Loading...
HomeMy WebLinkAboutTHE QUARRY BY WATERMARK - FDP210016 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORT Kumar & Associates, Inc.® TABLE OF CONTENTS SUMMARY .................................................................................................................................... 1 PURPOSE AND SCOPE OF STUDY ........................................................................................... 2 PROPOSED CONSTRUCTION .................................................................................................... 2 SITE CONDITIONS ...................................................................................................................... 3 SUBSURFACE CONDITIONS ...................................................................................................... 3 LABORATORY TESTING ............................................................................................................. 4 GEOTECHNICAL ENGINEERING CONSIDERATIONS .............................................................. 6 FOUNDATION RECOMMENDATIONS ........................................................................................ 7 FLOOR SLABS ........................................................................................................................... 11 CONCRETE FLATWORK ........................................................................................................... 12 SITE GRADING .......................................................................................................................... 13 SURFACE DRAINAGE ............................................................................................................... 15 SEISMIC DESIGN CRITERIA ..................................................................................................... 16 CLUBHOUSE SWIMMING POOL .............................................................................................. 17 LATERAL EARTH PRESSURES ................................................................................................ 18 PAVEMENT DESIGN ................................................................................................................. 19 DESIGN AND CONSTRUCTION SUPPORT SERVICES .......................................................... 21 LIMITATIONS ............................................................................................................................. 22 FIG. 1 – LOCATIONS OF EXPLORATORY BORINGS FIGS. 2 through 4 – LOGS OF EXPLORATORY BORINGS FIG. 5 – LEGEND AND NOTES FIGS. 6 through 11 – SWELL-CONSOLIDATION TEST RESULTS FIGS. 12 and 13 – REMOLDED SWELL-CONSOLIDATION TEST RESULTS FIG. 14 – GRADATION TEST RESULTS FIG. 15 – MOISTURE-DENSITY RELATIONSHIP (STANDARD PROCTOR) TABLE I – SUMMARY OF LABORATORY TEST RESULTS Kumar & Associates, Inc.® SUMMARY 1. The subsurface conditions at the site were explored by drilling 26 exploratory borings at the approximate locations shown on Fig. 1. Pre-existing fill was encountered in some of the borings on the eastern and southern portions of the site which consisted of sandy lean clays. The fill appeared to be re-worked natural material from a source on or near the project site. The thickness of the fill encountered in the borings ranged from approximately 2 to 5 feet below the existing ground surface. The natural clay soils at the surface or underlying the fill consisted of similar lean clays with varying sand. At greater depths, natural granular soils were encountered and consisted of silty clayey sands, and occasional poorly-graded sands and silts with gravel. The natural clay soils were slightly moist to moist and generally very stiff to hard, although some zones of medium stiff to stiff clay soils were encountered near groundwater. The natural granular soils were slightly moist to wet when encountered below groundwater and were generally medium dense to very dense based on sampler penetration resistance values (blow counts). Claystone and sandstone bedrock were encountered in all but two of the building borings at depths ranging from approximately 14.5 to 23 feet below the existing ground surface. The claystone bedrock was moist and hard to very hard. The sandstone bedrock was moist and firm to very hard in consistency with partial cementation in some of the very hard zones. Groundwater was encountered during drilling at approximately 9 to 15 feet. A follow-up groundwater measurement indicated stabilized groundwater levels at about 7.5 to 11.5 feet below the ground surface. 2. With proper subgrade preparation, shallow foundations and slab-on-grade construction is feasible for the buildings. Post-Tensioned slabs and shallow spread footings placed as described herein may be designed for net allowable bearing pressures of 2,000 and 3,000 psf, respectively. Further discussion on subgrade preparation is presented in this report. 3. The following table presents the recommended pavement thicknesses: Paved Area Full Depth Asphalt (inches) Composite Section (asphalt/ABC) inches Parking Stalls 6.0 4.0 / 7 Fire Access and Drive Lanes within the Parking Lots 7.0 4.5 / 9 ABC – Aggregate Base Course Dumpster pads and other areas where truck turning movements are concentrated should be paved with a minimum of 6.0 inches of Portland cement concrete. 2 Kumar & Associates, Inc.® PURPOSE AND SCOPE OF STUDY This report presents the results of a geotechnical engineering study and pavement thickness design for “The Quarry” multifamily residential project to be constructed southeast of Hobbit Street and South Shields Street in Ft. Collins, Colorado. The project site is shown on Fig. 1. The study was conducted for the purpose of obtaining subsurface data and developing geotechnical engineering recommendations for design and construction of the proposed development. This study has been performed in general accordance with our Proposal No. P-20-847 to Watermark Residential dated November 3, 2020. A field exploration program consisting of exploratory borings was conducted to obtain information on the subsurface conditions. Samples obtained during the field exploration were tested in the laboratory to determine their classification and engineering characteristics. The results of the field exploration and laboratory testing were analyzed to develop recommendations for foundation type, building floor slabs, and site pavements. The results of the field exploration and laboratory testing are presented herein. This report has been prepared to summarize the data obtained during this study and to present our conclusions and recommendations based on the proposed construction and the subsurface conditions encountered. Design parameters and a discussion of geotechnical engineering considerations related to construction of the proposed apartment buildings and pavement areas are included in the report. PROPOSED CONSTRUCTION Based on the information provided to us, the proposed development will include the construction of several multi-story apartment buildings including eight-3-story buildings and one-4-story building. A total of ten, one- to two-story duplexes will be constructed at the northeast portion of the property. A clubhouse with swimming pool will be constructed near the entrance off of South Shields Street. Paved drive lanes and automobile parking will be constructed around the buildings. Access to the new development will be located from the west off of South Shields Street and from the north off of Hobbit Street. With the exception of the swimming pool, there is no below-ground construction planned for this project. 3 Kumar & Associates, Inc.® Finished floor elevations for the buildings were not available at the time of this report, however we do not anticipate that a significant change of grade will be required to achieve finished floor elevations. If the proposed construction varies significantly from that generally described above or depicted in this report, we should be notified to reevaluate the conclusions and recommendations provided herein. SITE CONDITIONS The overall project site will be constructed on approximately 13.5 acres of vacant land. The site is bounded by Hobbit Street on the north, South Shields Street on the west, the Spring Creek Trail on the south and by single-family residential construction on the east. The Spring Creek itself is located immediately south of the aforementioned trail. Site topography is nearly level with existing grades trending down towards the southeast portion of the site. Based on a cursory review of site grades, overall elevation differences across the entire site are approximately 5 to 8 feet, with the more dramatic elevation changes occurring in the far southeastern corner of the property. Vegetation at the site was limited to sparse weeds and grasses. Large Cottonwood trees were present along Spring Creek, just south of the southern property boundary. SUBSURFACE CONDITIONS Field Exploration: The subsurface conditions were explored by drilling 26 exploratory borings (17 building, 9 pavement) at the approximate locations shown on Fig. 1. The exploratory borings were advanced through the overburden soils and bedrock using 4-inch diameter continuous flight augers. Samples of the soils encountered in the borings were obtained with a 2-inch diameter California-type drive sampler. The sampler was driven with blows from a 140-pound hammer falling 30 inches. This sampling procedure is similar to the standard penetration test described by ASTM D1586. Penetration resistance values indicate the relative density or consistency of the subsurface soils. 4 Kumar & Associates, Inc.® Graphic logs of the exploratory borings are presented on Figs. 2 through 4. A legend and notes describing the subsurface soils encountered is presented on Fig. 5. Subsurface Conditions: Pre-existing fill was encountered in some of the borings on the eastern and southern portions of the site which consisted of sandy lean clays. The fill appeared to be re- worked natural material from a source on or near the project site. The exact lateral and vertical extents of the soil and the degree of compaction of the fill was not evaluated as part of this study. The thickness of the fill encountered in the borings ranged from approximately 2 to 5 feet below the existing ground surface. The natural clay soils encountered at the surface/underlying the fill consisted of similar lean clays with varying sand. At greater depths, natural granular soils were encountered and consisted of silty clayey sands, and occasional poorly-graded sands and silts with gravel. The natural clay soils were slightly moist to moist and generally very stiff to hard, although some zones of medium stiff to stiff clay soils were encountered near groundwater. The natural granular soils were slightly moist to wet when encountered below groundwater and were generally medium dense to very dense based on sampler penetration resistance values (blow counts). Claystone and sandstone bedrock were encountered in all but two of the building borings at depths ranging from approximately 14.5 to 23 feet below the existing ground surface. The claystone bedrock was moist and hard to very hard. The sandstone bedrock was moist and firm to very hard in consistency with partial cementation in some of the very hard zones. Groundwater was encountered during drilling at approximately 9 to 15 feet. A follow-up groundwater measurement indicated stabilized groundwater levels at about 7.5 to 11.5 feet below the ground surface. Water levels may fluctuate with time, and fluctuate upward in response to heavy precipitation and landscape irrigation. LABORATORY TESTING Selected samples obtained from the exploratory borings were visually classified by the project engineer. Laboratory testing was performed on selected samples to determine in-situ soil moisture content and dry unit weight, liquid and plastic limits, swell-consolidation behavior, moisture-density relationship (standard Proctor) and concentration of water-soluble sulfates. The 5 Kumar & Associates, Inc.® results of the laboratory testing program are shown adjacent to the graphical boring logs on Figs. 2 through 4, plotted graphically on Figs. 6 through 15, and summarized the attached Table I. The testing was conducted in general accordance with recognized ASTM International and CDOT test procedures. Swell-Consolidation Testing: Swell-consolidation testing was conducted on samples of the on- site overburden clays to determine their swell or compressibility characteristics under loading and when wetted. Additional swell-consolidation testing was conducted on clayey samples which were remolded to near 95% of the maximum dry density at, and above optimum moisture content to help determine the suitability of the on-site material for use as structural fill below foundations and floor slabs. Each sample was prepared and placed in a confining ring between porous discs. A selected surcharge pressure of either 200 or 1,000 psf was applied to the samples, and each sample was allowed to compress to a stabilized height before being submerged in water. The sample height was monitored until deformation practically ceased under each load increment. The results of the laboratory swell-consolidation testing indicate that the tested in-situ samples of the on-site clays exhibited generally low swell potential in the majority of the samples and very high swell characteristics in two tested samples. The high to very high swell potential is due in part to the relatively low moisture content and relatively high in-situ dry density of the samples. One in-situ sample of clay exhibited additional compression under additional loading, which we believe to be the result of sample disturbance during sampling and handling. The remolded samples of the on-site clay exhibited low swell potential. Results of the swell- consolidation tests are presented on Figs. 6 through 13. Water-Soluble Sulfates: The concentration of water-soluble sulfates measured in samples of the on-site clay soils obtained from the exploratory borings ranged from 0.07% to 0.19%. These concentrations of water-soluble sulfates represent a Class S0 to borderline Class S1/S2 severity exposure of sulfate attack on concrete exposed to these materials. These degrees of attack are based on a range of Class S0, Class S1, Class S2, and Class S3 severity exposure as presented in ACI 201.2R. 6 Kumar & Associates, Inc.® Based on the laboratory data and our experience, we recommend all concrete exposed to the on- site materials meet the cement requirements for Class S2 exposure as presented in ACI 201.2R. Alternatively, the concrete could meet the Colorado Department of Transportation’s (CDOT) cement requirements for Class 2 exposure as presented in Section 601.04 of the latest version of the CDOT Standard Specifications for Road and Bridge Construction. GEOTECHNICAL ENGINEERING CONSIDERATIONS Pre-Existing Fill: As indicated, fill was encountered in a handful of borings at the site, which extended to as deep as 5 feet below the ground surface. Deeper concentrations of fill may be present. Pre-existing fill beneath foundations and floor slabs present a problem, particularly if the existing fill was placed in an uncontrolled fashion. As such, uncontrolled fill can be subject to variable and unpredictable settlement and/or heave-related movement under structural loading. Accordingly, the existing fill at the site should be considered non-engineered in its present condition. Therefore, all existing fill beneath foundation and floor slab areas should be over- excavated, and replaced with structural fill according to the material and placement recommendations provided in the “Site Grading” section of this report. Foundations and Floor Slabs: At the time of this report, we had not been provided with a grading plan. Based on the subsurface conditions encountered in the borings and the topography of this site, we assume soil conditions at foundation and floor slab subgrade elevation may consist of moderate to highly expansive clays. Foundations placed on expansive material such as the on- site clays soils are likely to experience movement in excess of normally accepted tolerances should the soils become subject to moisture changes. The safest approach to limit potentially excessive foundation movement due to potential moisture-related expansion is to support the building on a deep foundation system using straight-shaft piers drilled into bedrock or helical piers bearing in bedrock or dense granular soils. Using a deep foundation system has the advantage of bottoming the piers in a zone of relatively stable moisture content and concentrating the loads to help offset uplift forces from expansive soil and bedrock. Floor slabs also present a problem where potentially expansive materials are present near floor slab elevation because sufficient dead load cannot be imposed on them to resist the uplift generated when the materials are wetted and expand. The most positive method to avoid slab damage as a result of ground heave is to construct a structural floor above a well-vented crawl 7 Kumar & Associates, Inc.® space. The structural floor would be supported on grade beams and piers the same as the main structure. Alternatively, a “slab-on-void” construction approach may be used by constructing a structurally supported reinforced slab on void form material. We recognize deep foundation systems in combination with structural floors may be cost prohibitive to the project. Based on our experience, we believe slab-on-grade floors supported on a zone of compacted fill should be a practical and cost-effective alternative to structural floors for the proposed building. Additionally, the over-excavation required for slab-on-grade construction would also allow the use of a shallow foundation system bearing on the prepared fill. Acceptable performance will also rely on minimizing water infiltration into the soils by providing good surface drainage and implementing sensible landscaping and irrigation practices. The Owner should understand and accept the risk of distress resulting from some foundation and slab movement even though mitigation measures are used to reduce the potential for building and slab distress resulting from ground heave. If the potential for foundation settlement or uplift is not acceptable, a deep foundation system in combination with a structural floor should be used. Kumar & Associates can provide recommendations for deep foundations and structural floors, if requested. Given the above discussion and based on the proposed construction and the subsurface conditions encountered in the borings, we believe shallow foundations and slab on grade construction is feasible for the site structures. Shallow foundations may consist of Post- Tensioned (PT) slabs or spread footings placed on a minimum zone of re-conditioned structural fill placed and compacted to the recommendations presented in the “Site Grading” section of this report. FOUNDATION RECOMMENDATIONS Post-Tensioned Slabs: We assume that PT-slab foundation design will be conducted in accordance with the Post-Tensioning Institute’s (PTI) design approach. PTI’s current design approach is outlined in their publication "Design of Post-Tensioned Slabs-On-Ground (Third Edition, 2004)" and subsequent addenda, which revised the approach that was outlined in their publication "Design and Construction of Post-Tensioned Slabs-On-Ground (Second Edition, 1996)". It is the opinion of K+A and many other geotechnical engineers practicing in this area 8 Kumar & Associates, Inc.® that the guidelines provided in both the Second and Third Editions are empirical methods developed for application in other parts of the country, and may not be strictly applicable for local conditions due to the method not taking into account direct measurements of a soil’s swell- consolidation characteristics, which are routinely used for foundation design in the Denver area. The International Building Code (IBC) permits designing PT-slabs in accordance with the methods outlined in either the Second or Third Editions. The values presented for design are based on guidelines in the PTI’s Third Edition. The design and construction criteria presented below should be observed for a PT-slab foundation. The construction details should be considered when preparing project documents. 1. We recommend that PT-slab foundations be supported on a prepared subgrade consisting of at least 3 feet of properly moisture-conditioned and compacted structural fill extending to undisturbed natural soil. The minimum depth of fill should be measured from the bottom level of the turned down edge of the slab. The over-excavation for the compacted fill zone should extend beyond the limits of the PT-slab foundation to a minimum distance equal to the depth of over-excavation. Loose or soft material encountered within the foundation excavation should be removed and replaced with compacted structural fill according to the recommendations presented in the “Site Grading” section of this report. 2. PT-slab foundations bearing on compacted fill material placed as recommended herein should be designed for a maximum allowable bearing pressure of 2,000 psf. 3. Based on the methodology in PTI’s Third Edition, the slabs should be designed using the following criteria: Criteria Center Lift Edge Lift Moisture variation (em) (ft.) 9.0 4.6 Differential swell (ym) (in) 0.4 0.3 The parameters used to calculate these values include a controlling soil suction (pF) of 3.6, and a depth to constant soil suction of 7 feet in accordance with the PTI Manual 3rd Edition. These parameters were selected from the PTI Design Manual based on soil index 9 Kumar & Associates, Inc.® parameters and our opinion regarding the site's swell and compressibility potential; they are not actual measurements or estimates of soil suction and soil moisture distributions across the site. 4. The exterior perimeter slab beams should have sufficient embedment for frost protection. The down-turned edges should have a minimum of 36 inches of soil cover. 5. Once the building pad area has been prepared as described above, it should be protected from excessive wetting or drying until after the foundation has been completed. 6. We recommend an experienced PT-slab contractor construct the slabs. Representatives of the geotechnical and structural engineer should check the foundation excavations and tendon positions prior to placement of concrete, respectively. Fill placement and subgrade preparation should be observed and tested by a representative of the geotechnical engineer. Spread Footings: Shallow spread footings are feasible for foundation support of the site structures. Similar to PT-Slab foundations, footings should be placed on a minimum of 3 feet of properly moisture-conditioned and compacted structural fill extending to undisturbed natural soil. The design and construction criteria presented below should be observed for a spread footing foundation system. The construction details should be considered when preparing project documents. 1. Footings placed as described above should be designed for a net allowable soil bearing pressure of 3,000 psf. 2. Based on experience, we estimate total settlement for footings designed and constructed as discussed in this section will be less than 1-inch. Differential settlements across the building are estimated to be approximately ½ to ¾ of the total settlement. 3. Spread footings should have a minimum footing width of 16 inches for continuous footings and of 24 inches for isolated pads. 10 Kumar & Associates, Inc.® 4. Exterior footings and footings beneath unheated areas should be provided with adequate soil cover above their bearing elevation for frost protection. Placement of foundations at least 36 inches below the exterior grade is typically used in this area. 5. The lateral resistance of a spread footing placed as described herein will be a combination of the sliding resistance of the footing on the foundation materials and passive earth pressure against the side of the footing. Resistance to sliding at the bottoms of the footings can be calculated based on a coefficient of friction of 0.30. Passive pressure against the sides of the footings can be calculated using an equivalent fluid unit weight of 190 pcf. The above values are working values with a factor of safety of 2.0 applied. 6. Structural fill placed beneath footings should meet the placement and compaction recommendations presented in the “Site Grading” section of this report. Compacted fill placed against the sides of the footings to resist lateral loads should be a non-expansive material. 7. Excessive wetting or drying of the foundation excavations should be avoided during construction. Care should be taken to provide adequate surface drainage during the excavation of footings, and the contractor should have equipment available for removing water from excavations following precipitation, if needed. Footing excavations that are inundated as a result of uncontrolled surface runoff may soften, requiring possible additional moisture conditioning and re-compaction of the exposed subgrade soils, or removal of soft subgrade soils and replacement with new compacted structural fill. 8. Continuous foundation walls should be reinforced top and bottom to span an unsupported length of at least 10 feet. 9. A representative of the geotechnical engineer should observe all footing excavations prior to concrete placement. 11 Kumar & Associates, Inc.® FLOOR SLABS For slab on grade floors, the following measures should be taken to reduce damage which could result from movement should the under-slab materials be subjected to changes in moisture content. 1. Floor slabs should be supported on a minimum 5-foot-thick layer of properly compacted structural fill meeting the material and placement criteria in the “Site Grading” section of this report. 2. Floor slabs should be separated from all bearing walls and columns with expansion joints which allow unrestrained vertical movement. 3. Non-bearing partitions resting on floor slabs should be provided with slip joints so that, if the slabs move, the movement cannot be transmitted to the upper structure. This detail is also important for wallboards and door frames. Slip joints that will allow at least 2 inches of vertical movement are recommended. If wood or metal stud partition walls are used, the slip joints should preferably be placed at the bottoms of the walls so differential slab movement will not damage the partition wall. If slab-bearing masonry block partitions are constructed, the slip joints will have to be placed at the tops of the walls. If slip joints are provided at the tops of walls and the floors move, it is likely the partition walls will show signs of distress, such as cracking. An alternative, if masonry block walls or other walls without slip joints at the bottoms are required, is to found them on pad-supported grade beams and to construct the slabs independently of the foundation. If slab-bearing partition walls are required, distress may be reduced by connecting the partition walls to the exterior walls using slip channels. 4. Floor slab control joints should be used to reduce damage due to shrinkage cracking. Joint spacing is dependent on slab thickness, concrete aggregate size, and slump, and should be consistent with recognized guidelines such as those of the Portland Cement Association (PCA) or American Concrete Institute (ACI). The joint spacing and slab reinforcement should be established by the designer based on experience and the intended slab use. 12 Kumar & Associates, Inc.® 5. Floor slabs should not extend beneath exterior doors or over foundation grade beams, unless saw cut at the beam after construction. 6. If moisture-sensitive floor coverings will be used, mitigation of moisture penetration into the slabs, such as by use of a vapor barrier may be required. If an impervious vapor barrier membrane is used, special precautions will be required to prevent differential curing problems which could cause the slabs to warp. American Concrete Institute (ACI) 302.1R addresses this topic. 7. All plumbing lines should be tested before operation. Where plumbing lines enter through the floor, a positive bond break should be provided. Flexible connections should be provided for slab-bearing mechanical equipment. 8. The geotechnical engineer should evaluate the suitability of proposed under-slab fill material. The precautions and recommendations itemized above will not prevent the movement of floor slabs if the underlying materials are subjected to alternate wetting and drying cycles. However, the precautions should reduce the damage if such movement occurs. CONCRETE FLATWORK The depth of over-excavation and replacement beneath exterior flatwork immediately adjacent to the buildings including sidewalks and areas where reduction of heave potential is considered important should be done in accordance with the recommendations provided in the “Floor Slabs” section of this report. Where reduction of movement potential is less of a concern such as for patios and sidewalks located more than 10 feet from the building, subgrade preparation may be done in accordance with the subgrade preparation recommendations provided in the “Pavement Design” section of this report. Proper surface drainage measures as recommended in following sections of this report are also critical to limiting moisture- or frost-related movement. Upward heave-related movement of exterior flatwork adjacent to the building may result in adverse drainage conditions with runoff directed toward the building. In addition, upward 13 Kumar & Associates, Inc.® movement of exterior flatwork may restrict movement of outward swinging doors. Site grading and drainage design should consider those possibilities, particularly at entryways. SITE GRADING Site Preparation: Prior to placing new fills, the exposed subgrade should be scarified to a depth of 12 inches, adjusted to a moisture content within 2 percentage points of optimum, and recompacted to at least 95% of the standard Proctor (ASTM D698) maximum dry density. The compacted subgrade should be proof rolled with a heavily-loaded pneumatic-tired vehicle or a heavy, smooth-drum roller compactor. Areas that deform excessively during proof rolling should be removed and replaced to achieve a reasonably stable subgrade prior to placement of structural fill. Temporary Excavations: We assume that temporary excavations will be constructed by over- excavating the slopes to a stable configuration where enough space is available. Excavations generally will extend through existing fill and/or natural clay soils and are not anticipated to encounter groundwater. All excavations should be constructed in accordance with OSHA requirements, as well as state, local and other applicable requirements. The on-site natural clay soils will generally classify as Type B soils. Excavations encountering perched groundwater could require much flatter side slopes than those allowed by OSHA. Material Specifications: The following material specifications are presented for fills on the project site. 1. Fills Placed at the Site: The on-site soils are suitable for re-use as structural fill beneath buildings and pavements. If imported fill is required, the following requirements should be met: Percent Passing No. 200 Sieve Maximum 50 Liquid Limit Maximum 30 Plasticity Index Maximum 15 Fill source materials not meeting the above liquid limit and plasticity index criteria may be acceptable if the swell potential when remolded to 95% of the ASTM D698 (standard Proctor) maximum dry density at optimum moisture content under a 200 psf surcharge 14 Kumar & Associates, Inc.® pressure does not exceed 0.5%. Evaluation of potential import sources would require determination of laboratory moisture-density relationships and swell consolidation tests on remolded samples. 2. Utility Trench Backfill: Material excavated from the utility trenches may be used for backfill provided it does not contain unsuitable material or particles larger than 4 inches. 3. Material Suitability: The on-site soils including the existing fills, are generally suitable for use as structural fill material. The on-site overburden soils are generally expected to possess low swell potential when moisture conditioned and compacted according to the recommended criteria. All fill material should be free of vegetation, brush, sod and other deleterious substances and should not contain rocks, debris or lumps having a diameter of more than 4 inches. The geotechnical engineer should evaluate the suitability of proposed import fill materials prior to placement. Compaction Specifications: We recommend the following compaction criteria be used on the project: Moisture Content: Fill should be placed at a moisture content between 0 and +3 percentage points of optimum for predominantly clay fill materials, and at a moisture content within 2 percentage points of the optimum moisture content for predominantly granular fill materials. The contractor should be aware that the clayey soils may become somewhat unstable and deform under wheel loads if placed near the upper end of the moisture range. Degree of Compaction: The following compaction criteria should be followed during construction: 15 Kumar & Associates, Inc.® AREA MINIMUM PERCENTAGE OF MAXIMUM STANDARD PROCTOR DENSITY (ASTM D-698) Fills placed shallower than 8 feet 95% Fills beneath exterior slabs and pavement structures 95% Fills placed deeper than 8' 98% Utility Trenches 95% Foundation Wall Backfill 95% A representative of the geotechnical engineer should observe fill placement on a full-time basis. SURFACE DRAINAGE Proper surface drainage is important for acceptable performance of the structures during construction and after the construction has been completed. Drainage recommendations provided by local, state and national entities should be followed based on the intended use of the structures. The following recommendations should be used as guidelines and changes should be made only after consultation with the geotechnical engineer. 1. Excessive wetting or drying of the foundation and slab subgrades should be avoided during construction. 2. Exterior backfill should be adjusted to near optimum moisture content (generally ±2% of optimum unless indicated otherwise in the report) and compacted to at least 95% of the ASTM D698 (standard Proctor) maximum dry density. 3. The ground surface surrounding the exterior of the building should be positively sloped to drain away from the foundation in all directions. We recommend a minimum slope of 12 inches in the first 10 feet in unpaved areas. Site drainage beyond the 10-foot zone should be designed to promote runoff and reduce infiltration. These slopes may be changed to comply with the ADA Act. (Special Publication 43 of the Colorado Geologic Survey, “A Guide to Swelling Soils for Colorado Homebuyers and Homeowners,” provides useful information on drainage design and landscaping on expansive soil sites.) Surface diversion features should be provided around parking areas to prevent surface runoff from flowing across the paved surfaces. 16 Kumar & Associates, Inc.® 4. The upper 1 to 2 feet of the backfill should be relatively impervious material compacted as above to limit infiltration of surface runoff. 5. Ponding of water should not be allowed in backfill material of in a zone within 10 feet of the foundation walls, whichever is greater. 6. Roof downspouts and drains should discharge well beyond the limits of all backfill. 7. Landscaping adjacent to buildings underlain by moisture-sensitive soils should be designed to avoid irrigation requirements that would significantly increase soil moisture and potential infiltration of water within at least 10 feet of foundation walls. Landscaping located within 10 feet of foundation walls should be designed for irrigation rates that do not significantly exceed evapotranspiration rates. Use of vegetation with low water demand and/or drip irrigation systems are frequently used methods for limiting irrigation quantities. Lawn sprinkler heads and landscape vegetation that requires relatively heavy irrigation should be located at least 10 feet from foundation walls. Even in areas away from buildings, it is important to provide good drainage to promote runoff and reduce infiltration. Main pressurized zone supply lines, including those supplying drip systems, should be located more than 10 feet from buildings in the event that leaks occur. All irrigation systems, including zone supply lines, drip lines, and sprinkler heads should be routinely inspected for leaks, damage, and improper operation. SEISMIC DESIGN CRITERIA The soil profile generally consists of 15 to 25 feet of stiff to very stiff clayey overburden overlying firm to very hard claystone and sandstone bedrock. According to International Building Code (IBC) 2015, the overburden soils encountered at the site generally classify as IBC Site Class D, and the bedrock encountered classifies as Site Class C. Based on the soil profile encountered in our borings and the standard penetration testing from the field exploration, the estimated weighted average of shear wave velocity in the upper 100 feet indicates that IBC Site Class D should be used in the design. Based on the subsurface profile, site seismicity, and the anticipated ground water conditions, liquefaction is not a design consideration. 17 Kumar & Associates, Inc.® CLUBHOUSE SWIMMING POOL The boring drilled in the approximate area of the swimming pool (Boring 15) encountered pre- existing fill and natural overburden soil to a depth of about 20 feet, overlying bedrock. Groundwater was measured at approximately 11 feet below the surface 23 days after drilling. Proper design and construction of below-ground pool structures is critical to their satisfactory performance when expansive materials are present. All swimming pools have a tendency to leak. A small amount of leakage can cause the subsoils to swell and result in pool or slab movement which widens existing cracks and introduces more water into the subsoils, thereby compounding the problem. Based on these considerations and the subsurface conditions, we suggest the following precautions be taken in the design and construction of the proposed pool. 1. The pool should be designed and constructed to withstand differential movement without serious cracking. 2. Natural material below the pool should be removed to a depth of 12 inches and replaced with a non-expansive, impervious fill material compacted to 95% of the standard Proctor (ASTM D698) maximum dry density at or above optimum moisture content. 3. A perimeter drain should be constructed at the base of the pool and sloped at a minimum 1% to an outlet where water can be removed by gravity flow or pumped. The drains should consist of perforated pipe surrounded by a minimum of 12 inches of free-draining granular material. A minimum 4-inch-thick free-draining gravel layer should be placed beneath the pool deck and swimming pool floor. The drainage layer under the pool should slope to a drain line or collection point from which water can be removed by pumping or gravity drainage. The drainage layer under the deck should slope to a perimeter drain or be connected to the under-pool layer by free-draining backfill wrapped in a filter fabric. Free-draining aggregate should conform to the requirements of CDOT Class B or Class C Filter Material, unless a filter geotextile is used on the slab subgrade and around underdrain trenches; in that case a coarser free-draining gravel not necessarily meeting 18 Kumar & Associates, Inc.® graded filter criteria, such as AASHTO No. 57 or No. 67 Aggregate, may be used. Pipe slots or perforations should be sized in accordance with the type of free-draining material surrounding the pipe. We are available to assist in the underdrain system design if requested. 4. A tight joint should be provided between the pool and deck so water splashed from the pool will not infiltrate the subsoils. Cracks which develop on the deck while the pool is in service should be caulked to prevent water infiltration. 5. The pool deck and adjoining area should be sloped to minimize ponding and infiltration of moisture into the subsoils. Lawn irrigation should be kept to a minimum adjacent to the pool. 6. We recommend the bottom of the pool be kept at least 3 feet above groundwater to prevent hydrostatic uplift on the pool should groundwater levels rise. These precautions will not eliminate the risk of damage to the pool and deck due to expansive materials, but should reduce the chances of subsurface materials becoming wetted and subsequent movement due to changes in moisture content. LATERAL EARTH PRESSURES Earth retaining structures should be designed for the lateral earth pressure based on the degree of rigidity of the retaining structure and the type of backfill material used. Retaining structures that are laterally supported and can be expected to undergo only a moderate amount of deflection should be designed for earth pressures based on the following equivalent fluid unit weights: CDOT Class 1 (<20% passing No. 200 Sieve) ........................................................... 50 pcf On-site, moisture-conditioned cohesive soil backfills ................................................ 65 pcf Cantilevered retaining structures that can be expected to deflect sufficiently to mobilize the full active earth pressure condition should be designed for the following equivalent fluid unit weights: 19 Kumar & Associates, Inc.® CDOT Class 1 (<20% passing No. 200 Sieve) ........................................................... 40 pcf On-site, moisture-conditioned cohesive soil backfills ................................................ 55 pcf The pressures recommended above assume drained conditions behind the structures and a horizontal backfill surface. The buildup of water behind a wall or an upward sloping backfill surface will increase the lateral pressure imposed on a retaining structure. PAVEMENT DESIGN A pavement section is a layered system designed to distribute concentrated traffic loads to the subgrade. Performance of the pavement structure is directly related to the physical properties of the subgrade soils and traffic loadings. Soils are represented for pavement design purposes by means of a soil support value for flexible pavements and a modulus of subgrade reaction for rigid pavements. Both values are empirically related to strength. Subgrade Materials: Based on the results of the field and laboratory studies, the majority subgrade materials at the site classify as A-6 and A-7-6 soils with group indices between 3 and 32 in accordance with the American Association of State Highway and Transportation Officials (AASHTO) classification. A sample of sandy lean clay classified as A-4 with a group index of 3, and samples of poorly-graded sand with silt and gravel and silty clayey sand classified as A-2-4 with a group index of 0. Based on the subsurface soil properties, and on our experience with similar soils, a design resilient modulus of 3,025 psi was selected for flexible pavements and a modulus of subgrade reaction of 70 pci was selected for rigid pavements. Design Traffic: Since anticipated traffic loading information was not available at the time of report preparation, we are assuming that traffic to the site will consist primarily of automobile traffic and small moving vehicles that will utilize the facility on a routine basis. The following 18-kip equivalent single axle loading (ESAL) values were assumed as indicated below: Paved Area 18-kip ESALS Parking Stalls 36,500 Fire Access and Drive Lanes within the Parking Lots 109,500 20 Kumar & Associates, Inc.® The ESAL assumptions above are typical values we have used in the past for similar projects based on our experience. We should be contacted to reevaluate the recommendations provided herein if the any of the traffic distribution assumptions are found to be different than those described above. Pavement Design: The following table presents the recommended pavement thicknesses: Area Full Depth Asphalt (inches) Composite Section (Asphalt/ABC) inches Parking Stalls 6.0 4.0 / 7 Fire Access and Drive Lanes within the Parking Lots 7.0 4.5 / 9 ABC – Aggregate Base Course Dumpster pads and other areas where truck turning movements are concentrated should be paved with a minimum of 6.0 inches of Portland cement concrete. The concrete pavement should contain sawed or formed joints to ¼ of the depth of the slab at a maximum distance of 15 feet on center. Pavement Material Recommendations: Pavement Materials: The following are recommended material and placement requirements for pavement construction for this project site. 1. Aggregate Base Course: The aggregate base course used in the flexible composite alternative should meet the requirements Class 6 aggregate base course in accordance with CDOT specifications. The aggregate base course should be compacted to a minimum of 95 percent of the maximum modified Proctor dry density (AASHTO T180) at a moisture content within 2 percentage points of optimum. 2. Hot Mix Asphalt: Hot mix asphalt (HMA) materials and mix designs should meet the applicable requirements indicated in the current CDOT “Standard Specifications for Road and Bridge Construction”. We recommend that the HMA used for this project is designed in accordance with the SuperPave gyratory mix design method. The mix should meet Grading S specifications with a SuperPave gyratory design revolution (NDESIGN) of 75. A mix meeting Grading SX specification can be used for the top lift wearing course, 21 Kumar & Associates, Inc.® however, this is optional. The mix design(s) for the HMA should use a performance grade (PG) asphalt binder of PG 58-28 or PG 64-22. However, we recommend the PG 58-28 binder which tends to perform better under relatively low traffic volumes. Placement and compaction of HMA should follow current CDOT standards and specifications. Subgrade Preparation: Prior to placing the pavement section, the subgrade beneath pavements should be thoroughly scarified and well-mixed to a depth of 12 inches, adjusted to a moisture content between -1 to +3 percentage points of the optimum moisture content for clayey subgrades, and within 2 percentage points of the optimum moisture content for granular subgrades and compacted to at least 95% of the standard Proctor (ASTM D698) maximum dry density. Proof rolling should be performed after the specified compaction is obtained. Proof rolling should be performed with heavy rubber-tired equipment with a tire pressure of at least 100 psi capable of applying a minimum load of 18-kips per axle. Areas where excessive deflection occurs should be ripped, scarified, wetted or dried if necessary, and recompacted to the required moisture and density specifications. Drainage: The collection and diversion of surface drainage away from paved areas is extremely important to the satisfactory performance of pavement. Drainage design should provide for the removal of water from paved areas and prevent the wetting of the subgrade soils. DESIGN AND CONSTRUCTION SUPPORT SERVICES Kumar & Associates, Inc. should be retained to review the project plans and specifications for conformance with the recommendations provided in our report. We are also available to assist the design team in preparing specifications for geotechnical aspects of the project, and performing additional studies if necessary, to accommodate possible changes in the proposed construction. We recommend that Kumar & Associates, Inc. be retained to provide construction observation and testing services to document that the intent of this report and the requirements of the plans and specifications are being followed during construction. This will allow us to identify possible variations in subsurface conditions from those encountered during this study and to allow us to re-evaluate our recommendations, if needed. We will not be responsible for implementation of 22 Kumar & Associates, Inc.® the recommendations presented in this report by others, if we are not retained to provide construction observation and testing services. LIMITATIONS This study has been conducted in accordance with generally accepted geotechnical engineering practices in this area for exclusive use by the client for design purposes. The conclusions and recommendations submitted in this report are based upon the data obtained from the exploratory borings at the locations indicated on Fig. 1, and the proposed type of construction. This report may not reflect subsurface variations that occur between the exploratory borings, and the nature and extent of variations across the site may not become evident until site grading and excavations are performed. If during construction, fill, soil, rock or water conditions appear to be different from those described herein, Kumar & Associates, Inc. should be advised at once so that a re- evaluation of the recommendations presented in this report can be made. Kumar & Associates, Inc. is not responsible for liability associated with interpretation of subsurface data by others. The scope of services for this project does not include any environmental assessment of the site or identification of contaminated or hazardous materials or conditions. Swelling soils and bedrock are present at this site. Such materials are stable at their natural moisture content but will undergo high volume changes with changes in moisture content. The extent and amount of perched water beneath the building site as a result of area precipitation and irrigation, and inadequate surface drainage, is difficult, if not impossible, to foresee. The recommendations presented in this report are based on current theories and experience of our engineers on the behavior of swelling soil and bedrock in this area. The Owner should be aware that there is a risk in constructing buildings and pavements in an area of highly expansive soil and bedrock. Following the recommendations given by a geotechnical engineer, careful construction practice and prudent maintenance by the owner can, however, decrease the risk of foundation, slab and pavement movement due to expansive materials. RRK/js Rev. by: NK cc: file Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates Kumar & Associates TABLE I SUMMARY OF LABORATORY TEST RESULTS PROJECT NO.: 20-1-671 PROJECT NAME: The Quarry Multi-Family Development DATE SAMPLED: 11-13-2020 and 11-17-2020 DATE RECEIVED: 11-18-2020 SAMPLE LOCATION DATE TESTED NATURAL MOISTURE CONTENT (%) NATURAL DRY DENSITY (pcf) GRADATION PERCENT PASSING NO. 200 SIEVE ATTERBERG LIMITS WATER SOLUBLE SULFATES (%) MDD* (pcf) OMC* (%) AASHTO CLASSIFICATION (group index) SOIL OR BEDROCK TYPE BORING DEPTH (feet) GRAVEL (%) SAND (%) LIQUID LIMIT (%)PLASTICITY INDEX (%)1 4 11-18-20 16.6 112.3 0 20 80 35 20 0.07 A-6 (14) Lean Clay with Sand (CL) 2 4 11-27-20 18.1 107.7 74 37 21 A-6 (14) Lean Clay with Sand (CL) 3 4 11-27-20 13.0 115.0 77 38 20 A-6 (14) Lean Clay with Sand (CL) 4 4 11-27-20 9.5 119.5 58 26 10 A-4 (3) Sandy Lean Clay (CL) 5 1 11-27-20 11.0 118.9 90 44 28 A-7-6 (26) Lean Clay (CL) 6 9 11-27-20 26.2 97.8 96 49 31 A-7-6 (32) Lean Clay (CL) 7 4 11-18-20 15.7 108.2 0 18 82 34 20 0.07 A-6 (15) Lean Clay with Sand (CL) 8 9 11-27-20 27.5 96.5 94 42 24 A-7-6 (23) Lean Clay (CL) 9 4 11-27-20 8.4 105.0 52 26 11 A-6 (3) Sandy Lean Clay (CL) 10 4 11-27-20 8.1 113.6 6 38 56 34 20 A-6 (8) Sandy Lean Clay (CL) 11 1 11-27-20 6.8 96.5 49 30 16 A-6 (4) Clayey Sand (SC) 12 9 11-27-20 28.0 95.2 82 43 26 A-7-6 (21) Lean Clay with Sand (CL) 13 4 11-27-20 11.9 116.7 69 37 22 A-6 (13) Sandy Lean Clay (CL) 14 4 11-27-20 13.8 119.6 73 30 17 0.19 A-6 (10) Lean Clay with Sand (CL) 15 14 11-27-20 7.9 128.6 48 42 10 NV NP A-2-4 (0) Poorly-Graded Sand with Silt and Gravel (SP-SM) 16 4 11-27-20 9.9 118.2 55 34 18 A-6 (7) Sandy Lean Clay (CL) 17 4 11-27-20 9.2 124.5 62 35 20 A-6 (9) Fill: Sandy Lean Clay (CL) P-1 1 11-27-20 7.1 120.3 10 36 54 36 20 A-6 (7) Sandy Lean Clay (CL) P-3 1 11-27-20 3.3 110.8 4 71 25 22 6 A-2-4 (0) Silty Clayey Sand (SC-SM) P-5 4 11-27-20 9.2 108.2 64 35 20 A-6 (10) Sandy Lean Clay (CL) P-6 1 11-27-20 9.7 117.2 75 35 20 A-6 (13) Lean Clay with Sand (CL) P-7 1 11-27-20 6.0 110.6 16 38 46 33 18 A-6 (4) Clayey Sand with Gravel (SC) P-9 1 11-27-20 8.1 109.4 56 32 16 A-6 (6) Sandy Lean Clay (CL) B-5 4 – 9 71 35 20 105.7 / 15.3 A-6 (12) Lean Clay with Sand (CL) *Maximum Dry Density (MDD) and Optimum Moisture Content (OMC) as determined by ASTM D698