HomeMy WebLinkAboutTIMBERLINE - INTERNATIONAL - FDP210020 - SUBMITTAL DOCUMENTS - ROUND 1 - EROSION CONTROL LETTER/REPORT8/9/2021
Project:Disturbed Acres:1.39
Area to be Revegetated (Ac)0.58
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 421 $2.50 $1,052.50
L.F. 251 $4.00 $1,004.00
EA. 2 $100.00 $200.00
C.Y. 2 $45.00 $90.00
EA. 1 $2,000.00 $2,000.00
EA. 1 $3,000.00 $3,000.00
S.F. 256 $19.50 $4,992.00
Sub-Total: $12,338.50
1.5 x Sub-Total: $18,507.75
Amount of security: $18,507.75
Total Acres x Price/acre: $870.00
$1,500.00 Sub-Total: $870.00
1.5 x Sub-Total: $1,305.00
Amount to Re-seed: $1,305.00
Minimum escrow amount: $3,000.00
Erosion Control Escrow:$18,507.75
Fields in yellow should be amended for this project.
Erosion and Sediment Control Escrow/Security Calculation
for The City of Fort Collins
BMP Amount
Silt Fence (SF)
Vehicle Tracking Control (VTC)
Reseeding Amount
Scour Stop (TRM)
Gravel Inlet Protection(IP)@PondOutletStruct
Miniumum Escrow Amount
Timberline - International
Unit Price of Seeding per acre:
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the
cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever is
greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand dollars
($3,000) for commercial development”
Inlet Protection (IP)-Straw Wattle (SCL)
Concrete Washout Area (CWA)
Final Escrow Amount
Inlet Protection (IP)-Rock Sock
8/6/2021 1:29 PM S:\1805.00_TIM\PROJECTS\SWMP\TIM_Escrow