HomeMy WebLinkAboutNORTHFIELD COMMONS - FDP210022 - DOCUMENT MARKUPS - ROUND 2 - UTILITY PLANS (2)SITE
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCOVER SHEET9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C0.00
1 18
PROPOSED STREET LIGHT
PROPOSED STORM SEWER
EXISTING SANITARY SEWER MAIN
PROPOSED TELEPHONE LINE
EXISTING GAS
EXISTING STORM SEWER
EXISTING WATER MAIN
EXISTING MANHOLE
PROPOSED STORM INLET
LEGEND
PROPOSED CONCRETE
PROPOSED MINOR CONTOUR
PROPOSED SPOT ELEVATIONEXISTING SPOT ELEVATION
PROPOSED MAJOR CONTOUR
EXISTING MINOR CONTOUR
EXISTING MAJOR CONTOUR
EXISTING UTILITY POLE
EXISTING GUY WIRE
PROPOSED GAS
PROPOSED ELECTRIC LINEEXISTING ELECTRIC LINE
EXISTING TELEPHONE LINE
PROPOSED FIRE HYDRANTEXISTING FIRE HYDRANT
EXISTING WATER VALVE
PROPOSED SANITARY SEWER MAIN
PROPOSED WATER MAIN
EXISTING CONCRETE
EXISTING FLOWLINE, CURB & GUTTER PROPOSED FLOWLINE, CURB & GUTTER
PROPOSED FENCE
LIMITS OF CONSTRUCTION
EXISTING OVERHEAD UTILITY
EXISTING STORM SEWER INLET
PROPOSED WATER VALVE
PROPOSED MANHOLE
PROPOSED UTILITY POLE
EXISTING STREET LIGHT
PROPOSED SWALE
PROPOSED DIRECTION OF OVERLAND FLOW
EXISTING FIBER OPTIC LINE
PROPOSED HANDICAP RAMP
EXISTING OVERHEAD ELECTRIC LINE
EXISTING OVERHEAD TELEPHONE LINE
PROPOSED OVERHEAD ELECTRIC LINE
PROPOSED FIBER OPTIC LINE
PROPOSED OVERHEAD TELEPHONE LINE
EXISTING FENCE
PROPOSED OVERHEAD UTILITY
PROPOSED LIGHT POLES
EXISTING CABLE TV LINE PROPOSED CABLE TV
PROPOSED WATER SERVICE W/
CURB STOP AND METER PIT
PROPOSED SANITARY SEWER SERVICE W/
CLEANOUT
EXISTING ROW
Vicinity Map
Scale: 1" = 1000'
PROJECT DATUM: NAVD88
CITY OF FORT COLLINS BENCHMARK #43-97
ON THE SOUTH END OF THE WEST HEADWALL OF THE LAKE CANAL BRIDGE AT NORTH LEMAY AVENUE, 200 FEET SOUTH OF
THE INTERSECTION OF LEMAY AVENUE AND CONIFER STREET
ELEV= 4960.11
CITY OF FORT COLLINS BENCHMARK #12-07
SOUTH SIDE OF VINE DRIVE ON THE SOUTH HEADWALL OF THE BRIDGE OVER DRY CREEK BASIN 0.4 MILES EAST OF NORTH
LEMAY AVENUE
ELEV= 4947.86
BASIS OF BEARINGS:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED
NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY PURPOSE,
THE FOLLOWING EQUATIONS SHOULD BE USED:
NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4960.11 (NAVD88 DATUM) - 3.17'
NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4947.86 (NAVD88 DATUM) - 3.18'
UTILITY CONTACTS:
CIVIL PLANS FOR
NORTHFIELD COMMONS
A REPLAT OF TRACTS U AND V OF NORTHFIELD
LOCATED IN THE SOUTHEAST 1/4 SECTION 1, TOWNSHIP 7 NORTH, RANGE 69 WEST OF THE P.M.
CITY OF FORT COLLINS, LARIMER COUNTY, COLORADO
SEPTEMBER 2021
ABBREVIATION LIST
ABC AGGREGATE BASE COURSE
AD ALGEBRAIC DIFFERENCE
AE ACCESS EASEMENT
ARCH ARCHITECT
ARV AIR RELEASE VALVE
ASPH ASPHALT
BLDG BUILDING
BE BUILDING ENVELOPE
BFV BUTTERFLY VALVE
BOV BLOW OFF VALVE
BOS BOTTOM OF STEP
BOW BACK OF WALK
BVC BEGINNING VERTICAL CURVE
BW BOTTOM OF WALL
C&G CURB & GUTTER
CATV CABLE TELEVISION
CDOT COLORADO DEPARTMENT OF
TRANSPORTATION
CL CENTERLINE
CMP CORRUGATED METAL PIPE
CO CLEAN OUT
COMM COMMUNICATION
CON CONDENSATE
CONC CONCRETE
COORD COORDINATION
DE DRAINAGE EASEMENT
D&UE DRAINAGE & UTILITY EASEMENT
D,U,AE DRAINAGE, UTILITY & ACCESS EASEMENT
DEMO DEMOLITION
DIA DIAMETER
DIP DUCTILE IRON PIPE
E EAST(ING)
EAE EMERGENCY ACCESS EASEMENT
EEA EASEMENT EXCLUSION AREA
EG EXISTING GROUND
EL ELEVATION
ELEC ELECTRIC
EOA EDGE OF ASPHALT
EOC EDGE OF CONCRETE
ESMT EASEMENT
EST ESTIMATE(D)
EX EXISTING
EVC END VERTICAL CURVE
F FIRE LINE
FCLWD FORT COLLINS LOVELAND WATER DISTRICT
FDC FIRE DEPARTMENT CONNECTION
FES FLARED END SECTION
FF FINISHED FLOOR
FFE FINISHED FLOOR ELEVATION
FG FINISHED GRADE
FH FIRE HYDRANT
FL FLOWLINE
FO FIBER OPTIC
G GAS
GB GRADE BREAK
GF GARAGE FLOOR
GND GROUND
GV GATE VALVE
HBP HOT BITUMINOUS PAVEMENT
HORZ HORIZONTAL
HDPE HIGH DENSITY POLYETHYLENE
HP HIGH POINT
HW HEADWALL
IE IRRIGATION EASEMENT
INV INVERT
IRR IRRIGATION
LA LANDSCAPE (PLAN/ACRH)
LCUASS LARIMER COUNTY URBAN AREA STREET
STANDARDS
LF LINEAR FEET
LP LOW POINT
LT LEFT
MAX MAXIMUM
ME MATCH EXISTING
MEP MECHANICAL, ELECTRICAL, PLUMBING
ENGINEER
MH MANHOLE
MIN MINIMUM
N NORTH(ING)
NA NOT APPLICABLE
NTS NOT TO SCALE
OC ON CENTER
OHE OVERHEAD ELECTRIC
OHT OVERHEAD TELEPHONE
OHU OVERHEAD UTILITY
P&UE PEDESTRIAN & UTILITY EASEMENT
PE PEDESTRIAN EASEMENT
PERF PERFORATED
PC POINT OF CURVATURE
PCC PORTLAND CEMENT CONCRETE
PCR POINT OF CURB RETURN
PH POTHOLE
PI POINT OF INTERSECTION
PL PROPERTY LINE
PT POINT OF TANGENCY
PVC POLYVINYL CHLORIDE
R&R REMOVAL & REPLACEMENT
RCP REINFORCED CONCRETE PIPE
RD ROOF DRAIN
RE REFERENCE
RJ RESTRAINT JOINT
ROW RIGHT-OF-WAY
RT RIGHT
SCH SCHEDULE
S SOUTH
SD STORM DRAIN PIPE
SDMH STORM DRAIN MANHOLE
SFCSD SOUTH FORT COLLINS SANITATION DISTRICT
SRVC SERVICE
SS SANITARY SEWER
SSCO SANITARY SEWER CLEAN-OUT
SSMH SANITARY SEWER MANHOLE
SSWR SANITARY SEWER
STA STATION
SWMP STORMWATER MANAGEMENT PLAN
T TELEPHONE
TB THRUST BLOCK
TBC TOP BACK OF CURB
TBV TO BE VACATED
TBR TO BE REMOVED
TELE TELEPHONE
TEMP TEMPORARY
TR5 TIMNATH RACH SUBDIVISION- 5TH FILING
TF TOP OF FOUNDATION
TOS TOP OF STEP
TS TOP OF SLAB
TW TOP OF WALL
TYP TYPICAL
XS CROSS SECTION
UD UNDERDRAIN
UE UTILITY EASEMENT
UGE UNDERGROUND ELECTRIC
UTIL UTILITY
VCP VITRIFIED CLAY PIPE
VIF VERIFY IN FIELD
VERT VERTICAL
VPC VERTICAL POINT OF CURVATURE
VPI VERTICAL POINT OF INTERSECTION
VPT VERTICAL POINT OF TANGENCY
W WATERLINE OR WEST
WL WATERLINE
WQCE WATER QUALITY CONTROL ELEVATION
WSE WATER SURFACE ELEVATION
N
W E
S
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Traffic Operations,
Park Planning and Development,
Stormwater Utility,
Water & Wastewater Utility,
City Engineer,
APPROVED:
Environmental Planner,
Approved Sheets Date
APPROVED:
Approved Sheets Date
APPROVED:
Approved Sheets Date
APPROVED:
Approved Sheets Date
APPROVED:
Approved Sheets Date
APPROVED:
Approved Sheets Date
LIGHT & POWER
City of Fort Collins Light & Power
700 Wood Street
Fort Collins, Colorado 80522
Contact: Luke Unruh
Ph. 970.416.2724
STORMWATER,WATER & WASTEWATER
City of Fort Collins Utilities
700 Wood Street
Fort Collins, Colorado 80522
Contact: Dan Mogen
Ph. 970.221.6192
NATURAL GAS
Xcel Energy
1901 E. Horsetooth Road
Fort Collins, Colorado 80525
Contact: Stephanie Rich
Ph. 970.225.7828
TELEPHONE SERVICE
Century Link (Qwest)
3351 Eastbrook Drive
Fort Collins, Colorado 80525
Contact: Bill Johnson
Ph. 970.490.7501
CABLE SERVICE
Comcast
1201 University Dr.
Fort Collins, Colorado 80521
Contact: Don Kapperman
Ph. 970.567.0245
DEVELOPERS
Landmark Real Estate Holdings
6341 Fairgrounds Ave, Suite 100
Windsor, CO 80550
Ph. 970.460.0567
Mercy Housing
1600 Broadway, Suite 200
Denver, CO 80202
Ph. 303.830.3470
ENGINEER
Highland Development Services
6355 Fairgrounds Ave, Suite 100
Windsor, CO 80550
Ph. 970.674.7550
LANDSCAPE ARCHITECT
The Birdsall Group
444 Mountain Ave
Berthoud CO, 80513
Ph. 970.532.5891
SURVEYOR
PLS Group
532 W 66th Street
Loveland, CO 80538
Ph. 970.669.2100
ARCHITECT
alm2S
712 Whalers Way, Bldg B, Suite 100
Fort Collins, CO 80525
Ph. 970.223.1820
I HEREBY AFFIRM THAT THESE FINAL CONSTRUCTION PLANS WERE PREPARED UNDER MY
DIRECT SUPERVISION, IN ACCORDANCE WITH ALL APPLICABLE CITY OF FORT COLLINS
AND STATE OF COLORADO STANDARDS AND STATUTES, RESPECTIVELY, AND THAT I AM
FULLY RESPONSIBLE FOR THE ACCURACY OF ALL DESIGN, REVISIONS AND RECORD
CONDITIONS THAT I HAVE NOTED ON THESE PLANS.
INDEMNIFICATION STATEMENT:
THESE PLANS HAVE BEEN REVIEWED BY THE LOCAL ENTITY FOR CONCEPT ONLY. THE
REVIEW DOES NOT IMPLY RESPONSIBILITY BY THE REVIEWING DEPARTMENT, THE LOCAL
ENTITY ENGINEER, OR THE LOCAL ENTITY FOR ACCURACY AND CORRECTNESS OF THE
CALCULATIONS. FURTHERMORE, THE REVIEW DOES NOT IMPLY THAT QUANTITIES OF ITEMS
ON THE PLANS ARE THE FINAL QUANTITIES REQUIRED. THE REVIEW SHALL NOT BE
CONSTRUED IN ANY REASON AS ACCEPTANCE OF FINANCIAL RESPONSIBILITY BY THE
LOCAL ENTITY FOR ADDITIONAL QUANTITIES OF ITEMS SHOWN THAT MAY BE REQUIRED
DURING THE CONSTRUCTION PHASE.
JASON T. CLAEYS
P.E. NO. 42122PROJECT CONTACTS:
INDEX OF SHEETS
Sheet No.Discipline No.Description of Sheets
1 C0.00 COVER SHEET
2 C0.01 GENERAL NOTES
3 C0.02 EXISTING CONDITIONS
4-5 C1.00-C1.01 HORIZONTAL CONTROL PLAN
6 C2.00 DRAINAGE & EROSION CONTROL PLAN
7 C2.01 DETAILED GRADING PLAN
8 C3.00 OVERALL UTILITY PLAN
9 C3.01 SANITARY SEWER PLAN & PROFILE
10 C3.02 WATERLINE PLAN & PROFILE
11 C3.03 STORM PLAN & PROFILE
12-18 C4.00-C4.06 CONSTRUCTION DETAILS
City of Fort Collins Approved Plans
Approved by:
Date:
Grading/Stormwater Certification Accepted
(Certificat e of Occupancy Released)
Accepted by:
Date :
☐Escrow washeld forCO and is now released
Grading/Stormwater Plan Accepted
(Building Permit Released)
Accepted by:
Date :
Utility (Water/Sewer)Plan Approved
(Building Permit Released)
Approved by:
Date :
we
Fort Collins Utilities Redlines
Water, Wastewater & Stormwater
Thank you for the opportunity to review the se plans.
I encourage you to contact me to discuss questions &
revisions prior to resubmittal.
dmogen@fcgov.com or 970-305-5989
Reviewed by:
Date :
Dan Mogen
09/28/2021
1.ALL MATERIALS, WORKMANSHIP, AND CONSTRUCTION OF PUBLIC IMPROVEMENTS SHALL MEET OR EXCEED THE STANDARDS AND SPECIFICATIONS SET
FORTH IN THE LARIMER COUNTY URBAN AREA STREET STANDARDS AND APPLICABLE STATE AND FEDERAL REGULATIONS. WHERE THERE IS CONFLICT
BETWEEN THESE PLANS AND THE SPECIFICATIONS, OR ANY APPLICABLE STANDARDS, THE MOST RESTRICTIVE STANDARD SHALL APPLY. ALL WORK SHALL BE
INSPECTED AND APPROVED BY THE LOCAL ENTITY.
2.ALL REFERENCES TO ANY PUBLISHED STANDARDS SHALL REFER TO THE LATEST REVISION OF SAID STANDARD, UNLESS SPECIFICALLY STATED OTHERWISE.
3.THESE PUBLIC IMPROVEMENT CONSTRUCTION PLANS SHALL BE VALID FOR A PERIOD OF THREE YEARS FROM THE DATE OF APPROVAL BY THE LOCAL
ENTITY ENGINEER. USE OF THESE PLANS AFTER THE EXPIRATION DATE WILL REQUIRE A NEW REVIEW AND APPROVAL PROCESS BY THE LOCAL ENTITY PRIOR
TO COMMENCEMENT OF ANY WORK SHOWN IN THESE PLANS.
4.THE ENGINEER WHO HAS PREPARED THESE PLANS, BY EXECUTION AND/OR SEAL HEREOF, DOES HEREBY AFFIRM RESPONSIBILITY TO THE LOCAL ENTITY, AS
BENEFICIARY OF SAID ENGINEER'S WORK, FOR ANY ERRORS AND OMISSIONS CONTAINED IN THESE PLANS, AND APPROVAL OF THESE PLANS BY THE
LOCAL ENTITY ENGINEER SHALL NOT RELIEVE THE ENGINEER WHO HAS PREPARED THESE PLANS OF ALL SUCH RESPONSIBILITY. FURTHER, TO THE EXTENT
PERMITTED BY LAW, THE ENGINEER HEREBY AGREES TO HOLD HARMLESS AND INDEMNIFY THE LOCAL ENTITY, AND ITS OFFICERS AND EMPLOYEES, FROM
AND AGAINST ALL LIABILITIES, CLAIMS, AND DEMANDS WHICH MAY ARISE FROM ANY ERRORS AND OMISSIONS CONTAINED IN THESE PLANS.
5.ALL SANITARY SEWER, STORM SEWER, AND WATER LINE CONSTRUCTION, AS WELL AS POWER AND OTHER "DRY" UTILITY INSTALLATIONS, SHALL CONFORM
TO THE LOCAL ENTITY STANDARDS AND SPECIFICATIONS CURRENT AT THE DATE OF APPROVAL OF THE PLANS BY THE LOCAL ENTITY ENGINEER.
6.THE TYPE, SIZE, LOCATION AND NUMBER OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN SHOWN ON THE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER TO VERIFY THE EXISTENCE AND LOCATION OF ALL UNDERGROUND UTILITIES ALONG THE ROUTE OF THE WORK BEFORE
COMMENCING NEW CONSTRUCTION. THE DEVELOPER SHALL BE RESPONSIBLE FOR UNKNOWN UNDERGROUND UTILITIES.
7.THE CONTRACTOR SHALL CONTACT THE UTILITY NOTIFICATION CENTER OF COLORADO (UNCC) AT 1-800-922-1987, AT LEAST 2 WORKING DAYS PRIOR TO
BEGINNING EXCAVATION OR GRADING, TO HAVE ALL REGISTERED UTILITY LOCATIONS MARKED. OTHER UNREGISTERED UTILITY ENTITIES (I.E. DITCH /
IRRIGATION COMPANY) ARE TO BE LOCATED BY CONTACTING THE RESPECTIVE REPRESENTATIVE. UTILITY SERVICE LATERALS ARE ALSO TO BE LOCATED
PRIOR TO BEGINNING EXCAVATION OR GRADING. IT SHALL BE THE RESPONSIBILITY OF THE DEVELOPER TO RELOCATE ALL EXISTING UTILITIES THAT
CONFLICT WITH THE PROPOSED IMPROVEMENTS SHOWN ON THESE PLANS.
8.THE DEVELOPER SHALL BE RESPONSIBLE FOR PROTECTING ALL UTILITIES DURING CONSTRUCTION AND FOR COORDINATING WITH THE APPROPRIATE UTILITY
COMPANY FOR ANY UTILITY CROSSINGS REQUIRED.
9.IF A CONFLICT EXISTS BETWEEN EXISTING AND PROPOSED UTILITIES AND/OR A DESIGN MODIFICATION IS REQUIRED, THE DEVELOPER SHALL COORDINATE
WITH THE ENGINEER TO MODIFY THE DESIGN. DESIGN MODIFICATION(S) MUST BE APPROVED BY THE LOCAL ENTITY PRIOR TO BEGINNING CONSTRUCTION.
10.THE DEVELOPER SHALL COORDINATE AND COOPERATE WITH THE LOCAL ENTITY, AND ALL UTILITY COMPANIES INVOLVED, TO ASSURE THAT THE WORK IS
ACCOMPLISHED IN A TIMELY FASHION AND WITH A MINIMUM DISRUPTION OF SERVICE. THE DEVELOPER SHALL BE RESPONSIBLE FOR CONTACTING, IN
ADVANCE, ALL PARTIES AFFECTED BY ANY DISRUPTION OF ANY UTILITY SERVICE AS WELL AS THE UTILITY COMPANIES.
11.NO WORK MAY COMMENCE WITHIN ANY PUBLIC STORM WATER, SANITARY SEWER OR POTABLE WATER SYSTEM UNTIL THE DEVELOPER NOTIFIES THE
UTILITY PROVIDER. NOTIFICATION SHALL BE A MINIMUM OF 2 WORKING DAYS PRIOR TO COMMENCEMENT OF ANY WORK. AT THE DISCRETION OF THE
WATER UTILITY PROVIDER, A PRE-CONSTRUCTION MEETING MAY BE REQUIRED PRIOR TO COMMENCEMENT OF ANY WORK.
12.THE DEVELOPER SHALL SEQUENCE INSTALLATION OF UTILITIES IN SUCH A MANNER AS TO MINIMIZE POTENTIAL UTILITY CONFLICTS. IN GENERAL, STORM
SEWER AND SANITARY SEWER SHOULD BE CONSTRUCTED PRIOR TO INSTALLATION OF THE WATER LINES AND DRY UTILITIES.
13.THE MINIMUM COVER OVER WATER LINES IS 4.5 FEET AND THE MAXIMUM COVER IS 5.5 FEET UNLESS OTHERWISE NOTED IN THE PLANS AND APPROVED BY
THE WATER UTILITY.
14.A STATE CONSTRUCTION DEWATERING WASTEWATER DISCHARGE PERMIT IS REQUIRED IF DEWATERING IS REQUIRED IN ORDER TO INSTALL UTILITIES OR
WATER IS DISCHARGED INTO A STORM SEWER, CHANNEL, IRRIGATION DITCH OR ANY WATERS OF THE UNITED STATES.
15.THE DEVELOPER SHALL COMPLY WITH ALL TERMS AND CONDITIONS OF THE COLORADO PERMIT FOR STORM WATER DISCHARGE (CONTACT COLORADO
DEPARTMENT OF HEALTH, WATER QUALITY CONTROL DIVISION, (303) 692-3590), THE STORM WATER MANAGEMENT PLAN, AND THE EROSION CONTROL
PLAN.
16.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF STORM DRAINAGE FACILITIES LOCATED ON PRIVATE PROPERTY.
MAINTENANCE OF ONSITE DRAINAGE FACILITIES SHALL BE THE RESPONSIBILITY OF THE PROPERTY OWNER(S).
17.PRIOR TO FINAL INSPECTION AND ACCEPTANCE BY THE LOCAL ENTITY, CERTIFICATION OF THE DRAINAGE FACILITIES, BY A REGISTERED ENGINEER, MUST
BE SUBMITTED TO AND APPROVED BY THE STORMWATER UTILITY DEPARTMENT. CERTIFICATION SHALL BE SUBMITTED TO THE STORMWATER UTILITY
DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF A CERTIFICATE OF OCCUPANCY FOR SINGLE FAMILY UNITS. FOR COMMERCIAL
PROPERTIES, CERTIFICATION SHALL BE SUBMITTED TO THE STORMWATER UTILITY DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF ANY
BUILDING PERMITS IN EXCESS OF THOSE ALLOWED PRIOR TO CERTIFICATION PER THE DEVELOPMENT AGREEMENT.
18.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR ANY DAMAGES OR INJURIES SUSTAINED IN THIS DEVELOPMENT AS A RESULT OF GROUNDWATER
SEEPAGE, WHETHER RESULTING FROM GROUNDWATER FLOODING, STRUCTURAL DAMAGE OR OTHER DAMAGE UNLESS SUCH DAMAGE OR INJURIES ARE
SUSTAINED AS A RESULT OF THE LOCAL ENTITY FAILURE TO PROPERLY MAINTAIN ITS WATER, WASTEWATER, AND/OR STORM DRAINAGE FACILITIES IN THE
DEVELOPMENT.
19.TEMPORARY EROSION CONTROL DURING CONSTRUCTION SHALL BE PROVIDED AS SHOWN ON THE EROSION CONTROL PLAN. ALL EROSION CONTROL
MEASURES SHALL BE MAINTAINED IN GOOD REPAIR BY THE DEVELOPER, UNTIL SUCH TIME AS THE ENTIRE DISTURBED AREAS IS STABILIZED WITH HARD
SURFACE OR LANDSCAPING.
20.THE DEVELOPER SHALL BE RESPONSIBLE FOR INSURING THAT NO MUD OR DEBRIS SHALL BE TRACKED ONTO THE EXISTING PUBLIC STREET SYSTEM. MUD AND
DEBRIS MUST BE REMOVED WITHIN 24 HOURS BY AN APPROPRIATE MECHANICAL METHOD (I.E. MACHINE BROOM SWEEP, LIGHT DUTY FRONT-END
LOADER, ETC.) OR AS APPROVED BY THE LOCAL ENTITY STREET INSPECTOR.
21.NO WORK MAY COMMENCE WITHIN ANY IMPROVED OR UNIMPROVED PUBLIC RIGHT-OF-WAY UNTIL A RIGHT-OF-WAY PERMIT OR DEVELOPMENT
CONSTRUCTION PERMIT IS OBTAINED, IF APPLICABLE.
22.THE DEVELOPER SHALL BE RESPONSIBLE FOR OBTAINING ALL NECESSARY PERMITS FOR ALL APPLICABLE AGENCIES PRIOR TO COMMENCEMENT OF
CONSTRUCTION. THE DEVELOPER SHALL NOTIFY THE LOCAL ENTITY ENGINEERING INSPECTOR (FORT COLLINS - 221-6605) AND THE LOCAL ENTITY EROSION
CONTROL INSPECTOR (FORT COLLINS - 221-6700) AT LEAST 2 WORKING DAYS PRIOR TO THE START OF ANY EARTH DISTURBING ACTIVITY, OR
CONSTRUCTION ON ANY AND ALL PUBLIC IMPROVEMENTS. IF THE LOCAL ENTITY ENGINEER IS NOT AVAILABLE AFTER PROPER NOTICE OF CONSTRUCTION
ACTIVITY HAS BEEN PROVIDED, THE DEVELOPER MAY COMMENCE WORK IN THE ENGINEER ABSENCE. HOWEVER, THE LOCAL ENTITY RESERVES THE RIGHT
NOT TO ACCEPT THE IMPROVEMENT IF SUBSEQUENT TESTING REVEALS AN IMPROPER INSTALLATION.
23.THE DEVELOPER SHALL BE RESPONSIBLE FOR OBTAINING SOILS TESTS WITHIN THE PUBLIC RIGHT-OF-WAY AFTER RIGHT OF WAY GRADING AND ALL UTILITY
TRENCH WORK IS COMPLETE AND PRIOR TO THE PLACEMENT OF CURB, GUTTER, SIDEWALK AND PAVEMENT. IF THE FINAL SOILS/PAVEMENT DESIGN
REPORT DOES NOT CORRESPOND WITH THE RESULTS OF THE ORIGINAL GEOTECHNICAL REPORT, THE DEVELOPER SHALL BE RESPONSIBLE FOR A RE-DESIGN
OF THE SUBJECT PAVEMENT SECTION OR, THE DEVELOPER MAY USE THE LOCAL ENTITY'S DEFAULT PAVEMENT THICKNESS SECTION(S). REGARDLESS OF THE
OPTION USED, ALL FINAL SOILS/PAVEMENT DESIGN REPORTS SHALL BE PREPARED BY A LICENSED PROFESSIONAL ENGINEER. THE FINAL REPORT SHALL BE
SUBMITTED TO THE INSPECTOR A MINIMUM OF 10 WORKING DAYS PRIOR TO PLACEMENT OF BASE AND ASPHALT. PLACEMENT OF CURB, GUTTER,
SIDEWALK, BASE AND ASPHALT SHALL NOT OCCUR UNTIL THE LOCAL ENTITY ENGINEER APPROVES THE FINAL REPORT.
24.THE CONTRACTOR SHALL HIRE A LICENSED ENGINEER OR LAND SURVEYOR TO SURVEY THE CONSTRUCTED ELEVATIONS OF THE STREET SUBGRADE AND
THE GUTTER FLOWLINE AT ALL INTERSECTIONS, INLETS, AND OTHER LOCATIONS REQUESTED BY THE LOCAL ENTITY INSPECTOR. THE ENGINEER OR
SURVEYOR MUST CERTIFY IN A LETTER TO THE LOCAL ENTITY THAT THESE ELEVATIONS CONFORM TO THE APPROVED PLANS AND SPECIFICATIONS. ANY
DEVIATIONS SHALL BE NOTED IN THE LETTER AND THEN RESOLVED WITH THE LOCAL ENTITY BEFORE INSTALLATION OF BASE COURSE OR ASPHALT WILL BE
ALLOWED ON THE STREETS.
25.ALL UTILITY INSTALLATIONS WITHIN OR ACROSS THE ROADBED OF NEW RESIDENTIAL ROADS MUST BE COMPLETED PRIOR TO THE FINAL STAGES OF ROAD
CONSTRUCTION. FOR THE PURPOSES OF THESE STANDARDS, ANY WORK EXCEPT C/G ABOVE THE SUBGRADE IS CONSIDERED FINAL STAGE WORK. ALL
SERVICE LINES MUST BE STUBBED TO THE PROPERTY LINES AND MARKED SO AS TO REDUCE THE EXCAVATION NECESSARY FOR BUILDING CONNECTIONS.
26.PORTIONS OF LARIMER COUNTY ARE WITHIN OVERLAY DISTRICTS. THE LARIMER COUNTY FLOODPLAIN RESOLUTION SHOULD BE REFERRED TO FOR
ADDITIONAL CRITERIA FOR ROADS WITHIN THESE DISTRICTS.
27.ALL ROAD CONSTRUCTION IN AREAS DESIGNATED AS WILD FIRE HAZARD AREAS SHALL BE DONE IN ACCORDANCE WITH THE CONSTRUCTION CRITERIA
AS ESTABLISHED IN THE WILD FIRE HAZARD AREA MITIGATION REGULATIONS IN FORCE AT THE TIME OF FINAL PLAT APPROVAL.
28.PRIOR TO THE COMMENCEMENT OF ANY CONSTRUCTION, THE CONTRACTOR SHALL CONTACT THE LOCAL ENTITY FORESTER TO SCHEDULE A SITE
INSPECTION FOR ANY TREE REMOVAL REQUIRING A PERMIT.
29.THE DEVELOPER SHALL BE RESPONSIBLE FOR ALL ASPECTS OF SAFETY INCLUDING, BUT NOT LIMITED TO, EXCAVATION, TRENCHING, SHORING, TRAFFIC
CONTROL, AND SECURITY. REFER TO OSHA PUBLICATION 2226, EXCAVATING AND TRENCHING.
30.THE DEVELOPER SHALL SUBMIT A CONSTRUCTION TRAFFIC CONTROL PLAN, IN ACCORDANCE WITH MUTCD, TO THE APPROPRIATE RIGHT-OF-WAY
AUTHORITY. (LOCAL ENTITY, COUNTY OR STATE), FOR APPROVAL, PRIOR TO ANY CONSTRUCTION ACTIVITIES WITHIN, OR AFFECTING, THE RIGHT-OF-WAY.
THE DEVELOPER SHALL BE RESPONSIBLE FOR PROVIDING ANY AND ALL TRAFFIC CONTROL DEVICES AS MAY BE REQUIRED BY THE CONSTRUCTION
ACTIVITIES.
31.PRIOR TO THE COMMENCEMENT OF ANY CONSTRUCTION THAT WILL AFFECT TRAFFIC SIGNS OF ANY TYPE, THE CONTRACTOR SHALL CONTACT LOCAL
ENTITY TRAFFIC OPERATIONS DEPARTMENT, WHO WILL TEMPORARILY REMOVE OR RELOCATE THE SIGN AT NO COST TO THE CONTRACTOR; HOWEVER, IF
THE CONTRACTOR MOVES THE TRAFFIC SIGN THEN THE CONTRACTOR WILL BE CHARGED FOR THE LABOR, MATERIALS AND EQUIPMENT TO REINSTALL THE
SIGN AS NEEDED.
32.THE DEVELOPER IS RESPONSIBLE FOR ALL COSTS FOR THE INITIAL INSTALLATION OF TRAFFIC SIGNING AND STRIPING FOR THE DEVELOPMENT RELATED TO
THE DEVELOPMENT'S LOCAL STREET OPERATIONS. IN ADDITION, THE DEVELOPER IS RESPONSIBLE FOR ALL COSTS FOR TRAFFIC SIGNING AND STRIPING
RELATED TO DIRECTING TRAFFIC ACCESS TO AND FROM THE DEVELOPMENT.
33.THERE SHALL BE NO SITE CONSTRUCTION ACTIVITIES ON SATURDAYS, UNLESS SPECIFICALLY APPROVED BY THE LOCAL ENTITY ENGINEER, AND NO SITE
CONSTRUCTION ACTIVITIES ON SUNDAYS OR HOLIDAYS, UNLESS THERE IS PRIOR WRITTEN APPROVAL BY THE LOCAL ENTITY.
34.THE DEVELOPER IS RESPONSIBLE FOR PROVIDING ALL LABOR AND MATERIALS NECESSARY FOR THE COMPLETION OF THE INTENDED IMPROVEMENTS,
SHOWN ON THESE DRAWINGS, OR DESIGNATED TO BE PROVIDED, INSTALLED, OR CONSTRUCTED, UNLESS SPECIFICALLY NOTED OTHERWISE.
35.DIMENSIONS FOR LAYOUT AND CONSTRUCTION ARE NOT TO BE SCALED FROM ANY DRAWING. IF PERTINENT DIMENSIONS ARE NOT SHOWN, CONTACT
THE DESIGNER FOR CLARIFICATION, AND ANNOTATE THE DIMENSION ON THE AS-BUILT RECORD DRAWINGS.
36.THE DEVELOPER SHALL HAVE, ONSITE AT ALL TIMES, ONE (1) SIGNED COPY OF THE APPROVED PLANS, ONE (1) COPY OF THE APPROPRIATE STANDARDS
AND SPECIFICATIONS, AND A COPY OF ANY PERMITS AND EXTENSION AGREEMENTS NEEDED FOR THE JOB.
37.IF, DURING THE CONSTRUCTION PROCESS, CONDITIONS ARE ENCOUNTERED WHICH COULD INDICATE A SITUATION THAT IS NOT IDENTIFIED IN THE PLANS
OR SPECIFICATIONS, THE DEVELOPER SHALL CONTACT THE DESIGNER AND THE LOCAL ENTITY ENGINEER IMMEDIATELY.
38.THE DEVELOPER SHALL BE RESPONSIBLE FOR RECORDING AS-BUILT INFORMATION ON A SET OF RECORD DRAWINGS KEPT ON THE CONSTRUCTION SITE,
AND AVAILABLE TO THE LOCAL ENTITY'S INSPECTOR AT ALL TIMES. UPON COMPLETION OF THE WORK, THE CONTRACTOR(S) SHALL SUBMIT RECORD
DRAWINGS TO THE LOCAL ENTITY ENGINEER.
39.PROJECT BENCHMARKS:
PROJECT DATUM: NAVD88
CITY OF FORT COLLINS BENCHMARK #43-97
ON THE SOUTH END OF THE WEST HEADWALL OF THE LAKE CANAL BRIDGE AT NORTH LEMAY AVENUE, 200 FEET SOUTH OF THE INTERSECTION OF LEMAY
AVENUE. AND CONIFER STREET
ELEV= 4960.11
CITY OF FORT COLLINS BENCHMARK #12-07
SOUTH SIDE OF VINE DRIVE ON THE SOUTH HEADWALL OF THE BRIDGE OVER DRY CREEK BASIN 0.4 MILES EAST OF NORTH LEMAY AVENUE
ELEV= 4947.86
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED DATUM
(PRIOR CITY OF FORT COLLINS DATUM) FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY PURPOSE,THE FOLLOWING EQUATIONS SHOULD BE USED:
NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4960.11 (NAVD88 DATUM) - 3.17
NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = 4947.86 (NAVD88 DATUM) - 3.18
HORIZONTAL DATUM: COLORADO STATE PLAN COORDINATES NAD 83(2007) DATUM. HORIZONTAL CONTROL BASED VRS.
40.ALL STATIONING IS BASED ON FLOWLINE OF ROADWAYS UNLESS OTHERWISE NOTED.
41.DAMAGED CURB, GUTTER AND SIDEWALK EXISTING PRIOR TO CONSTRUCTION, AS WELL AS EXISTING FENCES, TREES, STREETS, SIDEWALKS, CURBS AND
GUTTERS, LANDSCAPING, STRUCTURES, AND IMPROVEMENTS DESTROYED, DAMAGED OR REMOVED DUE TO CONSTRUCTION OF THIS PROJECT, SHALL BE
REPLACED OR RESTORED IN LIKE KIND AT THE DEVELOPER'S EXPENSE, UNLESS OTHERWISE INDICATED ON THESE PLANS, PRIOR TO THE ACCEPTANCE OF
COMPLETED IMPROVEMENTS AND/OR PRIOR TO THE ISSUANCE OF THE FIRST CERTIFICATE OF OCCUPANCY.
42.WHEN AN EXISTING ASPHALT STREET MUST BE CUT, THE STREET MUST BE RESTORED TO A CONDITION EQUAL TO OR BETTER THAN ITS ORIGINAL CONDITION.
THE EXISTING STREET CONDITION SHALL BE DOCUMENTED BY THE LOCAL ENTITY CONSTRUCTION INSPECTOR BEFORE ANY CUTS ARE MADE. PATCHING
SHALL BE DONE IN ACCORDANCE WITH THE LOCAL ENTITY STREET REPAIR STANDARDS. THE FINISHED PATCH SHALL BLEND IN SMOOTHLY INTO THE
EXISTING SURFACE. ALL LARGE PATCHES SHALL BE PAVED WITH AN ASPHALT LAY-DOWN MACHINE. IN STREETS WHERE MORE THAN ONE CUT IS MADE, AN
OVERLAY OF THE ENTIRE STREET WIDTH, INCLUDING THE PATCHED AREA, MAY BE REQUIRED. THE DETERMINATION OF NEED FOR A COMPLETE OVERLAY
SHALL BE MADE BY THE LOCAL ENTITY ENGINEER AND/OR THE LOCAL ENTITY INSPECTOR AT THE TIME THE CUTS ARE MADE.
43.UPON COMPLETION OF CONSTRUCTION, THE SITE SHALL BE CLEANED AND RESTORED TO A CONDITION EQUAL TO, OR BETTER THAN, THAT WHICH EXISTED
BEFORE CONSTRUCTION, OR TO THE GRADES AND CONDITION AS REQUIRED BY THESE PLANS.
44.STANDARD HANDICAP RAMPS ARE TO BE CONSTRUCTED AT ALL CURB RETURNS AND AT ALL "T" INTERSECTIONS.
45.AFTER ACCEPTANCE BY THE LOCAL ENTITY, PUBLIC IMPROVEMENTS DEPICTED IN THESE PLANS SHALL BE GUARANTEED TO BE FREE FROM MATERIAL AND
WORKMANSHIP DEFECTS FOR A MINIMUM PERIOD OF TWO YEARS FROM THE DATE OF ACCEPTANCE.
46.THE LOCAL ENTITY SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF ROADWAY AND APPURTENANT IMPROVEMENTS, INCLUDING STORM
DRAINAGE STRUCTURES AND PIPES, FOR THE FOLLOWING PRIVATE STREETS: NO PRIVATE STREET PROPOSED.
47.APPROVED VARIANCES ARE LISTED AS FOLLOWS: APF MITIGATION VARIANCE, NO WESTBOUND RIGHT TURN LANE ON SUNIGA RD AT LANDMARK WAY
VARIANCE.
CITY OF FORT COLLINS CONSTRUCTION NOTES
A.STANDARD GRADING AND EROSION AND SEDIMENT CONTROL CONSTRUCTION PLAN NOTES
1.THE EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST TWENTY-FOUR (24) HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE.
2.THERE SHALL BE NO EARTH-DISTURBING ACTIVITY OUTSIDE THE LIMITS DESIGNATED ON THE ACCEPTED PLANS.
3.ALL REQUIRED PERIMETER SILT AND CONSTRUCTION FENCING SHALL BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING, STRIPPING,
GRADING, ETC). ALL OTHER REQUIRED EROSION CONTROL MEASURES SHALL BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE
AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTION PLANS, AND EROSION CONTROL REPORT.
4.AT ALL TIMES DURING CONSTRUCTION, THE DEVELOPER SHALL BE RESPONSIBLE FOR PREVENTING AND CONTROLLING ON-SITE EROSION INCLUDING
KEEPING THE PROPERTY SUFFICIENTLY WATERED SO AS TO MINIMIZE WIND BLOWN SEDIMENT. THE DEVELOPER SHALL ALSO BE RESPONSIBLE FOR
INSTALLING AND MAINTAINING ALL EROSION CONTROL FACILITIES SHOWN HEREIN.
5.PRE-DISTURBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL
BE LIMITED TO THE AREA(S) REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME.
6.ALL SOILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING, GRADING, UTILITY INSTALLATIONS, STOCKPILING, FILLING, ETC.) SHALL BE KEPT IN A
ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL
BMPS ARE INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHTS-OF-WAY SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE
THAN THIRTY (30) DAYS BEFORE REQUIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEED/MULCH, LANDSCAPING, ETC.) IS INSTALLED,
UNLESS OTHERWISE APPROVED BY THE LOCAL ENTITY.
7.IN ORDER TO MINIMIZE EROSION POTENTIAL, ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES SHALL:
a.BE INSPECTED AT A MINIMUM OF ONCE EVERY TWO (2) WEEKS AND AFTER EACH SIGNIFICANT STORM EVENT AND REPAIRED OR RECONSTRUCTED
AS NECESSARY IN ORDER TO ENSURE THE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION.
b.REMAIN IN PLACE UNTIL SUCH TIME AS ALL THE SURROUNDING DISTURBED AREAS ARE SUFFICIENTLY STABILIZED AS DETERMINED BY THE EROSION
CONTROL INSPECTOR.
c.BE REMOVED AFTER THE SITE HAS BEEN SUFFICIENTLY STABILIZED AS DETERMINED BY THE EROSION CONTROL INSPECTOR.
8.WHEN TEMPORARY EROSION CONTROL MEASURES ARE REMOVED, THE DEVELOPER SHALL BE RESPONSIBLE FOR THE CLEAN UP AND REMOVAL OF ALL
SEDIMENT AND DEBRIS FROM ALL DRAINAGE INFRASTRUCTURE AND OTHER PUBLIC FACILITIES.
9.THE CONTRACTOR SHALL CLEAN UP ANY INADVERTENT DEPOSITED MATERIAL IMMEDIATELY AND MAKE SURE STREETS ARE FREE OF ALL MATERIALS BY THE
END OF EACH WORKING DAY.
10.ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION
SO AS NOT TO CAUSE THEIR RELEASE INTO ANY WATERS OF THE UNITED STATES.
11.NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE
ROUGHENING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER THIRTY (30) DAYS SHALL BE SEEDED AND MULCHED.
12.THE STORMWATER VOLUME CAPACITY OF DETENTION PONDS WILL BE RESTORED AND STORM SEWER LINES WILL BE CLEANED UPON COMPLETION OF THE
PROJECT AND BEFORE TURNING THE MAINTENANCE OVER TO THE LOCAL ENTITY OR HOMEOWNERS ASSOCIATION (HOA).
13.CITY ORDINANCE AND COLORADO DISCHARGE PERMIT SYSTEM (CDPS) REQUIREMENTS MAKE IT UNLAWFUL TO DISCHARGE OR ALLOW THE DISCHARGE
OF ANY POLLUTANT OR CONTAMINATED WATER FROM CONSTRUCTION SITES. POLLUTANTS INCLUDE, BUT ARE NOT LIMITED TO DISCARDED BUILDING
MATERIALS, CONCRETE TRUCK WASHOUT, CHEMICALS, OIL AND GAS PRODUCTS, LITTER, AND SANITARY WASTE. THE DEVELOPER SHALL AT ALL TIMES
TAKE WHATEVER MEASURES ARE NECESSARY TO ASSURE THE PROPER CONTAINMENT AND DISPOSAL OF POLLUTANTS ON THE SITE IN ACCORDANCE WITH
ANY AND ALL APPLICABLE LOCAL, STATE, AND FEDERAL REGULATIONS.
14.A DESIGNATED AREA SHALL BE PROVIDED ON SITE FOR CONCRETE TRUCK CHUTE WASHOUT. THE AREA SHALL BE CONSTRUCTED SO AS TO CONTAIN
WASHOUT MATERIAL AND LOCATED AT LEAST FIFTY (50) FEET AWAY FROM ANY WATERWAY DURING CONSTRUCTION. UPON COMPLETION OF
CONSTRUCTION ACTIVITIES THE CONCRETE WASHOUT MATERIAL WILL BE REMOVED AND PROPERLY DISPOSED OF PRIOR TO THE AREA BEING RESTORED.
15.TO ENSURE THAT SEDIMENT DOES NOT MOVE OFF OF INDIVIDUAL LOTS ONE OR MORE OF THE FOLLOWING SEDIMENT/EROSION CONTROL BMPS SHALL BE
INSTALLED AND MAINTAINED UNTIL THE LOTS ARE SUFFICIENTLY STABILIZED, AS DETERMINED BY THE EROSION CONTROL INSPECTOR.
a.BELOW ALL GUTTER DOWNSPOUTS.
b.OUT TO DRAINAGE SWALES.
c.ALONG LOT PERIMETER.
d.OTHER LOCATIONS, IF NEEDED.
16.CONDITIONS IN THE FIELD MAY WARRANT EROSION CONTROL MEASURES IN ADDITION TO WHAT IS SHOWN ON THESE PLANS. THE DEVELOPER SHALL
IMPLEMENT WHATEVER MEASURES ARE DETERMINED NECESSARY, AS DIRECTED BY THE CITY/COUNTY.
17.A VEHICLE TRACKING CONTROL PAD SHALL BE INSTALLED WHEN NEEDED FOR CONSTRUCTION EQUIPMENT, INCLUDING BUT NOT LIMITED TO PERSONAL
VEHICLES EXITING EXISTING ROADWAYS. NO EARTHEN MATERIALS, I.E. STONE, DIRT, ETC. SHALL BE PLACED IN THE CURB & GUTTER OR ROADWAY AS A
RAMP TO ACCESS TEMPORARY STOCKPILES, STAGING AREAS, CONSTRUCTION MATERIALS, CONCRETE WASHOUT AREAS, AND/OR BUILDING SITES.
18.AN ONSITE DETENTION POND WILL BE PROVIDED TO CONTROL STORMWATER RUNOFF FROM THE SITE.
B. STREET IMPROVEMENT NOTES
1.ALL STREET CONSTRUCTION IS SUBJECT TO THE GENERAL NOTES ON THE COVER SHEET OF THESE PLANS AS WELL AS THE STREET IMPROVEMENTS NOTES
LISTED HERE.
2.A PAVING SECTION DESIGN, SIGNED AND STAMPED BY A COLORADO LICENSED ENGINEER, MUST BE SUBMITTED TO THE LOCAL ENTITY ENGINEER FOR
APPROVAL, PRIOR TO ANY STREET CONSTRUCTION ACTIVITY, (FULL DEPTH ASPHALT SECTIONS ARE NOT PERMITTED AT A DEPTH GREATER THAN 8 INCHES
OF ASPHALT). THE JOB MIX SHALL BE SUBMITTED FOR APPROVAL PRIOR TO PLACEMENT OF ANY ASPHALT.
3.WHERE PROPOSED PAVING ADJOINS EXISTING ASPHALT, THE EXISTING ASPHALT SHALL BE SAW CUT, A MINIMUM DISTANCE OF 12 INCHES FROM THE
EXISTING EDGE, TO CREATE A CLEAN CONSTRUCTION JOINT. THE DEVELOPER SHALL BE REQUIRED TO REMOVE EXISTING PAVEMENT TO A DISTANCE
WHERE A CLEAN CONSTRUCTION JOINT CAN BE MADE. WHEEL CUTS SHALL NOT BE ALLOWED UNLESS APPROVED BY THE LOCAL ENTITY ENGINEER IN
LOVELAND.
4.STREET SUBGRADES SHALL BE SCARIFIED THE TOP 12 INCHES AND RE-COMPACTED PRIOR TO SUBBASE INSTALLATION. NO BASE MATERIAL SHALL BE LAID
UNTIL THE SUBGRADE HAS BEEN INSPECTED AND APPROVED BY THE LOCAL ENTITY ENGINEER.
5.FT. COLLINS ONLY. VALVE BOXES AND MANHOLES ARE TO BE BROUGHT UP TO GRADE AT THE TIME OF PAVEMENT PLACEMENT OR OVERLAY. VALVE BOX
ADJUSTING RINGS ARE NOT ALLOWED.
6.WHEN AN EXISTING ASPHALT STREET MUST BE CUT, THE STREET MUST BE RESTORED TO A CONDITION EQUAL TO OR BETTER THAN ITS ORIGINAL CONDITION.
THE EXISTING STREET CONDITION SHALL BE DOCUMENTED BY THE INSPECTOR BEFORE ANY CUTS ARE MADE. CUTTING AND PATCHING SHALL BE DONE IN
CONFORMANCE WITH CHAPTER 25, RECONSTRUCTION AND REPAIR. THE FINISHED PATCH SHALL BLEND SMOOTHLY INTO THE EXISTING SURFACE. THE
DETERMINATION OF NEED FOR A COMPLETE OVERLAY SHALL BE MADE BY THE LOCAL ENTITY ENGINEER. ALL OVERLAY WORK SHALL BE COORDINATED
WITH ADJACENT LANDOWNERS SUCH THAT FUTURE PROJECTS DO NOT CUT THE NEW ASPHALT OVERLAY WORK.
7.ALL TRAFFIC CONTROL DEVICES SHALL BE IN CONFORMANCE WITH THESE PLANS OR AS OTHERWISE SPECIFIED IN M.U.T.C.D. (INCLUDING COLORADO
SUPPLEMENT) AND AS PER THE RIGHT-OF-WAY WORK PERMIT TRAFFIC CONTROL PLAN.
8.THE DEVELOPER IS REQUIRED TO PERFORM A GUTTER WATER FLOW TEST IN THE PRESENCE OF THE LOCAL ENTITY INSPECTOR AND PRIOR TO INSTALLATION
OF ASPHALT. GUTTERS THAT HOLD MORE THAN ¼ INCH DEEP OR 5 FEET LONGITUDINALLY, OF WATER, SHALL BE COMPLETELY REMOVED AND
RECONSTRUCTED TO DRAIN PROPERLY.
9.PRIOR TO PLACEMENT OF H.B.P. OR CONCRETE WITHIN THE STREET AND AFTER MOISTURE/DENSITY TESTS HAVE BEEN TAKEN ON THE SUBGRADE MATERIAL
(WHEN A FULL DEPTH SECTION IS PROPOSED) OR ON THE SUBGRADE AND BASE MATERIAL (WHEN A COMPOSITE SECTION IS PROPOSED), A MECHANICAL
"PROOF ROLL" WILL BE REQUIRED. THE ENTIRE SUBGRADE AND/OR BASE MATERIAL SHALL BE ROLLED WITH A HEAVILY LOADED VEHICLE HAVING A TOTAL
GVW OF NOT LESS THAN 50,000 LBS. AND A SINGLE AXLE WEIGHT OF AT LEAST 18,000 LBS. WITH PNEUMATIC TIRES INFLATED TO NOT LESS THAT 90 P.S.I.G.
“PROOF ROLL” VEHICLES SHALL NOT TRAVEL AT SPEEDS GREATER THAN 3 M.P.H. ANY PORTION OF THE SUBGRADE OR BASE MATERIAL WHICH EXHIBITS
EXCESSIVE PUMPING OR DEFORMATION, AS DETERMINED BY THE LOCAL ENTITY ENGINEER, SHALL BE REWORKED, REPLACED OR OTHERWISE MODIFIED TO
FORM A SMOOTH, NON-YIELDING SURFACE. THE LOCAL ENTITY ENGINEER SHALL BE NOTIFIED AT LEAST 24 HOURS PRIOR TO THE “PROOF ROLL.” ALL
“PROOF ROLLS” SHALL BE PREFORMED IN THE PRESENCE OF AN INSPECTOR.
C. TRAFFIC SIGNING AND PAVEMENT MARKING CONSTRUCTION NOTES
1.ALL SIGNAGE AND MARKING IS SUBJECT TO THE GENERAL NOTES ON THE COVER SHEET OF THESE PLANS, AS WELL AS THE TRAFFIC SIGNING AND
MARKING CONSTRUCTION NOTES LISTED HERE.
2.ALL SYMBOLS, INCLUDING ARROWS, ONLYS, CROSSWALKS, STOP BARS, ETC. SHALL BE PRE-FORMED THERMO-PLASTIC.
3.ALL SIGNAGE SHALL BE PER LOCAL ENTITY STANDARDS AND THESE PLANS OR AS OTHERWISE SPECIFIED IN MUTCD.
4.ALL LANE LINES FOR ASPHALT PAVEMENT SHALL RECEIVE TWO COATS OF LATEX PAINT WITH GLASS BEADS.
5.ALL LANE LINES FOR CONCRETE PAVEMENT SHOULD BE EPOXY PAINT.
6.PRIOR TO PERMANENT INSTALLATION OF TRAFFIC STRIPING AND SYMBOLS, THE DEVELOPER SHALL PLACE TEMPORARY TABS OR TAPE DEPICTING
ALIGNMENT AND PLACEMENT OF THE SAME. THEIR PLACEMENT SHALL BE APPROVED BY THE LOCAL TRAFFIC ENGINEER PRIOR TO PERMANENT
INSTALLATION OF STRIPING AND SYMBOLS.
7.PRE-FORMED THERMO-PLASTIC APPLICATIONS SHALL BE AS SPECIFIED IN THESE PLANS AND/OR THESE STANDARDS.
8.EPOXY APPLICATIONS SHALL BE APPLIED AS SPECIFIED IN CDOT STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION.
9.ALL SURFACES SHALL BE THOROUGHLY CLEANED PRIOR TO INSTALLATION OF STRIPING OR MARKINGS.
10.ALL SIGN POSTS SHALL UTILIZE BREAK-AWAY ASSEMBLIES AND FASTENERS PER THE STANDARDS.
11.A FIELD INSPECTION OF LOCATION AND INSTALLATION OF ALL SIGNS SHALL BE PERFORMED BY THE LOCAL TRAFFIC ENGINEER. ALL DISCREPANCIES
IDENTIFIED DURING THE FIELD INSPECTION MUST BE CORRECTED BEFORE THE 2-YEAR WARRANTY PERIOD WILL BEGIN.
12.THE DEVELOPER INSTALLING SIGNS SHALL BE RESPONSIBLE FOR LOCATING AND PROTECTING ALL UNDERGROUND UTILITIES.
13.SPECIAL CARE SHALL BE TAKEN IN SIGN LOCATION TO ENSURE AN UNOBSTRUCTED VIEW OF EACH SIGN.
14.SIGNAGE AND STRIPING HAS BEEN DETERMINED BY INFORMATION AVAILABLE AT THE TIME OF REVIEW. PRIOR TO INITIATION OF THE WARRANTY PERIOD,
THE LOCAL TRAFFIC ENGINEER RESERVES THE RIGHT TO REQUIRE ADDITIONAL SIGNAGE AND/OR STRIPING IF THE LOCAL TRAFFIC ENGINEER DETERMINES
THAT AN UNFORESEEN CONDITION WARRANTS SUCH SIGNAGE ACCORDING TO THE MUTCD OR THE CDOT M AND S STANDARDS. ALL SIGNAGE AND
STRIPING SHALL FALL UNDER THE REQUIREMENTS OF THE 2-YEAR WARRANTY PERIOD FOR NEW CONSTRUCTION (EXCEPT FAIR WEAR ON TRAFFIC
MARKINGS).
15.SLEEVES FOR SIGN POSTS SHALL BE REQUIRED FOR USE IN ISLANDS/MEDIANS. REFER TO CHAPTER 14, TRAFFIC CONTROL DEVICES, FOR ADDITIONAL
DETAIL.
B.STORM DRAINAGE NOTES
1.THE CITY OF FORT COLLINS SHALL NOT BE RESPONSIBLE FOR THE MAINTENANCE OF STORM DRAINAGE FACILITIES LOCATED ON PRIVATE PROPERTY.
MAINTENANCE OF ONSITE DRAINAGE FACILITIES SHALL BE THE RESPONSIBILITY OF THE PROPERTY OWNER(S).
2.PRIOR TO FINAL INSPECTION AND ACCEPTANCE BY THE CITY OF FORT COLLINS, CERTIFICATION OF THE DRAINAGE FACILITIES, BY A REGISTERED
ENGINEER, MUST BY SUBMITTED TO AND APPROVED BY THE STORMWATER UTILITY DEPARTMENT. CERTIFICATION SHALL BE SUBMITTED TO THE STORMWATER
UTILITY DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF A CERTIFICATE OF OCCUPANCY FOR SINGLE FAMILY UNITS. FOR COMMERCIAL
PROPERTIES, CERTIFICATION SHALL BY SUBMITTED TO THE STORMWATER UTILITY DEPARTMENT AT LEAST TWO WEEKS PRIOR TO THE RELEASE OF ANY
BUILDING PERMITS IN EXCESS OF THOSE ALLOWED PRIOR TO CERTIFICATION PER THE DEVELOPMENT AGREEMENT.
E. WATERLINE NOTE
1.THE MINIMUM COVER OVER WATER LINES IS 4.5 FEET AND THE MAXIMUM COVER IS 5.5 FEET UNLESS OTHERWISE NOTED IN THE PLANS AND APPROVED BY
THE WATER UTILITY.
F. WATER & SEWER NOTES
1.ALL WATER LINE CONSTRUCTION SHALL CONFORM TO THE CITY OF FORT COLLINS UTILITIES STANDARDS AND SPECIFICATIONS CURRENT TO THE DATE OF
CONSTRUCTION.
2.ALL SANITARY SEWER LINE CONSTRUCTION SHALL CONFORM TO THE CITY OF FORT COLLINS UTILITIES STANDARDS AND SPECIFICATIONS CURRENT TO THE
DATE OF CONSTRUCTION.
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONS----GENERAL NOTES9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C0.01
2 18
CITY OF FORT COLLINS GENERAL NOTES
SUNIGA ROAD
(115' ROW)
ROCKY MOUNTAIN
RAPTOR PROGRAM MATCHLINESEE THIS SHEETSTEELEY DRIVELAKE
C
A
N
AL
NORTHFIELD
TRACT U
(D,U,AE)
(TO BE VACATED)
SUNIGA ROAD
(115' ROW)LANDMARK WAYSWARTZ, DAVID A,
MILCAN, SUSAN MARIE
LOT 29 ARREOLA, MANUEL L
MONDRAGON, LUCY
V / CHRISTINA M,
LOT 28
ROCKY MOUNTAIN
RAPTOR PROGRAMMATCHLINESEE THIS SHEETSTEELEY DRIVENORTHFIELD
TRACT V
(D,U,AE)
(TO BE VACATED)
NORTHFIELD
TRACT W
(D,U,&AE)
POND D REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSEXISTING CONDITIONS9/8/21
1" = 40'
N/A
ACM
JTC
21-1037-00
C0.02
3 18
APPROX LIMITS OF SAWCUT LINE
DEMO UTILITIES / FENCE / ETC
DEMO ASPHALT / CONCRETE
TREE REMOVAL/RELOCATION
(RE: LA)
PROTECT EXISTING TREE
(RE: LA)
LEGEND
NOTES:
1.ALL EXISTING UTILITY LOCATIONS SHOWN HAVE BEEN DETERMINED FROM A COMBINATION OF RECORD
DRAWINGS, SURVEYED FIELD MARK-OUTS AND PHYSICAL OBSERVATIONS. THERE MAY BE OTHER UTILITIES NOT
SHOWN ON THE DRAWINGS WHICH PRESENTLY EXIST IN THE AREA OF CONSTRUCTION. THEREFORE, THE
CONTRACTOR SHALL VERIFY LOCATION AND DEPTH OF ALL EXISTING UTILITIES IN THE PROJECT VICINITY PRIOR
TO BEGINNING WORK. THE CONTRACTOR SHALL COORDINATE AND PROVIDE PROTECTION OF
CONFLICTING UTILITIES. NOTIFY OWNER/ENGINEER IF ANY CONFLICTS ARE ENCOUNTERED. THE OWNER
AND/OR ENGINEER ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OR COMPLETENESS SHOWN.
2.COORDINATE DEMOLITION REQUIREMENTS, LIMITS OF DEMOLITION, SALVAGE ITEMS, PROTECTION OF ITEMS
TO REMAIN, TREES, FENCING, ETC. WITH OWNER, ARCHITECT, AND RELEVANT CONSTRUCTION AND/OR
PHASING PLANS. ADDITIONAL DEMOTION OF PAVING, TREES, UTILITIES, STRUCTURES, ETC. TO BE PERFORMED
AS REQUIRED.
3.ALL EXISTING UTILITIES TO REMAIN SHALL BE ADJUSTED TO FINAL GRADE.
4.CONTRACTOR RESPONSIBLE FOR ALL SURFACE REPAIR/REPLACEMENT TO RESTORE SIDEWALKS, PAVEMENT,
CURB/GUTTER AND SOD AREAS DISTURBED BY NEW WORK. REPAIR/REPLACEMENTS SHALL BE COMPLETED
PER CITY OF FORT COLLINS STANDARDS AT CONTRACTOR EXPENSE.
5.EXISTING CONCRETE AND ASPHALT PAVING SHALL BE SAWCUT AND REMOVED PRIOR TO EXCAVATION.
REMOVE CONCRETE TO THE NEAREST JOINT.
6.CONTRACTOR TO PROVIDE ALL NECESSARY EROSION CONTROL MEASURES DURING CONSTRUCTION. PLACE
EROSION CONTROL PROTECTION AT ALL PROPOSED AND EXISTING INLETS DOWNSTREAM FROM
CONSTRUCTION AREA. EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS
COMPLETE AND ALL DISTURBED GROUND IS ADEQUATELY VEGETATED.
7.LIMITS OF STREET CUTS, ASPHALT, AND CONCRETE REMOVALS ARE APPROXIMATE. LIMITS OF REMOVAL TO BE
DETERMINED IN THE FIELD TO ADEQUATELY COMPLETE THE PROPOSED IMPROVEMENTS, WHILE MAINTAINING,
IF NOT IMPROVING, EXISTING CONDITIONS. ADDITIONAL REMOVAL IDENTIFIED IN THE FIELD SHALL BE
COMPLETED AT CONTRACTOR EXPENSE. ALL REPAIRS TO BE COMPLETED IN ACCORDANCE WITH CITY
STREET REPAIRS STANDARDS.
8.REFER TO LANDSCAPE TREE MITIGATION PLAN (IF APPLICABLE) FOR TREE REMOVAL, RELOCATION AND
PROTECTION. TREE REMOVAL INFORMATION SHOWN FOR COORDINATION PURPOSES ONLY.
9.REFERENCE LANDSCAPE PLANS FOR ADDITIONAL SITE DEMOLITION.
10.ALL UTILITIES TO BE PROTECTED IN PLACE UNLESS OTHERWISE NOTED.
11.IMPROVEMENTS SUCH AS, BUT NOT LIMITED TO, SUNIGA ROAD INFRASTRUCTURE, DETENTION/WATER QUALITY
POND D, ARE TO BE CONSTRUCTED WITH NORTHFIELD AND CONSIDERED TO BE EXISTING CONDITIONS.
N
W E
S
0
SCALE: 1" = 40'
80402040
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTSUNIGA ROAD
(115' ROW)
ROCKY MOUNTAIN
RAPTOR PROGRAM MATCHLINESEE THIS SHEETSTEELEY DRIVETRACT A
LAKE CANALD
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
SUNIGA ROAD
(115' ROW)LANDMARK WAYSWARTZ, DAVID A,
MILCAN, SUSAN MARIE
LOT 29
MONDRAGON, LUCY
V / CHRISTINA M,
LOT 28
ROCKY MOUNTAIN
RAPTOR PROGRAM MARTINEZ STREETMATCHLINESEE THIS SHEETSTEELEY DRIVETRACT B
TRACT C
(D&UE)
NORTHFIELD
TRACT W
(D,U,&AE)
POND D REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSHORIZONTAL CONTROL PLAN9/8/21
1" = 40'
N/A
ACM
JTC
21-1037-00
C1.00
4 18
N
W E
S
0
SCALE: 1" = 40'
80402040
RESERVED
PARKING
VANACCESSIBLE
CONCRETE SIDEWALK
CONCRETE PAVEMENT
HEAVY DUTY ASPHALT
PAVEMENT
LEGEND
P
FIRE LANE
LIGHT DUTY ASPHALT
PAVEMENT
4" MOUNTABLE CURB &
1' SPILL GUTTER
6" VERTICAL CURB &
1' CATCH GUTTER
6" VERTICAL CURB &
1' SPILL GUTTER
NOTES:
1.ALL ROAD AND PARKING DIMENSIONS BASED ON FLOWLINE OR CURB. VERIFY BUILDING PLAN
DIMENSIONS PRIOR TO CONSTRUCTION
2.CONTRACTOR SHALL BE RESPONSIBLE FOR TRAFFIC CONTROL PLANS FOR STREET RIGHT-OF-WAY
WORK.
3.TRAFFIC CONTROL, PERMITS, CONSTRUCTION AND FEES ASSOCIATED WITH THE RIGHT-OF-WAY
WORK, ARE THE SOLE RESPONSIBILITY OF THE GENERAL CONTRACTOR.
4.ALL PAVEMENTS AND EARTHWORK SHALL CONFORM TO THE GEOTECHNICAL REPORT FOR THE
SITE.
5.ALL WORK SHALL CONFORM TO LARIMER COUNTY URBAN AREA STREET STANDARDS.
6.COORDINATE LOCATION, HEIGHTS, ETC. OF WALLS FENCES, AND SITE FEATURES WITH
LANDSCAPE ARCHITECT.
7.STEELEY DRIVE IS PUBLIC RIGHT-OF-WAY AND ALL REMAINING STREETS ARE PRIVATE DRIVES AND
PRIVATELY MAINTAINED.
8.STEEELEY DRIVE TO BE CONSTRUCTED PER APPROVED "UTILITY PLANS FOR NORTHFIELD" DATED
2/26/20, WITH EXCEPTION TO REVISED ACCESSES.
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
2' CURB TRANSITION
STOP
ONLY
STOP
COMPACT PARKING
SPACE
Are specs for
thickened/reinforced
concrete called out?
(I'm not seeing it
here or for the
eastern water
access)HDS RESPONSE: UTILITY ACCESSES
HAVE BEEN CHANGED TO
CONCRETE PAVEMENT
LINE TABLE
LINE LENGTH DIRECTION START (N,E)
CURVE TABLE
CURVE LENGTH RADIUS DELTA CHORD DIRECTION CHORD LENGTH START (N,E)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSHORIZONTAL CONTROL PLAN9/8/21
1" = 40'
N/A
ACM
JTC
21-1037-00
C1.01
4 18
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTSUNIGA ROAD
(115' ROW)
ROCKY MOUNTAIN
RAPTOR PROGRAM
TRACT A
LAKE
C
A
N
AL MATCHLINESEE THIS SHEETSTEELEYDRIVED
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE UCTILEIRON
DRAINSTOWATERWAYS DNDYLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS DNDYLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
DYLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS DNDYLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTO
NOT
POLLUTE UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
DYLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
DYLOPLAST
ONOTPOLLUTE UCTILEIRON
DRAINSTOWATERWAYS
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
SUNIGA ROAD
(115' ROW)LANDMARK WAYMARTINEZ STREETSWARTZ, DAVID A,
MILCAN, SUSAN MARIE
LOT 29
MONDRAGON, LUCY
V / CHRISTINA M,
LOT 28
ROCKY MOUNTAIN
RAPTOR PROGRAM
TRACT B NORTHFIELD
TRACT W
(D,U,&AE)
RAIN GARDEN D1MATCHLINESEE THIS SHEETSTEELEYDRIVETRACT C
(D&UE)REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSDRAINAGE & EROSION CONTROL PLAN9/8/21
1" = 40'
N/A
ACB1
JTC
21-1037-00
C2.00
6 18
N
W E
S0
SCALE: 1" = 40'
80402040
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
LEGEND
EXISTING MAJOR CONTOUR
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
BASIN COEFFICIENT (100-YR)
BASIN DESIGNATION
BASIN AREA
DESIGN POINT
DRAINAGE FLOW ARROW
DRAINAGE BASIN BOUNDARY
DRAINAGE BASIN FLOW PATH
NOTES
1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL MEASURES PRIOR TO AND THROUGHOUT
CONSTRUCTION. PLACE EROSION CONTROL PROTECTION AT ALL EXISTING INLETS DOWNSTREAM FROM THE CONSTRUCTION AREA.
EROSION CONTROL PROTECTION SHALL REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETE AND ALL DISTURBED GROUND IS
ADEQUATELY VEGETATED WITH OWNER'S APPROVAL FOR REMOVAL.
2.THE EXTENT OF EROSION CONTROL PROTECTION SHALL BE OBSERVED AND ADJUSTED AS NEEDED DURING CONSTRUCTION BASED ON
SITE CONDITIONS AND THE PERFORMANCE OF THE EROSION CONTROL CONTROL MEASURES SHOWN, TO SUPPLY SUFFICIENT EROSION
CONTROL AND MINIMIZE DOWNSTREAM WATERWAY POLLUTION.
3.LIMIT DISTURBANCE TO AREAS WITHIN EROSION CONTROL BOUNDARIES. ADJUST EROSION CONTROL BOUNDARIES AS NECESSARY TO
ADEQUATELY COMPLETE PROPOSED WORK. ALL DISTURBED AREAS SHALL BE PREPARED (SEEDED & MULCHED, SURFACE ROUGHENING,
ETC.) TO MINIMIZE EROSION POTENTIAL AND SOIL MIGRATION.
4.STORMWATER MANAGEMENT PLAN SHALL BE PREPARED AND SUBMITTED BY CONTRACTOR PRIOR TO CONSTRUCTION COMMENCEMENT.
5.SEE LANDSCAPE PLAN FOR REVEGETATION METHODS AND DETAILS. DURING CONSTRUCTION, ANY SOIL DISTURBED AND NOT UNDER
ACTIVE CONSTRUCTION SHALL BE SEEDED AND MULCHED PER LCUASS STANDARDS.
6.ANY DISTURBED LAND MUST RECEIVE SURFACE ROUGHENING, INCLUDING BUT NOT LIMITED TO SLOPED AREAS.
7.AREAS THAT EXPERIENCE EROSION ISSUES FROM STEEP SLOPES OR WATER EROSION RESULTING IN SEED NOT BEING ABLE TO ESTABLISH
DURING THE FIRST GROWING SEASON SHALL REQUIRE RESEEDING AND EROSION CONTROL BLANKETS TO STABILIZE THE SOIL.
8.REFERENCE FINAL DRAINAGE REPORT.
9.THIS PROPERTY IS LOCATED IN THE FEMA REGULATED, 500-YR POUDRE RIVER FLOODPLAIN. ANY DEVELOPMENT WITHIN THE FLOODPLAIN
MUST COMPLY WITH THE SAFETY REGULATIONS OF CHAPTER 10 OF CITY MUNICIPAL CODE.
10.ESSENTIAL SERVICES CRITICAL FACILITIES AND AT RISK POPULATION CRITICAL FACILITIES ARE PROHIBITED IN THE 500-YR FLOODPLAIN.
11.THE NATURAL HABITAT BUFFER ZONE IS INTENDED TO BE MAINTAINED IN A NATIVE LANDSCAPE. PLEASE SEE SECTION 3.4.1 OF THE LAND
USE CODE FOR ALLOWABLE USES WITHIN THE NATURAL HABITAT BUFFER ZONE.
DETENTION POND D
100-YR VOLUME = 1.64 AC-FT
100-YR WSE = 4949.52 FT
WQCV (12-HR) = 2,459 CU-FT
(RAIN GARDEN)
WQCV (40-HR) = 4,008 CU-FT
WQCV WSE = 4946.88 FT
(STANDARD WQ)
PROPOSED NORTHFIELD
MAJOR CONTOUR
PROPOSED NORTHFIELD MINOR
CONTOUR
NATURAL HABITAT BUFFER ZONE
CONSTRUCTION ENTRANCE W/
VEHICLE TRACKING CONTROL
SILT FENCE
INLET PROTECTION
ROCK SOCKS
CULVERT PROTECTION
CONCRETE WASHOUT AREA
FW
F
FF
F
WWWWCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTSUNIGA ROAD
(115' ROW)
ROCKY MOUNTAIN
RAPTOR PROGRAMLAKE
C
A
N
AL MATCHLINESEE THIS SHEETSTEELEY DRIVEBLDG 1
COMMUNITY
CENTER
BLDG 2
BLDG 3
BLDG 4
BLDG 5
MANGOLD LANE
F
FW WFWFWFWFWD
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
SUNIGA ROAD
(115' ROW)LANDMARK WAYMARTINEZ STREETSWARTZ, DAVID A,
MILCAN, SUSAN MARIE
LOT 29
MONDRAGON, LUCY
V / CHRISTINA M,
LOT 28
ROCKY MOUNTAIN
RAPTOR PROGRAMMATCHLINESEE THIS SHEETSTEELEY DRIVECOMMUNITY BLDG 6 BLDG 7
BLDG 10a
BLDG 11a BLDG 13a
BLDG 12a
MANGOLD LANE REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSDETAILED GRADING PLAN9/8/21
1" = 40'
N/A
ACB1
JTC
21-1037-00
C2.01
7 18
N
W E
S0
SCALE: 1" = 40'
80402040
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
LEGEND
EXISTING MAJOR CONTOUR
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
NOTES
1.CONTRACTOR TO PROVIDE AND MAINTAIN ALL NECESSARY EROSION CONTROL
MEASURES PRIOR TO AND THROUGHOUT CONSTRUCTION.
2.SPOT ELEVATIONS SHOWN ARE ON FLOWLINE OR BACK OF WALK UNLESS
OTHERWISE LABELED.
3.WALKWAYS SLOPE 2.0% AWAY FROM BUILDINGS AND/OR TOWARD
PARKING/DRIVE AREAS. WALK LABELS ARE SHOWN ON THE HIGH SIDE OF THE
WALK.
4.ALL SUBGRADE TO BE PLACED/COMPACTED PER GEOTECHNICAL ENGINEER
RECOMMENDATIONS.
5.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM ELEVATIONS
REQUIRED FOR PROTECTION FROM THE 100 YEAR STORM. THE LOWEST OPENING
ELEVATIONS SHOWN ARE AT LEAST ONE FOOT ABOVE THE 100 YEAR STORM
ELEVATION OF ADJACENT STREETS, CHANNELS, DITCHES, SWALES, OR OTHER
DRAINAGE FACILITIES.
6.THE NATURAL HABITAT BUFFER ZONE IS INTENDED TO BE MAINTAINED IN A NATIVE
LANDSCAPE. PLEASE SEE SECTION 3.4.1 OF THE LAND USE CODE FOR ALLOWABLE
USES WITHIN THE NATURAL HABITAT BUFFER ZONE.
PROPOSED NORTHFIELD
MAJOR CONTOUR
PROPOSED NORTHFIELD MINOR
CONTOUR
NATURAL HABITAT BUFFER ZONE
FW
F
FF
F
WWWWCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTSUNIGA ROAD
(115' ROW)
ROCKY MOUNTAIN
RAPTOR PROGRAM MATCHLINESEE THIS SHEETSTEELEY DRIVETRACT A
LAKE CANALF
FW WFWFWFWFWD
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
SUNIGA ROAD
(115' ROW)LANDMARK WAYSWARTZ, DAVID A,
MILCAN, SUSAN MARIE
LOT 29
MONDRAGON, LUCY
V / CHRISTINA M,
LOT 28
ROCKY MOUNTAIN
RAPTOR PROGRAM
RAIN GARDEN D1MATCHLINESEE THIS SHEETSTEELEY DRIVETRACT B
TRACT C
(D&UE)
NORTHFIELD
TRACT W
(D,U,&AE)
POND D REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSOVERALL UTILITY PLAN9/8/21
1" = 40'
N/A
ACM
JTC
21-1037-00
C3.00
8 18
NOTES:
1.ALL EXISTING UTILITY LOCATIONS SHOWN HAVE BEEN PROVIDED BY OTHERS AND DETERMINED FROM A
COMBINATION OF RECORD DRAWINGS, SURVEYED FIELD MARK-OUTS AND PHYSICAL OBSERVATIONS. THERE
MAY BE UTILITIES NOT SHOWN ON THE DRAWINGS WHICH PRESENTLY EXIST IN THE AREA OF CONSTRUCTION.
THEREFORE, THE CONTRACTOR SHALL VERIFY LOCATION AND DEPTH OF ALL EXISTING UTILITIES IN THE PROJECT
VICINITY PRIOR TO BEGINNING WORK. THE CONTRACTOR SHALL BE FULLY AND SOLELY RESPONSIBLE FOR ANY
AND ALL DAMAGES AND COSTS WHICH MIGHT OCCUR BY THE CONTRACTOR'S FAILURE TO EXACTLY LOCATE
AND PRESERVE ANY AND ALL UTILITIES. THE CONTRACTOR SHALL NOTIFY ALL PUBLIC AND PRIVATE UTILITY
COMPANIES AND DETERMINE THE LOCATION OF ALL EXISTING UTILITIES PRIOR TO PROCEEDING WITH
GRADING AND CONSTRUCTION. ALL WORK PERFORMED IN THE AREA OF UTILITIES SHALL BE PERFORMED AND
INSPECTED ACCORDING TO THE REQUIREMENTS OF THE UTILITY OWNER. LIKEWISE, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING AND MAPPING ANY EXISTING UTILITY (INCLUDING DEPTH) WHICH MAY
CONFLICT WITH THE PROPOSED CONSTRUCTION, AND FOR RELOCATING ENCOUNTERED UTILITIES AS
DIRECTED BY THE ENGINEER. CONTRACTOR SHALL CONTACT AND RECEIVE APPROVAL FROM OWNER/UTILITY
OWNER BEFORE RELOCATING ANY ENCOUNTERED UTILITIES. CONTRACTOR RESPONSIBLE FOR SERVICE
CONNECTIONS, AND RELOCATING AND RECONNECTING AFFECTED UTILITIES AS COORDINATED WITH UTILITY
OWNER AND/OR ENGINEER, INCLUDING NON-MUNICIPAL UTILITIES (TELEPHONE, GAS, CABLE, ETC., WHICH
SHALL BE COORDINATED WITH THE UTILITY OWNER). THE CONTRACTOR SHALL IMMEDIATELY CONTACT
ENGINEER UPON DISCOVERY OF A UTILITY DISCREPANCY OR CONFLICT. AT LEAST 48 HOURS PRIOR TO
CONSTRUCTION, THE CONTRACTOR SHALL NOTIFY THE UTILITY NOTIFICATION CENTER OF COLORADO
(1-800-922-1987, WWW.UNCC.ORG).
2.IN ADDITION TO MEETING APPLICABLE LCUASS, STATE OR FEDERAL STANDARDS, ALL MATERIALS,
WORKMANSHIP AND CONSTRUCTION OF PUBLIC WATER AND WASTEWATER SYSTEM IMPROVEMENTS SHALL
MEET OR EXCEED THE STANDARDS SET FORTH IN THE CITY OF FORT COLLINS WATER AND WASTEWATER
DEVELOPMENT STANDARDS.
3.IN CASES OF CONFLICT BETWEEN THESE SIGNED PLANS AND APPLICABLE STANDARDS, THE MOST RESTRICTIVE
STANDARD SHALL APPLY.
4.ALL WATER MAINS AND FIRE LINES SHALL BE AWWA C900 PLASTIC PRESSURE PIPE (DR-18, PRESSURE CLASS
305). ALL PLASTIC PRESSURE PIPE SHALL HAVE TRACER WIRE PER STANDARDS. ALL FITTINGS ON THE
PROPOSED FIRE LINES AND FIRE HYDRANT LATERALS SHALL BE FULLY RESTRAINED JOINTS PER DISTRICT
STANDARDS (MEGA-LUG OR APPROVED EQUAL).
5.ALL WATER SERVICES SHALL BE TYPE K SOFT COPPER.
6.ALL WATER MAINS AND SERVICES SHALL HAVE A MINIMUM COVER OF 4.5' AND A MAXIMUM OF 5.5', UNLESS
OTHERWISE NOTED.
7.ALL SANITARY SEWER MAINS AND SERVICES SHALL BE SDR 35 PVC. VERIFY BUILDING CONNECTION ELEVATION
(RE: MEP).
8.ALL SANITARY SEWER & STORM SEWER CLEANOUTS LOCATED WITHIN THE PAVEMENT SHALL BE TRAFFIC RATED
CLEANOUTS.
9.INVERT SHAPING ON SANITARY SEWER MANHOLES TO BE AT LEAST TO SPRING LINE.
10.SITE CONTRACTOR SHALL COORDINATE UTILITY CONNECTIONS AT THE BUILDING WITH BUILDING
CONTRACTOR.
11.ALL PROPOSED STORM SEWER IMPROVEMENTS SHALL BE IN ACCORDANCE WITH THE CITY OF FORT COLLINS
STANDARDS AND SPECIFICATIONS.
12.STORM PIPES SHALL BE ADS HP STORM PIPE UNLESS OTHERWISE NOTED.
13.COORDINATE SITE LIGHTING AND ELECTRIC SERVICE ROUTING, DEMOLISHING, RELOCATING, AND
MODIFICATIONS WITH THE ELECTRICAL ENGINEER, ARCHITECT, AND OWNER.
14.ALL MANHOLE RIM AND INLET GRATE ELEVATIONS SHOWN ARE APPROXIMATE. CONFIRM FINAL ELEVATIONS
PRIOR TO INSTALLATION.
15.PIPE LENGTHS ARE PROVIDED FROM CENTER OF STRUCTURE TO CENTER OF STRUCTURE. LENGTH OF FLARED
END SECTIONS ARE INCLUDED IN PIPE LENGTHS.
16.THIS PROPERTY IS LOCATED IN THE FEMA REGULATED, 500-YR POUDRE RIVER FLOODPLAIN. ANY DEVELOPMENT
WITHIN THE FLOODPLAIN MUST COMPLY WITH THE SAFETY REGULATIONS OF CHAPTER 10 OF CITY MUNICIPAL
CODE.
17.ESSENTIAL SERVICES CRITICAL FACILITIES AND AT RISK POPULATION CRITICAL FACILITIES ARE PROHIBITED IN THE
500-YR FLOODPLAIN.
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
N
W E
S
0
SCALE: 1" = 40'
80402040
separate water/
sewer services are
required for this
mixed-use building
to serve the MF and
community spaces.
FYI, easement
bounds don't seem
to match up with
what is shown on
site plan.
please keep
alignment within
the drive aisle.
Can this be
achieved with
22.5s instead of
45s?
to be clear, I'm
interpreting the ring
and lid will be
outside of the
concrete pan - I'm
ok with that if
needed to make
these alignments
work in the drive
aisle.
please call out
restrained - that is
typically how installs
are required to be
done rather than
thrust blocks.
are sanitary
services shown?
(typ)
doesn't appear
landscape
separations are
being met here (I
also have notes on
landscape plan)
HDS RESPONSE: SANITARY
SERVICES ADDED
HDS RESPONSE: THESE
EASEMENTS ARE MOST CURRENT
HDS RESPONSE: 22.5° ANGLES
WERE USED FOR 2ND PDP
SUBMITTAL
HDS RESPONSE: THAT IS
THE INTENTHDS RESPONSE: FCU STANDARD DETAILS
FOR FH SHOW TB RESTRAINT. PLEASE
PROVIDE STANDARD RESTRAINT JOINT
DETAILS.
HDS RESPONSE: SEPARATE
WATER AND SANITARY SEWER
SERVICES HAVE BEEN ADDED
F
FW WFWFWF
FF
F
WWWWCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
SS01 PROFILE
4945
4950
4955
4960
4965
4945
4950
4955
4960
4965
9+5010+0010+5011+0011+5012+0012+5013+0013+5014+0014+5015+0015+5016+00
SS01 PROFILE
4945
4950
4955
4960
4965
4945
4950
4955
4960
4965
16+0016+5017+0017+5018+0018+5019+0019+5020+0020+5021+0021+5022+0022+5023+0023+50 REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSSANITARY SEWER PLAN & PROFILE9/8/21
1" = 40'
1" = 4'
ACB1
JTC
21-1037-00
C3.03
9 18
N
W E
S
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
0
SCALE: 1" = 40'
80402040
HORIZONTAL
VERTICAL
SCALE: 1" =4'
NOTES:
1.IN ADDITION TO MEETING APPLICABLE LCUASS, STATE OR FEDERAL STANDARDS, ALL
MATERIALS, WORKMANSHIP AND CONSTRUCTION OF PUBLIC WATER AND
WASTEWATER SYSTEM IMPROVEMENTS SHALL MEET OR EXCEED THE STANDARDS SET
FORTH IN THE DEVELOPMENT STANDARDS.
2.ALL SANITARY SEWER MAINS AND SERVICES SHALL BE SDR 35 PVC. VERIFY BUILDING
CONNECTION ELEVATION (RE: MEP).
3.ALL SANITARY SEWER & STORM SEWER CLEANOUTS LOCATED WITHIN THE PAVEMENT
SHALL BE TRAFFIC RATED CLEANOUTS.
4.ALL SANITARY SEWER, STORM SEWER, AND WATER MAINS AND SERVICES MUST
MAINTAIN MINIMUM 10' HORIZONTAL AND 18" VERTICAL SEPARATION.
5.INVERT SHAPING ON SANITARY SEWER MANHOLES TO BE AT LEAST TO SPRING LINE.
6.SITE CONTRACTOR SHALL COORDINATE UTILITY CONNECTIONS AT THE BUILDING
WITH BUILDING CONTRACTOR.
7.ALL MANHOLE RIM AND INLET GRATE ELEVATIONS SHOWN ARE APPROXIMATE.
CONFIRM FINAL ELEVATIONS PRIOR TO INSTALLATION.
8.PIPE LENGTHS ARE PROVIDED FROM CENTER OF STRUCTURE TO CENTER OF
STRUCTURE. LENGTH OF FLARED END SECTIONS ARE INCLUDED IN PIPE LENGTHS.
9.ADJUST ALL EXISTING UTILITIES TO FINISHED GRADE.MATCHLINE(SEE BELOW)MATCHLINE(SEE ABOVE)CONSTRUCTION NOTES:
CONCRETE ENCASE (6" MINIMUM)
SSWR FOR 10' MINIMUM PAST POINT
OF CROSSING.
please show all
services with sizes,
slopes, etc.
manholes set to
existing grade?
2' cover?
3' min is allowable with insulation.
How will sewer services and the water main
being at a similar depth impact the water main?
Will lowering or other accommodations be
necessary? Please show impacts to water, that
can be done on the sanitary/storm profiles or
wherever makes best sense, but a callout
indicating where lowereings are shown would
be helpful.0.52 inHDS RESPONSE: SANITARY
SERVICES ADDED
HDS RESPONSE: WATERLINE &
ACCOMMODATIONS SHOWN ON
SANITARY PROFILE
HDS RESPONSE: OOPS,
MANHOLES SET TO FG
HDS RESPONSE: FG RAISED
ABOUT 1', COVER IS AT LEAST 3'.
BLUEBOARD NOTED WHERE
NEEDED
FWCOMPACTCOMPACTCOMPACT
COMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTWL PROFILE
4950
4955
4960
4965
4970
4950
4955
4960
4965
4970
8+679+009+5010+0010+5011+0011+5012+00 REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSWATERLINE PLAN & PROFILE9/8/21
1" = 40'
1" = 4'
ACB1
JTC
21-1037-00
C3.02
10 18NWESCALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
0
SCALE: 1" = 40'
80402040
HORIZONTAL
VERTICAL
SCALE: 1" =4'
NOTES:
1.IN ADDITION TO MEETING APPLICABLE LCUASS, STATE OR FEDERAL STANDARDS, ALL
MATERIALS, WORKMANSHIP AND CONSTRUCTION OF PUBLIC WATER AND
WASTEWATER SYSTEM IMPROVEMENTS SHALL MEET OR EXCEED THE STANDARDS SET
FORTH IN THE DEVELOPMENT STANDARDS.
2.SITE CONTRACTOR SHALL COORDINATE UTILITY CONNECTIONS AT THE BUILDING
WITH BUILDING CONTRACTOR.
3.ADJUST ALL EXISTING UTILITIES TO FINISHED GRADE.
I recall hearing that
this install needed
to be modified from
plan. Is as-built
information now
available?
HDS RESPONSE: WE
ARE NOT AWARE OF
ANY ADJUSTMENTS
F
FW WFWFWWFWF
F WWCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACTCOMPACT COMPACTCOMPACTCOMPACT
COMPACT
COMPA
C
T
COMP
A
C
T
COM
P
A
C
T
COM
P
A
CT
STEELEY DRIVETRACT A
TRACT B
TRACT C
(D&UE)
POND D
SD01 PROFILE
4945
4950
4955
4960
4965
4945
4950
4955
4960
4965
9+5010+0010+5011+0011+5012+0012+5013+0013+5014+0014+5015+0015+5016+0016+5017+0017+5018+0018+5019+0019+5020+0020+5021+0021+50 FWD
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLASTONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS D
N
D
YLOPLAST
ONOTPOLLUTE
UCTILEIRON
DRAINSTOWATERWAYS
NORTHFIELD
TRACT W
(D,U,&AE)
SD02 PROFILE
4945
4950
4955
4960
4965
4945
4950
4955
4960
4965
9+5010+0010+5011+0011+5012+0012+5013+0013+5014+0014+5015+0015+50 REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSSTORM PLAN & PROFILE9/8/21
1" = 40'
1" = 4'
ACB1
JTC
21-1037-00
C3.01
11 18
N
W E
S
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
CALL 2-BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
before you dig.Call
Know what's below.
R
0
SCALE: 1" = 40'
80402040
HORIZONTAL
VERTICAL
SCALE: 1" =4'
NOTES:
1.ALL PROPOSED STORM SEWER IMPROVEMENTS SHALL BE IN ACCORDANCE WITH THE
CITY OF FORT COLLINS STANDARDS AND SPECIFICATIONS.
2.STORM PIPES SHALL BE ADS HP STORM UNLESS OTHERWISE NOTED.
3.ALL MANHOLE RIM AND INLET GRATE ELEVATIONS SHOWN ARE APPROXIMATE.
CONFIRM FINAL ELEVATIONS PRIOR TO INSTALLATION.
4.PIPE LENGTHS ARE PROVIDED FROM CENTER OF STRUCTURE TO CENTER OF
STRUCTURE. LENGTH OF FLARED END SECTIONS ARE INCLUDED IN PIPE LENGTHS.
5.ALL STORM PIPES AND STRUCTURES ARE PRIVATELY OWNED AND MAINTAINED
EXCEPT WHERE SPECIFICALLY IDENTIFIED AND LABELED ON THESE PLANS AS PUBLIC.
6.INSTALL CUT OFF WALLS 5' UPSTREAM OF ALL STORM MANHOLES AND INLETS
CONSISTING OF COMPACTED CLAY MATERIAL EXTENDING BEYOND THE SPRINGLINE
OF THE PIPE.
CONSTRUCTION NOTES:
WRAP SSWR JOINTS 10' EACH SIDE OF
CROSSING WITH 12" WIDE BUTYL ADHESIVE
TAPE (EZ WRAP OR EQUIVALENT). NO
CASING OR ENCASEMENT REQUIRED UNDER
ADS HP STORM ONLY, SPECIFIC APPROVAL
NEEDED UNDER RCP.
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.00
12 18
6" CURB AND 1' SPILL GUTTER
6" CURB AND 1' CATCH GUTTER
4" MOUNTABLE CURB AND 1' SPILL GUTTER
CURB AND GUTTER DETAIL (ON-SITE ONLY)
CURB RAMP DETAIL (W/ DETECTABLE WARNING PLATE)
CONTRACTION JOINT DETAIL EXPANSION JOINT DETAIL
CURB AND GUTTER DETAIL (ON-SITE ONLY)
CONCRETE PAN DETAIL
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.01
13 18
SIGN DETAIL
SIDEWALK CHASE DETAIL
24" DRAIN CHANNEL
PLAN
SECTION A-A
ELEVATION
DRAIN PAN COBBLE RIPRAP RUNDOWN
NTS
STORM SEWER OUTLET
ISOMETRIC VIEW
SECTION B-B
STORM SEWER HEADWALL RIPRAP DETAIL
SECTION A-A
STABILIZED BURIED RIPRAP
ALL RIPRAP IS TO BE BURIED
PER BURIED RIPRAP DETAIL
CONCRETE HEADWALL DETAIL
NTS
type M is minimum
per criteria.
HDS: NO RIPRAP, IT DIRECTLY
CONNECTS TO A CONCRETE PAN.
DETAIL HAS BEEN UPDATED.
BTW, TYPE M RIPRAP IS A BIT
EXCESSIVE IN THIS APPLICATION
;)
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.02
14 18
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.03
15 18
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.04
16 18
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.05
17 18
REVISIONNO.BYDATEHIGHLANDDEVELOPMENT SERVICES6355 FAIRGROUNDS AVENUE, SUITE 100 | WINDSOR, CO 80550PHONE: 970.674.7550 | EMAIL: Info@Highland-DS.com | www.Highland-DS.comPREPARED BY OR UNDER THE
DIRECT SUPERVISION OF:
FOR AND ON BEHALF OF HIGHLAND
DEVELOPMENT SERVICES
REVIEW SET
NOT FOR
CONSTRUCTION
OFSHEET
DRAWN BY
CHECKED BY
DATE
SCALE (H)
HDS PROJECT #
SCALE (V)NORTHFIELD COMMONSCONSTRUCTION DETAILS9/8/21
N/A
N/A
ACM
JTC
21-1037-00
C4.06
18 18
CLEANOUT DETAIL
PLAN VIEW