fcgov.com/developmentreviewRE:MosaicNeighborhoodCenter,PDP210003,RoundNumber2
Please see the following summary of comments from City staff and outside reviewingagencies for your submittal of Mosaic Neighborhood Center.If you have questions aboutany comments, you
may contact the individual commenter or direct your questions throughyourDevelopmentReviewCoordinator,BrandyBethuremHarrasvia phone at
970-416-2744orviaemailatbbethuremharras@fcgov.com.
CommentSummary:
Department:DevelopmentReviewCoordinatorContact: BrandyBethuremHarras,970-416-2744,bbethuremharras@fcgov.comTopic:General
CommentNumber:1
02/08/2021:INFORMATION:
I will be your primary point of contact throughout the development review andpermitting process. If you have any questions, need additional meetings with theproject reviewers, or need
assistance throughout the process, please let meknowand Icanassistyou and yourteam.Please include me inallemail
correspondencewithotherreviewersandkeepmeinformedofanyphoneconversations.Thankyou!Response: Acknowledged.
Department:PlanningServicesContact: Pete Wray,970-221-6754,pwray@fcgov.comTopic:General
CommentNumber:4
02/15/2021:FORHEARING:
BIKEPARKING:For the minimum 10 bike parking spaces provided for the pool recreation use, staff recommendsadding additional racks since you stated a majority of Mosaic neighbors may walk
or ride to center.Response: Additional bike racks have been added to the plan – these are located adjacent to the community space outside of the pool fence area.CommentNumber:5
02/15/2021:FORHEARING:
PARKINGPERIMETERLANDSCAPINGPlease include screening of parking lot from both Sykes Drive and ConquestWay frontages in the form of wall, full landscape hedge or other combination tomeetparking
lotperimeterlandscapingreqjuirement.Response: A full landscape area is proposed and was discussed prior to hearing – this planting area will consist of deciduous shrubs, ornamental
grasses and perennials tall enough to block the parking area.
CommentNumber:6
04/18/2021:FORHEARING:
SECTION3.5.3-BUILDINGSTANDARDSPlease include pool house and commercial building color elevations, addsummarytabletoshowmaterials,finishesandcolorstomatchelevations.Response: Color elevations
have been included in the FDP submittal.
CommentNumber:7
04/18/2021:FORHEARING:
IcanreviewPDFsofchangeslistedabove,thenPlanningisreadyforhearing.Response: Acknowledged
Department:EngineeringDevelopmentReviewContact: Marc Virata,970-221-6567,mvirata@fcgov.comTopic:General
CommentNumber:4
04/20/2021:FORFINALPLAN:
The City has updated its utility plan approval block and is only required on thecover sheet. A direct download to this can be found here:https://www.fcgov.com/engineering/files/utilitysigblock.pdf?1611856399
Response: Block updated.
Department:TrafficOperationContact: SteveGilchrist,970-224-6175,sgilchrist@fcgov.comTopic:General
CommentNumber:2
04/16/2021:FORINFORMATION:
The Utility Plans look like they are trying to indicate available parking spaces onConquestinfrontofthesite.Itshould be notedthatthe CityTrafficCode
restrictsparkingwithin30feetofaStopsign,andthesespotsshouldbeadjustedtomeetthiscodeResponse: The parking spaces have been adjusted to accommodate the 30’ requirement.
Department:LightAndPowerContact: TylerSiegmund,970-416-2772,tsiegmund@fcgov.comTopic:General
CommentNumber:1
02/17/2021:FORINFORMATION:
Light and Power has conduit stubbed at the northeast corner of theMulberry/Sykes intersection that can be extended to the site to provide power.Response: Acknowledged
CommentNumber:2
02/17/2021:FORINFORMATION:
Electric capacity fees, development fees, building site charges and any systemmodification charges necessary to feed the site will apply to this development.Please contact me to discuss
the preliminary estimate or visit the followingwebsite foranestimate ofchargesand feesrelatedto this project:
http://www.fcgov.com/utilities/business/buildersanddevelopers/plantinvestmentdevelopmentfeesResponse: Acknowledged
CommentNumber:3
04/20/2021:FORHEARING:
It was understood from previous discussions that you will need 3phase electricservicesforthemainbuildingandpool.Wedonotinstall3phasetransformers
in vaults. There will need to be a 3phase pad mount transformer installed to feed both buildings.Please show proposed transformer pad location on site and meet all utility spacing requirements.Response:
The transformer has been placed in the parking lot island at the entrance – this location was reviewed and approved prior to theplanning and zoning hearing.
02/17/2021:FORHEARING:
Transformer locations will need to be coordinated with Light & Power.Transformersmustbeplacedwithin10ftofadrivablesurfaceforinstallationand maintenance purposes. The transformer must
also have a front clearance of10 ft and side/rear clearance of 3 ft minimum. When located close to a building,pleaseprovide requiredseparationfrombuildingopeningsasdefinedinFiguresESS4ESS7
within the Electric Service Standards.Please show allproposed transformerlocations on theUtilityPlans.Response: See comment response above.
CommentNumber:4
02/17/2021:FORHEARING:
During utility infrastructure design, please provide adequate space of all serviceand main lines internal to the site to ensure proper utility installation and to meetminimum utility
spacing requirements. A minimum of 10 ft separation isrequiredbetweenwater,sewerandstormwaterfacilities,andaminimumof3ft
separationisrequiredbetweenNaturalGas.PleaseshowallelectricalroutingontheUtilityPlans.
Response: Acknowledged
CommentNumber:5
02/17/2021:FORFINALPLAN:
A commercial service information form (C 1 form) and a one line diagram for allcommercial meters will need to be completed and submitted to Light & PowerEngineeringforreview.AlinktotheC1formis
below:
http://www.fcgov.com/utilities/business/buildersanddevelopers/developmentformsguidelinesregulationsResponse: A C-1 form will be completed and submitted to the City after the FDP submittal.
CommentNumber:6
02/17/2021:FORFINALPLAN:
Ontheone-linediagram,pleaseshowthemaindisconnectsizeandmetersequencing.
A copy of our meter sequencing can be found in our electricpolicies practices and procedures below.http://www.fcgov.com/utilities/business/builders-and-developers/development-forms-guidelines-regulationsResponse:
A C-1 form will be completed and submitted to the City after the FDP submittal
CommentNumber:7
02/17/2021:FORFINALPLAN:
Please coordinate meter locations with Light and Power and show on the utilityplans during Final Design.These locations will need to comply with our electricmetering standards. Electric
meter locations will need to be coordinated withLight and Power Engineering.Reference Section 8 of our Electric ServiceStandards for electric metering standards.A link has been provided
below.https://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandards_FINAL_18November2016_Amendment.pdf
Response: Acknowledged
CommentNumber:8
02/17/2021:FORINFORMATION:
All light and Power infrastructure needed for the project will need to be withinpublicrightofway ordedicatedutility easements.Response: Acknowledged
CommentNumber:9
02/17/2021:FORINFORMATION:
The services to the buildings will be consider a commercial services; therefore,the service lines from the transformers to the meters are required to beinstalled,owned,andmaintainedbythepropertyowner.Response:
Acknowledged
Department:EnvironmentalPlanningContact: ScottBenton,(970)416-4290,sbenton@fcgov.comTopic:General
CommentNumber:2
04/19/2021:FORHEARING:
PleasereplacethelanguageofNote#9ofTreeProtectionNotesonpageTR101toreadasfollows:
NO TREES SHALL BE REMOVED DURING THE SONGBIRD NESTINGSEASON (FEBRUARY 1 TO JULY 31) WITHOUT FIRST HAVING APROFESSIONAL ECOLOGIST OR WILDLIFE BIOLOGIST COMPLETE ANESTING SURVEY TO IDENTIFY
ANY ACTIVE NESTS EXISTING ON THEPROJECT SITE. THE SURVEY SHALL BE SENT TO THE CITYENVIRONMENTAL PLANNER. IF ACTIVE NESTS ARE FOUND, THE CITYWILL COORDINATE WITH RELEVANT STATE AND FEDERALREPRESENTATIVES
TO DETERMINE WHETHER ADDITIONALRESTRICTIONSONTREEREMOVAL ANDCONSTRUCTIONAPPLY.Response: The note has been added to the Tree Protection Plan, sheet TR101.
Department:ForestryContact: MollyRoche,224-616-1992,mroche@fcgov.comTopic:General
CommentNumber:18
4/20/2021:FORFINALAPPROVAL–UPDATED:
Thank you for labeling the mitigation trees on the landscape plan, however the mitigation treesare not labeled in the plant list and the height is still shown at 6-ft. Please update
for next round.Response: The mitigation trees have been updated on the landscape plan accordingly.
\2/17/2021:FOR FINALAPPROVAL:
Pleaseshowmitigationevergreentreesat8-ftheightandlabelthemasmitigationtreesintheplantlist.Response: The evergreen trees have been updated on the landscape plan accordingly.
CommentNumber:19
4/20/2021:INFORMATIONONLY:
Forestryisreadyforhearing.Response: Acknowledged.
Department:TechnicalServicesContact: JeffCounty,970-221-6588,jcounty@fcgov.comTopic:General
CommentNumber:1
04/19/2021:INFORMATIONONLY:
UnlessrequiredduringPDP,acompletereviewofallplanswillbedoneatFDP.Response: Acknowledged.
Department:ErosionControlContact: BasilHamdan,970-222-1801,bhamdan@fcgov.comTopic:ErosionControl
CommentNumber:1
04/15/2021:FORFINALPLAN-UPDATED:
Please indicate the amount of disturbed area on the Erosion and Sediment Control Plan with a note.PleaseprovideanErosionand sediment Control Securityestimate.
Response: Disturbed area and estimate provided with final submittal in separate doc.
02/11/2021:INFORMATIONONLY:
Thank you submitting ESC plans at PDP level, these meet the City's criteria for Erosion Control plans.Please indicatethetotaldisturbedareaontheplanwithanote.Response: Acknowledged
FORFINALPLAN:
Please provide an erosion control security estimate, if it was already posted aspart of the overall Mosaic development, this would be for documentation only incase this project lags
behind the rest of the site or vice versa and a partialreimbursementis soughtbythedeveloper.
The City Manager’s development review fee schedule under City Code 7.5-2wasupdatedtoincludefeesforErosionControlandStormwaterInspections.
AsofJanuary1st,2021,thesefeeswillbecollectedonallprojectsforsuchinspections.
The Erosion Control fees are based on; the number of lots, the total sitedisturbance, the estimated number of years the project will be active and theStormwater Inspection Fees are based
on the number of LID/WQ Features thatare designed for on this project. Based on the proposed site constructionassociated with this project we are assuming 1 lots, 1 acres of disturbance,
1yearfromdemothroughbuildoutofconstructionandanadditional1year'tilfull
vegetative stabilization due to seeding. Which results in an Erosion Control Fee estimate of $ 900.46.BasedonnoStormwaterLID/WQfeatureson thissitethere isnoLID/WQInspection fee.
Ihaveprovidedacopyofthespreadsheetusedtoarriveattheseestimatesforyourreview.
Response: Erosion control estimate provided in separate doc.
.