HomeMy WebLinkAboutH-25 MULTI-FAMILY - FDP210008 - DOCUMENT MARKUPS - ROUND 2 - UTILITY PLANS100-YR
FLOODPLAIN
100-YR
FLOODWAY
HARMONY ROAD
STRAUSS CABIN ROAD20' EXISTING WATERLINE EASEMENT
20.00' EXISTING EASEMENT
(PURPOSE UNKNOWN)
EXISTING
UNPAVED ACCESS
EXISTING
ROW
EXISTING
ROW
EXISTING DIRT ROAD
SHALL BE USED FOR
CONSTRUCTION TRAFFIC
LIMITS OF
CONSTRUCTION
LIMITS OF
CONSTRUCTION
APPROXIMATE AREA FOR
STOCKPILED MATERIAL
BLDG
1
BLDG
2 BLDG
3
BLDG
6
BLDG
12
BLDG
10
BLDG
7
BLDG
9
BLDG
4
BLDG
11
BLDG
5
BLDG
8
CAR CARE
CENTER
0 50
SCALE: 1" = 50'
1002550
NORTH
NOTE:
-EXISTING UNDERGROUND INSTALLATIONS & PRIVATE UTILITIES SHOWN ARE INDICATED ACCORDING TO THE BEST INFORMATION AVAILABLE TO THE ENGINEER. THE
ENGINEER DOES NOT GUARANTEE THE ACCURACY OF SUCH INFORMATION. SERVICE LINES (WATER, POWER, GAS, STORM, SEWER, TELEPHONE & TELEVISION) MAY NOT BE
STRAIGHT LINES OR AS INDICATED ON THE PLANS. STATE LAW REQUIRES CONTRACTOR TO CALL ALL UTILITY COMPANIES BEFORE EXCAVATION FOR EXACT LOCATIONS.
-UNLESS OTHERWISE SPECIFIED, ALL CONSTRUCTION LAYOUT AND STAKING SHALL BE PERFORMED UNDER THE RESPONSIBLE CHARGE OF A LAND SURVEYOR LICENSED IN
THE STATE WHERE THE PROJECT IS LOCATED AND BY A PARTY CHIEF OR ENGINEERING TECHNICIAN EXPERIENCED IN CONSTRUCTION LAYOUT AND STAKING TECHNIQUES AS
ARE REQUIRED BY THE SPECIFIC TYPE OF WORK BEING PERFORMED.FILE:PROJECT NO:CAD:QUALITY ASSURANCE:DRAWING HISTORYDATE DESCRIPTIONHARMONY & STRAUSS CABIN ROADEROSION CONTROL PLANH-25 MULTI FAMILY DEVELOPMENT FORT COLLINS, COC7.0 CJS19059.02_EROSION_PROD.DWGRS/EB/VJG2/19/20 1ST PDP SUBMITTAL7/01/209/30/2010/26/204/07/21--2ND PDP SUBMITTAL3RD PDP SUBMITTAL4TH PDP SUBMITTAL1ST FDP SUBMITTAL----19059.02CONTOUR NOTE:
·PROPOSED CONTOURS ARE SHOWN AT 1' MAJOR AND 0.5' MINOR
·EXISTING CONTOURS ARE SHOWN AT 5' MAJOR AND 1' MINOR
AREA OF FILL REMOVAL AND GRADING = 637,109 SF (14.63 ACRES)
EARTHWORK QUANTITIES
CUT 7,910 CY
FILL 27,840 CY
FLOODPLAIN USE PERMIT NO. 11411
CONSTRUCTION SEQUENCE:
1. OBTAIN ALL REQUIRED PERMITS FOR PROPOSED WORK.
2. INSTALL ROCK SOCKS AND INLET PROTECTION.
3. INSTALL VEHICLE TRACKING CONTROL.
4. INSTALL STABILIZED STAGING AREA.
5. INSTALL ALL PERIMETER BMPs.
6. PERFORM STRIPPING, GRUBBING AND STABILIZE STOCKPILED MATERIALS.
7. PERFORM EARTHWORK.
10. STABILIZE STOCKPILED MATERIALS AND GRADED/DISTURBED AREAS, AS REQUIRED.
9. INSTALL UTILITIES, PAVEMENTS AND REMAINING IMPROVEMENTS.
10. SEED AND MULCH NEWLY GRADED AND DISTURBED AREAS.
11. REMOVE ALL TEMPORARY BMPs ACCEPT FOR PERIMETER CONTROLS.
12. REMOVE PERIMETER CONTROLS UPON ESTABLISHED 70% VEGETATED GROUND COVER.
PROJECT CONTROL/DATUM:
VERTICAL DATUM:
NORTH AMERICAN VERTICAL DATUM 1988 (NAVD88).
VERTICAL CONTROL BASED UPON TRIMBLE VRS NETWORK SOLUTION.
HORIZONTAL DATUM:
COLORADO STATE PLANE COORDINATES NAD 83(2011) DATUM.
HORIZONTAL CONTROL BASED UPON TRIMBLE VRS NETWORK SOLUTION.
DATUM NOTE:
1. THIS DRAWING IS AT MODIFIED STATE PLANE. TO REDUCE TO STATE
PLANE COORDINATES, SCALE AT 0.99973537 (1.00026470) ABOUT THE
ORIGIN 0,0.
EROSION CONTROL LEGEND
STOCKPILE MANAGEMENT
STABILIZED STAGING AREA
PERMANENT SEEDING
SILT FENCE
STREET SWEEPING
SURFACE ROUGHNING
EROSION CONTROL PLANGENERAL NOTES
1. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL REQUIRED PERMITS PRIOR TO COMMENCEMENT OF ANY
WORK ON THE PROJECT.
2. THE CONTRACTOR SHALL BE SOLELY AND COMPLETELY RESPONSIBLE FOR THE CONDITIONS AT AND ADJACENT TO
THE JOB SITE, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY, DURING THE PERFORMANCE OF THE WORK. THIS
REQUIREMENT SHALL APPLY CONTINUOUSLY AND SHALL NOT BE LIMITED TO NORMAL WORKING HOURS. THE DUTY
OF THE CITY TO CONDUCT CONSTRUCTION REVIEW OF THE CONTRACTOR'S PERFORMANCE IS NOT INTENDED TO
INCLUDE REVIEW OF THE ADEQUACY OF THE CONTRACTOR'S SAFETY MEASURES IN, ON, OR NEAR THE
CONSTRUCTION SITE.
3. THE CONTRACTOR SHALL PROVIDE ALL LIGHTS, SIGNS, BARRICADES, FLAG PERSONS, OR OTHER DEVICES NECESSARY
TO PROVIDE FOR PUBLIC SAFETY IN ACCORDANCE WITH THE CURRENT MANUAL ON UNIFORM TRAFFIC CONTROL
DEVICES.
4. THE CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF ALL SURVEY MONUMENTS. ANY MONUMENT THAT MUST
BE DESTROYED FOR CONSTRUCTION SHALL BE REPLACED. THE CONTRACTOR SHALL ENGAGE THE SERVICES OF A
LICENSED SURVEYOR PRIOR TO DISTURBING ANY MONUMENTS.
5. IT IS THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE OWNER AND THE ENGINEER OF ANY PROBLEMS IN IT IS
THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE OWNER AND THE ENGINEER OF ANY PROBLEMS IN
CONFORMING TO THESE PLANS FOR ANY ELEMENT OF THE PROPOSED IMPROVEMENTS PRIOR TO ITS CONSTRUCTION.
6. CONTRACTOR SHALL COORDINATE THE IMPROVEMENTS WITH AND PROVIDE NOTIFICATION OF CONSTRUCTION
SCHEDULING TO THE OWNER OF ANY BUSINESS WHERE PROPOSED IMPROVEMENTS MAY AFFECT THE DAILY
OPERATIONS OF THAT OWNER'S BUSINESS.
7. CONTRACTOR SHALL OBTAIN OWNER APPROVAL FOR ANY IMPROVEMENTS NOT CONTAINED WITHIN THESE PLANS.
8. IT IS THE RESPONSIBILITY OF THE CONTRACTOR DURING CONSTRUCTION ACTIVITIES TO RESOLVE CONSTRUCTION
PROBLEMS DUE TO CHANGED CONDITIONS ENCOUNTERED DURING THE PROGRESS OF ANY PORTION OF THE
PROJECT.
9. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROTECTION OF ALL EXISTING OVERHEAD AND UNDERGROUND
UTILITIES. IF A UTILITY IS DAMAGED DURING CONSTRUCTION, THEN IT SHALL BE REPAIRED BY THE CONTRACTOR AT
NO EXPENSE TO THE OWNER. CONTRACTOR SHALL COORDINATE WITH UTILITY OWNER/PROVIDER REGARDING ANY
RE- ROUTING, REMOVAL, AND/OR MODIFICATION TO ANY EXISTING UTILITY LINE AND/OR APPURTENANCE.
CONTRACTOR TO COORDINATE WITH A LICENSED ELECTRICIAN, AS REQUIRED, REGARDING ON - SITE ELECTRICAL
ABANDONMENT,RE- ROUTING AND/OR PRESERVATION.
10. ALL EXISTING UTILITIES SHOWN IN THESE PLANS ARE APPROXIMATE AND SOME UTILITIES MAY NOT BE SHOWN AT
ALL. SITE CONTRACTOR SHALL VERIFY THE HORIZONTAL AND VERTICAL LOCATION OF ALL EXISTING UTILITIES
SHOWN OR NOT SHOWN IN THESE PLANS PRIOR TO CONSTRUCTION.
CALL UTILITY NOTIFICATION
CENTER OF COLORADO
811
ROCK SOCK
CONCRETE WASHOUT AREA
HARMONY 25, PARCEL 86030000281/29/20ISSUED FOR CONSTRUCTIONOVERLAND FLOW ARROW
EROSION CONTROL CALCULATION TABLE
AREA DESCRIPTION AREA (ac)
TOTAL PROJECT AREA ±16.0 ACRES
TOTAL AREA OF DISTURBANCE ±16.0 ACRES
TOTAL AREA OF STAGING/STORAGE ±0.4 ACRES
TOTAL AREAS FOR HAULING N/A
TOTAL VOLUME OF MATERIAL TO BE RELOCATED 7,910 CY
VEHICLE TRACKING CONTROL INLET PROTECTION
STAKED SEDIMENT CONTROL LOG
LIMITS OF CONSTRUCTION
CITY OF FORT COLLINS, COLORADO
UTILITY PLAN APPROVAL
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CITY ENGINEER DATE
STORMWATER UTILITY DATE
PARKS & RECREATION DATE
TRAFFIC ENGINEER DATE
ENVIRONMENTAL PLANNER DATE
P:\19059_02_H25_Multi_Family_Dev_Ph_I\CADD_C3D\PRODUCTION_DWG\19059.02_EROSION_PROD.dwg, C7.0 EROSION CONTROL PLAN, 4/6/2021 7:55:50 PM, VGentry, 1:1Inlet protection and rock socks have
been added along Harmony Rd and
proposed chases
The requested note regarding debris
in streets has been added
The EC security
estimate is provided at
end of this report
FINAL DEVELOPMENT PLANFILE:PROJECT NO:CAD:QUALITY ASSURANCE:DRAWING HISTORYDATE DESCRIPTIONHARMONY & STRAUSS CABIN ROADEROSION CONTROL NOTESH-25 MULTI FAMILY DEVELOPMENT FORT COLLINS, COC7.1 CJS19059.02_DETAIL_PROD.DWGRS/EB/VJG2/19/20 1ST PDP SUBMITTAL7/01/209/30/2010/26/204/07/21--2ND PDP SUBMITTAL3RD PDP SUBMITTAL4TH PDP SUBMITTAL1ST FDP SUBMITTAL----19059.02“”
“”
CITY OF FORT COLLINS, COLORADO
UTILITY PLAN APPROVAL
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CITY ENGINEER DATE
STORMWATER UTILITY DATE
PARKS & RECREATION DATE
TRAFFIC ENGINEER DATE
ENVIRONMENTAL PLANNER DATE
P:\19059_02_H25_Multi_Family_Dev_Ph_I\CADD_C3D\PRODUCTION_DWG\19059.02_DETAIL_PROD.dwg, C7.1 EROSION CONTROL NOTES, 4/6/2021 7:57:03 PM, VGentry, 1:1
FINAL DEVELOPMENT PLANFILE:PROJECT NO:CAD:QUALITY ASSURANCE:DRAWING HISTORYDATE DESCRIPTIONHARMONY & STRAUSS CABIN ROADEROSION CONTROL DETAILSH-25 MULTI FAMILY DEVELOPMENT FORT COLLINS, COC7.2 CJS19059.02_DETAIL_PROD.DWGRS/EB/VJG2/19/20 1ST PDP SUBMITTAL7/01/209/30/2010/26/204/07/21--2ND PDP SUBMITTAL3RD PDP SUBMITTAL4TH PDP SUBMITTAL1ST FDP SUBMITTAL----19059.02CITY OF FORT COLLINS, COLORADO
UTILITY PLAN APPROVAL
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CITY ENGINEER DATE
STORMWATER UTILITY DATE
PARKS & RECREATION DATE
TRAFFIC ENGINEER DATE
ENVIRONMENTAL PLANNER DATE
P:\19059_02_H25_Multi_Family_Dev_Ph_I\CADD_C3D\PRODUCTION_DWG\19059.02_DETAIL_PROD.dwg, C7.2 EROSION CONTROL DETAILS, 4/6/2021 7:57:07 PM, VGentry, 1:1
FINAL DEVELOPMENT PLANFILE:PROJECT NO:CAD:QUALITY ASSURANCE:DRAWING HISTORYDATE DESCRIPTIONHARMONY & STRAUSS CABIN ROADEROSION CONTROL DETAILSH-25 MULTI FAMILY DEVELOPMENT FORT COLLINS, COC7.3 CJS19059.02_DETAIL_PROD.DWGRS/EB/VJG2/19/20 1ST PDP SUBMITTAL7/01/209/30/2010/26/204/07/21--2ND PDP SUBMITTAL3RD PDP SUBMITTAL4TH PDP SUBMITTAL1ST FDP SUBMITTAL----19059.02CITY OF FORT COLLINS, COLORADO
UTILITY PLAN APPROVAL
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CITY ENGINEER DATE
STORMWATER UTILITY DATE
PARKS & RECREATION DATE
TRAFFIC ENGINEER DATE
ENVIRONMENTAL PLANNER DATE
P:\19059_02_H25_Multi_Family_Dev_Ph_I\CADD_C3D\PRODUCTION_DWG\19059.02_DETAIL_PROD.dwg, C7.3 EROSION CONTROL DETAILS, 4/6/2021 7:57:17 PM, VGentry, 1:1
FINAL DEVELOPMENT PLANFILE:PROJECT NO:CAD:QUALITY ASSURANCE:DRAWING HISTORYDATE DESCRIPTIONHARMONY & STRAUSS CABIN ROADEROSION CONTROL DETAILSH-25 MULTI FAMILY DEVELOPMENT FORT COLLINS, COC7.4 CJS19059.02_DETAIL_PROD.DWGRS/EB/VJG2/19/20 1ST PDP SUBMITTAL7/01/209/30/2010/26/204/07/21--2ND PDP SUBMITTAL3RD PDP SUBMITTAL4TH PDP SUBMITTAL1ST FDP SUBMITTAL----19059.02CITY OF FORT COLLINS, COLORADO
UTILITY PLAN APPROVAL
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CITY ENGINEER DATE
STORMWATER UTILITY DATE
PARKS & RECREATION DATE
TRAFFIC ENGINEER DATE
ENVIRONMENTAL PLANNER DATE
P:\19059_02_H25_Multi_Family_Dev_Ph_I\CADD_C3D\PRODUCTION_DWG\19059.02_DETAIL_PROD.dwg, C7.4 EROSION CONTROL DETAILS, 4/6/2021 7:57:22 PM, VGentry, 1:1