Community Planning and Environmental Services
Planning Department
January 4, 1994
Taco Bell
c/o Al Hauser, Architecture One
Palmer Gardens, Suite 200
150 East 29th Street
Loveland, CO 80538
Dear Mr. Hauser:
For your information, attached is a copy of the Staff's comments concerning Taco
Bell at Market Place P.U.D., presented before the Conceptual Review Team on
January 4, 1994.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely,
Ted Shepard, AICP
Senior Planner
TS/gjd
Attachments
cc: Transportation Department
Stormwater Department
Project Planner
File
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750
•
CONCEPTUAL REVIEW STAFF COMMENTS
City of Fort Collins
MEETING DATE: January 3, 1994
ITEM: Taco Bell at Market Place P.U.D.
APPLICANT: Taco Bell c/o Al Hauser, Architecture One, Palmer
Gardens, Suite 200, 150 East 29th Street, Loveland,
CO. 80538.
LAND USE DATA: Request for a 1,986 square foot fast food
restaurant, with drive-thru, located on Pad A of the Market Place
P.U.D., 4200 block of South College Avenue. Site is 35,000 square
feet, formerly approved for Italian Oven restaurant. Taco Bell M-
70 store would seat 70 patrons.
COMMENTS:
1. Light and Power has an existing oval vault located along
College Avenue that can serve the site. The proposed location
of the transformer, on the east side of the building, looks
suitable but please coordinate with Light and Power prior to
development. Normal development charges will apply.
2. The transformer must be within 10 feet of hard surface for
emergency change -out. The transformer must be screened by an
enclosure or landscape materials. If screened by an
enclosure, there are minimum clearances that must be met. The
transformer should be totally screened from College Avenue.
3. Water and sewer mains are installed with stubs to the pad
site. The water stub is a one inch diameter tap size. An
exterior grease interceptor must be installed in accordance
with the requirements of the Water and Wastewater Division.
4. Bicycle racks should be provided near the front entry. Racks
should be permanently anchored to concrete and not interfere
with pedestrian sidewalks. Racks should not be placed
haphazardly as an afterthought.
5. The site is located in the McClelland - Mail Creek Drainage
Basin. Stormwater fees in this basin are $3,717 per developed
acre. A Drainage Report, Drainage and Grading Plan, and
Erosion Control Plan were approved for Italian Oven. The Taco
Bell proposal should conform to the approved plans, or submit
the necessary revisions accordingly. It should be noted
whether the drainage patterns and the amount of impervious
COMMUNITY PLANNING &
ENVIRONMENTAL SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 80522-0580 (303)221-6750
PLANNING DEPARTMENT
•
•
surface conform or differ from
If you have further questions,
Stormwater Engineer, 221-6589.
the previously approved P.U.D.
please contact Glen Schlueter,
6. The existing traffic study should be updated. The study
should investigate the difference between a standard
restaurant (Italian Oven) and the proposed fast food/drive-
thru restaurant. Please adjust the trip generation rates and
the associated impacts on the surrounding circulation network.
It is recommended that the traffic consultant use Taco Bell's
own numbers on expected number of trips and time of day versus
I.T.E. (It may be useful to include expected numbers during
the Saturday noon peak time also.)
7. Staff is concerned about shared parking assumptions for the
center and how parking is distributed between the pad users,
the anchors, and the in -line retail. There is a concern that
the site is being pushed to the limit regarding land use
intensity and parking capability. The P.U.D. should indicate
how the shared parking will work given the proposed Taco Bell.
Again, it seems the Saturday noon peak time may be appropriate
by which to evaluate the shared parking program.
8. The Utility Plans that were done for Italian Oven were in
final form and may have been signed off by the City. These
existing plans may or may not need to be revised. It is
likely that the Drainage Sheet may be the only affected
portion of the Utility Plans.
9. The Street Oversizing Fee is $14,005 per acre payable at the
time of Building Permit issuance.
10. The site is located along State Highway 287. Consequently,
Taco Bell must make an application to the Colorado State
Highway Department for an access permit. Please have the data
from the updated traffic memo available for this application.
The City's Engineering Department will coordinate the
application process. Please refer to Kerrie Ashbeck, 221-
6750, for further information regarding this process.
11. Will there be any outdoor dining? If so, please indicate.
12. The drive-thru lane and menu board should be effectively
screened. The headlights of vehicles exiting the drive-thru
lane may conflict with cars traveling on South College Avenue.
This headlight glare must be mitigated.
13. The menu board will count as a sign. If two signs are not
allowed by the Sign Code, then an application for a variance
must be made to the Zoning Board of Appeals. Please contact
Peter Barnes, Zoning Administrator, 221-6760, for application
details for a variance.
14. If any exterior light fixtures are to be added, then they must
match the light fixtures already in place within the center.
15. All exterior light fixtures must not cause any light spillage
offsite. It is strongly recommended that building security
lighting be high pressure sodium, not mercury vapor or metal
halide so as to not distract drivers on College Avenue.
16. As you are aware, there has been an attempt to promote a
unified, cohesive design not only within the Market Place
P.U.D., but also with Best Buy and Foutainhead P.U.D. The
predominant theme among these three properties is the use of
a plum -colored block with blue as an accent color. While it
is acknowledged that this existing theme does not fit the
corporate standard for Taco Bell, every effort should be made
so that there is a unifying architectural element that ties
Taco Bell back to the center. As a pad site, Taco Bell must
not appear to be a stand-alone store that is more reminiscent
of strip development versus a planned unit development. To a
practical extent, the use or matching plum -colored block must
be used to promote a unified P.U.D. A good example of this
how Taco Bell in Longmont uses compatible materials to blend
in with the Twin Peaks Mall.
17. Staff is concerned about monument signage along College
Avenue. The free-standing sign must comply with the
Preliminary P.U.D. established for the whole center. The
Market Place P.U.D. has an approved Master P.U.D. Sign Plan
that allows two, double face, illuminated signs on the pad
sites (one for each pad, two total). These signs are to be no
larger than 6' x 61. (Please note that the Burger King sign
fits this criterion.) It will be important for the center to
demonstrate unified cohesiveness by complying with the size,
height, and dimensions of the Master P.U.D. Sign Plan. A copy
of this Master Sign P.U.D. Plan is available.