December 06, 2018
Jennifer Daniels
Verizon Wireless / Centerline Solutions
16035 Table Mountain Pkwy
Golden, CO 80403
RE: FTC OLD TOWN, BDR180018, Round Number 3
Please see the following summary of comments from City staff and outside reviewing agencies for
your submittal of the above referenced project. If you have questions about any comments, you
may contact the individual commenter or direct your questions through your Development Review
Coordinator, Brandy Bethurem Harras, at bbethuremharras@fcgov.com or 970.416.2744.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray@fcgov.com
Topic: General
Comment Number: FOR APPROVAL:
Add to FC Notes on Page GN-1.
REPLACEMENT: ANY LANDSCAPE ELEMENT THAT DIES, OR IS
OTHERWISE REMOVED, SHALL BE PROMPTLY REPLACED IN
ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS.
Note Added to GN-1
Department: Forestry
Contact: Molly Roche, 224-616-1992, mroche@fcgov.com
Topic: Landscape Plans
Comment Number: 1
FOR APPROVAL:
Continued: An on-site meeting to receive tree inventory and mitigation information has not been
scheduled with City Forestry. City Forestry will not resolve BDR comments related to existing trees
until this information is received and included on the site plans. Please contact Forestry Specialist,
2
Molly Roche, to schedule this meeting – mroche@fcgov.com.
9/17/2018: Continued: Thank you for including the City of Fort Collins Tree Protection Notes. According
to the site plan, it appears that the proposed fiber line will be installed between
several existing trees on-site. Although no impacts are expected, please
schedule a meeting with City Forestry to obtain tree inventory and mitigation
information, which is to be included on the site plan. In the instance where the
fiber line trenches through and cuts existing tree roots, certain trees might not
be able to withstand the impacts of root loss or damage. Any questions, please
contact Molly Roche (mroche@fcgov.com).
7/9/2018: There appears to be existing trees on-site, and a few that are in close proximity
to the proposed wireless communications device. Please include the City of
Fort Collins tree protection notes to the site plan, which are available from City
Forestry or the project planner. In addition, please schedule an on-site meeting
to obtain tree inventory and mitigation information if there are any proposed or
expected impacts to existing trees.
TM-1 sheet added to include tree inventory
Department: Parks
Contact: Jill Wuertz, 970-416-2062, jwuertz@fcgov.com
Topic: Landscape Plans
Comment Number: 2
11/30/2018: FOR DCP/BUILDING PERMIT:
Please coordinate with the Parks Department regarding impacts
to Library Park, including existing irrigation, turf, shrubs/trees and sidewalk.
Work will need to be inspected by Parks. Please contact Jill with any further
questions - JWUERTZ@FCGOV.COM.
Comment Number: 3
11/30/2018: FOR DCP/BUILDING PERMIT:
Please coordinate with the Parks Department with regards to
large events potentially coinciding with the time of construction. Please contact
Jill with any further questions - JWUERTZ@FCGOV.COM.
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreager@fcgov.com
Topic: General
Comment Number: 1
12/04/2018: INFORMATION ONLY:
Light and Power acknowledges that this will require a new service.
09/18/2018: Light and Power has an existing 300kVA 277/480v transformer on
the property. Is the plan to add an additional meter for the proposed cell site? If
not, you can disregard the following:
Site will require new service with new meter, reference sheet U1
Comment Number: 2
12/04/2018: FOR BUILDING PERMIT:
3
Light and Power has a copy of a C-1 form. The C-1 form does not
currently reflect a 277/480 service that would need to be installed. Before
construction, we will need a complete C-1.
09/18/2018: Please provide a one line diagram and a C-1 form to Light and
Power Engineering. The C-1 form can be found at:
http://zeus.fcgov.com/utils-procedures/files/EngWiki/WikiPdfs/C/C-1Form.pdf
Comment Number: 4
09/18/2018: INFORMATION ONLY:
This would be a commercial service, therefor, the applicant would
be responsible for running the secondary service to our power source.
Comment Number: 5
09/18/2018: INFORMATION ONLY:
You may contact FCU Light & Power, project engineering if you
have questions. (970) 221-6700. You may reference Light & Power’s Electric
Service Standards at
http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar
ds_FINAL_18November2016_Amendment.pdf
You may reference our policies, development charge processes, and use our
fee estimator at http://www.fcgov.com/utilities/business/builders-and-developers.
Comment Number: 6
12/04/2018: PRIOR TO MYLARS:
Due to Verizon running their own service to the transformer, we will
need the totality of our primary line as well as our transformer placed in a utility
easement.
Utility easement updated to encompass transformer as well
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: General
Comment Number: 5
12/03/2018: FOR APPROVAL:
Please revise the legal description as marked. See redlines.
Corrected on T1
Department: PFA
Contact: Andrew Rosen, 970-416-2599, arosen@poudre-fire.org
Topic: General
Comment Number: 1
9-17-2018: INFORMATION ONLY:
PFA has no further comments at this time
07/05/2018: SIGNAGE
To assist with emergency response, signage should be clearly visible at ground
level and at the access ladder to indicate the most appropriate access to the
Verizon equipment.
CONTINUED – FORRESTRY COMMENTS (ADDED HERE BY AEROSOLUTIONS)
4
2
12/6/18:
City Forestry will provide the Development Review Coordinator with the updated tree inventory information. This table will include
species, diameter, condition, and appraised value for each tree. Please include this information on the site plan. Redlines provided
to show matching tree #s.
Reference TM-1
3
12/6/18:
City Forestry has reviewed the layout of the new fiber line and would like to request that this line be installed through boring
techniques. Forestry requests that the boring start near the right-of-way along Olive and then work toward the building. Working in
this direction will limit the impact of boring equipment and drilling near the tree closest to the building. In addition, the boring
should be done at a minimum of 48” or deeper to avoid all tree roots. Tree protection in the form of concrete blankets around tree
trunks should be installed prior to on-site construction.
Note added to TM-1
4
12/6/18:
The appraised values of each tree within proximity to the project is shown in the tree inventory table. Please add the following note
to the site plan, preferably below the tree inventory table: “Any damage to a tree as a direct result of this activity will result in fines
equal to $1,000 per inch of damaged area up to the total appraised value of each tree. If a tree is girdled 40% or higher, then the
full appraised value of the tree will be collected by City Forestry.”
Reference TM-1