HomeMy WebLinkAboutSW PROSPECT AND I 25 ROADWAY PROJECT - RP180001 - SUBMITTAL DOCUMENTS - ROUND 3 - EROSION CONTROL LETTER/REPORTProject Number: 232-043 Location: Fort Collins, CO
Date: January 30, 2019 Total Acres: 7.27
EROSION CONTROL MEASURE Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 1890 $1.50 $2,835.00
Construction Fence w/Rock Sock L.F. 0 $4.50 $0.00
each 0 $200.00 $0.00
each 1 $2,500.00 $2,500.00
each 1 $1,850.00 $1,850.00
each 28 $150.00 $4,200.00
L.F. 70 $3.50 $245.00
per hour 24 $60.00 $1,440.00
Sub-Total: $13,070.00
1.5 x Sub-Total: $19,605.00
Amount of security: $19,605.00
Total Acres x $1325/acre: $9,632.75
Sub-Total: $9,632.75
1.5 x Sub-Total: $14,449.13
Cost to Re-seed: $14,449.13
Minimum escrow amount: $3,000.00
Erosion Control Escrow: $19,605.00
NOTE: 'Total Acres' represents total disturbed area.
Prospect Road / I-25
Erosion Control Cost Estimate
Silt Fencing
Inlet Protection
Vehicle Tracking Control Pads
Option 2 | Cost to Re-seed Disturbed acreage
Option 3 | Miniumum Escrow Amount
Final Escrow Amount
Concrete Washout Area
Rock Sock
Sawcutting Pollution Prevention
Street Sweeping and Cleaning
Option 1 | BMP Costs