April 09, 2021
Cassie Younger
Maverik
185 State Street
Salt Lake City, UT 8411
RE: Maverik, FDP210003, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Maverik. If you have questions about any comments, you may
contact the individual commenter or direct your questions through your Development
Review Coordinator, Brandy Bethurem Harras via phone at 970-416-2744 or via email at
bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras, 970-416-2744, bbethuremharras@fcgov.com
Topic: General
Comment Number: 1
04/06/2021: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone conversations. Thank you!
Comment Number: 2
04/06/2021: INFORMATION:
As part of your resubmittal you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color. When replying to the comment letter please be detailed in
your responses, as all comments should be thoroughly addressed. Provide
reference to specific project plans or explanations of why comments have not
been addressed, when applicable. DCI Response: Noted see attached comment/response letter.
2
Comment Number: 3
04/06/2021: INFORMATION:
When you are ready to resubmit your plans, please notify with as much
advanced notice as possible, thank you. DCI Response: Noted
Comment Number: 4
04/06/2021: FOR FINAL APPROVAL:
All "For Final Approval / For Approval" comments need to be addressed and
resolved prior to moving forward with the final documents and recording of this project.
I will provide a recording checklist and process information when we are closer to this step.
DCI Response: Noted
Comment Number: 5
04/06/2021: INFORMATION:
Temporary Service Changes - City of Fort Collins Development Review
In order to continue providing thorough reviews and giving every project the
attention it deserves, the City of Fort Collins is implementing temporary
changes in how we serve our development customers. As you may be aware,
we are experiencing staff shortages in a number of key departments, which has
begun to impact the quality and timeliness of our reviews. We recognize that
development and construction play a critical role in our community’s vibrancy
and economic recovery, and we have been exploring options for mitigating
impacts to our customers. As a result, we will be making some temporary service changes.
Beginning Monday May 10th one additional week of review time will be added
to all 1st and 2nd round submittals (increase from 3 weeks to 4 weeks). DCI Response: Noted
Department: Planning Services
Contact: Will Lindsey, , wlindsey@fcgov.com
Topic: General
Comment Number: 1
04/02/2021: FOR FINAL APPROVAL:
Please see redline comments about missing information on Site Plan submittal
documentation, and inconsistencies between the Utility Plan set Site Plan and
the FDP Site Plan. DCI Response: see redlines for additional responses
Comment Number: 2
04/02/2021: FOR FINAL APPROVAL:
Please see redline comments on Landscape Plan related to Coniferous Tree
numbers, and landscaping area east of the building.
RMS Response: Due to the utility easement along the outside of the property planting bigger
evergreen trees where indicated would result in the trees overgrowing into the drive aisle. Larger
limber pines have been shown on the north-east where there is more room for them. Five of the
trees on the east have been updated to be evergreen to address board concerns. Due to previous
comments from Forestry about spacing out proposed trees from existing trees we cannot add any
additional trees. We have changed out of of the ornamental tree for another pinyon pine tree. A toal
of 6 evergreen trees are now in the buffer areas.
Comment Number: 3
3
04/02/2021: INFORMATION ONLY:
Per our correspondence in January 2020 the proposed reductions of the
building footprint and alterations to the building architecture will not constitute a
formal Amendment process, and are instead being incorporated into the FDP.
Staff has reviewed the changes to the building architecture and finds that it still
meets the LUC standards. DCI Response: Noted
Department: Engineering Development Review
Contact: Spencer Smith, 970-221-6603, smsmith@fcgov.com
Topic: General
Comment Number: 1
04/06/2021: FOR FINAL APPROVAL:
This comment is just a reminder that there is a repayment due to the City of Fort
Collins for previously constructed I-25/Hwy 392 interchange improvements. I
believe I provided an estimated cost of the repay in a previous comment or
email. Please contact me if you would like to have the exact amount provided.
DCI Response: see redlines for additional responses
Comment Number: 2
04/06/2021: DEVELOPMENT AGREEMENT:
A development agreement (DA) will be required for this project. Please
complete and submit a development agreement information form (included in
the comments/redlines for this submittal). I will need this in order to prepare the
draft agreement. I will try and get a draft DA ready for review by our City
Attorney by the time we issue comments on your next submittal. Once our
attorney has reviewed the agreement, the draft will be provided to you for
review. The DA will need to be completed prior to final approval. For more
information on development agreements, please visit the City Development
Review Engineering website: https://www.fcgov.com/engineering/devrev.php
DCI Response: see attached agreement from Maverik
Comment Number: 3
04/06/2021: DEVELOPMENT CONSTRUCTION PERMIT:
A development construction permit (DCP) will be required prior to commencing
construction of any public improvements. Once the plans are close to approval,
we will need an engineer's opinion of cost submitted by the consulting engineer
(licensed in CO). This cost estimate will be reviewed by Engineering and
Engineering Inspections staff. Once approved, it will serve as the basis for
Engineering inspection fees as well as public improvement surety that will be
required prior to DCP issuance. For more information on the DCP process,
requirements and cost estimate template, visit the City Development Review
Engineering website: https://www.fcgov.com/engineering/devrev.php
DCI Response: see attached agreement from Maverik
Comment Number: 4
04/06/2021: FOR FINAL APPROVAL:
The City is utilizing a new signature block for utility plans to help us with
electronic processing. A copy of the new signature block is included with these
4
comments/redlines. Please remove all of the existing City signature blocks
throughout the utility plans and place the new signature block on the cover sheet only.
DCI Response: Revised on cover sheet and removed signature block on all other
sheets.
Comment Number: 5
04/06/2021: FOR FINAL APPROVAL:
There are going to be quite a few easement dedications and vacations for this
site. They will need to be processed by separate instrument, which will require
legal descriptions and exhibits for each, as well as deeds of dedication or
vacation resolutions. We will want to see the survey documents as soon as
possible once the site, utilities, etc. are pretty well set and not going to change.
You will need to submit a completed TDRF application and fees for the
easements ($250/dedication and $400/vacation). There is more information as
well as template deeds of dedication on our website: City Development Review
Engineering website: https://www.fcgov.com/engineering/devrev.php.
Please note that this comment only applies to easements to be dedicated to the City of
Fort Collins or City easements being vacated. Easements dedicated to or
being vacated that are owned by another municipality would be handled per that
entity's standards and coordinated with them. We would just need the
documentation (reception #) for those dedications/vacations to be shown on the plans.
DCI Response: the proposed easements are being prepared by the surveyor and
will be dedicated by separate documents. An additional easement plan has been
provided in the FDP plans.
Comment Number: 6
04/06/2021: FOR APPROVAL:
Please add additional information, details, etc. to demolition plan (see redlines).
DCI Response: See redlines for additional responses
Comment Number: 7
04/06/2021: FOR FINAL APPROVAL:
Please add directional pedestrian ramps at the site access to the frontage road
(see redlines). Also make sure to include City standard details in detail sheets.
DCI Response: this comment no longer applies base on the video meeting and further discussion
with Spencer.
Comment Number: 8
04/06/2021: FOR FINAL APPROVAL:
I'm a little unsure of what the existing easements that cross your site are. You
are calling out for the temporary construction one to be dedicated by separate
instrument, which doesn't make any sense. The other one is called out to be
vacated by separate instrument. Who's easements are these and are there any
existing improvements within them? We will need to confirm that the easement
owner is approving of any vacations. The vacation information will need to be
provided on the plans as well (reception #'s).
DCI Response: These easements have been vacated and no longer are shown on
plan set to avoid confusion.
Comment Number: 9
04/06/2021: FOR FINAL APPROVAL:
5
Please try and make the proposed easement limits as clear as possible. Some
of them are hard to follow due to overlapping linework and lack of dimensions, labels, etc.
DCI Response: An additional easement plan has been provided in the FDP plans.
Comment Number: 10
04/06/2021: FOR FINAL APPROVAL:
There are some issues with the proposed grading plan. There are proposed
contours shown behind the back of walk along the frontage road. The contours
are too steep and there is not supposed to be any grading behind the walk.
There are also spot elevations labeled that don't look correct when compared to
the contours. In some cases it looks like your 2 foot max thickened edge would
have to be taller if the elevations matched the contours.
DCI Response: The grading has been update. The thickened edge does exceed
the 2 foot limit at most by 0.5 feet. This will need to be updated to 2.5 feet max.
height need for thickened edge.
Comment Number: 11
04/06/2021: FOR FINAL APPROVAL:
Your frontage road p&p sheets shows a horizontal as well as a vertical angle
point. Since you're matching the existing frontage road alignment and profile,
this doesn't seem correct. We don't want angle points in the proposed walk that don't meet standards.
DCI Response: revised this linework to better represent “match existing”
roadway conditions. Also added a “note” to the roadway plans.
Comment Number: 12
04/06/2021: FOR FINAL APPROVAL:
Please make sure that a qualified geotechnical engineer has designed and/or
approved of the thickened edge along the proposed back of walk. I want to
make sure that we won't have any slope or walkway/roadway stability issues with the proposed design.
DCI Response: Noted.
Comment Number: 13
04/06/2021: FOR FINAL APPROVAL:
Please go through the City standard details and make sure that all applicable
details are included in the detail sheets. It seems like some are not included that should be.
DCI Response: additional details have been provided in the FDP plans.
Comment Number: 14
04/06/2021: FOR FINAL APPROVAL:
Please review the redlines for additional comments.
DCI Response: see redlines for additional responses
Department: Traffic Operation
Contact: Steve Gilchrist, 970-224-6175, sgilchrist@fcgov.com
Topic: General
Comment Number: 1
04/06/2021: FOR FINAL APPROVAL:
6
We will need to see a final signing and striping plan for the frontage road. This
will need to be reviewed by CDOT. Items to note, the bike lane should be
signed and stenciled, with a bike lane ends sign to the north of your access.
The bike lane at your access should be next to the through lane, and the right
turn lane should be next to the curb. This should also have stencils.
Department: Stormwater Engineering
Contact: Dan Mogen, 970-305-5989, dmogen@fcgov.com
Topic: General
Comment Number: 2
04/05/2021: FOR FINAL APPROVAL:
There are numerous redlines from preliminary review that have not been
addressed including details on the spill containment system, the sand filters and
forebays. Please review current redlines, and provide written responses on the PDFs.
I encourage you to reach out with any questions or to review potential revisions,
and I’d be happy to set up a meeting or conference call to do so in place of written responses.
DCI Response: see redlines for additional responses
Comment Number: 3
04/05/2021: FOR FINAL APPROVAL:
Please clarify proposed drainage easements areas to include all sand filters,
detention pond, and outfall. Please provide easement dedication or plat for review.
DCI Response: see redlines for additional responses
Comment Number: 4
04/05/2021: FOR FINAL APPROVAL:
Please provide evidence that the detention basin is in compliance with drain
times per Colorado Revised Statute 37-92-602(8). More information on this
statute is available at http://tinyurl.com/RevisedStatuteMemo, and a
spreadsheet to show compliance is available for download at
http://tinyurl.com/ComplianceSpreadsheet. Please contact Dan Mogen at
(970)305-5989 or dmogen@fcgov.com with any questions about this
requirement or for assistance with the spreadsheet.
DCI Response: see redlines for additional responses
Comment Number: 5
04/05/2021: DEVELOPMENT AGREEMENT:
Please provide spill containment details in Standard Operating Procedures
(SOPs) for inclusion in the DA. Please see redlines for additional details
needed on the spill containment systems.
DCI Response: SOP has been added to the end of the drainage report
Comment Number: 6
04/05/2021: INFORMATION:
Please note that all City construction detail drawings are to be used in their
7
original, unaltered state. ANY modification(s) must be clearly distinguished and
all City logos/identifiers must be removed from the modified detail. Detail
drawings can be found in both .pdf and .dwg formats through the links to
“Construction Drawings” on www.fcgov.com/utility-development.
DCI Response: see redlines for additional responses, added and used city standard outlet structure
detail
Department: Fort Collins Loveland Water District
Contact: Nate Ensley, PE, (480)358-5163, DevelopmentReview@fclwd.com, ,
Topic: General
Comment Number: 1
04/09/2021: FOR FINAL APPROVAL:
Please see attached redlines.
DCI Response: see redlines for additional responses
Department: Environmental Planning
Contact: Scott Benton, (970)416-4290, sbenton@fcgov.com
Topic: General
Comment Number: 1
03/30/2021: FOR FINAL APPROVAL:
As of March 30, 2021, Environmental Planning has not received any
communication from the applicant or from Animal & Pest Control Specialists.
As per previous comments provided during the development review process
and from the 'Prairie Dog Management Plan' provided by the applicant, a
written plan of action should have been provided 1 week prior to initiation of
removal activities, and a summary of actions should have been provided after
completion of activities. Work was anticipated to be completed no later than
March 15, 2021, two weeks prior to writing this comment.
Additionally, was any attempt made to contact Rocky Mountain Raptor Program
(https://www.rmrp.org/, 970-484-7756) prior to euthanization? They accept
prairie dog donations year round. Copies of communications with them need to be provided.
Maverik Response: see management plan
Comment Number: 2
03/30/2021: FOR DCP AND DEVELOPMENT AGREEMENT:
Since a humane form of fumigation is to be used (PERC) the lower
payment-in-lieu fee of $3,797.08 is available. The payment-in-lieu is due prior to issuance of the
DCP, and the fee and payment mechanism is required to be recorded in the Development Agreement.
Department: Forestry
Contact: Nils Saha, , nsaha@fcgov.com
Topic: General
Comment Number: 1
04/06/2021: FOR APPROVAL:
The existing tree inventory and the Tree Protection Notes seem to be missing from the FDP submittal.
RMS Response: Tree inventory included in resubmittal. No changes have been proposed.
8
Comment Number: 2
4/6/2021: FOR APPROVAL:
Please see redlines.
RMS Response: Please see redline responses on PDF.
Department: PFA
Contact: Marcus Glasgow, 970-416-2338, mglasgow@fcgov.com
Topic: General
Comment Number: 1
04/02/2021: INFORMATION:
No comments at this time from PFA.
Department: Erosion Control
Contact: Basil Hamdan, 970-222-1801, bhamdan@fcgov.com
Topic: Erosion Control
Comment Number: 1
04/01/2021: INFORMATION ONLY:
The City Manager’s development review fee schedule under City Code 7.5-2
was updated to include fees for Erosion Control and Stormwater Inspections.
As of January 1st, 2021, these fees will be collected on all projects for such inspections.
The Erosion Control fees are based on; the number of lots, the total site
disturbance and the estimated number of years the project will be active; the
Stormwater Inspection Fees are based on the number of LID/WQ Features that
are designed for on this project. Based on the proposed site construction
associated with this project we are assuming 1 lot, 2.89 acres of disturbance, 1
year from demo through build out of construction and an additional 3 years till full
vegetative stabilization due to seeding.
Which results in an Erosion Control Fee estimate of $ 1,172.09
Based on 1 extended detention and 2 sand filters/underground treatments, the
estimate of the Stormwater LID/WQ Inspection fee to is $ 1,080.
Please note that as the plans and any subsequent review modifications of the
above-mentioned values change the fees may need to be modified. I have
provided a copy of the spreadsheet used to arrive at these estimates for your review.
FOR FINAL APPROVAL:
Please address all redlined comments provided on the Final Erosion and Sediment Control Plan.
DCI Response: addressed redlines
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 3
04/05/2021: FOR FINAL APPROVAL:
9
There were 2 plan sets in this submittal. We will need to know which set will be
filed after approval, so we can review that set.
Comment Number: 4
04/05/2021: FOR FINAL APPROVAL:
Benchmark Y401 is a about 5 miles from the project site. Please add another
benchmark that is close to the project site and in the City's Vertical Control
Network. Please contact our office if you need any help with benchmark information.
DCI Response: added an alternative City of Fort Collins benchmark closer to site.
Topic: Site Plan
Comment Number: 1
04/05/2021: FOR FINAL APPROVAL:
Sheet 1 0f 2 is missing from the submittal. We will need to see all plans that will be filed after approval.
DCI Response: added missing sheets
Comment Number: 2
04/05/2021: FOR FINAL APPROVAL:
There are line over text issues. See redlines.
DCI Response: revised
Department: Building Services
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
04/02/2021: BUILDING PERMIT:
Construction shall comply with adopted codes as amended. Current adopted codes are:
2018 International Building Code (IBC) with local amendments
2018 International Existing Building Code (IEBC) with local amendments
2018 International Energy Conservation Code (IECC) with local amendments
2018 International Mechanical Code (IMC) with local amendments
2018 International Fuel Gas Code (IFGC) with local amendments
2018 International Swimming Pool and Spa Code (ISPSC) with local amendments
2018 International Plumbing Code (IPC) as amended by the State of Colorado
2020 National Electrical Code (NEC) as amended by the State of Colorado
Copies of current City of Fort Collins code amendments can be found at fcgov.com/building.
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Loads: Risk Category II (most structures):
· 140mph (Ultimate) exposure B or
· Front Range Gust Map published by The Structural Engineer's Association of
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code: 2018 IECC commercial chapter.
INFORMATIONAL ITEMS:
10
· Commercial occupancies must provide 10ft setback from property line and 20
feet between other buildings or provide fire rated walls and openings per
chapter 6 and 7 of the IBC.
· City of Fort Collins amendments to the 2018 IBC require a full NFPA-13 sprinkler system per
IBC chapter 9 or when building exceeds 5000 sq.ft. (or meet fire containment requirements).
· Prescriptive energy compliance with increased insulation values is required for buildings using electric heat.
· A City licensed commercial general contractor is required to construct any new commercial structure.
Building Permit Pre-Submittal Meeting:
Please schedule a pre-submittal meeting with Building Services for this project.
Pre-Submittal meetings assist the designer/builder by assuring, early on in the
design, that the new projects are on track to complying with all of the adopted
City codes and Standards listed below. The proposed project should be in the
early to mid-design stage for this meeting to be effective. Applicants of new
projects should their coordinator to schedule a pre-submittal
meeting. Applicants should be prepared to present site plans, floor plans, and
elevations and be able to discuss code issues of occupancy, square footage,
type of construction, and energy compliance method being proposed.
Comment Number: 2
04/02/2021: BUILDING PERMIT:
A passing building air tightness test (blower door) is required before CO can be issued.
Department: Outside Agencies
Contact: Sandra Mezzetti, 970-674-2430, smezzetti@windsorgov.com, ,
Topic: General
Comment Number: 1
04/05/2021: INFORMATION ONLY:
Thank you for the opportunity to review and comment on the above project. The
project has been reviewed by the Development Review Committee and the
committee has no further comments.
Thank you,
Sandra Mezzetti, AICP,Planner II
Town of Windsor | Planning
301 Walnut Street | Windsor, CO 80550
Dir: 970-674-2430 | Mobile: 970-388-2934
smezzetti@windsorgov.com
www.windsorgov.com
Contact: Tawn Hillenbrand, ,
Topic: General
Comment Number: 1
03/24/2021: INFORMATION ONLY:
Thank you for providing the County an opportunity to review and comment on the
proposed Maverik station located at the NW corner of I-25 and Hwy 392. The
Planning Department does not have any comments or concerns about the
proposed project. I have forwarded this referral on to the Larimer County
Engineering Department so that they may review the proposed project and provide comment if necessary.
11
Tawn Hillenbrand
Planner on Call
Larimer County Planning Department
200 W. Oak Street, Suite 3100
PO Box 1190
Fort Collins, CO 80522-1190
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1
03/26/2021: BUILDING PERMIT:
Irrigation plans are required no later than at the time of building permit. The
irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of
the Land Use Code. Direct questions concerning irrigation requirements to Eric
Olson, at 221-6704 or eolson@fcgov.com