HomeMy WebLinkAboutNORTHERN INTEGRATED SUPPLY PROJECT - SPA210001 - SUBMITTAL DOCUMENTS - ROUND 1 - EROSION CONTROL LETTER/REPORTTechnical Memorandum #3
Erosion Control/ Landscaping/ Tree
Mitigation
Site Plan Advisory Review Process
Prepared for:
City of Fort Collins
Prepared by:
Northern Integrated Supply Project
Water Activity Enterprise
May 14, 2021 Revision
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 1
Memorandum
Date: May 14, 2021
To: City of Fort Collins Planning Department
From: Bridget Mitchell, P.E. and Sydney Shell, P.L.A. - Pinyon Environmental
Subject: Northern Integrated Supply Project (NISP) – City of Fort Collins Site Plan Advisory
Review (SPAR) Erosion Control/Landscape and Wetlands Restoration Plan
This memorandum presents Erosion Control and Landscape and Wetlands Restoration methods proposed for
the Northern Integrated Supply Project (NISP or the Project) within the City of Fort Collins (“City”), in
accordance with Fort Collins Land Use Code requirements. This memorandum documents proposed erosion
control and landscaping within the portion of NISP inside the boundaries of the City of Fort Collins (“Project
Area”) in support of the NISP Site Plan Advisory Review application to the City. The NISP Water Activity
Enterprise (WAE) is the permittee and the entity that will retain a contractor to implement construction
activities. Northern Colorado Water Conservancy District (Northern Water), acting by and through the NISP
WAE, has contracted Pinyon Environmental, Inc. (Pinyon), to provide environmental compliance services during
the pre-construction phase of the Project.
The Project includes the Poudre River Intake Structure and approximately 18,000 linear feet of the Poudre
River Intake Pipeline within Fort Collins city limits. This proposed pipeline is an approximately 32- and 36-inch-
diameter waterline that will be installed approximately five feet underground. The typical trench section will
be about six feet wide. Soil stockpiles, vehicle traffic, and surface disturbance will be limited to a working area
of 100-ft width. Conventional excavation equipment, including diesel-powered hydraulic excavators and front-
end loaders, will be used to construct the new waterline and intake. Disturbance area at wetland and water
crossings will be limited to a working area of 60-ft width for crossings less than or equal to 500 feet in length
and 80-ft in width for crossings greater than 500 feet in length. Major road crossings will be bored. The pipeline
within the City will cross three irrigation ditches and three wetland areas. The intake structure will be
constructed along the bank of the Poudre River. Except for the intake structure, proposed surface impacts are
temporary. Disturbed areas will be restored to pre-construction conditions. More detail is provided below.
The Project is located on City property and private land. Restoration will follow this plan, but specific
techniques or the seed mix may be amended after coordination with the property owner.
Erosion Control
The Project will result in greater than one acre of land disturbance and therefore triggers a Colorado
Department of Public Health and Environment (CDPHE) construction stormwater discharge permit. Erosion
Control Plans (including report) will be developed in accordance with CDPHE permit requirements and City
Erosion Control Guidance (specifically the City’s Stormwater Criteria Manual Chapter 2, Section 6).
The Erosion Control Plan will identify potential Project pollutants and describe control measures to be
implemented to prevent pollutants from leaving the site and entering sensitive resources. Table 1 identifies
potential pollutants, their applicability to the Project, and potential control measures to mitigate impacts.
Control measures proposed will meet City standards per the City’s Stormwater Criteria Manual.
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 2
Table 1. Summary of Control Measures
Potential Pollutant
Potential
with this
Project?
Description of
Activities Measures to Control Source
Disturbed and stored
soils
Yes Brush Cutting, Clearing,
Grubbing, Excavation,
Grading
Vegetation buffers, sediment
control logs, construction
fencing, silt fence, rock sock,
inlet/outlet protection, surface
roughening, seeding and
mulching
Vehicle tracking of
sediments
Yes Vehicles entering and
exiting site
Vehicle tracking control (VTC)
Management of
contaminated soils
No None expected on-site None expected on-site
Loading and unloading
Operations
Yes Material Deliveries Good housekeeping
Outdoor storage
activities
Yes Material storage Good housekeeping, stabilized
staging areas
Vehicle and equipment
maintenance and refueling
Yes Fueling and maintenance
on equipment
Stabilized staging areas, good
housekeeping
Dust or particulate
generating processes
Yes Grading operations and
the presence of bare soil
A water truck may be used to
manage dust generation during
construction
Activities involving
fertilizers, pesticides,
detergents, etc.
Yes Soil amendments and/or
fertilizers may be used
during seeding operations
Good housekeeping
On site waste
management practices
Yes Portable toilets, sanitary
waste
Good housekeeping; siting and
securing portable toilets
Concrete
truck/equipment washing
Yes Delivering concrete Contractor will use portable,
contained washouts
Dedicated
asphalt/concrete batch
plants
No None expected on-site None expected on-site
Non-industrial waste
sources
Yes Construction waste Good housekeeping; trash
containers
Other areas where spills
could potentially occur
No None expected on-site None expected on-site
Control measures will be placed prior to land disturbance activity. Vehicle tracking controls, sediment control
logs, silt fence, construction fence, storm drain inlet protection, and rock socks will be installed and maintained
during construction. A brief description of their proposed use is provided below: Vehicle tracking controls
will be placed as a source control to prevent tracking of sediment from disturbed areas to adjacent paved areas.
Construction fence will be placed to protect sensitive resources and prevent public from entering
construction areas where appropriate.
Erosion control logs and/or silt fence will be placed downgradient of disturbed areas to contain
construction sediment.
Inlet/outlet protection will be placed over the top of culvert inlets and outlets within the project area.
Inlet protection will also be installed at inlet grates and throats to prevent sediment from entering the
stormwater drainage system.
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 3
Rock socks will be placed in paved areas immediately downgradient of disturbed areas as needed. Rock
socks may also be used for inlet protection.
Proposed stormwater control measure details are provided in Attachment 1 for reference.
The proposed pipeline will cross wetland and streams. Additional stormwater control measures will be
implemented in these areas to protect these resources. Refer to the preliminary details provided in
Attachment 2.
Permanent stabilization methods are discussed in the Landscape and Wetlands Restoration Plan section.
Landscape and Wetlands Restoration Plan
This section describes landscape and wetlands restoration methods proposed for use on City of Fort Collins
Natural Areas properties and non-natural areas/other properties. This Landscape and Wetlands Restoration
Plan has been developed in accordance with the City’s Land Use Code Section 3.2.1 requirements and includes
methods of reclamation and proposed reseeding for temporarily impacted areas (including wetlands). Existing
tree inventory, removal, protection, and mitigation is detailed in Attachment 3.
Natural Areas
During site excavation the Contractor will strip and stockpile topsoil based on the following:
Native vegetation areas will be excavated to a depth of 8 inches and stockpiled separately.
Non-native vegetation areas will be stripped, and the top 2 inches will be removed to remove non-native
seed source. Then an additional 8 inches will be excavated and stockpiled separately.
As soon as practicable following installation of the pipeline, the trench will be backfilled with native material.
Back-filled trenches will be compacted to 95% Standard Proctor Density. Areas within the limits of disturbance
that have been driven over, compacted, or rutted by equipment must be scarified to a depth of 8 inches (not
exceeding 10 inches between intervals), and regraded to original grade and contours prior to seeding.
After compaction to final subgrade (8 inches below finished grade), the top 6 inches of subsoil must be ripped
(no more than 20 inches between intervals), and the previously stripped and stockpiled topsoil materials spread
evenly over the excavated areas in the corresponding zones immediately following the completion of
construction. Soils in backfilled, compacted, and topsoiled trenches must match the grade of the surrounding
undisturbed areas.
All topsoil, either imported or salvaged in the Project area, will be treated with a herbicide for noxious weeds
prior to final seeding (herbicide application will be timed so that it does not impact seed germination).
The Contractor will seed all disturbed and topsoiled areas with native seed mixes (see below). Seed will be
mixed by a wholesale seed supplier in the proportions determined by the Project team and approved by the
City in order to obtain the approved application rate. Seed will conform to current State and Federal
regulations and will be subject to the testing provisions of the Association of Official Seed Analysis. Seed and
seed mixes will be furnished in bags or containers clearly labeled to show the name and address of the supplier,
the common, scientific, and variety name(s) of the seed(s), the lot number, point of origin, net weight, percent
of weed content, and the guaranteed percentage of purity and germination. These labels will be submitted to
the Project team for approval prior to seeding.
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 4
The following seed mixes are proposed for use in wetland, riparian, and upland areas. The Project will
coordinate with the City’s Land Conservation Manager to review, approve, and potentially amend seed mixes
for use on individual natural area properties within the Project area. Additional seed mixes and landscaping
may be required to match existing landscape conditions.
Table 2. Seed Mixes for Temporary Impact Areas Grasses Latin Name Common Name Mix % - PSS Mix % - RI Mix % - UM
Pascopyrum smithii Western Wheatgrass 10 15 15
Elymus trachycaulus trachycalus Slender Wheatgrass 15 10 5
Panicum virgatum Switchgrass 10 10 10
Poa palustris Fowl Bluegrass 5
Spartina pectinata Prairie Cordgrass 15 10
Elymus canadensis Canada Wildrye 10 10 10
Nassella viridula Green Needlegrass 10 10 5
Sporobolus crytandrus Sand Dropseed 5 5
Schizachyrium scoparium Little Bluestem 5 10 10
Bouteloua gracilis Sideoats Grama 10
Bouteloua curtipendula Blue Grama 10
Sporobolus airoides Alkali Sacaton 10
Shrubs Latin Name Common Name
Rhus trilobata Threeleaf Sumac 5 5
Chrysothamnus nauseosis Rubber Rabbitbrush 5
Rosa woodsii Wood's Rose 5 5
Amelanchier alnifolia Saskatoon Serviceberry 5 5
Cornus sericea ssp. Sericea Red Osier Dogwood 5
Prunus Americana American Plum 5 5
Total Percent = 100 100 100
Legend
PSS - Wetland Scrub-Shrub
RI - Riparian
UM - Upland Meadow
Note: Actual mixture of plant species, size, and density will be determined by the property owner based
on availability at the time of planting and discretion of restoration ecologist.
The Contractor will drill-seed into the soil to an approximate depth of ¼ to ½ inch, using a range drill (not a
Brillion). Immediately following seeding the Contractor will roll the seeded areas with a sheep’s foot roller to
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 5
lightly compact and imprint the soil to remove air voids, provide better seed-soil contact, and create
indentations in the soil that will capture moisture.
All seeded areas will be hydromulched in accordance with the City’s Storm Drainage Design Criteria and
Construction Standards. The Contractor will obtain and submit to the Project manager certifications from
suppliers of hydraulic mulch that laboratory and field testing of their product has been accomplished, and that
it meets requirements pertaining to wood cellulose fiber mulch.
Vegetation cover will be inspected in accordance with the Project construction stormwater discharge permit
until final stabilization is achieved. According to the discharge permit, “Final stabilization is reached when all
ground surface disturbing activities at the construction site are complete; and, for all areas of ground surface
disturbing activities, either a uniform vegetative cover with an individual plant density of at least 70 percent of
pre-disturbance levels is established, or equivalent permanent alternative stabilization methods are
implemented” (CDPHE CDPS, 2019).
Non-Natural Areas and Private Properties
During site excavation the Contractor will strip and stockpile topsoil separately from any subsoil. As soon as
practicable following installation of the pipeline, the trench will be backfilled. After compaction to final subgrade
the top 6 inches of subsoil will be ripped and the previously stripped and stockpiled topsoil materials spread
evenly over the excavated area. Areas within the limits of disturbance that have been impacted will be restored
to original grade and contours, and disturbed areas will be revegetated using the seed mixes in Table 2 (or as
otherwise directed by the property owner). The Project will coordinate with the City or private property
owners to review and approve the proposed plant material on individual properties within the Project area. At
minimum, the proposed design shall replace landscape conditions in-kind.
Stormwater Engineering
Vegetation cover will be inspected in accordance with the Project construction stormwater discharge permit
until final stabilization is achieved. According to the discharge permit, “Final stabilization is reached when all
ground surface disturbing activities at the construction site are complete; and, for all areas of ground surface
disturbing activities, either a uniform vegetative cover with an individual plant density of at least 70 percent of
pre-disturbance levels is established, or equivalent permanent alternative stabilization methods are
implemented” (CDPHE CDPS, 2019).
The Project will not increase impervious area greater than 1,000 square feet, therefore no permanent
stormwater features are proposed.
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan Page 6
References
Colorado Department of Public Health and Environment (CDPHE) Water Quality Control Division, “CDPS
General Permit Stormwater Discharges Associated with Construction Activity Authorization to
Discharge Under the Colorado Discharge Permit System (CDPS), CDPHE. Effective on April 1, 2019.
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan
Attachment 1 – Stormwater Control Measure Details (City of Fort Collins Stormwater Criteria
Manual Appendix E)
Silt Fence (SF) SC-1
November 2010 Urban Drainage and Flood Control District SF-3
Urban Storm Drainage Criteria Manual Volume 3
Sediment Control Log (SCL) SC-2
November 2010 Urban Drainage and Flood Control District SCL-3
Urban Storm Drainage Criteria Manual Volume 3
SC-2 Sediment Control Log (SCL)
SCL-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
SC-5 Rock Sock (RS)
RS-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
SC-6 Inlet Protection (IP)
IP-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Inlet Protection (IP) SC-6
November 2010 Urban Drainage and Flood Control District IP-5
Urban Storm Drainage Criteria Manual Volume 3
SC-6 Inlet Protection (IP)
IP-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
SM-3 Construction Fence (CF)
CF-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-3
Urban Storm Drainage Criteria Manual Volume 3
SM-4 Vehicle Tracking Control (VTC)
VTC-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-5
Urban Storm Drainage Criteria Manual Volume 3
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan
Attachment 2 – Preliminary Wetland and Stream Crossing Details
Technical Memorandum
NISP SPAR Erosion Control/Landscape and Wetlands Restoration Plan
Attachment 3 – Tree Inventory and Mitigation Memorandum
Technical Memorandum
NISP SPAR Tree Inventory and Mitigation Plan Page 1
Memorandum
Date: April 30, 2021
To: City of Fort Collins Planning Department
From: Allison Haraminac, Pinyon Environmental, Inc.
Subject: Northern Integrated Supply Project (NISP) – City of Fort Collins Site Plan Advisory
Review (SPAR) Tree Inventory and Mitigation Memorandum
Introduction
This memorandum presents the tree inventory and mitigation measures for the Northern Integrated Supply
Project (NISP or the Project) within the city limits of the City of Fort Collins (City), in accordance with Fort
Collins Land Use Code requirements and in support of the NISP Site Plan Advisory Review application to the
City. The NISP Water Activity Enterprise (WAE) is the permittee and the entity that will retain a contractor
to implement construction activities. Northern Colorado Water Conservancy District (Northern Water),
acting by and through the NISP WAE, has contracted Pinyon Environmental, Inc. (Pinyon), to provide
environmental compliance services during the pre-construction phase of the Project. Pinyon, in conjunction
with Precision Surveying, Inc., has conducted a tree inventory for the project. This Tree Inventory and
Mitigation Memorandum documents the results of the tree inventory and mitigation requirements outlined by
the City Forestry Division.
Methods
On March 18, 19, 23, and 24, Pinyon biologist Tim Merlino visited the site with Precision Surveying, Inc. to
inventory trees within the Project area. The surveyor mapped tree locations using a sub-meter accurate Global
Positioning System (GPS) unit and recorded the diameter at breast height (DBH) and species for each tree,
with input from Mr. Merlino. On April 9, 2021, Mr. Merlino visited the site again with representatives from the
City Forestry Division and Northern Water to view trees outside of City Natural Areas proposed to be
impacted by the project. The City Forestry Division assessed the condition of each tree and determined
mitigation requirements for trees outside of Natural Areas during this site visit.
Results
A total of 1,427 trees were inventoried within and near the project area. Of these, 77 trees are proposed for
removal (Table 1; Attachment 1). Tree removals would be necessary where trees are present within the
proposed excavation zone and are incompatible with project infrastructure. The project’s engineering team
has conservatively estimated the trees that would be removed based on potential working space for equipment
and excavation requirements. Northern Water is proposing mitigation for anticipated impacts by planting trees
and shrubs, with input from the City Forestry Division for tree replacements on properties outside of Natural
Areas (Table 1; Attachment 1).
Technical Memorandum
NISP SPAR Tree Inventory and Mitigation Plan Page 2
Table 1. Impacted Trees and Proposed Mitigation
Label1 Species Common Name Species Scientific Name Diameter Mitigation
70275 Common Hackberry Celtis occidentalis 8 1.5 trees
70576 Siberian Elm Ulmus pumila 12 3 trees
70577 Siberian Elm Ulmus pumila 6 3 trees
70578 Siberian Elm Ulmus pumila 24 3 trees
70579 Siberian Elm Ulmus pumila 4 0 trees2
70580 Siberian Elm Ulmus pumila 12 3 trees
70581 Siberian Elm Ulmus pumila 35 3 trees
70582 Plains Cottonwood Populus deltoides 12 3 trees
70676 Plains Cottonwood Populus deltoides 26 3 trees
70677 Siberian Elm Ulmus pumila 24 3 trees
70678 Plains Cottonwood Populus deltoides 12 3 trees
70716 Narrowleaf Cottonwood Populus angustifolia 10 3 trees
70759 American Elm Ulmus americana 12 3 trees
70706 Willow Salix amygdaloides or Salix fragilis 84
10 trees for
this cluster
70711 Willow Salix amygdaloides or Salix fragilis 40
70712 Willow Salix amygdaloides or Salix fragilis 48
70713 Willow Salix amygdaloides or Salix fragilis 52
70714 Willow Salix amygdaloides or Salix fragilis 24
70760 American Elm Ulmus americana 3
70761 American Elm Ulmus americana 6
70762 Plains Cottonwood Populus deltoides 48
70763 American Elm Ulmus americana 4
70764 American Elm Ulmus americana 4
70765 American Elm Ulmus americana 4
70766 American Elm Ulmus americana 24
70783 American Elm Ulmus americana 3
70784 American Elm Ulmus americana 3
70785 Green Ash Fraxinus pennsylvanica 4
70786 Green Ash Fraxinus pennsylvanica 4
70787 American Elm Ulmus americana 3
70788 Plains Cottonwood Populus deltoides 5
70789 Green Ash Fraxinus pennsylvanica 5
70851 Willow Salix amygdaloides or Salix fragilis 40
10 trees for
this cluster
70852 Willow Salix amygdaloides or Salix fragilis 72
70918 American Elm Ulmus americana 4
Technical Memorandum
NISP SPAR Tree Inventory and Mitigation Plan Page 3
Label1 Species Common Name Species Scientific Name Diameter Mitigation
70919 American Elm Ulmus americana 4
70920 Willow Salix amygdaloides or Salix fragilis 12
70921 Plains Cottonwood Populus deltoides 38
70922 Plains Cottonwood Populus deltoides 28
70923 Plains Cottonwood Populus deltoides 32
70936 Willow Salix amygdaloides or Salix fragilis 24
70937 Willow Salix amygdaloides or Salix fragilis 24
70938 Willow Salix amygdaloides or Salix fragilis 34
70944 Plains Cottonwood Populus deltoides 6
70949 Plains Cottonwood Populus deltoides 8
71149 Plains Cottonwood Populus deltoides 6
6 trees for
this cluster
71150 Plains Cottonwood Populus deltoides 6
71151 Plains Cottonwood Populus deltoides 4
71167 American Elm Ulmus americana 10 3 trees
71181 Willow Salix amygdaloides or Salix fragilis 20
2.5 trees for
this cluster
71182 Russian Olive Elaeagnus angustifolia 10
71183 Russian Olive Elaeagnus angustifolia 10
71291 Plains Cottonwood Populus deltoides 4
3 trees for
this cluster
71292 Plains Cottonwood Populus deltoides 4
71296 Plains Cottonwood Populus deltoides 6
71297 Plains Cottonwood Populus deltoides 4
71298 Plains Cottonwood Populus deltoides 4
71303 Russian Olive Elaeagnus angustifolia 10 1.5 trees
71311 Willow Salix amygdaloides or Salix fragilis 12 2 large shrubs
71312 American Elm Ulmus americana 12 1.5 trees
74086 Unknown Unknown 5 0 trees2
74128 Chokecherry Prunus virginiana 6 3 trees
74129 Chokecherry Prunus virginiana 10 3 trees
74130 Plains Cottonwood Populus deltoides 20 3 trees
74131 Plains Cottonwood Populus deltoides 20 3 trees
74151 Siberian Elm Ulmus pumila 24 3 trees
74155 Siberian Elm Ulmus pumila 24 3 trees
74156 Siberian Elm Ulmus pumila 38 3 trees
70221 Green Ash Fraxinus pennsylvanica 8 3 trees
70220 Chokecherry Prunus virginiana 8 3 trees
70943 Willow Salix amygdaloides or Salix fragilis 86 3 trees
Technical Memorandum
NISP SPAR Tree Inventory and Mitigation Plan Page 4
Label1 Species Common Name Species Scientific Name Diameter Mitigation
74095 Russian Olive Elaeagnus angustifolia 10 3 trees
74096 Siberian Elm Ulmus pumila 30 3 trees
74097 Russian Olive Elaeagnus angustifolia 10 3 trees
74098 Russian Olive Elaeagnus angustifolia 10 3 trees
74099 Russian Olive Elaeagnus angustifolia 12 3 trees
74100 Russian Olive Elaeagnus angustifolia 10 3 trees
Total Proposed Mitigation
120 trees, 2
large shrubs
1See Attachment 1, Landscape Plan
2Mitigation is not recommended or required for these trees due to their small size.
Plantings will follow City of Fort Collins guidance and Land Use Code requirements. Replacement trees will
have the following calipers:
Canopy Shade Trees: 2.0” caliper balled and burlapped
Ornamental Trees: 2.0” caliper balled and burlapped
Evergreen Trees: 8’ height balled and burlapped
Please see the Landscape Plan (Attachment 1) for planting notes and details. Trees not slated for removal
will be protected with temporary construction fencing to avoid impacts.
Conclusions and Recommendations
One hundred and twenty trees and two large shrubs will be planted to offset the tree removals proposed for
the project (Attachment 1). Trees will be planted as close as possible to the proposed temporary easement
area (and outside of the permanent easement area) for the pipeline. Final placements will be determined in
coordination with the City Forestry Division and property owner.
Attachments:
Attachment 1 – Landscape Plan