October 1, 2021
Cathy Mathis
TB Group
444 Mountain Avenue
Berthoud, CO 80513
RE: Northfield Commons, FDP210022, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Northfield Commons. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Todd Sullivan via phone at 970-221-6695 or via email at
tsullivan@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Todd Sullivan, 970-221-6695, tsullivan@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/28/2021
I will be your primary point of contact throughout the development review and
permitting processes. If you have any questions, need additional meetings with
the project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. To best serve you, please include me
in all email correspondence with other reviewers and keep me informed of any
phone conversations. Thank you!
Comment Number: 2 Comment Originated: 09/28/2021
As part of your resubmittal, you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color. When replying to the comment letter please be detailed in
your responses, as all comments should be thoroughly addressed. Provide
reference to specific project plans or explanations of why comments have not
been addressed, when applicable, avoiding responses like noted or acknowledged.
Please follow the Electronic Submittal Requirements and File Naming
Page 2 of 8
Standards found at https://www.fcgov.com/developmentreview/files/electronic
submittal requirements and file naming standards_v1_8 1 19.pdf?1566857888.
Files are to be named PLAN NAME_PROJECT NAME_REVIEW TYPE_ROUND NO.
Example: UTILITY PLANS_MY PROJECT_PDP_RD1.pdf
Comment Number: 3 Comment Originated: 09/28/2021
Temporary Service Changes - City of Fort Collins Development Review
To best provide thorough reviews and give every project the attention it
deserves, the City of Fort Collins is implementing temporary changes in how we
serve our development customers. As you may be aware, we are experiencing
staff shortages in a number of key departments, which has begun to impact the
timeliness of our reviews. We recognize that development and construction play
a critical role in our community’s vibrancy and economic recovery, and we have
been exploring options for mitigating impacts to our customers. As a result, we
will be making some temporary service level adjustments.
Currently, one additional week of review time will be added to all 1st and 2nd
round submittals (increase from 3 weeks to 4 weeks). Lengths of subsequent
rounds of review will be considered after each round of review. Also,
Completeness Checks will be performed on all initial and Round 2 submittals
during this time. Please reach out with any questions or concerns.
Comment Number: 4 Comment Originated: 09/28/2021
FOR FINAL APPROVAL:
All "FOR FINAL APPROVAL / FOR APPROVAL" comments need to be
addressed and resolved prior to moving forward with the final documents and
recording of this project. I will provide a recording checklist and process
information when we are closer to this step.
Department: Planning Services
Contact: Kai Kleer, 970-416-4284, kkleer@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/24/2021
09/24/2021 FOR APPROVAL:
Can sheet LS1 be updated to include the entry feature for the Major Walkway Spine.
RESPONSE: Entry feature landscaping has been added to LS1.
Comment Number: 2 Comment Originated: 09/24/2021
09/24/2021 FOR APPROVAL: Regarding the fencing around the basketball
court, can the court be rotated to reduce the need for fencing or can
landscaping (upright juniper, evergreen, ornamental trees?) be added between
the street sidewalk and fence to soften public view into the site?
RESPONSE: Basketball court has been rotated and landscaping added.
Comment Number: 3 Comment Originated: 09/24/2021
09/24/2021: It appears that the landscape plan and site plan have been
combined (which is preferred). At time of recording, please make sure that the
duplicate landscape plan is not included in the recording package.
RESPONSE: Yes, we will separate these sheets.
Page 3 of 8
Department: Engineering Development Review
Contact: Spencer Smith, 970-221-6603, smsmith@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/28/2021
09/28/2021: DEVELOPMENT AGREEMENT (DA)
Based on internal discussion with City staff regarding the need for a new DA for
this project, I'd like to have a meeting with the applicant team and staff to
discuss if we need a DA, or if we need to do an amendment, etc.
RESPONSE: DA discussions are occurring.
Department: Light And Power
Contact: Luke Unruh, 9704162724, lunruh@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/27/2021
FOR FINAL APPROVAL:
Please show L&P's electric line on the utility plan. I have the design completed.
Reach out to me and I will send it to you
RESPONSE: L&P electric layout is now shown on the utility plans
Comment Number: 2 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
Please ensure L&P's electric line and transformers are in a utility easement
RESPONSE: The easements are shown on the utility plan. If these are acceptable, they will be transferred
to the plat prior.
Comment Number: 3 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL
Please add a note to the utility plan that says,
The electric service conduit and conductor shall be installed, owned and maintained by the owner.
RESPONSE: Note is added to the utility plan.
Comment Number: 4 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPOVAL
Meter location will need to be coordinated with Light and Power. Please show
proposed meter location on the utility plan. Reference Section 8 of our Electric
Service Standards for electric metering standards. A link has been provided below.
https://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStanda
rds_FINAL_18November2016_Amendment.pdf
RESPONSE: The proposed electrical meter locations per building are included with the Architectural Site
Plan.
Comment Number: 5 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
A commercial service information form (C-1 form) and a one-line diagram will
need to be completed and submitted to Light & Power Engineering for review.
A link to the C-1 form is below:
http://www.fcgov.com/utilities/business/builders-and-developers/development-forms-guidelines-regulations
RESPONSE: The completed C-1 form, and final one-line diagram will be submitted at the time of building
permit submittal after the final Construction Documents have been completed.
Department: Stormwater Engineering
Page 4 of 8
Contact: Dan Mogen, 970-305-5989, dmogen@fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 09/28/2021
09/28/2021: FOR FINAL APPROVAL:
Please see redlines. I encourage you to reach out with any questions or to review
potential revisions, and I’d be happy to set up a meeting or conference call to do so.
RESPONSE: Redlines address. Please see responses.
Department: Stormwater Engineering – Erosion and Sediment Control
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 09/23/2021
09/23/2021: For Final:
Please address redline associated with the erosion control plans and escrow
calculations for next review.
RESPONSE: Comments addressed
Comment Number: 2 Comment Originated: 09/23/2021
09/23/2021: For Final:
The City Manager’s development review fee schedule under City Code 7.5-2
was updated to include fees for Erosion Control and Stormwater Inspections.
As of January 1st, 2021, these fees will be collected on all projects
for such inspections.
The Erosion Control fees are based on the number of lots,
the total site disturbance, the estimated number of years the project will
be active and the Stormwater Inspection Fees are based on the number of
LID/WQ Features that are designed for on this project.
Based on the proposed site construction associated with this project we are
assuming 11 lots, 6.32 acres of disturbance, 3 years from demo through build
out of construction and an additional 3 years till full vegetative stabilization due
to seeding. Which results in an Erosion Control Fee estimate of $2914.
Based on 0 number of porous pavers, 1 number of bioretention/level
spreaders, 1 number of extended detention basins, and 0 number of
underground treatments, results in an estimate of the Stormwater
LID/WQ Inspection fee to be $565.
Please note that as the plans and any subsequent review modifications of the
above-mentioned values change the fees may need to be modified. I have
provided a copy of the spreadsheet used to arrive at these estimates for
you to review.
Please respond to this comment with any changes to
these assumed estimates and why, so that we may have a final
fee estimate ready for this project. The fee will need to be provided at the time
of erosion control escrow.
RESPONSE: Your assumptions are correct with exception to the extended detention basin (EDB). The
EBD is being constructed with Northfield Phase 1 and should be covered by the associated fees.
Page 5 of 8
Department: Water-Wastewater Engineering
Contact: Dan Mogen, 970-305-5989, dmogen@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/28/2021
09/28/2021: FOR FINAL APPROVAL:
Please see redlines on plat, landscape plans, and utility plans regarding:
separate water/sewer services are needed for each use in the -mixed use- clubhouse building
- sewer main cover around Steeley Dr, and
- showing sewer services and impacts to water main/services.
I encourage you to reach out with any questions or to review potential revisions,
and I’d be happy to set up a meeting or conference call to do so.
RESPONSE: Comments addressed. Please see responses.
Comment Number: 2 Comment Originated: 09/28/2021
09/28/2021: FOR FINAL APPROVAL:
The water services and meters for this project site will need to be sized based
on the AWWA M22 manual design procedure. A sizing justification letter that
includes demand calculations for maximum flows and estimated continuous
flows will need to be provided as a part of the final submittal package for this project.
RESPONSE: The water meter justification for all of the buildings has been completed and is included with
this 2nd FDP Submittal.
Comment Number: 3 Comment Originated: 09/28/2021
09/28/2021: INFORMATION:
Starting Jan 1, 2022, all non-residential and multifamily developments will be
required to have a separate irrigation tap and meet update water supply
requirements. Staff encourages developments to take these upcoming
requirements into consideration now. Specific information can be found at
fcgov.com/wsr-update.
For this project, it appears separate irrigation service(s)/meter(s) will be
required, and I encourage you to add these to the plans prior to approval.
RESPONSE: The number of irrigation taps are still being negotiated with the City.
Comment Number: 4 Comment Originated: 09/28/2021
09/28/2021: INFORMATION:
Please note that all City construction detail drawings are to be used in their
original, unaltered state. ANY modification(s) must be clearly distinguished and
all City logos/identifiers must be removed from the modified detail. Detail
drawings can be found in both .pdf and .dwg formats through the links to
“Construction Drawings” on www.fcgov.com/utility-development.
Comment Number: 5 Comment Originated: 09/28/2021
09/28/2021: INFORMATION:
Please note that all City of Fort Collins Utility Customers are subject to City
Code requirements for wastewater. These requirements include Section
26-306 Wastewater Discharge Permit Requirements and Section 26-332
Prohibitive Discharge Standards. A permit may be required depending on
activities on the site; however, discharge standards apply to every customer,
both large and small, regardless of what activities take place on the site.
Please contact Industrial Pretreatment, Industrial_Pretreatment@fcgov.com or
(970)221-6900, to discuss these requirements and how they apply to this development.
Page 6 of 8
Comment Number: 6 Comment Originated: 09/29/2021
09/29/2021: DEVELOPMENT AGREEMENT:
Please include me in the conversation to make updates to the existing, or
establish a new, development agreement for the project.
RESPONSE: Acknowledged.
Department: Environmental Planning
Contact: Scott Benton, (970)416-4290, sbenton@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/24/2021
09/24/2021: FOR FINAL APPROVAL: There are still errors and confusion
persisting in the delineation, labelling, and allowable landscaping within the
NHBZ. Please contact me to resolve these issues.
To resolve:
-The line work on the landscape plan indicates that you are seeding within the
banks of the ditch; this should not be.
-No non-native turf is allowed within the NHBZ; landscape plan indicates that there is.
-It still seems that there are sidewalks and similar within the NHBZ.
RESPONSE: NHBZ hatch and corresponding legend has been revised.
Comment Number: 2 Comment Originated: 09/24/2021
09/24/2021: FOR FINAL APPROVAL: Please remove Native Grass Seed Mix
Note #1. Specific seed companies should not be required, the seed mix simply
needs to meet the required specifications.
RESPONSE: Note #1 has been removed.
Comment Number: 3 Comment Originated: 09/24/2021
09/24/2021: FOR FINAL APPROVAL: 'Native Grass Seed Mix' notes and
'Native Seed Mix Notes' need to be combined or simply go with one set.
Having two is unnecessary and confusing.
RESPONSE: Native Seed Notes have been combined to one set.
Comment Number: 4 Comment Originated: 09/24/2021
09/24/2021: FOR FINAL APPROVAL: Replace Tree Protection Note #9 with the following:
"NO TREES SHALL BE REMOVED DURING THE SONGBIRD NESTING
SEASON (FEBRUARY 1 TO JULY 31) WITHOUT FIRST HAVING A
PROFESSIONAL ECOLOGIST OR WILDLIFE BIOLOGIST COMPLETE A
NESTING SURVEY TO IDENTIFY ANY ACTIVE NESTS EXISTING ON THE
PROJECT SITE. THE SURVEY SHALL BE SENT TO THE CITY
ENVIRONMENTAL PLANNER. IF ACTIVE NESTS ARE FOUND, THE CITY
WILL COORDINATE WITH RELEVANT STATE AND FEDERAL
REPRESENTATIVES TO DETERMINE WHETHER ADDITIONAL
RESTRICTIONS ON TREE REMOVAL AND CONSTRUCTION APPLY."
RESPONSE: Tree Note #9 revised.
Department: PFA
Contact: Marcus Glasgow, 970-416-2869, marcus.glasgow@poudre-fire.org
Page 7 of 8
Topic: General
Comment Number: 1 Comment Originated: 09/24/2021
09/24/2021: PFA has no comments for the FDP at this time.
Department: Internal Services
Contact: Katy Hand, , khand@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1 Comment Originated: 09/28/2021
09/28/2021: FOR BUILDING PERMIT: The third-floor units must meet 125 ft
max exit travel distance. This may require the exit stair be a 1-hour rated interior
exit stair (enclosed) per 1023 of IBC.
RESPONSE: The exist stair is designed to be a 1-hour enclosure.
Comment Number: 2 Comment Originated: 09/28/2021
09/28/2021: FOR BUILDING PERMIT:
Please visit our website for current adopted codes, local amendments and
submittal requirements.
https://www.fcgov.com/building/application.php
https://www.fcgov.com/building/codes.php
https://www.fcgov.com/building/energycode
Comment Number: 3 Comment Originated: 09/28/2021
09/28/2021: INFORMATIONAL:
10% of all parking spaces must be EV ready (conduit in place) including
accessible spaces. Coordinate underground work accordingly.
Comment Number: 3 Comment Originated: 09/28/2021
09/28/2021: INFORMATIONAL:
Accessibility is required per IBC, ICC-A117.1 and state law CRS 9-5
Comment Number: 4 Comment Originated: 09/28/2021
09/28/2021: INFORMATIONAL:
A City licensed commercial general contractor is required to construct any new
multi-family structure.
Comment Number: 5 Comment Originated: 09/28/2021
09/28/2021: INFORMATIONAL: City of Fort Collins amendments to the 2018
IBC require a full NFPA-13 sprinkler system in multifamily buildings. Coordinate
fire line/water service accordingly.
Comment Number: 6 Comment Originated: 09/28/2021
09/28/2021: Building Permit Pre-Submittal Meeting:
Please work with your review coordinator to schedule a pre-submittal meeting
for any new commercial or multi-family building with Building Services for this
project. Pre-Submittal meetings assist the designer/builder by assuring, early
on in the design, that the new projects are on track to complying with all of the
adopted City codes and Standards. This should be scheduled when
architectural drawings are at least 50% complete. Be prepared to present site
plans, floor plans, and elevations and be able to discuss code issues of occupancy,
square footage, type of construction, egress, accessibility and energy compliance.
Page 8 of 8
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 2 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
Please revise the Benchmark Statement as marked. See redlines.
RESPONSE: Revised
Comment Number: 3 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
There are line over text issues. See redlines.
RESPONSE: Corrected
Comment Number: 4 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
There are sheet numbering issues. See redlines.
RESPONSE: Corrected
Topic: Plat
Comment Number: 1 Comment Originated: 09/27/2021
09/27/2021: FOR FINAL APPROVAL:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the redlines, please contact John
Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
RESPONSE: Comments addressed
Department: Outside Agencies
Contact: Todd Sullivan, 970-221-6695, tsullivan@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 09/28/2021
09/28/2021: FOR APPROVAL
The plat needs another signature block in addition to DFC Northfield LLC,
Please add signatures for NORTHFIELD LAND LLC per a 2021 sale deed.
Thank you,
Megan Harrity
Subdivision Supervisor
Larimer County Office of the Assessor
970-498-7065
RESPONSE: Signers added.