Loading...
HomeMy WebLinkAboutLANDMARK APARTMENTS EXPANSION - FDP190002 - SUBMITTAL DOCUMENTS - ROUND 3 - SUPPLEMENTAL INFORMATION (3)Landmark Prepared by: Opinion of Probable Costs 4.30.19 Landmark UNIT EXTENDED ITEM QUANTITY UNIT COST COST General Conditions General Conditions / Mobilization @ 5.0% 1 lump sum $ 1,165.82 $ 1,165.82 Insurance / Bonding @ 3.5% 1 lump sum $ 816.07 $ 816.07 Overhead and Fees @ 7.0% 1 lump sum $ 1,632.14 $ 1,632.14 Earthwork and Grading Erosion Control 17,658 Sq. Ft. $ 0.08 $ 1,324.35 Fine Grading 17,658 Sq. Ft. $ 0.20 $ 3,531.60 Landscape Trees 16 Each $ 525.00 $ 8,400.00 Shrubs (5 gallon) 218 Each $ 38.00 $ 8,284.00 Native Seeding 14,803 Sq. Ft. $ 0.12 $ 1,776.36 CONSTRUCTION SUBTOTAL $ 26,930.34 CONSTRUCTION TOTAL $ 26,930.34 Notes: X 125% = $11,806.45 1 - All unit prices include labor, materials and machinery used to properly stock, prepare, install and maintain the work. 2 - This is an estimate to be used for budgetary analysis only. 3 - Design fees are not included in this estimate. 4 - The Birdsall Group, LLC is not held responsible for any discrepancies of actual quantities, fees or construction costs. 5 - All civil components are excluded from this estimate including but not limited to ashphalt, curb and gutter, utitilies, pervious pavers, ramps and stairs