September 17, 2019
Cathy Mathis
TB Group
444 Mountain Ave
Berthoud, CO 80513
RE: Dutch Bros, FDP190017, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, please contact your Development Review Coordinator Brandy Bethurem Harras at
970.416.2744 or bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras, 970-416-2744, bbethuremharras@fcgov.com
Topic: General
Comment Number: 1
09/12/2019: INFORMATION ONLY:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone
conversations. Thank you!
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray@fcgov.com
Topic: General
Comment Number: 1
09/13/2019: INFORMATION ONLY:
Ready for mylars.
2
RESPONSE: Thank you.
Department: Engineering Development Review
Contact: Morgan Uhlman, 970-416-4344, muhlman@fcgov.com
Topic: General
Comment Number: 1
09/16/2019: FOR FINAL APPROVAL:
In the south elevation it appears that the steel canopies will overhang the
allocated building envelope that is shown on the plat by about 3 feet. The width
shown on the south elevations measures out to be 31 feet wide, where the
dimension on the plat is only 28 feet. The E-W dimension of the building
envelope looks large enough, the west elevation measures the building to be 46
feet long and the length on the plat is 46.5 feet.
RESPONSE: Building envelope has been adjusted.
Comment Number: 2
09/16/2019: FOR FINAL APPROVAL:
Some of the utility work for this project will happen on the adjacent property. We
believe that the installation and removal of utilities is acceptable in a utility
easement. We just want to verify that communication with the adjacent property
owner has happened to inform/coordinate the construction impacts.
RESPONSE: The owner of the Jiffy Lube property is also the owner of the Dutch Bros lot and there is a
partnership between the two entities. All improvements will be constructed at one time.
Comment Number: 4
09/16/2019: FOR FINAL APPROVAL:
Please depict the stairs along Kensington if they are still intended for the
pedestrian connection closest to the College/Kensington intersection.
RESPONSE: Now depicted on utility plans.
Comment Number: 5
09/16/2019: FOR FINAL APPROVAL:
Please see my redlines for more details and additional comments.
RESPONSE: Redlines addressed.
Comment Number: 6
09/16/2019: Development Construction Permit:
A Development Construction Permit ("DCP") will be needed for this project.
Please fill out the application and submit the estimated costs and quantities
spreadsheet. For more information and to find the application and the
costs and quantities spreadsheets for this permit, please follow this link:
https://www.fcgov.com/engineering/devrev.php
RESPONSE: Thank you.
Comment Number: 7
09/16/2019: Development Agreement:
Thank you for the information sheet for the DA, once comments from all
contributing departments have been resolved I can put a draft together and have
the City Attorneys office review it. Once the City Attorneys review the draft, I will
send it on to the applicant for review. Once we have a finalized draft we can
work on getting the document recorded at the county.
3
RESPONSE: Thank you.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: General
Comment Number: 1
09/17/2019: INFORMATION ONLY: No comments in addition to those from the Engineering
Department. Once those are addressed, Traffic is ready for mylars.
Department: Colorado Department of Transportation
Contact: Gloria Hice-Idler, gloria.hice-idler@state.co.us
Topic: General
Comment Number: 1
09/12/2019: FOR APPROVAL:
CDOT's only comment regarding this proposal would be if any improvement is
planned for the access off of College Avenue. An access permit would be required.
RESPONSE: There are no improvements planned along College Avenue.
Department: Water-Wastewater Engineering
Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com
Topic: General
Comment Number: 1
09/16/2019: FOR FINAL APPROVAL:
See the redlined plans and drainage report for additional minor comments.
(W/WW/SW)
RESPONSE: Redlines have been addressed.
Comment Number: 2
09/16/2019: FOR FINAL APPROVAL:
On the Landscape Plan – regarding the plantings around the proposed fire
hydrant on the southwest corner of the lot: Please confirm these grasses will not
be tall and block view of the hydrant, or revise layout so that view of the hydrant
would not be obscured from the alley.
RESPONSE: The grasses have been removed near the hydrant.
Department: Stormwater Engineering
Contact: Basil Hamdan, 970-224-6035, bhamdan@fcgov.com
Topic: Erosion Control
Comment Number: 8
09/17/2019: FOR FINAL APPROVAL: Please add notes that the underground
storage system will be built at the end of the construction sequence and will be
protected throughout the construction period from sedimentation due to
construction activities on the site. RESPONSE: Notes added.
Please add a construction fence along the
property line between Lot 2 and Lot 3 to prevent cross access to and from this
site while construction activities are occurring. RESPONSE: Construction Fence
and details added.
4
Please add a note to the Erosion Control Plan stating that no tracking of mud and
debris will be allowed onto the surrounding streets and properties. In case
any tracking occurs, it shall be cleaned immediately by the contractor.
RESPONSE: Note added.
The rock socks along College Avenue may cause a traffic concern if they
protrude into the traffic lane. Please clarify how these will be placed, provide a
detail showing that there will be at least one foot of contact between the rock socks
and the curb. RESPONSE: Notes added to detail to clarify placement.
Please update the Erosion Control Cost Estimate as needed based on the provided comments.
RESPONSE: Erosion Control Cost Estimate updated and submitted with package.
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: General
Comment Number: 9
09/18/2019: FOR FINAL APPROVAL: Please clarify how permanent water quality treatment
facilities (underground storage) will be protected during construction activities on this site.
RESPONSE: Notes added to Erosion Control Sheet to clarify protection.
Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com
Topic: General
Comment Number: 1
09/16/2019: FOR FINAL APPROVAL:
My review calculations showed that the two proposed single grate inlets (at
each design point location) do not have the capacity for the design flows. See
the redlined PDF for more information. Please contact me to discuss if you have any questions.
RESPONSE: Inlet updated to curb inlet and capacity calc based on manufacturers chart. Chart is i
ncluded in Appendix of drainage report.
Comment Number: 2
09/16/2019: FOR FINAL APPROVAL:
The City highly recommends combination curb inlets – please consider
switching from grate only inlets. (Recommended, not required).
RESPONSE: Changed to combo curb inlets.
Comment Number: 3
09/16/2019: FOR FINAL APPROVAL:
There is a clearance issue with existing light pole and proposed storm drain on
the east side of the site. The light is 3-ft away from the proposed storm, 6 to
10-feet of clearance is needed. See redlined plans.
RESPONSE: Light pole is to be removed and now noted as such on the plans.
Comment Number: 4
09/16/2019: FOR FINAL APPROVAL:
Please add to the drainage report the compliance statement from Fort Collins
Stormwater Criteria Manual:
“I hereby attest that this report for the [preliminary or final] drainage design for
the [project name] was prepared by me or under my direct supervision, in
accordance with the provisions of the Fort Collins Stormwater Criteria Manual. I
understand that the City of Fort Collins does not and will not assume liability for
drainage facilities designed by others.”
Registered professional engineer must affix their seal with signature and date.
RESPONSE: Added
5
Comment Number: 5
09/16/2019: FOR FINAL APPROVAL:
See the redlined plans and drainage report for additional minor comments.
RESPONSE: Redlines addressed.
Comment Number: 6
09/16/2019: INFORMATION ONLY:
We will approve the requested drainage variance. Thank you for working with
us on the stormwater design for this site. For final approval, at the time of
mylars, please submit the same form you have provided, with the owner’s
signature. These pages should remain in the drainage report.
RESPONSE: Thanks. Owner signature included.
Comment Number: 7
09/16/2019: FOR FINAL APPROVAL:
Due to the subdivision of the parcel there will be joint stormwater facilities. This
will require a maintenance agreement or covenant between these two parcels.
This will need to detail the ownership, maintenance, and cost sharing of these joint facilities.
RESPONSE: Noted.
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreager@fcgov.com
Topic: General
Comment Number: 1
09/17/2019: FOR FINAL APPROVAL:
I know that we have worked through the utility conflicts prior to hearing, but
please label the existing electric line as needing to be relocated on the utility
plans along with the proposed relocation route. Thank you.
RESPONSE: Labeled.
Comment Number: 2
09/17/2019: INFORMATION ONLY:
Thank you for providing a preliminary C-1 form and one-line diagram. A fully
completed C-1 form will be needed prior to construction.
RESPONSE:
Comment Number: 3
09/17/2019: INFORMATION ONLY:
You may contact Austin Kreager, project engineering if you have questions.
(970) 224-6152. You may reference Light & Power’s Electric Service Standards at
http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar
ds_FINAL_18November2016_Amendment.pdf
You may reference our policies, development charge processes, and use our fee estimator at
http://www.fcgov.com/utilities/business/builders-and-developers.
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak@fcgov.com
Topic: General
Comment Number: 1
09/05/2019: INFORMATION ONLY:
6
No further comments.
Department: Forestry
Contact: Molly Roche, 224-616-1992, mroche@fcgov.com
Topic: Landscape Plans
Comment Number: 12
9/16/2019: FOR FINAL APPROVAL – UNRESOLVED:
This has not been corrected. Please remove all symbols for existing trees that
are to be removed from sheet L-1 of the landscape plan.
RESPONSE: All symbols have been removed from this sheet.
7/22/2019: FOR FINAL APPROVAL – UNRESOLVED:
Thank you for removing the note. However, the tree symbol is still shown on this
page. Please remove all symbols for existing trees that are to be removed from
sheet L-1 of the landscape plan.
7/16/2019: FOR FINAL APPROVAL – UNRESOLVED:
Thank you for updating the tree symbol for tree #11 on sheet L-3. However, on
sheet L-1 this tree is shown as EXISTING TREE TO REMAIN. Since this tree is
to be removed, please remove the tree symbol from this sheet. In addition, this
same tree is shown to remain on the utility plans sheet 2. Please place an X
over the symbol. This tree’s symbol should also be removed from sheet 3 of the utility plans.
5/13/2019: COMPLETE BY HEARING
Tree #11 is shown to be removed in the Tree Inventory and Mitigation table, but
does not have the correct symbol on sheet L-3.
Comment Number: 15
9/16/2019: FOR FINAL APPROVAL – UNRESOLVED
This has not been corrected. Due to Coralburst Crabapple’s wide branching
structure, please specify a Hot Wings Maple to go in the right-of-way along
Kensington. Please update plant list to include this species.
RESPONSE: Tree has been changed to a 2” caliper Hot Wings single stem Maple.
7/22/2019: FOR FINAL APPROVAL – UNRESOLVED
Due to Coralburst Crabapple’s wide branching structure, please specify a Hot
Wings Maple to go in the right-of-way along Kensington. Please update plant list
to include this species.
7/16/2019: FOR FINAL PLAN:
The Sterling Silver Linden tree that is proposed along Kensington Drive is less
than 40 ft from the existing streetlight. Since there isn’t adequate room to fit a
canopy shade tree in this location, please change this tree to an upsized
(mitigation) ornamental tree such as Hot Wings Maple. Update Plant List as needed.
Comment Number: 17
9/16/2019: FOR FINAL APPROVAL – UNRESOLVED
This has not been addressed.
RESPONSE: Street Tree Permit Note added to Sheet L-1.
7/22/2019: FOR FINAL APPROVAL – UNRESOLVED
This has not been addressed.
7/16/2019: FOR FINAL PLAN:
Please include the Street Tree Permit Note on sheet L-1 of the Landscape Plans.
7
Comment Number: 19
9/16/2019: FOR FINAL APPROVAL
Please size mitigation trees at the following calipers:
Canopy Shade Trees: 2.0" caliper balled and burlap or equivalent.
Ornamental Trees: 2.0" caliper balled and burlap or equivalent.
Evergreen Trees: 8' height balled and burlap or equivalent.
RESPONSE: Tree mitigation sizes have been updated.
Comment Number: 20
9/16/2019: FOR FINAL APPROVAL
According to LUC3.2.1.(D)(c), Canopy shade trees shall constitute at least 50%
of all tree plantings. Currently, canopy shade trees make up 23% of plantings on
this plan. Please increase canopy shade tree plantings by substituting shade
trees in the drive-thru median.
RESPONSE: We have added two canopy shade trees and two additional ornamental trees to the plans.
Department: PFA
Contact: Andrew Rosen, 970-416-2599, arosen@poudre-fire.org
Topic: General
Comment Number: 1
09/06/2019: INFORMATION ONLY:
All PFA comments have been resolved regarding fire lane access, hydrant
location and address posting with no outstanding comments. Thank you.
Department: Building Services
Contact: Katy Hand, khand@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
9/17/2019: BUILDING PERMIT:
Please visit our website for a list of current adopted building codes and local
amendments: https://www.fcgov.com/building/codes.php
Department: Technical Services
Contact: Jeff County, 970-221-6588 jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 8
09/17/2019: FOR FINAL APPROVAL:
Please provide the following information for the Benchmark Statement in the
EXACT format shown below.
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION
ELEVATION:
BENCHMARK # w/ DESCRIPTION
ELEVATION:
8
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL
DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29
UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) FOR
THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS
DATUM) IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATION
SHOULD BE USED: NGVD29 UNADJUSTED DATUM (PRIOR CITY OF
FORT COLLINS DATUM) = NAVD88 DATUM - X.XX’.
RESPONSE: Corrected.
Comment Number: 9
09/17/2019: FOR FINAL APPROVAL:
All Benchmark Statements must match on all sheets.
RESPONSE: Corrected.
Comment Number: 10
09/17/2019: FOR FINAL APPROVAL:
Some of the easement descriptions shown are incorrect. If they are going to
stay on the plan, they should match what is shown on the Subdivision Plat.
RESPONSE: Corrected.
Comment Number: 11
09/17/2019: FOR FINAL APPROVAL:
There are line over text issues. See redlines.
RESPONSE: Corrected.
Topic: Landscape Plans
Comment Number: 6
09/17/2019: FOR FINAL APPROVAL:
Please revise the title as marked. See redlines.
RESPONSE: Title has been revised to include the word “Coffee”.
Comment Number: 7
09/17/2019: FOR FINAL APPROVAL:
Some of the easement descriptions shown are incorrect. If they are going to
stay on the plan, they should match what is shown on the Subdivision Plat.
RESPONSE: Easement depictions have been corrected.
Topic: Plat
Comment Number: 1
09/12/2019: FOR FINAL APPROVAL:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter.
RESPONSE: Redlines have been addressed.
Topic: Site Plan
Comment Number: 2
09/17/2019: FOR FINAL APPROVAL:
Please revise the titles & sub-title as marked. See redlines.
9
RESPONSE: Titles have been changed.
Comment Number: 3
09/17/2019: FOR FINAL APPROVAL:
Please fix all of the text errors & remove text boxes. See redlines.
RESPONSE: This was an issue caused by combining the PDF’s into one set and has been corrected.
Comment Number: 4
09/17/2019: FOR FINAL APPROVAL:
There are what appear to be random lines on sheet 2. Please remove if not
needed, or label if needed. See redlines.
RESPONSE: Those lines were on the CAD base as the north flowline of Kensington. The viewport
window has been enlarged to better show the complete linework.
Comment Number: 5
09/17/2019: FOR FINAL APPROVAL:
Please correct the Property Line linetype in the legend to match the linetype
shown on the plan. See redlines.
RESPONSE: Linetypes have been updated.