTRUCTION DETAILS
30 - 31 DT5 - DT6 SITE CONSTRUCTION DETAILS Harvest Land
Company Jacob Davis 855 Norway Maple Drive Loveland,
Colorado 80538 970-
227-9795
Terracon Consultants, Inc.
Eric D.
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
CS2
GENERAL
NOTES2 A. GENERAL
NOTES 1.All materials, workmanship, and construction of public improvements shall meet or exceed the standards and specifications set forth in the
Larimer County Urban Area Street Standards and applicable state and federal regulations. Where there is conflict between these plans and
the specifications, or any applicable standards, the most restrictive standard shall apply. All work shall be inspected and approved by the City of
Fort
Collins.2.All references to any published standards shall refer to the latest revision of said standard, unless specifically stated
otherwise.3.These public improvement construction plans shall be valid for a period of three years from the date of approval by the City of Fort Collins
Engineer.Use of these plans after the expiration date will require a new review and approval process by the City of Fort Collins prior to commencement
of any work shown in these
plans.4.The engineer who has prepared these plans, by execution and/or seal hereof, does hereby affirm responsibility to the City of Fort Collins,
as beneficiary of said engineer's work, for any errors and omissions contained in these plans, and approval of these plans by the City of Fort
Collins Engineer shall not relieve the engineer who has prepared these plans of all such responsibility. Further, to the extent permitted by law, the
engineer hereby agrees to hold harmless and indemnify the City of Fort Collins, and its officers and employees, from and against all liabilities, claims,
and demands which may arise from any errors and omissions contained in these
plans.5.All storm sewer construction, as well as power and other "dry" utility installations, shall conform to the City of Fort Collins standards
and specifications current at the date of approval of the plans by the City of Fort Collins
Engineer.6.The type, size, location and number of all known underground utilities are approximate when shown on the drawings. It shall be the responsibility
of the Developer to verify the existence and location of all underground utilities along the route of the work before commencing new construction.
The Developer shall be responsible for unknown underground
utilities.7.The Developer shall contact the Utility Notification Center of Colorado (UNCC) at 1-800-922-1987, at least 2 working days prior to
beginning excavation or grading, to have all registered utility locations marked. Other unregistered utility entities (i.e. ditch / irrigation company) are to
be located by contacting the respective representative. Utility service laterals are also to be located prior to beginning excavation or grading. It shall
be the responsibility of the Developer to relocate all existing utilities that conflict with the proposed improvements shown on these
plans.8.The Developer shall be responsible for protecting all utilities during construction and for coordinating with the appropriate utility company for
any utility crossings
required.9.If a conflict exists between existing and proposed utilities and/or a design modification is required, the Developer shall coordinate with the
engineer to modify the design. Design modification(s) must be approved by the City of Fort Collins prior to beginning
construction.10.The Developer shall coordinate and cooperate with the City of Fort Collins, and all utility companies involved, to assure that the work
is accomplished in a timely fashion and with a minimum disruption of service. The Developer shall be responsible for contacting, in advance,
all parties affected by any disruption of any utility service as well as the utility
companies.11.No work may commence within any public storm water, sanitary sewer or potable water system until the Developer notifies the utility
provider.Notification shall be a minimum of 2 working days prior to commencement of any work. At the discretion of the water utility provider,
a pre-construction meeting may be required prior to commencement of any
work.12.The Developer shall sequence installation of utilities in such a manner as to minimize potential utility conflicts. In general, storm sewer and
sanitary sewer should be constructed prior to installation of the water lines and dry
utilities.13.The minimum cover over water lines is 4.5 feet and the maximum cover is 5.5 feet unless otherwise noted in the plans and approved by the
Water
Utility.14.A State Construction Dewatering Wastewater Discharge Permit is required if dewatering is required in order to install utilities or if water
is discharged into a storm sewer, channel, irrigation ditch or any waters of the United
States.15.The Developer shall comply with all terms and conditions of the Colorado Permit for Storm Water Discharge (Contact Colorado Department
of Health, Water Quality Control Division, (303) 692-3590), the Storm Water Management Plan, and the Erosion Control
Plan.16.The City of Fort Collins shall not be responsible for the maintenance of storm drainage facilities located on private property. Maintenance of
onsite drainage facilities shall be the responsibility of the property owner(
s).17.Prior to final inspection and acceptance by the City of Fort Collins, certification of the drainage facilities, by a registered engineer, must
be submitted to and approved by the Stormwater Utility Department. Certification shall be submitted to the Stormwater Utility Department at least
two weeks prior to the release of a certificate of occupancy for single family units. For commercial properties, certification shall be submitted to
the Stormwater Utility Department at least two weeks prior to the release of any building permits in excess of those allowed prior to certification per
the Development
Agreement.18.The City of Fort Collins shall not be responsible for any damages or injuries sustained in this Development as a result of groundwater
seepage,whether resulting from groundwater flooding, structural damage or other damage unless such damage or injuries are sustained as a result of
the City of Fort Collins failure to properly maintain its water, wastewater, and/or storm drainage facilities in the
development.19.All recommendations of the Final Drainage Letter and LID Report for Forty-Three Prime by Northern Engineering dated 7/28/2021 and the
Final Drainage and Erosion Control Report for Provincetowne PUD Filing Two, dated March 22, 2001 by Manhard Consulting, Ltd., shall be followed
and
implemented.20.Temporary erosion control during construction shall be provided as shown on the Erosion Control Plan. All erosion control measures shall
be maintained in good repair by the Developer, until such time as the entire disturbed areas is stabilized with hard surface or
landscaping.21.The Developer shall be responsible for insuring that no mud or debris shall be tracked onto the existing public street system. Mud and debris
must be removed within 24 hours by an appropriate mechanical method (i.e. machine broom sweep, light duty front-end loader, etc.) or as approved
by the the City of Fort Collins street
inspector.22.No work may commence within any improved or unimproved public Right-of-Way until a Right-of-Way Permit or Development Construction
Permit is obtained, if
applicable.23.The Developer shall be responsible for obtaining all necessary permits for all applicable agencies prior to commencement of construction.
The Developer shall notify the the City of Fort Collins Inspector (Fort Collins - 221-6605) and the City of Fort Collins Erosion Control Inspector (
Fort Collins - 221-6700) at least 2 working days prior to the start of any earth disturbing activity, or construction on any and all public improvements.
If the City of Fort Collins Engineer is not available after proper notice of construction activity has been provided, the Developer may commence
work in the Engineer absence. However, the City of Fort Collins reserves the right not to accept the improvement if subsequent testing reveals
an improper
installation.24.The Developer shall be responsible for obtaining soils tests within the Public Right-of-Way after right of way grading and all utility trench work
is complete and prior to the placement of curb, gutter, sidewalk and pavement. If the final soils/pavement design report does not correspond with
the results of the original geotechnical report, the Developer shall be responsible for a re-design of the subject pavement section or, the Developer
may use the City of Fort Collins' default pavement thickness section(s). Regardless of the option used, all final soils/pavement design reports shall
be prepared by a licensed Professional Engineer. The final report shall be submitted to the Inspector a minimum of 10 working days prior to
placement of base and asphalt. Placement of curb, gutter, sidewalk, base and asphalt shall not occur until the City of Fort Collins Engineer approves the
final
report.25.The contractor shall hire a licensed engineer or land surveyor to survey the constructed elevations of the street subgrade and the gutter flowline
at all intersections, inlets, and other locations requested by the the City of Fort Collins inspector. The engineer or surveyor must certify in a letter
to the City of Fort Collins that these elevations conform to the approved plans and specifications. Any deviations shall be noted in the letter and
then resolved with the City of Fort Collins before installation of base course or asphalt will be allowed on the
streets.26.All utility installations within or across the roadbed of new residential roads must be completed prior to the final stages of road construction. For
the purposes of these standards, any work except c/g above the subgrade is considered final stage work. All service lines must be stubbed to
the property lines and marked so as to reduce the excavation necessary for building
connections.27.Portions of Larimer County are within overlay districts. The Larimer County Flood Plain Resolution should be referred to for additional criteria
for roads within these
districts.28.All road construction in areas designated as Wild Fire Hazard Areas shall be done in accordance with the construction criteria as established in
the Wild Fire Hazard Area Mitigation Regulations in force at the time of final plat
approval.29.Prior to the commencement of any construction, the contractor shall contact the Local Entity Forester to schedule a site inspection for any
tree removal requiring a
permit.30.The Developer shall be responsible for all aspects of safety including, but not limited to, excavation, trenching, shoring, traffic control, and
security.Refer to OSHA Publication 2226, Excavating and
Trenching.31.The Developer shall submit a Construction Traffic Control Plan, in accordance with MUTCD, to the appropriate Right-of-Way authority. (The City
of Fort Collins, Larimer County, Colorado), for approval, prior to any construction activities within, or affecting, the Right-of-Way. The Developer
shall be responsible for providing any and all traffic control devices as may be required by the construction
activities.32.Prior to the commencement of any construction that will affect traffic signs of any type, the contractor shall contact the City of Fort Collins
Traffic Operations Department, who will temporarily remove or relocate the sign at no cost to the contractor, however, if the contractor moves the
traffic sign then the contractor will be charged for the labor, materials and equipment to reinstall the sign as
needed.33.The Developer is responsible for all costs for the initial installation of traffic signing and striping for the Development related to the Development'
s local street operations. In addition, the Developer is responsible for all costs for traffic signing and striping related to directing traffic access to
and from the
Development.34.There shall be no site construction activities on Saturdays, unless specifically approved by the City of Fort Collins Engineer, and no
site construction activities on Sundays or holidays, unless there is prior written approval by City of Fort
Collins.35.The Developer is responsible for providing all labor and materials necessary for the completion of the intended improvements, shown on
these drawings, or designated to be provided, installed, or constructed, unless specifically noted
otherwise.36.Dimensions for layout and construction are not to be scaled from any drawing. If pertinent dimensions are not shown, contact the Designer
for clarification, and annotate the dimension on the as-built record
drawings.37.The Developer shall have, onsite at all times, one (1) signed copy of the approved plans, one (1) copy of the appropriate standards
and specifications, and a copy of any permits and extension agreements needed for the
job.38.If, during the construction process, conditions are encountered which could indicate a situation that is not identified in the plans or
specifications,the Developer shall contact the Designer and the City of Fort Collins Engineer
immediately.39.The Developer shall be responsible for recording as-built information on a set of record drawings kept on the construction site, and available to
the Larimer County's Inspector at all times. Upon completion of the work, the contractor(s) shall submit record drawings to the City of Fort
Collins
Engineer.40.The Designer shall provide, in this location on the plan, the location and description of the nearest survey benchmarks (2) for the project as well
as the basis of bearings. The information shall be as
follows:PROJECT DATUM:
NAVD88 City of Fort Collins Benchmark 24-
94 Northeast corner of East Trilby Rd and Portner Dr., on top of the West end of a concrete
headwall.ELEV. = 4960.
69 City of Fort Collins Benchmark 25-
94 Northwest corner of East Trilby Rd. and South Lemay Ave, on top of the Southeast edge of the concrete ring to an electric
manhole.ELEV. = 4913.
16 Please Note: This plan set is using NAVD88 for a vertical datum. Surrounding developments have used NGVD29 Unadjusted for their
vertical
datums.If NGVD29 Unadjusted Datum is required for any purpose, the following equation should be
used:NGVD29 Unadjusted = NAVD88 - 3.
19'Basis of
Bearings The Basis of Bearings is the North line of the Northeast Quarter of Section 13-6-69 as bearing North 88° 11' 32" West (assumed
bearing).41.All stationing is based on centerline of roadways unless otherwise
noted.42.Damaged curb, gutter and sidewalk existing prior to construction, as well as existing fences, trees, streets, sidewalks, curbs and
gutters,landscaping, structures, and improvements destroyed, damaged or removed due to construction of this project, shall be replaced or restored in
like kind at the Developer's expense, unless otherwise indicated on these plans, prior to the acceptance of completed improvements and/or prior to
the issuance of the first Certificate of
Occupancy.43.When an existing asphalt street must be cut, the street must be restored to a condition equal to or better than its original condition. The
existing street condition shall be documented by the City of Fort Collins Construction Inspector before any cuts are made. Patching shall be done
in accordance with the City of Fort Collins Street Repair Standards. The finished patch shall blend in smoothly into the existing surface. All
large patches shall be paved with an asphalt lay-down machine. In streets where more than one cut is made, an overlay of the entire street
width,including the patched area, may be required. The determination of need for a complete overlay shall be made by the Larimer County
Engineer and/or the City of Fort Collins Inspector at the time the cuts are
made.44.Upon completion of construction, the site shall be cleaned and restored to a condition equal to, or better than, that which existed
before construction, or to the grades and condition as required by these
plans.45.Standard Handicap ramps are to be constructed at all curb returns and at all "T"
intersections.46.After acceptance by the City of Fort Collins, public improvements depicted in these plans shall be guaranteed to be free from material
and workmanship defects for a minimum period of two years from the date of
acceptance.47.The City of Fort Collins shall not be responsible for the maintenance of roadway and appurtenant improvements, including storm
drainage structures and pipes, for the following private streets: N.
A.48.Approved Variances are listed as
follows: 1) Water quality treatment for entire site (
Stormwater)2) Level of Service (
Transportation)CONSTRUCTION
NOTES A. Grading and Erosion Control
Notes 1.The erosion control inspector must be notified at least twenty-four (24) hours prior to any construction on this
site.2.There shall be no earth-disturbing activity outside the limits designated on the accepted
plans.3.All required perimeter silt and construction fencing shall be installed prior to any land disturbing activity (stockpiling, stripping, grading, etc).
All other required erosion control measures shall be installed at the appropriate time in the construction sequence as indicated in the approved
project schedule, construction plans, and erosion control
report.4.At all times during construction, the Developer shall be responsible for preventing and controlling on-site erosion including keeping the
property sufficiently watered so as to minimize wind blown sediment. The Developer shall also be responsible for installing and maintaining all
erosion control facilities shown
herein.5.Pre-disturbance vegetation shall be protected and retained wherever possible. Removal or disturbance of existing vegetation shall be limited to
the area(s) required for immediate construction operations, and for the shortest practical period of
time.6.All soils exposed during land disturbing activity (stripping, grading, utility installations, stockpiling, filling, etc.) shall be kept in a roughened
condition by ripping or disking along land contours until mulch, vegetation, or other permanent erosion control BMPs are installed. No soils in areas
outside project street rights-of-way shall remain exposed by land disturbing activity for more than thirty (30) days before required temporary or
permanent erosion control (e.g. seed/mulch, landscaping, etc.) is installed, unless otherwise approved by the City/
County.7.In order to minimize erosion potential, all temporary (structural) erosion control measures
shall:a.Be inspected at a minimum of once every two (2) weeks and after each significant storm event and repaired or reconstructed as necessary
in order to ensure the continued performance of their intended
function.b.Remain in place until such time as all the surrounding disturbed areas are sufficiently stabilized as determined by the erosion control
inspector.c.Be removed after the site has been sufficiently stabilized as determined by the erosion control
inspector.8.When temporary erosion control measures are removed, the Developer shall be responsible for the clean up and removal of all sediment
and debris from all drainage infrastructure and other public
facilities.9.The contractor shall immediately clean up any construction materials inadvertently deposited on existing streets, sidewalks, or other public rights
of way, and make sure streets and walkways are cleaned at the end of each working
day.10.All retained sediments, particularly those on paved roadway surfaces, shall be removed and disposed of in a manner and location so as not
to cause their release into any waters of the United
States.11.No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be protected from sediment transport by surface roughening,
watering,and perimeter silt fencing. Any soil stockpile remaining after thirty (30) days shall be seeded and
mulched.12.The stormwater volume capacity of detention ponds will be restored and storm sewer lines will be cleaned upon completion of the project
and before turning the maintenance over to the City/County or Homeowners Association (
HOA).13.City Ordinance and Colorado Discharge Permit System (CDPS) requirements make it unlawful to discharge or allow the discharge of any
pollutant or contaminated water from construction sites. Pollutants include, but are not limited to discarded building materials, concrete truck
washout,chemicals, oil and gas products, litter, and sanitary waste. The developer shall at all times take whatever measures are necessary to assure
the proper containment and disposal of pollutants on the site in accordance with any and all applicable local, state, and federal
regulations.14.A designated area shall be provided on site for concrete truck chute washout. The area shall be constructed so as to contain washout material
and located at least fifty (50) feet away from any waterway during construction. Upon completion of construction activities the concrete
washout material will be removed and properly disposed of prior to the area being
restored.15.Conditions in the field may warrant erosion control measures in addition to what is shown on these plans. The Developer shall implement
whatever measures are determined necessary, as directed by the
City.16.For additional information see separate Stormwater Management Plan / Erosion Control Report for Forty-Three
Prime.B. Street Improvement
Notes 1.All street construction is subject to the General Notes on the cover sheet of these plans as well as the Street Improvements Notes listed
here.2.A paving section design, signed and stamped by a Colorado licensed Engineer, must be submitted to the City of Fort Collins Engineer for
approval,prior to any street construction activity, (full depth asphalt sections are not permitted at a depth greater than 8 inches of asphalt). The job mix
shall be submitted for approval prior to placement of any
asphalt.3.Where proposed paving adjoins existing asphalt, the existing asphalt shall be saw cut, a minimum distance of 12 inches from the existing edge,
to create a clean construction joint. The Developer shall be required to remove existing pavement to a distance where a clean construction joint
can be made. Wheel cuts shall not be allowed unless approved by the City of Fort Collins Engineer in Fort
Collins.4.Street subgrades shall be scarified the top 12 inches and re-compacted prior to subbase installation. No base material shall be laid until
the subgrade has been inspected and approved by the City of Fort Collins
Engineer.5.Ft. Collins only. Valve boxes and manholes are to be brought up to grade at the time of pavement placement or overlay. Valve box adjusting
rings are not
allowed.6.When an existing asphalt street must be cut, the street must be restored to a condition equal to or better than its original condition. The
existing street condition shall be documented by the Inspector before any cuts are made. Cutting and patching shall be done in conformance with
Chapter 25, Reconstruction and Repair. The finished patch shall blend smoothly into the existing surface. The determination of need for a complete
overlay shall be made by the City of Fort Collins Engineer. All overlay work shall be coordinated with adjacent landowners such that future projects do
not cut the new asphalt overlay
work.7.All traffic control devices shall be in conformance with these plans or as otherwise specified in M.U.T.C.D. (including Colorado supplement) and
as per the Right-of-Way Work Permit traffic control
plan.8.The Developer is required to perform a gutter water flow test in the presence of the City of Fort Collins Inspector and prior to installation of
asphalt.Gutters that hold more than 1/4 inch deep or 5 feet longitudinally, of water, shall be completely removed and reconstructed to drain
properly.9.Prior to placement of H.B.P. or concrete within the street and after moisture/density tests have been taken on the subgrade material (when a
full depth section is proposed) or on the subgrade and base material (when a composite section is proposed), a mechanical "proof roll" will be
required.The entire subgrade and/or base material shall be rolled with a heavily loaded vehicle having a total GVW of not less than 50,000 lbs. and a
single axle weight of at least 18,000 lbs. with pneumatic tires inflated to not less that 90 p.s.i.g. "Proof roll" vehicles shall not travel at speeds greater
than 3 m.p.h. Any portion of the subgrade or base material which exhibits excessive pumping or deformation, as determined by the City of Fort
Collins Engineer, shall be reworked, replaced or otherwise modified to form a smooth, non-yielding surface. The City of Fort Collins Engineer shall
be notified at least 24 hours prior to the "proof roll." All "proof rolls" shall be preformed in the presence of an
Inspector.C. Traffic Signing and Pavement Marking Construction
Notes 1.All signage and marking is subject to the General Notes on the cover sheet of these plans, as well as the Traffic Signing and Marking
Construction Notes listed
here.2.All symbols, including arrows, ONLYS, crosswalks, stop bars, etc. shall be pre-formed thermo-
plastic.3.All signage shall be per the City of Fort Collins Standards and these plans or as otherwise specified in
MUTCD.4.All lane lines for asphalt pavement shall receive two coats of latex paint with glass
beads.5.All lane lines for concrete pavement should be epoxy
paint.6.Prior to permanent installation of traffic striping and symbols, the Developer shall place temporary tabs or tape depicting alignment and
placement of the same. Their placement shall be approved by the City of Fort Collins Traffic Engineer prior to permanent installation of striping and
symbols.7.Pre-formed thermo-plastic applications shall be as specified in these Plans and/or these
Standards.8.Epoxy applications shall be applied as specified in CDOT Standard Specifications for Road and Bridge
Construction.9.All surfaces shall be thoroughly cleaned prior to installation of striping or
markings.10.All sign posts shall utilize break-away assemblies and fasteners per the
Standards.11.A field inspection of location and installation of all signs shall be performed by the City of Fort Collins Traffic Engineer. All discrepancies
identified during the field inspection must be corrected before the 2-year warranty period will
begin.12.The Developer installing signs shall be responsible for locating and protecting all underground
utilities.13.Special care shall be taken in sign location to ensure an unobstructed view of each
sign.14.Signage and striping has been determined by information available at the time of review. Prior to initiation of the warranty period,the City of
Fort Collins Traffic Engineer reserves the right to require additional signage and/or striping if the City of Fort Collins Traffic Engineer determines that
an unforeseen condition warrants such signage according to the MUTCD or the CDOT M and S Standards. All signage and striping shall fall under
the requirements of the 2-year warranty period for new construction (except fair wear on traffic
markings).15.Sleeves for sign posts shall be required for use in islands/medians. Refer to Chapter 14, Traffic Control Devices, for additional
detail.D. Storm Drainage
Notes 1.The City of Fort Collins shall not be responsible for the maintenance of storm drainage facilities located on private property. Maintenance of
onsite drainage facilities shall be the responsibility of the property owner(
s).2.All recommendations of the Final Drainage Letter and LID Report for Forty-Three Prime by Northern Engineering dated 7/28/2021, and the
Final Drainage and Erosion Control Report for Provincetowne PUD Filing Two, dated March 22, 2001 by Manhard Consulting, Ltd., shall be followed
and
implemented.3.Prior to final inspection and acceptance by the City of Fort Collins, certification of the drainage facilities, by a registered engineer, must
by submitted to and approved by the Stormwater Utility Department. Certification shall be submitted to the Stormwater Utility Department at least
two weeks prior to the release of a certificate of occupancy for single family units. For commercial properties, certification shall by submitted to
the Stormwater Utility Department at least two weeks prior to the release of any building permits in excess of those allowed prior to certification per
the Development
Agreement.E.Utility
Notes 1.All waterlines shall be C900, DR 18 PVC pipe with a minimum 12 gage insulated tracer
wire.2.The size, type and location of all known underground utilities are approximate when shown on these drawings. It shall be the responsibility of
the contractor to verify the existence of all underground utilities in the area of the work. Before commencing new construction, the contractor shall
be responsible for locating all underground utilities and shall be responsible for all unknown underground
utilities.3.Water service provided by Fort Collins-Loveland Water District. Sanitary service provided by South Fort Collins Sanitation
District.4.Utility services are shown in a schematic fashion only. Exact locations shall be per the requirements of the respective utility providers, and
are subject to change in the
field.5.All water fittings and valves are only graphically represented and are not to
scale.6.Minimum depth of cover over water mains shall be 5.0'. Maximum cover shall be 6.
0'.7.Maintain 10' horizontal and 18" vertical minimum separation between all sanitary sewer mains, water mains and
services.8.Manhole rim elevations are to be adjusted to 1/4" below finished grade. If necessary, cone sections shall be rotated to prevent lids being
located within bicycle or vehicle wheel
paths.9.All connections to existing manholes shall be core drilled according to the South Fort Collins Sanitation District standard construction specifications.
SheetFORTY-THREE
4YD4YD4YD4YDUD
UDUDSSSSSWWW
W
STT
TEEEEEEE E E
E
EE
E
E
WEMGMEMGMEMEMEMEEMGMGM GM
GM
IRE
E
E E E E E EEEE
EM
WEE E E E
TE
EEEEEESS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS
SSSSSS
STSTSTSTTELECELEC
ELEC ELEC
C
TELE
C
T
VAULT
ELEC
VAULT
ELEC
FES
FE
SCONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRR
CONTROL
IRRFES
FE
SLID
LID SLID
S
S
S
S
S
SSSS
SS
SS
SS
SS
SS
SS
SS
SS
SSSSSSSSSSSSSSSSSSSSSSSSEE
E
CTVTCTVT
CTV CTV CTV
CTV TCTVCTVEE
WWWWWWWWWWWW
WWWWWW
W
W
W
W
W
WW
W
W
W
W
W W
W / / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /
E E E E E E E
E
E E
E
E E E E E E E
E
E E E E E E E E E E E E E E E E
T T T T
T T T T T T T T T
T T T T T
T T T T
CTVCTVCTVCTVCTVCTVCTVCTVCTVCTVTTTTTTTTTTTCTV CTV CTV CTV CTV CTV CTV CTV CTV
CTV
CTV
T
T
TTTTTT
D
D
D
D
D
D
D
D
S
S
S
S
S
SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS
EXISTING 8"
SANITARY SEWER
EXISTING
8" WATER
EXISTING 8"
SANITARY SEWER
EXISTING
12" WATER
EXISTING 8"
SANITARY SEWER
EXISTING 8"
SANITARY SEWER
EXISTING INLET
EXISTING INLET
EXISTING INLET
EXISTING INLET
EXISTING INLET
EXISTING IRRIGATION
CONTROL BOX
TYP.)
EXISTING 36" RCP
STORM DRAIN
PROPOSED
WATER METER
TYP.)
PROPOSED
WATER SERVICE
TYP.)
REMOVE EXISTING FH
CONNECT 8" PVC WATER
EXISTING
8" WATER
PROPOSED FH
PROPOSED 8"
PVC WATER
PROPOSED 8"
PVC WATER
REMOVE EXISTING FH
CONNECT 8" PVC WATER
PROPOSED 8"
PVC WATER
PROPOSED FH
PROPOSED 8"
PVC WATER
EXISTING 30" RCP
STORM DRAIN
EXISTING 18" HDPE
STORM DRAIN
EXISTING 42" HDPE
STORM DRAIN
PROPOSED
RAIN GARDEN
PROPOSED 2'
SIDEWALK CHASES
PROPOSED 2'
CONCRETE CHASE
40' DRAINAGE &
UTILITY EASEMENT47'
DRAINAGE &
UTILITY EASEMENTPROPOSED
SANITARY
SERVICE TYP.)EAST
TRILBY ROAD CAND L E W O O D D RI
V
E BRITTANY
DRIVEAUTUMN
RIDGE DRIVEPROPOSED
AREA
DRAIN PROPOSED
AREA
DRAIN PROPOSED
AREA DRAIN
PROPOSED RAIN
GARDEN LOT
2
TRACT
A LOT
1
PROPOSED UNDERDRAIN
1'
SIDEWALK CHASE
1'
SIDEWALK CHASE 1'
SIDEWALK
CHASE 7.5'
SIDEWALK CULVERT
20' UTILITY & EMERGENCY
ACCESS EASEMENT
20' UTILITY &
EMERGENCY ACCESS EASEMENT
10'
UTILITY EASEMENT
20'
UTILITY EASEMENT
10'
UTILITY EASEMENT
10'
UTILITY
EASEMENT
10' UTILITY
EASEMENT PROPOSED
CULVERTS BLDG
A BLDG
B BLDG
C BLDG
D BLDG
E BLDG
F
PROPOSED
ELECTRIC
TRANSFORMER (
TYP.)MAIL
KIOSK
PROPOSED CULVERT
10'
UTILITY EASEMENTS
10'
UTILITY
EASEMENTS
17'
DRAINAGE EASEMENT
DRAINAGE
EASEMENT
SheetFORTY-
THREE PRIMEThese drawings areinstruments of serviceprovided by NorthernEngineering Services, Inc.and are not to
be used forany type of constructionunless signed and sealed bya Professional Engineer inthe employ of
NorthernEngineering Services, Inc.NOT FOR CONSTRUCTIONREVIEW SETENGINEERNGIEHTRONRNFORT COLLINS: 301 North Howes Street, Suite 100,
80521GREELEY: 820 8th Street, 80631970.221.4158northernengineering.comof 31 OU1
OVERALL UTILITY PLAN5 NOTES:1.THE SIZE, TYPE AND LOCATION
OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT
SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE
EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF
THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL
UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR
ALL UNKNOWN UNDERGROUND UTILITIES.2.ALL WATER CONSTRUCTION SHALL BE PER FORT COLLINS-
LOVELAND WATER DISTRICT STANDARD CONSTRUCTION SPECIFICATIONS LATEST EDITION. SEWER CONSTRUCTION SHALL BE
PER SOUTH FORT COLLINS SANITATION DISTRICT STANDARD CONSTRUCTION SPECIFICATIONS LATEST EDITION.3.
EXISTING MANHOLES SHALL
BE ADJUSTED TO FINISHED GRADE IN ACCORDANCE WITH SOUTH FORT COLLINS SANITATION DISTRICT STANDARDS SPECIFICATIONS
AND REQUIREMENTS.4.SOUTH FORT COLLINS SANITATION DISTRICT NOT RESPONSIBLE FOR REPAIR OR REPLACEMENT OF BOCCE
COURT IF REPLACEMENT OR MAINTENANCE IS REQUIRED TO SANITARY SEWER LINE.5.REDUCED
PRESSURE
PRINCIPLE BACK-FLOW PREVENTION DEVICES SHALL BE REQUIRED ON DOMESTIC WATER SERVICES.6.
ALL WATER FITTINGS AND
VALVES ARE ONLY GRAPHICALLY REPRESENTED AND ARE NOT TO SCALE.7.UTILITY SERVICES ARE
SHOWN IN A SCHEMATIC FASHION ONLY. EXACT
LOCATIONS SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE UTILITY PROVIDERS, AND ARE SUBJECT TO CHANGE IN
THE FIELD.8.MAINTAIN 10' HORIZONTAL AND 18" VERTICAL MINIMUM SEPARATION BETWEEN ALL SANITARY
SEWER
MAINS, WATER MAINS & SERVICES.9.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES,
EASEMENTS, LOT DIMENSIONS, UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
10.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE DETERMINED IN
THE FIELD BY THE CITY ENGINEERING INSPECTOR. ALL REPAIRS TO BE IN
ACCORDANCE WITH CITY STREET REPAIR STANDARDS.11.ANY DAMAGED CURB, GUTTER AND SIDEWALK
EXISTING PRIOR TO CONSTRUCTION, AS WELL AS STREETS, SIDEWALKS, CURBS AND GUTTERS, DESTROYED, DAMAGED OR
REMOVED DUE TO CONSTRUCTION OF THIS PROJECT, SHALL BE REPLACED OR RESTORED
TO CITY OR FORT COLLINS STANDARDS AT
THE DEVELOPER'S EXPENSE PRIOR TO THE ACCEPTANCE OF COMPLETED IMPROVEMENTS AND/OR
PRIOR TO THE ISSUANCE OF THE FIRST CERTIFICATE OF OCCUPANCY.12.REFER TO
PLUMBING
PLANS FOR ALL WATER SERVICE AND SANITARY SEWER SERVICE LOCATIONS. IF CONFLICT
OCCURS, BOTH THE
PLUMBING ENGINEER AND CIVIL ENGINEER SHALL BE CONTACTED PRIOR TO INSTALLATION OR ORDERING OF
MATERIALS.13.ALL SANITARY SEWER SERVICE CONNECTION INVERTS AND LOCATIONS BASED ON
BEST AVAILABLE DATA. CONTRACTOR TO VERIFY LOCATION PRIOR TO CONSTRUCTION AND NOTIFY ENGINEER OF ANY
DISCREPANCIES.14.CONTRACTOR SHALL CONFIRM AND COORDINATE ALL SERVICE SIZES WITH STAMPED ARCHITECTURAL AND PLUMBING PLANS.
15.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND INLET BOX STRUCTURES.SPECIFIED LENGTH OF PIPE INCLUDES
THE LAYING LENGTH OF FLARED END SECTIONS.16.ALL RCP SHALL BE CLASS
III OR GREATER. PIPE MATERIAL, BEDDING, AND INSTALLATION WITHIN PUBLIC RIGHTS-OF-WAY SHALL BE GOVERNED BY
THE CITY OF FORT COLLINS. ALTERNATES (SUCH AS ADS N-12 OR HP
SANITITE) OUTSIDE OF THE R.O.W. SHALL BE APPROVED IN ADVANCE BY
THE ENGINEER. ALL JOINTS SHALL BE 'WATERTIGHT' USING APPROPRIATE GASKETS OR JOINT
WRAPS (PER ASTM C443/C877 FOR RCP AND PER ASTM F477 /
D3212 FOR PLASTIC PIPE). STORM DRAINS SHOWN ON THIS DRAWING AS POLYVINYL CHLORIDE (
PVC) SHALL BE SDR-35 OR APPROVED
EQUAL.17.CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES AND POTHOLING OF SUBSURFACE
UTILITIES. ENGINEER AND CITY SHALL BE NOTIFIED OF ANY POTENTIAL CONFLICTS.18.CONTRACTOR SHALL COORDINATE ANY
NECESSARY TELEPHONE, CABLE AND ELECTRIC LOWERINGS OR RE-ROUTING) WITH THE
RESPECTIVE UTILITY PROVIDERS TO FACILITATE THE INSTALLATION OF THE PROPOSED STORM DRAIN AND UTILITY
SERVICES.19.ALL AREA DRAIN BASINS SHALL BE INSTALLED PER THE INLET SCHEDULE ON SHEET
DT4.
20.THE FINAL SIZE, NUMBER, AND LOCATION OF ALL UTILITY CONDUIT SHALL
BE DETERMINED IN THE FIELD. CONDUITS SHALL
BE CLOSELY COORDINATED WITH THE OWNER, LANDSCAPE / IRRIGATION CONTRACTOR,
AND THE RESPECTIVE DRY UTILITY PROVIDERS. TOP OF CONDUITS TO BE PLACED A MINIMUM OF
2' BELOW FINISHED GRADE. FINAL BURY DEPTH SHALL BE PER DRY UTILITY PROVIDER REQUIREMENTS.21.REFER TO
LANDSCAPE PLANS
FOR ADDITIONAL LIGHT
POLE
LOCATION
INFORMATION
AND
COORDINATE
WITH UTILITY PROVIDERS
TO AVOID
CONFLICTS.22.
BUILDINGS TO
BESPRINKLEDOFFDOMESTICWATER
LINE.23.THE
NATURAL HABITAT BUFFER
ZONE IS INTENDED TO BE MAINTAINED IN
A NATIVE LANDSCAPE.
PLEASE SEE SECTION
3.4.
1 OF
LAND USE CODE
FOR ALLOWABLE USES
WITHIN THE NATURAL
HABITATBUFFER
ZONE.EXISTING
WATERMAIN
LEGEND:
W G T E EXISTING STORM SEWER PROPOSED
ELECTRIC
EXISTING TELEPHONE EXISTING GAS
SPROPOSED
SEWER
SERVICE &
CLEAN OUT
EXISTING SANITARY SEWER
PROPOSED CURB & GUTTER
PROPOSED WATER
SERVICE, CURB STOP, & METER PIT
PROPOSED FIRE HYDRANT EXISTING FIRE
HYDRANT EASEMENT LINE PROPERTY BOUNDARY PROPOSED WATER MAIN
PROPOSED SANITARY SEWER PROPOSED STORM SEWER GPROPOSED GAS
CTVEXISTING CABLE EEXISTING
ELECTRIC W PROPOSED IRRIGATION SERVICE,
CURB
STOP, & METER PIT
IR SS PROPOSEDUNDER
DRAIN
UD
DT2
CONSTRUCTION
DETAILSWATER &
SANITARY27 SheetFORTY-
THREE PRIMEThesedrawings areinstruments ofserviceprovided by NorthernEngineering Services, Inc.and arenot
to beused forany typeof constructionunless signedand
sealed bya
Professional
Engineer inthe employ
of NorthernEngineering
Services, Inc.
NOT
FORCONSTRUCTIONREVIEW
SETENGINEERNGIEHTRONRNFORT
COLLINS: 301
North Howes Street, Suite
100, 80521GREELEY: 820
8th
Street, 80631970.
221.
4158northernengineering.comof 31 WATER
MAIN BEDDING201 TYPICAL WATER
SERVICE202
AIR
RELEASE / VACCUM
WALVE203 WATER
MAIN LOWERING204
CONCRETE THRUST
BLOCKS205 FIRE
HYDRANT INSTALLATION206
SERVICE
WYE DETAIL207
PRE-
FORMED MANHOLE SECTION A-
A FROST LID 90°
ELBOW FINISHED BIRD SCREEN4'5'-
5"
4'1'
MIN.
1'312"1'-
4"1'6" FABRICATED STEEL
PIPE 6"x90° SCHEDULE GRADE PLASTIC
GASKET 2'-4"PLAN RINGS (
GROUT IN PLACE)PRE-CAST CONCRETE
GRADE
A A FOOTING (TYP.)
1'1'2'2'
2'2'MANHOLE STEP
STEP (TYP.)36" (MIN.)
6" MIN.TYP.)
6" MIN.(
TYP.)TAPPING
SADDLE NOTES:
ALL FITTINGS,
VALVES AND SADDLES SHALL BE
BRASS RATED 250
PSI OR BETTER.1'(
TYP.)4' MIN.CONCRETE FOOTING (TYP.)
CONCRETE 40 PVC
ELBOW MANHOLE PIPE OPENING (
FILL WITH
NON-SHRINK GROUT
ALL AROUND PIPE)MANOLE
PIPE OPENING (FILL
WITH NON-
SHRINK
GROUT ALL
AROUND
PIPE)1.
DETAIL
NOT
TO SCALE2.6"
SCHEDULE 40 PVC 6"
SCHEDULE 40 PVC GLUE-ON
FEMALE
ADAPTER TO IP
THREAD1'PLAN VIEW
CROSS VIEW