HomeMy WebLinkAboutRAINTREE ANIMAL HOSPITAL - PDP/FDP - 22-98A - CORRESPONDENCE - (17)• February 24, 2000..... The project planner's staff comment letter went
out to the applicant's planning consultant.
• March 8, 2000..... The applicant submitted revisions in response to the
City staffs comment letter.
- After review of the latest revisions staff determined that the
RAINTREE ANIMAL CLINIC, PDP could be scheduled for a
required administrative public hearing. The hearing was set for
April 13, 2000.
• March 30, 2000..... The Current Planning Department mailed out the
required notification letter for the April 13, 2000 administrative public
hearing.
• April 13, 2000..... The administrative public hearing was conducted
before the hearing officer at 6:30 p.m. at 281 North College Avenue.
• April 21, 2000..... The administrative hearing officer rendered (in writing)
a decision of APPROVAL of the RAINTREE ANIMAL CLINIC, PDP.
The total development review time for the PDP, from formal submittal of the
RAINTREE ANIMAL CLINIC to the official approval of the PDP, was 5 months &
5 days.
• April 6, 2001..... Mylars of the Site Plan, Landscape Plan, Building
Elevations, and the original Site & Landscape Covenants form, signed
by the developer, were submitted to the Current Planning Department by
the applicant's planning consultant for a final check prior to recording.
The Director of Planning signed the Site Plan on May 3, 2001, and the
aforementioned documents may now be recorded.
• April 13, 2001..... Mylars of the utility plans and the necessary signed
easements were submitted to the Engineering Department by the
applicant's engineer for a final check and signatures from several City
departments. The mylars were due to be returned to the City's
development review engineer by April 20, 2001.
The utility plans and necessary signed easements for the RAINTREE ANIMAL
CLINIC development were submitted to the City for final checks and signatures
11 months & 22 days after approval of the RAINTREE ANIMAL CLINIC, PDP.
Comma y Planning and Environmental -vices
Current Planning
City of Fort Collins
h')1a)J)[•1ZJA 1910J)i
Date: May 3, 2001
To: Greg Byrne
Cameron Gloss
Dave Stringer
From: Steve Olt 0
Re: A chronology of the RAINTREE ANIMAL CLINIC development
review process
The following is information regarding the documentation provided, and
associated dates, for the RAINTREE ANIMAL CLINIC, Project Development Plan
(PDP) development review by the City.
• February 1, 1999..... The applicant brought a plan to City staff at
Conceptual Review.
• November 16, 1999..... The applicant submitted a PDP (complete
package) to the City, with a Small Project Fee of $200.00.
• The first round of staff review was the standard 4 weeks.
- December 15, 1999..... The staff review meeting to discuss the
development proposal If
• December 23, 1999..... The project planner's staff comment letter went
out to the applicant's planning consultant.
• January 26, 2000..... The applicant submitted revisions in response to
the City staffs comment letter.
• The second round of staff review was the standard 3 weeks.
- February 16, 2000..... The staff review meeting to discuss the
development proposal and revisions.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6750 • FAX (970) 416-2020