HomeMy WebLinkAboutCOUNTRY CLUB RESERVE - FDP180030 - SUBMITTAL DOCUMENTS - ROUND 1 - STORMWATER MANAGEMENT PLANSTORMWATER MANAGEMENT PLAN (SWMP)
COUNTRY CLUB RESERVE
Fort Collins, CO
December 12, 2018
Prepared for:
Crystal Cove Development
8020 S. County Road 5, Unit 200
Fort Collins, CO 80528
Prepared by:
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
Phone: 970.221.4158 Fax: 970.221.4159
www.northernengineering.com
Project Number: 1324-001
This Drainage Report is consciously provided as a PDF.
Please consider the environment before printing this document in its entirety.
When a hard copy is absolutely necessary, we recommend double-sided printing.
December 12, 2018
City of Fort Collins
Stormwater Utility
700 Wood Street
Fort Collins, Colorado 80521
RE: Stormwater Management Plan
COUNTRY CLUB RESERVE
To Whom It May Concern:
Northern Engineering Services, Inc. is pleased to submit this Stormwater Management Plan for the
Country Club Reserve project. This report outlines Best Management Practices (BMPs) to be
implemented with the proposed construction in order to minimize potential pollutants in stormwater
discharges.
We have prepared this report to accompany the Colorado Department of Public Health and
Environment General Permit for Stormwater Discharge Associated with Construction Activities (aka,
Stormwater Discharge Permit or SDP). The General Permit No. for this SDP is (to be filled-in by
permittee) and the Certification No. for this SDP is (to be filled-in by permittee). The Permit
Certification is Effective beginning (to be filled-in by permittee), and initial certification expires (to be
filled-in by permittee). A copy of the issuance cover letter can be found in the Appendix D of this
document (to be provided by permittee).
Please note: this Stormwater Management plan (including the Site Maps) is not a static document.
It is a dynamic device that should be kept current and logged as construction takes place. As such,
this version was prepared to facilitate initial plan approvals and permitting, but does not necessarily
reflect the final version, or the transitions throughout the construction process. As the site develops
and changes, the Contractor is expected and encouraged to make changes to what is contained
herein so that the SWMP works as effectively and efficiently as possible. It shall be the
responsibility of the SWMP Administrator and/or the permit holder (or applicant thereof) to ensure
the plan is properly maintained and followed.
If you should have any questions or comments as you review this report, please feel free to contact
us at your convenience.
Sincerely,
NORTHERN ENGINEERING SERVICES, INC.
Laurie Clark, PE
Project Engineer
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan
TABLE OF CONTENTS
Vicinity Map
1.0 General Requirements ................................................................................................ 1
1.1 Objectives .................................................................................................................. 1
1.2 SMWP Availability ...................................................................................................... 1
1.3 Definitions.................................................................................................................. 1
1.4 Additional Permitting ................................................................................................... 1
2.0 Narrative Site Description ........................................................................................... 2
2.1 Existing Site Description .............................................................................................. 2
2.2 Nature of Construction Activity ..................................................................................... 2
2.3 Sequence of Major Activities ......................................................................................... 2
2.4 Site Disturbance ......................................................................................................... 2
2.5 Existing Data .............................................................................................................. 2
2.6 Existing Vegetation ...................................................................................................... 2
2.7 Potential Pollution Sources ........................................................................................... 2
2.8 Non-stormwater discharges .......................................................................................... 3
2.9 Receiving Waters ........................................................................................................ 3
3.0 Stormwater Management Controls ............................................................................... 4
3.1 SWMP Administrator ................................................................................................... 4
3.2 Best Management Practices (BMP’s) for Stormwater Pollution Prevention.......................... 4
3.3 Structural Practices for Erosion and Sediment Control ..................................................... 4
3.4 Non-Structural Practices for Erosion and Sediment Control .............................................. 7
3.5 Phased BMP Installation .............................................................................................. 9
3.6 Material Handling and Spill Prevention ........................................................................ 10
3.7 Dedicated Concrete or Asphalt Batch Plant .................................................................. 11
3.8 Vehicle Tracking Control ............................................................................................ 11
3.9 Waste Management and Disposal ............................................................................... 11
3.10 Groundwater and Stormwater Dewatering .................................................................... 11
4.0 Final Stabilization and Long-Term Stormwater Management ........................................ 12
4.1 Final Stabilization ..................................................................................................... 12
4.2 Long-Term Stormwater Management ........................................................................... 12
5.0 Inspection, Maintenance and Record Keeping ............................................................. 12
5.1 BMP Inspection ........................................................................................................ 12
5.2 BMP Maintenance .................................................................................................... 13
5.3 Record Keeping ........................................................................................................ 13
6.0 Additional SWMP and BMP Resources ....................................................................... 15
References ............................................................................................................... 16
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan
LIST OF TABLES:
Table 1 – Preliminary Permit and Construction Schedule ........................................................ 10
APPENDICES:
APPENDIX A – Site Maps
APPENDIX B – Erosion Control Details
APPENDIX C – Landscape Plan
APPENDIX D – Copies of Permits/Applications
APPENDIX E – Inspection Logs
APPENDIX F – Contractor Inserts (as needed)
APPENDIX G – Contractor Inserts (as needed)
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 1
1.0 General Requirements
1.1 Objectives
The objective of a Stormwater Management Plan (SWMP) is to identify all potential sources of
pollution likely to occur as a result of construction activity associated with the site construction, and
to describe the practices that will be used to reduce the pollutants in stormwater discharges from
the site. The SWMP must be completed and implemented at the time the project breaks ground,
and revised as necessary as construction proceeds to accurately reflect the conditions and practices
at the site.
This report summarizes the Stormwater Management Plan for the construction activity that will
occur with Country Club Reserve in Fort Collins, CO. This plan has been prepared according to
regulations of the Colorado Department of Public Health and Environment (CDPHE), Water Quality
Control Division.
1.2 SMWP Availability
This report is intended to remain on the aforementioned construction site to allow for maintenance
and inspection updates, and for review during inspection.
1.3 Definitions
BMP – Best Management Practice encompassing a wide range of erosion and sediment control
practices, both structural and non-structural in nature, which are intended to reduce or eliminate
any possible water quality impacts from stormwater leaving a construction site.
Erosion Control BMPs – Practices that PREVENT the erosion of soil, such as minimizing the amount
of disturbed area through phasing, temporary stabilization, and preserving existing vegetation.
Sediment Control BMP’s – Practices to REMOVE sediment from runoff, such as sediment basins,
silt fence, or inlet protection.
Non-structural BMP’s – The implementation of methods, practices, and procedures to minimize
water quality impacts, such as the preservation of natural vegetation, preventive maintenance and
spill response procedures.
Structural BMP’s – Physical devices that prevent or minimize water quality impacts, such as
sediment basins, inlet protection, or silt fence.
1.4 Additional Permitting
As mentioned above, this Stormwater Management Plan is associated with the Colorado
Department of Public Health and Environment Stormwater Permit that is issued by the Water
Quality Control Division of the CDPHE. Additional Environmental permitting not described in this
report may be required as a part of this project. An example is the Construction Dewatering Permit
for groundwater. Another example is the Air Pollution Emission Notice (APEN). The CDPHE
website contains links to both of these permits, as well as many other potential permits. The
Contractor is responsible for ensuring the proper permits are acquired.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 2
2.0 Narrative Site Description
2.1 Existing Site Description
The project site is located just southwest of the intersection of Turnberry Road and East Douglas
Road. More specifically, the project site is located in the northeast quarter of Section 30, Township
8 North, Range 68 West of the 6th Principal Meridian, City of Fort Collins, County of Larimer, State
of Colorado.
2.2 Nature of Construction Activity
The proposed Country Club Reserve project is a single-family residential subdivision that will include
internal roadways, improvements to Turnberry Road and East Douglas Road, utility services and
drainage facilities.
2.3 Sequence of Major Activities
To complete the project, many basic categories of construction activity will take place. The first
part will be construction of offsite improvements, followed by construction of onsite utility services
and roadways. Next, overlot grading and construction of drainage facilities will begin. Vertical
construction of the single-family buildings will commence after the utility and roadway work is
complete. The final stages of site construction will be fine grading of the areas around the
buildings, and the installation of landscaping throughout the project. The aforementioned
sequencing is an initial best guess, and is subject to change at the Contractor’s discretion.
2.4 Site Disturbance
The site disturbance will occur across roughly 78 acres. It is recommended that existing site
condition photos be taken prior to commencement of construction activities.
2.5 Existing Data
In order to complete the associated construction plans, a topographical survey of the site was
completed. This survey consisted of field measurements made by Northern Engineering on May 12,
2017.
In addition to the field survey, that Natural Resources Conservation Service (NRCS) Soil Survey was
used to determine existing soil types found on-site. According to the NRCS Soil Survey, the site
primarily consists of Fort Collins Loam, which falls into Hydrologic Soil Group B and C, and
Longmont Clay, which falls into Hydrologic Soil Group D.
2.6 Existing Vegetation
The existing site vegetation consists of native grasses.
2.6 Potential Pollution Sources
As is typical with most construction sites, there are a number of potential pollution sources which
could affect water quality. It is not possible for this report to identify all materials that will be used
or stored on the construction site. It is the sole responsibility of the Contractor to identify and
properly handle all materials that are potential pollution sources. The following are some common
examples of potential pollution sources:
• Exposed and stored soils
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 3
• Management of contaminated soils
• Off-site tracking of soils and sediment
• Loading and unloading operations
• Outdoor storage of building materials, fertilizers, chemicals, etc.
• Vehicle and equipment maintenance and fueling
• Significant dust or particulate generating processes
• Routine maintenance activities involving fertilizers, pesticides, detergents, fuels, solvents, oils, etc.
• On-site waste disposal practices (waste piles, dumpsters, etc.)
• Concrete truck/equipment washing
• Non-industrial waste sources that may be significant, such as worker trash and portable toilets
• Uncovered trash bins
• Other areas or procedures where potential spills can occur
• Stockpiling of materials that can be transported to receiving waterway(s)
Management of Contaminated Soils: We are not aware of on-site contaminated soils. However, the
contractor should conduct a thorough, pre-construction environmental site assessment. If
contaminated soils are discovered, the contractor will identify appropriate practices and procedures
for the specific contaminants discovered on-site.
Loading and Unloading Operations: As site development and building construction progresses,
space constraints will limit the number of on-site locations for loading and unloading activities to
the building from Perennial Lane. The contractor will be responsible for the proper handling and
management of pollution sources during loading and unloading operations.
Dedicated Asphalt and Concrete Batch Plants: Neither a dedicated asphalt or concrete batch plant
will be constructed on-site.
2.7 Non-stormwater discharges
The Stormwater Construction Permit only covers discharges composed entirely of stormwater.
Emergency firefighting water is the only authorized exception. Concrete Washout water can NOT be
discharged to surface waters or to storm sewer systems without separate permit coverage. The
discharge of Concrete Washout water to the ground, under specific conditions, may be allowed by
the Stormwater Construction Permit when appropriate BMPs are implemented.
The discharge of pumped stormwater, ONLY, from excavations, ponds, depressions, etc. to surface
waters, or to a municipal storm sewer system is allowed by the Stormwater Construction Permit, as
long as the dewatering activity and associated BMPs are identified in the Stormwater Management
Plan (SWMP) and are implemented in accordance with the SWMP.
Aside from the exceptions noted above, non-stormwater discharges must be addressed in a separate
permit issued for that discharge. If groundwater is encountered, and dewatering is required, a
Construction Dewatering Permit must be acquired from the Colorado Department of Public Health
and Environment.
2.8 Receiving Waters
The property historically drains from southwest to northeast, discharging into the No. Eight Ditch.
Country Club Reserve is located within the Boxelder/Cooper Slough Master Drainage Basin and is
ultimately received by the Cache la Poudre River.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 4
3.0 Stormwater Management Controls
3.1 SWMP Administrator
A SWMP Administrator must be designated in conjunction with the Stormwater Permit. This person
shall be responsible for developing, implementing, maintaining, and revising the SWMP. The
SWMP Administrator will also be the contact for all SWMP-related issues and will be the person
responsible for the accuracy, completeness, and implementation of the SWMP. The Administrator
should be a person with authority to adequately manage and direct day-to-day stormwater quality
management activities at the site.
The SWMP Administrator for this site is:
Name: (to be filled-in by permittee)
Company: (to be filled-in by permittee)
Phone: (to be filled-in by permittee)
E-mail: (to be filled-in by permittee)
3.2 Best Management Practices (BMP’s) for Stormwater Pollution Prevention
Beginning from mobilization, and throughout the entire construction of the project, erosion control
devices shall be installed to ensure minimal pollutant migration. These erosion control devices may
be installed in phases, or not at all, depending on actual conditions encountered at the site. It is
the responsibility of the Contractor to make the determination as to what practices should be
employed and when. In the event that a review agency deems BMPs to be insufficient, it shall be
the responsibility of the contractor to implement modifications as directed.
Best Management Practices (BMPs) are loosely defined as a method, activity, maintenance
procedure, or other management practice for reducing the amount of pollution entering a water
body. The term originated from rules and regulations in Section 208 of the Clean Water Act.
Details for Structural and Non-Structural BMPs have been included in Appendix B. These details
should be used for additional information on installation and maintenance of BMPs specified in this
report. It is also intended to serve as a resource for additional BMPs that may be appropriate for
the site that have not specifically been mentioned in the report.
3.3 Structural Practices for Erosion and Sediment Control
Structural BMPs are physical devices that are implemented to prevent erosion from happening or to
limit erosion once it occurs. These devices can be temporary or permanent, and installation of
individual components will vary depending on the stage of construction.
A table depicting construction sequence and BMP application/removal has been placed on the
“Dynamic Site Plan” to help document the implementation of these BMPs. Refer to the Stormwater
Management Plan Static Site Plan in the Appendix for the assumed location of all BMPs.
Construction Details for Temporary BMPs are located in the Appendix for reference.
Again, the final determination for which BMP’s will be installed, where they will be located, and
when they will be installed shall be made by the Contractor, along with all documentation
throughout the construction process.
Silt Fencing (Phase I)
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 5
Silt fencing shall be provided to prevent migration of sediment off-site or into adjacent properties.
All silt fencing shall be installed prior to any land disturbing activity (demolition, stockpiling,
stripping, grading, etc.). Silt fencing is to be installed prior to site excavation or earthwork
activities.
Inspections of the silt fence should identify tears or holes in the material, and should check for
slumping fence or undercut areas that allow flows to bypass the fencing. Damaged sections of the
silt fence should be removed to maintain BMP effectiveness, typically before it reaches a depth of 6
inches.
It is suggested that silt fencing be located along north and east property lines, as well as around the
perimeter of Rain Garden 3/Pond 3 to protect the existing wetland area.
Sediment Control Log – aka “Straw Wattles” (Phase I)
A Sediment Control Log is a linear roll made of natural materials, such as straw, coconut fiber, or
other fibrous material trenched into the ground and held with a wooden stake. Sediment Control
Logs can be used in many instances. Examples include perimeter control for stockpiles, as part of
inlet protection designs, as check dams in small drainage ways, on disturbed slopes to shorten flow
lengths, or in lieu of silt fencing (where appropriate).
Sediment Control Logs should be inspected for excess sediment accumulation. Sediment should be
removed prior to reaching half the height of the log.
At a minimum, Sediment Control Logs should be used around soil stockpiles (including landscape
materials) and along the flowline of swales.
Vehicle Tracking Control Pads (Phase I)
Vehicle tracking control pads shall be provided to minimize tracking of mud and sediment onto
paved surfaces and neighboring roadways. All vehicle tracking control pads shall be installed prior
to any land disturbing activity (demolition – as necessary, stockpiling, stripping, grading, etc.).
Location of vehicle tracking control pads will be located at any and all existing and future vehicle
accesses being used during any of the construction phases. These locations will primarily be
dictated by gates or openings in the temporary construction fencing that is expected to be installed.
Vehicle tracking control pads are to be installed prior to demolition (as appropriate), site excavation
or earthwork activities.
Vehicle tracking pads should be inspected for degradation and aggregate material should be
replaced as needed. If the area becomes clogged with water, excess sediment should be removed.
Aggregate material should remain rough, and at no point should aggregate be allowed to compact in
a manner that causes the tracking pad to stop working as intended.
Suggested locations for vehicle tracking pads are at the proposed access points from Douglas Road
and Turnberry Road.
Inlet Protection (Phase I & II)
Inlet protection shall be provided for existing inlets to prevent sediment transport from adjacent
earthwork disturbance. Installation of these filters shall occur before adjacent earth disturbing
activities (Phase I implementation). Wattle type filters are to be implemented for new and existing
inlets where asphalt does not exist. For these inlets, if pavement is constructed adjacent to the
structure or if the area adjacent to the inlet is changed such that the wattle type filter is no longer
effective, it shall be the responsibility of the Contractor to ensure that an appropriate method is
used instead. For example, the wattle filter could be reused, or a gravel-block inlet filter may be
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 6
installed. It will be left to the discretion of the Contractor as to whether replacement of any inlet
filter is necessary.
Inlet protection should be inspected regularly for tears that can result in sediment entering an inlet.
Inlet protection should also be inspected for sediment accumulation upstream of the inlet, and
sediment should be removed when the less than half of the capacity is available, or per
manufacturer specifications.
The Contractor shall provide inlet protection for all proposed inlets as they are installed (Phase II
implementation). The Contractor shall also provide inlet protection for the nearest existing inlets
downstream of the proposed outfalls into Douglas Road, Turnberry Road and the outfall to No. Eight
Ditch.
Erosion Control Blankets (Phase II)
A temporary degradable rolled erosion control product composed of natural flexible fibers shall be
used on all seeded slopes 3:1 and greater (excluding mulched shrub bed areas). Erosion control
blankets should be utilized to provide erosion control and to facilitate vegetation establishment.
During installation, it is important to ensure that no gaps or voids exist under the material and that
all corners of the material are secured using stakes and trenching. Stakes should be made of
materials that are biodegradable. Continuous contact between the product and the soil is necessary
to avoid failure.
Erosion Control Blankets should be inspected regularly for signs of erosion, including beneath the
mat. If voids are apparent, they should be filled with suitable soil. Inspections should also identify
loose or damaged stakes, as well as loose portions of the blanket. If deficiencies are found, they
should be repaired or replaced.
Concrete Washout Area (Phase II)
A concrete washout should be provided on the site. The washout can be lined or unlined excavated
pits in the ground, commercially manufactured prefabricated containers, or aboveground holding
areas. The concrete washout must be located a minimum of 400 feet from any natural drainage
way or body of water, and at least 1000 feet from any wells or drinking water sources. Washout
areas should not be located in an area where shallow groundwater may be present. Contractor
shall clearly show the desired location and access to the Concrete Washout Area on the Stormwater
Management Plan - Dynamic Site Plan. Contractor shall place a Vehicle Tracking Pad if the
selected location for the Concrete Washout Area is detached from pavement. Clear signage
identifying the concrete washout should also be provided.
The Concrete Washout Area should be inspected regularly. Particular attention should be paid to
signage to ensure that the area is clearly marked. Confirmation that the washout is being used
should also be noted to ensure that other undesignated areas of the site are not being used
incorrectly as a concrete washout.
It is recommended that the concrete wash out pit be placed next to the vehicle tracking pad along
Douglas Road. This location is only a suggestion and can be relocated at the discretion of the
Contractor.
Permanent/Established Vegetation (Phase IV)
Permanent or established vegetation and landscaping is considered a permanent form of sediment
and erosion control for common open spaces, steep slopes and areas not exposed to prolonged
scour velocities, or acute incipient motion bed shear stresses that will create soil erosion, rill
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 7
formation and subsequent sediment transport. Areas where the previous conditions apply will
contain sufficient permanent BMPs, such as riprap or cobble mulch. Permanent vegetation shall
conform to the approved Landscape Plan prepared by Ripley Design Inc. Permanent/Established
vegetation and hardscape defines Phase IV of development.
3.4 Non-Structural Practices for Erosion and Sediment Control
Non-Structural BMPs are practices or activities that are implemented to prevent erosion from
happening or to limit erosion once it occurs. These BMPs can be a practice resulting in physical
change to the site, such as mulching or slope stabilization. They can also result in behavioral
changes on the site, such as changes to construction phasing to minimize exposure to weather
elements, or increased employee awareness gained through training.
Protection of Existing Vegetation (Phases I-IV)
Protection of existing vegetation on a construction site can be accomplished through installation of a
construction fence around the area requiring protection. In cases where up-gradient areas are
disturbed, it may also be necessary to install perimeter controls to minimize sediment loading to
sensitive areas such as wetlands.
Trees that are to remain after construction is complete must be protected. Most tree roots grow
within the top 12”-18” of soil, and soil compaction is a significant threat to tree health. As such,
particular care should be taken to avoid activities within the drip-line of the tree. Direct equipment
damage should also be prevented. The most effective way to ensure the health of trees is to
establish a protection zone at the drip-line of the tree to prevent unintended activity in the area
directly surrounding the tree.
Fencing should be inspected and repaired when needed. If damage occurs to a tree, an arborist
should be consulted on how to care for the tree. If a tree is damage beyond repair, the City Forester
should be consulted on remediation measures.
At a minimum, protection to all trees identified for retention on the approved landscape plans.
Stockpile Management (Phases I-III)
Stockpile management should be utilized to minimize erosion and sediment transport from soil
stockpiles. In general, soil stockpiles should be located a minimum of 100 feet from any drainage
way and 50 feet from any storm sewer inlets. Where practical, choose a stockpile location that will
remain undisturbed for the longest period of time as the phases of construction progress. Sediment
control BMPs should be placed around the perimeter of the stockpile, and a designated access point
on the upstream side of the stockpile should be identified. BMPs such as surface roughening,
temporary seeding, mulching, erosion control blankets, or soil binders should be used to stabilize
the stockpile surface.
As a part of stockpile management, regular inspections of the perimeter controls should be
completed. If BMPs have been utilized to stabilize the surface of the stockpile, they should be
inspected and repaired as needed.
The location of any temporary stockpiles shall be the responsibility of the SWMP Administrator.
Mulching (Phase I-III)
Mulching helps reduce erosion by protecting bare soil from rainfall impact, increasing infiltration,
and reducing runoff. Although often applied in conjunction with temporary or permanent seeding, it
can also be used for temporary stabilization of areas that cannot be reseeded due to seasonal
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 8
constraints. The most common type of mulch used is hay or grass that is crimped into the soil to
keep it secure. However, crimping may not be practical on slopes steeper than three to one
(3H:1V).
The Contractor shall mulch all planted areas within twenty-four (24) hours after planting. Only
weed-free and seed-free straw mulch may be used. Straw mulch should be applied at two (2) tons
per acre, and shall be adequately secured by crimping, tackifier, netting or blankets. Hydraulic
mulching may also be used on steep slopes or where access is limited. In the case that hydraulic
mulching is utilized, the Contractor shall use wood cellulose fibers mixed with water at two
thousands to two thousand five hundred (2,000-2,500) pounds per acre and organic tackifier at
one hundred to four hundred (100-400) pounds per acre.
The Contractor is responsible for applying wood chip mulch to all planted trees and shrubs as
shown on the approved Landscape Plans.
Wind Erosion/Dust Control (Phase I-IV)
Wind Erosion and Dust Control BMP’s help to keep soil particles from entering the air as a result of
land disturbing construction activities. Attached at the end of the Appendix B is the Fort Collins
Dust Prevention and Control Manual. The purpose of this manual is to establish minimum
requirements consistent with nationally recognize BMP’s for controlling fugitive dust emissions and
to describe applicable best management practices to prevent, minimize, and mitigate off-property
transport or off-vehicle transport of fugitive dust emissions pursuant to Chapter 12, Article X of the
Fort Collins City Code (§12-150 et. seq) for specific dust generating activities and sources.
Examples include use of a water truck or irrigation/sprinkler system to wet the top layer of disturbed
soil, seeding and mulching, soil binders, or wind fences.
Please refer to the last three pages of Appendix B for the Dust Control Plan. A Dust Control Plan is
required for all development projects or construction sites with greater than five (5) acres in size.
Street Sweeping (Phases I -IV)
Street sweeping should be used to remove sediment that has been tracked onto adjacent roadways.
Roadways should be inspected at least once a day, and sediment should be removed as needed. A
check of the area inlet protection should be completed after sweeping to ensure nothing was
displaced during sweeping operations. Street sweeping can reduce the sediment washed into the
existing storm drain system. Street sweeping may be necessary on the existing hardscape areas
which receive runoff from the disturbed areas.
Saw Cutting Pollution Prevention (Phase I)
The following protocol is recommended to prevent dust and slurry from asphalt and concrete saw
cutting activities from migrating into the existing storm drain system.
• Slurry and cuttings shall be vacuumed during cutting and surfacing operations
• Slurry and cuttings shall not remain on permanent concrete or asphalt pavement
overnight
• Slurry and cuttings shall not drain to any natural or constructed drainage conveyance
• Collected slurry and cuttings shall be disposed of in a manner that does not violate
groundwater or surface water standards
Good Housekeeping Practices (All phases)
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 9
Good housekeeping practices that will prevent pollution associated with solid, liquid, and hazardous
construction-related materials and wastes should be implemented throughout the project.
Examples of good housekeeping include providing an appropriate location for waste management
containers, establishing proper building material staging areas, designating paint and concrete
washout areas, establishing proper equipment/vehicle fueling and maintenance practices.
Development of a spill prevention and response plan is another example of Good Housekeeping
practices that should be used on the project. The following items are detailed examples of some of
the good housekeeping practices that should be utilized throughout the project. It should be noted
that a complete list of practices and detailed discussion regarding good housekeeping has been
included with Appendix B.
Street Sweeping and Vacuuming – Street sweeping and vacuuming should be used to remove
sediment that has been tracked onto adjacent roadways. Roadways should be inspected at least
once a day, and sediment should be removed as needed. A check of inlet protection should be
completed after sweeping to ensure nothing was displaced during sweeping operations.
Waste Management – Designate trash and bulk waste collection areas on-site. When possible,
materials should be recycled. Hazardous material waste should be segregated from other solid
waste. Waste collection areas should be located away from streets, gutters, watercourses, and
storm drains. Dumpsters should be located near site entrances to minimize traffic on disturbed
soils, and they should be placed on a level soil surface.
Establish Proper Building Material Handling and Staging areas – Clearly designate site areas for
staging and storage of building materials. Provide appropriate BMPs to ensure that spills or leaks
are contained.
Establish Proper Equipment/Vehicle Fueling and Maintenance Practices – If needed, create a
clearly designated on-site fueling and maintenance area that is clean and dry. Provide appropriate
BMPs to ensure that spills or leaks are contained.
3.5 Phased BMP Installation
It is important to recognize the four (4) major Development Phases as defined by the State of
Colorado’s Stormwater Discharge Permit (SDP). These four development phases (referred to as
Sequencing by the City of Fort Collins) have been distinguished to aid in the appropriate timing of
installation/implementation of BMPs at different stages of the construction process. These phases
are described as follows:
Phase I – Grading Stage; BMPs for initial installation of perimeter controls
Phase II – Infrastructure Stage; BMPs for utility, paving and curb installation
Phase III – Vertical Construction Stage; BMPs for individual building construction.
Phase IV – Permanent BMPs and final site stabilization.
The following is a rough estimate of the anticipated construction sequence for site improvements.
The schedule outlined below is subject to change as the project progresses and as determined by
the General Contractor.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 10
Table 1 – Preliminary Permit and Construction Schedule
TASK
BEGINNING
DATE
ENDING DATE
"BMP-PHASE OF
DEVELOPMENT"
Development Construction Permit
Issued by City of Fort Collins
March 2019 March 2019 I
Overlot Grading (Demolition) March 2019 March 2019 I
Utility Installation March 2019 April 2019 II
Building Construction April 2019 December 2019 III
Final Stabilization November 2019 December 2019 IV
Included in the back map pockets are five Site Plans: a “Static” Site Plan and four “Dynamic” Site
Plans. The “Static” plan serves to display the overall management plan all at once. However,
proper implementation of BMPs does not occur at once, and certain BMPs may move location in
the construction process; therefore, the “Dynamic” Site Plans are intended for the Contractor to
write in the BMP symbols to document the location and time the BMPs are installed and
maintained throughout the entire construction process.
3.6 Material Handling and Spill Prevention
Potential pollution sources, as discussed in earlier sections, are to be to be identified by the
Contractor. Spill prevention procedures are to be determined and put in place prior to construction
by the Contractor. A spill and flooding response procedure must also be determined and put in
place prior to construction by the Contractor. Additionally, steps should be taken to reduce the
potential for leaks and spills to come in contact with stormwater runoff, such as storing and
handling toxic materials in covered areas or by storing chemicals within berms or other secondary
containment devices.
A notification procedure must be put in place by the Contractor, by which workers would first notify
the site construction superintendent, who would then notify the SWMP Administrator. Depending
on the severity of the spill, the site construction superintendent and SWMP Administrator would
possibly notify the Colorado Department of Public Health and Environment - Water Quality Control
Division, downstream water users, or other appropriate agencies. The release of any chemical, oil,
petroleum product, sewage, etc., which enter waters of the State of Colorado (which include
surface water, ground water, and dry gullies or storm sewers leading to surface water) must be
reported immediately to the Division’s emergency spill reporting line at (877) 518-5608. All
spills that will require cleanup, even if the spill is minor and does not need to be reported to the
state, should still be reported to the City of Fort Collins Utilities office at 970-221-6700.
While not expected with this project, it will be the responsibility of the Contractor to designate a
fueling area and take the necessary precautions to ensure that no stormwater pollution occurs in the
event that a fueling area is needed. Fueling areas shall be located a minimum 100 feet from all
drainage courses. A 12-inch high compacted earthen ridge capable of retaining potential spills
shall enclose fueling areas. Other secondary containment devices can be used instead of the
earthen ridge. The area shall be covered with a non-porous lining to prevent soil contamination.
Printed instructions for cleanup procedures shall be posted in the fueling area and appropriate fuel
absorbents shall be available along with containers for used absorbents within the fueling area.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 11
3.7 Dedicated Concrete or Asphalt Batch Plant
There are not any dedicated concrete or asphalt batch plants anticipated with this project. In the
event that a plant is needed, the Contractor should be aware that additional permitting will be
required. In particular, an Air Pollutant Emission Notice (APEN) will need to be obtained from the
CDPHE.
3.8 Vehicle Tracking Control
In addition to the vehicle tracking pads discussed previously, additional measures can be taken to
minimize and control sediment discharges from the site due to vehicle tracking. These measures
can include fencing around the site to control access points. Regular street sweeping can also be
used to minimize the transmission of sediment from the site due to vehicles leaving the site. The
use of gravel parking areas and wash racks can also be implemented to ensure minimal vehicle
tracking from the site.
3.9 Waste Management and Disposal
It will be the responsibility of the Contractor to designate a concrete truck chute washout area and
to clearly identify that area. Detailed information about the design and maintenance of the Concrete
Washout can be found under the Structural Practices section of this report. At no time should
untreated wash water be allowed to discharge from the site or to enter a storm drain system or
stream. Upon completion of construction activities the concrete washout material shall be removed
and properly disposed of prior to the area being restored.
Any waste material that currently exists on the site or that is generated by construction will be
disposed of in such a manner as to not cause pollutants in stormwater discharges. If waste is to be
stored on-site, it shall be in an area located a minimum of 100 feet from all drainage courses.
Whenever waste is not stored in a non-porous container, it shall be in an area enclosed by a 12-
inch high compacted earthen ridge or some other approved secondary containment device. The area
shall be covered with a non-porous lining to prevent soil contamination. Whenever precipitation is
predicted, the waste shall be covered with a non-porous cover, anchored on all sides to prevent its
removal by wind, in order to prevent precipitation from leaching out potential pollutants from the
waste. On-site waste disposal practices, such as dumpsters, should be covered or otherwise
contained as to prevent dispersion of waste materials from wind. It shall also be the responsibility
of the Contractor to maintain a clean jobsite as to prevent dispersion of waste material and potential
pollutants into adjacent properties or waterways.
The location of, and protective measures for, temporary restroom facilities shall be the responsibility
of the SWMP Administrator.
3.10 Groundwater and Stormwater Dewatering
The BMPs selected for construction dewatering vary depending on the site-specific features, such as
soils, topography, discharge quantities, and discharge location. Typically, dewatering involves
pumping water from an inundated area to a BMP, prior to the water being released downstream
into a receiving waterway, sediment basin, or well-vegetated area. Acceptable BMPs included
discharging water into a sediment trap or basin, using a dewatering filter bag, or using a series of
sediment logs. A settlement tank or an active treatment system can also be utilized. Another
commonly used method to handle the pumped water is the “sprinkler method,” which involves
applying the water to vegetated areas through a perforated discharge hose. Dispersal from a water
truck for dust control can also be used to disperse the pumped water.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 12
4.0 Final Stabilization and Long-Term Stormwater Management
4.1 Final Stabilization
All disturbed areas will be seeded, crimped and mulched. Soil amendments such as compost, peat,
aged manure, or other similar materials, shall also be utilized. Soil amendments shall be tilled into
the soil to a minimum depth of 6”, and should comply with the requirements found in City Code
Section 12-132 (refer also to Land Use Code 3.8.21). As defined by the Colorado Department of
Public Health and Environment (CDPHE) in the General Permit Application for Stormwater
Discharges, “Final stabilization is reached when all soil disturbing activities at the site have been
completed, and uniform vegetative cover has been established with a density of at least 70 percent
of pre-disturbance levels or equivalent permanent, physical erosion reduction methods have been
employed.”
Table 2 - Native Grass Seed Mix
Preferred
Varieties
Seeded Rate
(lbs. per acre,
drilled)
PLS
Seeded/acre
Leymus Cinereus Great Basin Wilrye Mangar 3 285,000
Nassella Viridula Green Needlegrass Lodorm 2 362,000
Chnatherum Hymenoides Indian Ricegrass Paloma, Nezpar 1 188,000
Elymus Trachycaulus Slender Wheatgrass Primar, Revenue 2 320,000
Elymus Lanceolatus Thickspike Wheatgrass Critana 3 580,500
Pascopyrum Smithii Western Wheatgrass Arriba, Barton 4 504,000
Totals 15 2,239,500
Species
4.2 Long-Term Stormwater Management
Long-term stormwater management will include permanent erosion control facilities at the outfall to
the No. Eight Ditch. All disturbed areas will receive permanent paving or will be vegetated per the
Landscape Plan.
5.0 Inspection, Maintenance and Record Keeping
5.1 BMP Inspection
All temporary erosion control facilities shall be inspected at a minimum of once every two (2) weeks
and after each significant storm event or snowmelt. Repairs or reconstruction of BMPs, as
necessary, shall occur as soon as possible in order to ensure the continued performance of their
intended function. It is the responsibility of the SWMP Administrator to conduct bi-weekly
inspections, maintain BMPs if needed, to keep records of site conditions and inspections, and to
update the SWMP as necessary.
The construction site perimeter, disturbed areas, all applicable/installed erosion and sediment
control measures, and areas used for material storage that are exposed to precipitation shall be
inspected for evidence of, or the potential for, pollutants entering the drainage system. Erosion and
sediment control measures identified in the SWMP shall be observed to ensure that they are
operating correctly. Attention should be paid to areas that have a significant potential for
stormwater pollution, such as demolition areas, concrete washout locations, and vehicle entries to
the site. The inspection must be documented to ensure compliance with the permit requirements.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 13
5.2 BMP Maintenance
Any BMP’s not operating in accordance with the SWMP must be addressed as soon as possible,
immediately in most cases, to prevent the discharge of pollutants. If modifications are necessary,
such modifications shall be documented so that the SWMP accurately reflects on-site conditions.
The SWMP needs to accurately represent field conditions at all times.
Uncontrolled releases of mud, muddy water, or measurable amounts of sediment found off-site will
be recorded with a brief explanation of the measures taken to clean-up the sediment that has left
the site, as well as the measures taken to prevent future releases. This record shall be made
available to the appropriate public agencies (Colorado Department of Public Health and
Environment, Water Quality Control Division; Environmental Protection Agency; City of Fort Collins;
etc.) upon request.
Preventative maintenance of all temporary and permanent erosion control BMPs shall be provided
in order to ensure the continued performance of their intended function. Temporary erosion control
measures are to be removed after the site has been sufficiently stabilized as determined by the City
of Fort Collins. Maintenance activities and actions to correct problems shall be noted and recorded
during inspections.
Inspection and maintenance procedures specific to each BMP identified with this SWMP are
discussed in Section 3. Details have also been included with Appendix B.
5.3 Record Keeping
Documentation of site inspections must be maintained. The following items are to be recorded and
kept with the SWMP:
• Date of Inspection
• Name(s) and title(s) of personnel making the inspection
• Location(s) of sediment discharges or other pollutants from the site
• Location(s) of BMP’s that need to be maintained
• Location(s) of BMP’s that failed to operate as designed or proved inadequate
• Locations(s) where additional BMP’s are needed that were not in place at the time of inspection
• Deviations from the minimum inspection schedule
• Descriptions of corrective action taken to remedy deficiencies that have been identified
• The report shall contain a signed statement indicating the site is in compliance with the permit to the
best of the signer’s knowledge and belief after corrective actions have been taken.
Provided within Appendix E of this SWMP is an Example Inspection Log to aid in the record keeping
of BMP inspections and maintenance. Photographs, field notebooks, drawings and maps should be
included by the SWMP Administrator when appropriate.
In addition to the Inspection Log, records should be kept documenting:
• BMP maintenance and operation
• Stormwater contamination
• Contacts with suppliers
• Notes on the need for and performance of preventive maintenance and other repairs
• Implementation of specific items in the SWMP
• Training events (given or attended)
• Events involving materials handling and storage
• Contacts with regulatory agencies and personnel
• Notes of employee activities, contact, notifications, etc.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 14
Records of spills, leaks, or overflows that result in the discharge of pollutants must be documented
and maintained. A record of other spills that are responded to, even if they do not result in a
discharge of pollutants, should be made. Information that should be recorded for all occurrences
includes the time and date, weather conditions, reasons for the spill, etc. Some spills may need to
be reported to authorities immediately. Specifically, a release of any chemical, oil, petroleum
product, sewage, etc., which may enter waters of the State of Colorado (which include surface
water, ground water and dry gullies or storm sewers leading to surface water) must be reported to
the CDPHE.
Additionally, the “Dynamic Site Plan” is intended to be a “living” document where the SWMP
Administrator can hand write the location of BMPs as they are installed to appropriately reflect the
current site conditions. Also on the “Dynamic Site Plan” is a “Table of Construction Sequence and
BMP Application/Removal” that the SWMP Administrator can use to document when BMPs were
installed or removed in conjunction with construction activities. These items have been included as
an aid to the SWMP Administrator, and other methods of record keeping are at his or her discretion.
This Stormwater Management Plan (both the text and map) is not a static document. It
is a dynamic device intended to be kept current and logged as construction takes place.
It shall be the responsibility of the SWMP Administrator and/or the permit holder (or
applicant thereof) to ensure the plan is properly maintained and followed. Diligent
administration is critical, including processing the Notice to Proceed and noting on the
Stormwater Management Plan the dates that various construction activities occur and
respective BMPs are installed and/or removed.
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 15
6.0 Additional SWMP and BMP Resources
Urban Drainage and Flood Control District
Urban Storm Drainage Criteria Manual - Volume 3 “Best Management Practices”
Colorado Department of Transportation
Erosion Control and Stormwater Quality Guide
BMP Field Academy
EPA Menu of BMP’s
Construction Site Storm Water Runoff Control
International Stormwater Best Management (BMP) Database
Rocky Mountain Education Center
Rocky Mountain Education Center
Red Rocks Community College, Lakewood
Keep It Clean Partnership
Boulder
ADDRESS:
200 S. College Ave. Suite 10
Fort Collins, CO 80524
PHONE: 970.221.4158
FAX: 970.221.4159
WEBSITE:
www.northernengineering.com
Country Club Reserve
Stormwater Management Plan 16
References
1. Final Drainage Report for Country Club Reserve, Northern Engineering Services,
November 21, 2018 (NE Project No. 1324-001)
2. Soil Resource Report for Larimer County Area, Colorado, Natural Resources
Conservation Service, United States Department of Agriculture.
3. Preliminary Geotechnical Exploration Report, Earth Engineering Consultants, INC.,
February 22, 2006 (Project No. 1062013)
4. Urban Storm Drainage Criteria Manual, Volumes 1-3, Urban Drainage and Flood Control
District, Water Resources Publications, LLC., Denver, Colorado, updated August 2018.
APPENDIX A
SITE MAPS
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W
V
.P.
V.P.
A.R.V.
GAS
GAS
V.P. V.P.
X X
X X
X
X
G
G
G
G
G
G
G
G
G
G
G G
G G G
G
G
G
G
G
G
G
G
G
G
G
G
E
E
E
E
E
E
E
E
E E E
E
E
E
E E E
E
E
E
E
4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W
V
.P.
V.P.
A.R.V.
GAS
X
X
X X
X
X
G
G G G G G
G G
E E
E
E
E
E
E E E E
E E E E E E
E
E
E
E E
E
E
E
E
WV
H
Y
D
WV
WV
X
X
X X
X X
X X
X
X
X
M
X
X X
X
X X
X X X X
F
E
S
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W 4" W
4" W 4" W
4" W 4" W
V
.P.
WV
WV
WV
WV
WV
WV
X
X
F
E
S
M
F
E
S
X X X X X X X X X
W
S
O
X
V.P.
V
AULT
CABLE
BOX
CABLE
H2O
X
OHE
OHE
OHE
OHE OHE OHE
ST
B
B
10"W 1976 (AC)
4" (AC)
10"W 1976 (AC)
4" (AC)
W
W W W
W W
W W W
W
14"W 1976 (AC)
14"W 1976 (AC)
LOD LOD
LOD
LOD
LOD
LOD
GAS
X
X
V.P. V.P.
X
X X
X
G
G
G G
G
G G G
G
G
G
G G G
G
G
G
G
G
G
G
G
G
G
G
G
G
G
G
E E
E
E
E
E
E
E E
E
E
E
E
E E
E
E
E E
E E E E
E
E
E
E
E
E E
E
X
X X X X
X
X X
X
X
V.P.
X X X
X
X
G
G
G
G
G
G
G
G G G
G G G
G G
G
G G
E E
E
E
E E E E E
E
E
E
E
E E
E
E
X
X
X X
X
X X X X X
X
X
V
.P.
X
M
GAS
X
X X
OHE OHE
OHE
OHE OHE
OHE
B
B
ST ST
W
W
W W W
W W
W
W W
W
W W W
14"W 1976 (AC)
LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD LOD
LOD LOD LOD
APPENDIX B
EROSION CONTROL DETAILS
EC2
EROSION CONTROL DETAILS
14
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
3'-4'
ADJACENT ROLLS SHALL
TIGHTLY ABUT
W1 NOTES:
INSTALLATION:
WHEN INSTALLING RUNNING LENGTHS OF WATTLES, BUTT THE SECOND
WATTLE TIGHTLY AGAINST THE FIRST, DO NOT OVERLAP THE ENDS. STAKE
THE WATTLES AT EACH END AND FOUR FOOT ON CENTER. FOR EXAMPLE:
A 25 FOOT WATTLE USES 6 STAKES
A 20 FOOT WATTLE USES 5 STAKES
A 12 FOOT WATTLE USES 4 STAKES
STAKES SHOULD BE DRIVEN THROUGH THE MIDDLE OF THE WATTLE.
LEAVING 2 - 3 INCHES OF THE STAKE PROTRUDING ABOVE THE WATTLE. A
HEAVY SEDIMENT LOAD WILL TEND TO PICK THE WATTLE UP AND COULD
PULL IT OFF THE STAKES IF THEY ARE DRIVEN DOWN TOO LOW. IT MAY BE
NECESSARY TO MAKE A HOLE IN THE WATTLE WITH A PICK END OF YOUR
MADDOX IN ORDER TO GET THE STAKE THROUGH THE STRAW. WHEN
STRAW WATTLES ARE USED FOR FLAT GROUND APPLICATIONS, DRIVE THE
STAKES STRAIGHT DOWN; WHEN INSTALLING WATTLES ON SLOPES, DRIVE
THE STAKES PERPENDICULAR TO THE SLOPE.
DRIVE THE FIRST END STAKE OF THE SECOND WATTLE AT AN ANGLE
TOWARD THE FIRST WATTLE IN ORDER TO HELP ABUT THEM TIGHTLY
TOGETHER. IF YOU HAVE DIFFICULTY DRIVING THE STAKE INTO EXTREMELY
HARD OR ROCKY SLOPES, A PILOT BAR MAY BE NEEDED TO BEGIN THE
STAKE HOLE.
1"x 1" WOOD STAKES
18"-24"
BAILING WIRE OR
NYLON ROPE
Silt Fence (SF) SC-1
November 2010 Urban Drainage and Flood Control District SF-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph SF-1. Silt fence creates a sediment barrier, forcing
sheet flow runoff to evaporate or infiltrate.
Description
A silt fence is a woven geotextile fabric
attached to wooden posts and trenched
into the ground. It is designed as a
sediment barrier to intercept sheet flow
runoff from disturbed areas.
Appropriate Uses
A silt fence can be used where runoff is
conveyed from a disturbed area as sheet
flow. Silt fence is not designed to
receive concentrated flow or to be used
as a filter fabric. Typical uses include:
Down slope of a disturbed area to
accept sheet flow.
Along the perimeter of a receiving
water such as a stream, pond or
wetland.
At the perimeter of a construction site.
Design and Installation
Silt fence should be installed along the contour of slopes so that it intercepts sheet flow. The maximum
recommended tributary drainage area per 100 lineal feet of silt fence, installed along the contour, is
approximately 0.25 acres with a disturbed slope length of up to 150 feet and a tributary slope gradient no
steeper than 3:1. Longer and steeper slopes require additional measures. This recommendation only
applies to silt fence installed along the contour. Silt fence installed for other uses, such as perimeter
control, should be installed in a way that will not produce concentrated flows. For example, a "J-hook"
installation may be appropriate to force runoff to pond and evaporate or infiltrate in multiple areas rather
than concentrate and cause erosive conditions parallel to the silt fence.
See Detail SF-1 for proper silt fence installation, which involves proper trenching, staking, securing the
fabric to the stakes, and backfilling the silt fence. Properly installed silt fence should not be easily pulled
out by hand and there should be no gaps between the ground and the fabric.
Silt fence must meet the minimum allowable strength requirements, depth of installation requirement, and
other specifications in the design details. Improper installation
of silt fence is a common reason for silt fence failure; however,
when properly installed and used for the appropriate purposes, it
can be highly effective.
Silt Fence
Functions
Erosion Control No
Sediment Control Yes
Site/Material Management No
SC-1 Silt Fence (SF)
SF-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Photograph SF-2. When silt fence is not installed along
the contour, a "J-hook" installation may be appropriate
to ensure that the BMP does not create concentrated
flow parallel to the silt fence. Photo courtesy of Tom
Gore.
Maintenance and Removal
Inspection of silt fence includes observing the
material for tears or holes and checking for slumping
fence and undercut areas bypassing flows. Repair of
silt fence typically involves replacing the damaged
section with a new section. Sediment accumulated
behind silt fence should be removed, as needed to
maintain BMP effectiveness, typically before it
reaches a depth of 6 inches.
Silt fence may be removed when the upstream area
has reached final stabilization.
Silt Fence (SF) SC-1
November 2010 Urban Drainage and Flood Control District SF-3
Urban Storm Drainage Criteria Manual Volume 3
SC-1 Silt Fence (SF)
SF-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Sediment Control Log (SCL) SC-2
November 2015 Urban Drainage and Flood Control District SCL-1
Urban Storm Drainage Criteria Manual Volume 3
Photographs SCL-1 and SCL-2. Sediment control logs used as 1) a
perimeter control around a soil stockpile; and, 2) as a "J-hook"
perimeter control at the corner of a construction site.
Description
A sediment control log is a linear roll
made of natural materials such as
straw, coconut fiber, or compost. The
most common type of sediment control
log has straw filling and is often
referred to as a "straw wattle." All
sediment control logs are used as a
sediment barrier to intercept sheet flow
runoff from disturbed areas.
Appropriate Uses
Sediment control logs can be used in
the following applications to trap
sediment:
As perimeter control for stockpiles
and the site.
As part of inlet protection designs.
As check dams in small drainage
ditches. (Sediment control logs
are not intended for use in
channels with high flow
velocities.)
On disturbed slopes to shorten flow
lengths (as an erosion control).
As part of multi-layered perimeter control along a receiving water such as a stream, pond or wetland.
Sediment control logs work well in combination with other layers of erosion and sediment controls.
Design and Installation
Sediment control logs should be installed along the contour to avoid concentrating flows. The maximum
allowable tributary drainage area per 100 lineal feet of sediment control log, installed along the contour, is
approximately 0.25 acres with a disturbed slope length of up to 150 feet and a tributary slope gradient no
steeper than 3:1. Longer and steeper slopes require additional measures. This recommendation only
applies to sediment control logs installed along the contour. When installed for other uses, such as
perimeter control, it should be installed in a way that will not
produce concentrated flows. For example, a "J-hook"
installation may be appropriate to force runoff to pond and
evaporate or infiltrate in multiple areas rather than concentrate
and cause erosive conditions parallel to the BMP.
Sediment Control Log
Functions
Erosion Control Moderate
Sediment Control Yes
Site/Material Management No
SC-2 Sediment Control Log (SCL)
SCL-2 Urban Drainage and Flood Control District November 2015
Urban Storm Drainage Criteria Manual Volume 3
Although sediment control logs initially allow runoff to flow through the BMP, they can quickly become
a barrier and should be installed as if they are impermeable.
Design details and notes for sediment control logs are provided in the following details. Sediment logs
must be properly installed per the detail to prevent undercutting, bypassing and displacement. When
installed on slopes, sediment control logs should be installed along the contours (i.e., perpendicular to
flow).
Improper installation can lead to poor performance. Be sure that sediment control logs are properly
trenched (if lighter than 8 lb/foot), anchored and tightly jointed.
Maintenance and Removal
Be aware that sediment control logs will eventually degrade. Remove accumulated sediment before the
depth is one-half the height of the sediment log and repair damage to the sediment log, typically by
replacing the damaged section.
Once the upstream area is stabilized, remove and properly dispose of the logs. Areas disturbed beneath
the logs may need to be seeded and mulched. Sediment control logs that are biodegradable may
occasionally be left in place (e.g., when logs are used in conjunction with erosion control blankets as
permanent slope breaks). However, removal of sediment control logs after final stabilization is typically
appropriate when used in perimeter control, inlet protection and check dam applications. Compost from
compost sediment control logs may be spread over the area and seeded as long as this does not cover
newly established vegetation.
Sediment Control Log (SCL) SC-2
November 2015 Urban Drainage and Flood Control District SCL-3
Urban Storm Drainage Criteria Manual Volume 3
SC-2 Sediment Control Log (SCL)
SCL-4 Urban Drainage and Flood Control District November 2015
Urban Storm Drainage Criteria Manual Volume 3
Sediment Control Log (SCL) SC-2
November 2015 Urban Drainage and Flood Control District SCL-5
Urban Storm Drainage Criteria Manual Volume 3
SC-2 Sediment Control Log (SCL)
SCL-6 Urban Drainage and Flood Control District November 2015
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph VTC-1. A vehicle tracking control pad constructed with
properly sized rock reduces off-site sediment tracking.
Descr iption
Vehicle tracking controls provide
stabilized construction site access where
vehicles exit the site onto paved public
roads. An effective vehicle tracking
control helps remove sediment (mud or
dirt) from vehicles, reducing tracking onto
the paved surface.
Appropriate Uses
Implement a stabilized construction
entrance or vehicle tracking control where
frequent heavy vehicle traffic exits the
construction site onto a paved roadway. An
effective vehicle tracking control is
particularly important during the following conditions:
Wet weather periods when mud is easily tracked off site.
During dry weather periods where dust is a concern.
When poorly drained, clayey soils are present on site.
Although wheel washes are not required in designs of vehicle tracking controls, they may be needed at
particularly muddy sites.
Design and Installation
Construct the vehicle tracking control on a level surface. Where feasible, grade the tracking control
towards the construction site to reduce off-site runoff. Place signage, as needed, to direct construction
vehicles to the designated exit through the vehicle tracking control. There are several different types of
stabilized construction entrances including:
VTC-1. Aggregate Vehicle Tracking Control. This is a coarse-aggregate surfaced pad underlain by a
geotextile. This is the most common vehicle tracking control, and when properly maintained can be
effective at removing sediment from vehicle tires.
VTC-2. Vehicle Tracking Control with Construction Mat or Turf Reinforcement Mat. This type of
control may be appropriate for site access at very small construction sites with low traffic volume over
vegetated areas. Although this application does not typically remove sediment from vehicles, it helps
protect existing vegetation and provides a stabilized entrance.
Vehicle Tracking Control
Functions
Erosion Control Moderate
Sediment Control Yes
Site/Material Management Yes
SM-4 Vehicle Tracking Control (VTC)
VTC-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Photograph VTC-2. A vehicle tracking control pad with wheel wash
facility. Photo courtesy of Tom Gore.
VTC-3. Stabilized Construction Entrance/Exit with Wheel Wash. This is an aggregate pad, similar
to VTC-1, but includes equipment for tire washing. The wheel wash equipment may be as simple as
hand-held power washing equipment to more advance proprietary systems. When a wheel wash is
provided, it is important to direct wash water to a sediment trap prior to discharge from the site.
Vehicle tracking controls are sometimes installed in combination with a sediment trap to treat runoff.
Maintenance and Removal
Inspect the area for degradation and
replace aggregate or material used for a
stabilized entrance/exit as needed. If the
area becomes clogged and ponds water,
remove and dispose of excess sediment
or replace material with a fresh layer of
aggregate as necessary.
With aggregate vehicle tracking controls,
ensure rock and debris from this area do
not enter the public right-of-way.
Remove sediment that is tracked onto the
public right of way daily or more
frequently as needed. Excess sediment
in the roadway indicates that the
stabilized construction entrance needs
maintenance.
Ensure that drainage ditches at the
entrance/exit area remain clear.
A stabilized entrance should be removed only when there is no longer the potential for vehicle tracking to
occur. This is typically after the site has been stabilized.
When wheel wash equipment is used, be sure that the wash water is discharged to a sediment trap prior to
discharge. Also inspect channels conveying the water from the wash area to the sediment trap and
stabilize areas that may be eroding.
When a construction entrance/exit is removed, excess sediment from the aggregate should be removed
and disposed of appropriately. The entrance should be promptly stabilized with a permanent surface
following removal, typically by paving.
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-3
Urban Storm Drainage Criteria Manual Volume 3
SM-4 Vehicle Tracking Control (VTC)
VTC-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-5
Urban Storm Drainage Criteria Manual Volume 3
SM-4 Vehicle Tracking Control (VTC)
VTC-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Inlet Protection (IP) SC-6
August 2013 Urban Drainage and Flood Control District IP-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph IP-1. Inlet protection for a curb opening inlet.
Description
Inlet protection consists of permeable
barriers installed around an inlet to
filter runoff and remove sediment prior
to entering a storm drain inlet. Inlet
protection can be constructed from rock
socks, sediment control logs, silt fence,
block and rock socks, or other materials
approved by the local jurisdiction.
Area inlets can also be protected by
over-excavating around the inlet to
form a sediment trap.
Appropriate Uses
Install protection at storm sewer inlets
that are operable during construction.
Consider the potential for tracked-out
sediment or temporary stockpile areas to contribute sediment to inlets when determining which inlets
must be protected. This may include inlets in the general proximity of the construction area, not limited
to downgradient inlets. Inlet protection is not a stand-alone BMP and should be used in conjunction with
other upgradient BMPs.
Design and Installation
To function effectively, inlet protection measures must be installed to ensure that flows do not bypass the
inlet protection and enter the storm drain without treatment. However, designs must also enable the inlet
to function without completely blocking flows into the inlet in a manner that causes localized flooding.
When selecting the type of inlet protection, consider factors such as type of inlet (e.g., curb or area, sump
or on-grade conditions), traffic, anticipated flows, ability to secure the BMP properly, safety and other
site-specific conditions. For example, block and rock socks will be better suited to a curb and gutter
along a roadway, as opposed to silt fence or sediment control logs, which cannot be properly secured in a
curb and gutter setting, but are effective area inlet protection measures.
Several inlet protection designs are provided in the Design Details. Additionally, a variety of proprietary
products are available for inlet protection that may be approved for use by local governments. If
proprietary products are used, design details and installation procedures from the manufacturer must be
followed. Regardless of the type of inlet protection selected, inlet protection is most effective when
combined with other BMPs such as curb socks and check dams. Inlet protection is often the last barrier
before runoff enters the storm sewer or receiving water.
Design details with notes are provided for these forms of inlet
protection:
IP-1. Block and Rock Sock Inlet Protection for Sump or On-grade
Inlets
IP-2. Curb (Rock) Socks Upstream of Inlet Protection, On-grade
Inlets
Inlet Protection
(various forms)
Functions
Erosion Control No
Sediment Control Yes
Site/Material Management No
SC-6 Inlet Protection (IP)
IP-2 Urban Drainage and Flood Control District August 2013
Urban Storm Drainage Criteria Manual Volume 3
IP-3. Rock Sock Inlet Protection for Sump/Area Inlet
IP-4. Silt Fence Inlet Protection for Sump/Area Inlet
IP-5. Over-excavation Inlet Protection
IP-6. Straw Bale Inlet Protection for Sump/Area Inlet
CIP-1. Culvert Inlet Protection
Propriety inlet protection devices should be installed in accordance with manufacturer specifications.
More information is provided below on selecting inlet protection for sump and on-grade locations.
Inlets Located in a Sump
When applying inlet protection in sump conditions, it is important that the inlet continue to function
during larger runoff events. For curb inlets, the maximum height of the protective barrier should be lower
than the top of the curb opening to allow overflow into the inlet during larger storms without excessive
localized flooding. If the inlet protection height is greater than the curb elevation, particularly if the filter
becomes clogged with sediment, runoff will not enter the inlet and may bypass it, possibly causing
localized flooding, public safety issues, and downstream erosion and damage from bypassed flows.
Area inlets located in a sump setting can be protected through the use of silt fence, concrete block and
rock socks (on paved surfaces), sediment control logs/straw wattles embedded in the adjacent soil and
stacked around the area inlet (on pervious surfaces), over-excavation around the inlet, and proprietary
products providing equivalent functions.
Inlets Located on a Slope
For curb and gutter inlets on paved sloping streets, block and rock sock inlet protection is recommended
in conjunction with curb socks in the gutter leading to the inlet. For inlets located along unpaved roads,
also see the Check Dam Fact Sheet.
Maintenance and Removal
Inspect inlet protection frequently. Inspection and maintenance guidance includes:
Inspect for tears that can result in sediment directly entering the inlet, as well as result in the contents
of the BMP (e.g., gravel) washing into the inlet.
Check for improper installation resulting in untreated flows bypassing the BMP and directly entering
the inlet or bypassing to an unprotected downstream inlet. For example, silt fence that has not been
properly trenched around the inlet can result in flows under the silt fence and directly into the inlet.
Look for displaced BMPs that are no longer protecting the inlet. Displacement may occur following
larger storm events that wash away or reposition the inlet protection. Traffic or equipment may also
crush or displace the BMP.
Monitor sediment accumulation upgradient of the inlet protection.
Inlet Protection (IP) SC-6
August 2013 Urban Drainage and Flood Control District IP-3
Urban Storm Drainage Criteria Manual Volume 3
Remove sediment accumulation from the area upstream of the inlet protection, as needed to maintain
BMP effectiveness, typically when it reaches no more than half the storage capacity of the inlet
protection. For silt fence, remove sediment when it accumulates to a depth of no more than 6 inches.
Remove sediment accumulation from the area upstream of the inlet protection as needed to maintain
the functionality of the BMP.
Propriety inlet protection devices should be inspected and maintained in accordance with
manufacturer specifications. If proprietary inlet insert devices are used, sediment should be removed
in a timely manner to prevent devices from breaking and spilling sediment into the storm drain.
Inlet protection must be removed and properly disposed of when the drainage area for the inlet has
reached final stabilization.
SC-6 Inlet Protection (IP)
IP-4 Urban Drainage and Flood Control District August 2013
Urban Storm Drainage Criteria Manual Volume 3
Inlet Protection (IP) SC-6
August 2013 Urban Drainage and Flood Control District IP-5
Urban Storm Drainage Criteria Manual Volume 3
SC-6 Inlet Protection (IP)
IP-6 Urban Drainage and Flood Control District August 2013
Urban Storm Drainage Criteria Manual Volume 3
Inlet Protection (IP) SC-6
August 2013 Urban Drainage and Flood Control District IP-7
Urban Storm Drainage Criteria Manual Volume 3
SC-6 Inlet Protection (IP)
IP-8 Urban Drainage and Flood Control District August 2013
Urban Storm Drainage Criteria Manual Volume 3
Rolled Erosion Control Products (RECP) EC-6
November 2010 Urban Drainage and Flood Control District RECP-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph RECP-1. Erosion control blanket protecting the slope from
erosion and providing favorable conditions for revegetation.
Description
Rolled Erosion Control Products
(RECPs) include a variety of
temporary or permanently installed
manufactured products designed to
control erosion and enhance vegetation
establishment and survivability,
particularly on slopes and in channels.
For applications where natural
vegetation alone will provide sufficient
permanent erosion protection,
temporary products such as netting,
open weave textiles and a variety of
erosion control blankets (ECBs) made
of biodegradable natural materials
(e.g., straw, coconut fiber) can be used.
For applications where natural
vegetation alone will not be sustainable under expected flow conditions, permanent rolled erosion control
products such as turf reinforcement mats (TRMs) can be used. In particular, turf reinforcement mats are
designed for discharges that exert velocities and sheer stresses that exceed the typical limits of mature
natural vegetation.
Appropriate Uses
RECPs can be used to control erosion in conjunction with revegetation efforts, providing seedbed
protection from wind and water erosion. These products are often used on disturbed areas on steep
slopes, in areas with highly erosive soils, or as part of drainageway stabilization. In order to select the
appropriate RECP for site conditions, it is important to have a general understanding of the general types
of these products, their expected longevity, and general characteristics.
The Erosion Control Technology Council (ECTC 2005) characterizes rolled erosion control products
according to these categories:
Mulch control netting: A planar woven natural fiber or extruded geosynthetic mesh used as a
temporary degradable rolled erosion control product to anchor loose fiber mulches.
Open weave textile: A temporary degradable rolled erosion control product composed of processed
natural or polymer yarns woven into a matrix, used to provide erosion control and facilitate
vegetation establishment.
Erosion control blanket (ECB): A temporary
degradable rolled erosion control product composed of
processed natural or polymer fibers which are
mechanically, structurally or chemically bound together
to form a continuous matrix to provide erosion control
and facilitate vegetation establishment. ECBs can be
further differentiated into rapidly degrading single-net
and double-net types or slowly degrading types.
Rolled Erosion Control Products
Functions
Erosion Control Yes
Sediment Control No
Site/Material Management No
EC-6 Rolled Erosion Control Products (RECP)
RECP-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Turf Reinforcement Mat (TRM): A rolled erosion control product composed of non-degradable
synthetic fibers, filaments, nets, wire mesh, and/or other elements, processed into a permanent, three-
dimensional matrix of sufficient thickness. TRMs, which may be supplemented with degradable
components, are designed to impart immediate erosion protection, enhance vegetation establishment
and provide long-term functionality by permanently reinforcing vegetation during and after
maturation. Note: TRMs are typically used in hydraulic applications, such as high flow ditches and
channels, steep slopes, stream banks, and shorelines, where erosive forces may exceed the limits of
natural, unreinforced vegetation or in areas where limited vegetation establishment is anticipated.
Tables RECP-1 and RECP-2 provide guidelines for selecting rolled erosion control products appropriate
to site conditions and desired longevity. Table RECP-1 is for conditions where natural vegetation alone
will provide permanent erosion control, whereas Table RECP-2 is for conditions where vegetation alone
will not be adequately stable to provide long-term erosion protection due to flow or other conditions.
Rolled Erosion Control Products (RECP) EC-6
November 2010 Urban Drainage and Flood Control District RECP-3
Urban Storm Drainage Criteria Manual Volume 3
Table RECP-1. ECTC Standard Specification for Temporary Rolled Erosion Control Products
(Adapted from Erosion Control Technology Council 2005)
Product Description
Slope
Applications*
Channel
Applications*
Minimum
Tensile
Strength1
Expected
Longevity
Maximum
Gradient
C Factor2,5
Max. Shear
Stress3,4,6
Mulch Control Nets 5:1 (H:V)
≤0.10 @
5:1
0.25 lbs/ft2
(12 Pa)
5 lbs/ft
(0.073 kN/m)
Up to 12
months
Netless Rolled
Erosion Control
Blankets
4:1 (H:V)
≤0.10 @
4:1
0.5 lbs/ft2
(24 Pa)
5 lbs/ft
(0.073 kN/m)
Single-net Erosion
Control Blankets &
Open Weave Textiles
3:1 (H:V)
≤0.15 @
3:1
1.5 lbs/ft2
(72 Pa)
50 lbs/ft
(0.73 kN/m)
Double-net Erosion
Control Blankets
2:1 (H:V)
≤0.20 @
2:1
1.75 lbs/ft2
(84 Pa)
75 lbs/ft
(1.09 kN/m)
Mulch Control Nets 5:1 (H:V)
≤0.10 @
EC-6 Rolled Erosion Control Products (RECP)
RECP-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Table RECP-2. ECTC Standard Specification for Permanent1 Rolled Erosion Control Products
(Adapted from: Erosion Control Technology Council 2005)
Product Type
Slope
Applications
Channel Applications
TRMs with a minimum thickness of
0.25 inches (6.35 mm) per ASTM D
6525 and UV stability of 80% per
ASTM D 4355 (500 hours
exposure).
Maximum
Gradient
Maximum
Shear Stress4,5
Minimum
Tensile
Strength2,3
0.5:1 (H:V) 6.0 lbs/ft2 (288 Pa)
125 lbs/ft (1.82
kN/m)
0.5:1 (H:V) 8.0 lbs/ft2 (384 Pa)
150 lbs/ft (2.19
kN/m)
0.5:1 (H:V) 10.0 lbs/ft2 (480 Pa)
175 lbs/ft (2.55
kN/m)
1 For TRMs containing degradable components, all property values must be obtained on the non-
degradable portion of the matting alone.
2 Minimum Average Roll Values, machine direction only for tensile strength determination using ASTM
D 6818 (Supersedes Mod. ASTM D 5035 for RECPs)
3 Field conditions with high loading and/or high survivability requirements may warrant the use of a TRM
with a tensile strength of 44 kN/m (3,000 lb/ft) or greater.
4 Required minimum shear stress TRM (fully vegetated) can sustain without physical damage or excess
erosion (> 12.7 mm (0.5 in.) soil loss) during a 30-minute flow event in large scale testing.
5 Acceptable large-scale testing protocols may include ASTM D 6460, or other independent testing
deemed acceptable by the engineer.
Design and Installation
RECPs should be installed according to manufacturer’s specifications and guidelines. Regardless of the
type of product used, it is important to ensure no gaps or voids exist under the material and that all
corners of the material are secured using stakes and trenching. Continuous contact between the product
and the soil is necessary to avoid failure. Never use metal stakes to secure temporary erosion control
products. Often wooden stakes are used to anchor RECPs; however, wood stakes may present installation
and maintenance challenges and generally take a long time to biodegrade. Some local jurisdictions have
had favorable experiences using biodegradable stakes.
This BMP Fact Sheet provides design details for several commonly used ECB applications, including:
ECB-1 Pipe Outlet to Drainageway
ECB-2 Small Ditch or Drainageway
ECB-3 Outside of Drainageway
Rolled Erosion Control Products (RECP) EC-6
November 2010 Urban Drainage and Flood Control District RECP-5
Urban Storm Drainage Criteria Manual Volume 3
Staking patterns are also provided in the design details according to these factors:
ECB type
Slope or channel type
For other types of RECPs including TRMs, these design details are intended to serve as general
guidelines for design and installation; however, engineers should adhere to manufacturer’s installation
recommendations.
Maintenance and Removal
Inspection of erosion control blankets and other RECPs includes:
Check for general signs of erosion, including voids beneath the mat. If voids are apparent, fill the
void with suitable soil and replace the erosion control blanket, following the appropriate staking
pattern.
Check for damaged or loose stakes and secure loose portions of the blanket.
Erosion control blankets and other RECPs that are biodegradable typically do not need to be removed
after construction. If they must be removed, then an alternate soil stabilization method should be installed
promptly following removal.
Turf reinforcement mats, although generally resistant to biodegradation, are typically left in place as a
dense vegetated cover grows in through the mat matrix. The turf reinforcement mat provides long-term
stability and helps the established vegetation resist erosive forces.
EC-6 Rolled Erosion Control Products (RECP)
RECP-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Rolled Erosion Control Products (RECP) EC-6
November 2010 Urban Drainage and Flood Control District RECP-7
Urban Storm Drainage Criteria Manual Volume 3
EC-6 Rolled Erosion Control Products (RECP)
RECP-8 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Rolled Erosion Control Products (RECP) EC-6
November 2010 Urban Drainage and Flood Control District RECP-9
Urban Storm Drainage Criteria Manual Volume 3
Concrete Washout Area (CWA) MM-1
November 2010 Urban Drainage and Flood Control District CWA-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph CWA-1. Example of concrete washout area. Note gravel
tracking pad for access and sign.
Description
Concrete waste management involves
designating and properly managing a
specific area of the construction site as a
concrete washout area. A concrete
washout area can be created using one of
several approaches designed to receive
wash water from washing of tools and
concrete mixer chutes, liquid concrete
waste from dump trucks, mobile batch
mixers, or pump trucks. Three basic
approaches are available: excavation of a
pit in the ground, use of an above ground
storage area, or use of prefabricated haul-
away concrete washout containers.
Surface discharges of concrete washout
water from construction sites are prohibited.
Appropriate Uses
Concrete washout areas must be designated on all sites that will generate concrete wash water or liquid
concrete waste from onsite concrete mixing or concrete delivery.
Because pH is a pollutant of concern for washout activities, when unlined pits are used for concrete
washout, the soil must have adequate buffering capacity to result in protection of state groundwater
standards; otherwise, a liner/containment must be used. The following management practices are
recommended to prevent an impact from unlined pits to groundwater:
The use of the washout site should be temporary (less than 1 year), and
The washout site should be not be located in an area where shallow groundwater may be present, such
as near natural drainages, springs, or wetlands.
Design and Installation
Concrete washout activities must be conducted in a manner that does not contribute pollutants to surface
waters or stormwater runoff. Concrete washout areas may be lined or unlined excavated pits in the
ground, commercially manufactured prefabricated washout containers, or aboveground holding areas
constructed of berms, sandbags or straw bales with a plastic liner.
Although unlined washout areas may be used, lined pits may be required to protect groundwater under
certain conditions.
Do not locate an unlined washout area within 400 feet
of any natural drainage pathway or waterbody or
within 1,000 feet of any wells or drinking water
sources. Even for lined concrete washouts, it is
advisable to locate the facility away from waterbodies
and drainage paths. If site constraints make these
Concrete Washout Area
Functions
Erosion Control No
Sediment Control No
Site/Material Management Yes
MM-1 Concrete Washout Area (CWA)
CWA-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
setbacks infeasible or if highly permeable soils exist in the area, then the pit must be installed with an
impermeable liner (16 mil minimum thickness) or surface storage alternatives using prefabricated
concrete washout devices or a lined aboveground storage area should be used.
Design details with notes are provided in Detail CWA-1 for pits and CWA-2 for aboveground storage
areas. Pre-fabricated concrete washout container information can be obtained from vendors.
Maintenance and Removal
A key consideration for concrete washout areas is to ensure that adequate signage is in place identifying
the location of the washout area. Part of inspecting and maintaining washout areas is ensuring that
adequate signage is provided and in good repair and that the washout area is being used, as opposed to
washout in non-designated areas of the site.
Remove concrete waste in the washout area, as needed to maintain BMP function (typically when filled to
about two-thirds of its capacity). Collect concrete waste and deliver offsite to a designated disposal
location.
Upon termination of use of the washout site, accumulated solid waste, including concrete waste and any
contaminated soils, must be removed from the site to prevent on-site disposal of solid waste. If the wash
water is allowed to evaporate and the concrete hardens, it may be recycled.
Photograph CWA-3. Earthen concrete washout. Photo
courtesy of CDOT.
Photograph CWA-2. Prefabricated concrete washout. Photo
courtesy of CDOT.
Concrete Washout Area (CWA) MM-1
November 2010 Urban Drainage and Flood Control District CWA-3
Urban Storm Drainage Criteria Manual Volume 3
MM-1 Concrete Washout Area (CWA)
CWA-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Temporary and Permanent Seeding (TS/PS) EC-2
June 2012 Urban Drainage and Flood Control District TS/PS-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph TS/PS -1. Equipment used to drill seed. Photo courtesy of
Douglas County.
Description
Temporary seeding can be used to
stabilize disturbed areas that will be
inactive for an extended period.
Permanent seeding should be used to
stabilize areas at final grade that will not
be otherwise stabilized. Effective seeding
includes preparation of a seedbed,
selection of an appropriate seed mixture,
proper planting techniques, and protection
of the seeded area with mulch, geotextiles,
or other appropriate measures.
Appropriate Uses
When the soil surface is disturbed and
will remain inactive for an extended
period (typically 30 days or longer),
proactive stabilization measures should be implemented. If the inactive period is short-lived (on the order
of two weeks), techniques such as surface roughening may be appropriate. For longer periods of
inactivity, temporary seeding and mulching can provide effective erosion control. Permanent seeding
should be used on finished areas that have not been otherwise stabilized.
Typically, local governments have their own seed mixes and timelines for seeding. Check jurisdictional
requirements for seeding and temporary stabilization.
Design and Installation
Effective seeding requires proper seedbed preparation, selection of an appropriate seed mixture, use of
appropriate seeding equipment to ensure proper coverage and density, and protection with mulch or fabric
until plants are established.
The USDCM Volume 2 Revegetation Chapter contains detailed seed mix, soil preparations, and seeding
and mulching recommendations that may be referenced to supplement this Fact Sheet.
Drill seeding is the preferred seeding method. Hydroseeding is not recommended except in areas where
steep slopes prevent use of drill seeding equipment, and even in these instances it is preferable to hand
seed and mulch. Some jurisdictions do not allow hydroseeding or hydromulching.
Seedbed Preparation
Prior to seeding, ensure that areas to be revegetated have
soil conditions capable of supporting vegetation. Overlot
grading can result in loss of topsoil, resulting in poor quality
subsoils at the ground surface that have low nutrient value,
little organic matter content, few soil microorganisms,
rooting restrictions, and conditions less conducive to
infiltration of precipitation. As a result, it is typically
necessary to provide stockpiled topsoil, compost, or other
Temporary and Permanent Seeding
Functions
Erosion Control Yes
Sediment Control No
Site/Material Management No
EC-2 Temporary and Permanent Seeding (TS/PS)
TS/PS-2 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
soil amendments and rototill them into the soil to a depth of 6 inches or more.
Topsoil should be salvaged during grading operations for use and spread on areas to be revegetated later.
Topsoil should be viewed as an important resource to be utilized for vegetation establishment, due to its
water-holding capacity, structure, texture, organic matter content, biological activity, and nutrient content.
The rooting depth of most native grasses in the semi-arid Denver metropolitan area is 6 to 18 inches. At a
minimum, the upper 6 inches of topsoil should be stripped, stockpiled, and ultimately respread across
areas that will be revegetated.
Where topsoil is not available, subsoils should be amended to provide an appropriate plant-growth
medium. Organic matter, such as well digested compost, can be added to improve soil characteristics
conducive to plant growth. Other treatments can be used to adjust soil pH conditions when needed. Soil
testing, which is typically inexpensive, should be completed to determine and optimize the types and
amounts of amendments that are required.
If the disturbed ground surface is compacted, rip or rototill the surface prior to placing topsoil. If adding
compost to the existing soil surface, rototilling is necessary. Surface roughening will assist in placement
of a stable topsoil layer on steeper slopes, and allow infiltration and root penetration to greater depth.
Prior to seeding, the soil surface should be rough and the seedbed should be firm, but neither too loose
nor compacted. The upper layer of soil should be in a condition suitable for seeding at the proper depth
and conducive to plant growth. Seed-to-soil contact is the key to good germination.
Seed Mix for Temporary Vegetation
To provide temporary vegetative cover on disturbed areas which will not be paved, built upon, or fully
landscaped or worked for an extended period (typically 30 days or more), plant an annual grass
appropriate for the time of planting and mulch the planted areas. Annual grasses suitable for the Denver
metropolitan area are listed in Table TS/PS-1. These are to be considered only as general
recommendations when specific design guidance for a particular site is not available. Local governments
typically specify seed mixes appropriate for their jurisdiction.
Seed Mix for Permanent Revegetation
To provide vegetative cover on disturbed areas that have reached final grade, a perennial grass mix should
be established. Permanent seeding should be performed promptly (typically within 14 days) after
reaching final grade. Each site will have different characteristics and a landscape professional or the local
jurisdiction should be contacted to determine the most suitable seed mix for a specific site. In lieu of a
specific recommendation, one of the perennial grass mixes appropriate for site conditions and growth
season listed in Table TS/PS-2 can be used. The pure live seed (PLS) rates of application recommended
in these tables are considered to be absolute minimum rates for seed applied using proper drill-seeding
equipment.
If desired for wildlife habitat or landscape diversity, shrubs such as rubber rabbitbrush (Chrysothamnus
nauseosus), fourwing saltbush (Atriplex canescens) and skunkbrush sumac (Rhus trilobata) could be
added to the upland seedmixes at 0.25, 0.5 and 1 pound PLS/acre, respectively. In riparian zones,
planting root stock of such species as American plum (Prunus americana), woods rose (Rosa woodsii),
plains cottonwood (Populus sargentii), and willow (Populus spp.) may be considered. On non-topsoiled
upland sites, a legume such as Ladak alfalfa at 1 pound PLS/acre can be included as a source of nitrogen
for perennial grasses.
Temporary and Permanent Seeding (TS/PS) EC-2
June 2012 Urban Drainage and Flood Control District TS/PS-3
Urban Storm Drainage Criteria Manual Volume 3
Seeding dates for the highest success probability of perennial species along the Front Range are generally
in the spring from April through early May and in the fall after the first of September until the ground
freezes. If the area is irrigated, seeding may occur in summer months, as well. See Table TS/PS-3 for
appropriate seeding dates.
Table TS/PS-1. Minimum Drill Seeding Rates for Various Temporary Annual Grasses
Speciesa
(Common name)
Growth
Season
b
Pounds of
Pure Live Seed
(PLS)/acre
c
Planting
Depth
(inches)
1. Oats Cool 35 - 50 1 - 2
2. Spring wheat Cool 25 - 35 1 - 2
3. Spring barley Cool 25 - 35 1 - 2
4. Annual ryegrass Cool 10 - 15 ½
5. Millet Warm 3 - 15 ½ - ¾
6. Sudangrass Warm 5–10 ½ - ¾
7. Sorghum Warm 5–10 ½ - ¾
8. Winter wheat Cool 20–35 1 - 2
9. Winter barley Cool 20–35 1 - 2
10. Winter rye Cool 20–35 1 - 2
11. Triticale Cool 25–40 1 - 2
a Successful seeding of annual grass resulting in adequate plant growth will
usually produce enough dead-plant residue to provide protection from
wind and water erosion for an additional year. This assumes that the cover
is not disturbed or mowed closer than 8 inches.
Hydraulic seeding may be substituted for drilling only where slopes are
steeper than 3:1 or where access limitations exist. When hydraulic
seeding is used, hydraulic mulching should be applied as a separate
operation, when practical, to prevent the seeds from being encapsulated in
the mulch.
b See Table TS/PS-3 for seeding dates. Irrigation, if consistently applied,
may extend the use of cool season species during the summer months.
c Seeding rates should be doubled if seed is broadcast, or increased by 50
percent if done using a Brillion Drill or by hydraulic seeding.
EC-2 Temporary and Permanent Seeding (TS/PS)
TS/PS-4 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
Table TS/PS-2. Minimum Drill Seeding Rates for Perennial Grasses
Common
a
Name
Botanical
Name
Growth
Season
b
Growth
Form
Seeds/
Pound
Pounds of
PLS/acre
Alakali Soil Seed Mix
Alkali sacaton Sporobolus airoides Cool Bunch 1,750,000 0.25
Basin wildrye Elymus cinereus Cool Bunch 165,000 2.5
Sodar streambank wheatgrass Agropyron riparium 'Sodar' Cool Sod 170,000 2.5
Jose tall wheatgrass Agropyron elongatum 'Jose' Cool Bunch 79,000 7.0
Arriba western wheatgrass Agropyron smithii 'Arriba' Cool Sod 110,000 5.5
Total 17.75
Fertile Loamy Soil Seed Mix
Ephriam crested wheatgrass
Agropyron cristatum
'Ephriam'
Cool Sod 175,000 2.0
Dural hard fescue Festuca ovina 'duriuscula' Cool Bunch 565,000 1.0
Lincoln smooth brome
Bromus inermis leyss
'Lincoln'
Cool Sod 130,000 3.0
Sodar streambank wheatgrass Agropyron riparium 'Sodar' Cool Sod 170,000 2.5
Arriba western wheatgrass Agropyron smithii 'Arriba' Cool Sod 110,000 7.0
Total 15.5
High Water Table Soil Seed Mix
Meadow foxtail Alopecurus pratensis Cool Sod 900,000 0.5
Redtop Agrostis alba Warm Open sod 5,000,000 0.25
Reed canarygrass Phalaris arundinacea Cool Sod 68,000 0.5
Lincoln smooth brome
Bromus inermis leyss
'Lincoln'
Cool Sod 130,000 3.0
Pathfinder switchgrass
Panicum virgatum
'Pathfinder'
Warm Sod 389,000 1.0
Alkar tall wheatgrass
Agropyron elongatum
'Alkar'
Cool Bunch 79,000 5.5
Total 10.75
Transition Turf Seed Mix
c
Ruebens Canadian bluegrass Poa compressa 'Ruebens' Cool Sod 2,500,000 0.5
Dural hard fescue Festuca ovina 'duriuscula' Cool Bunch 565,000 1.0
Citation perennial ryegrass Lolium perenne 'Citation' Cool Sod 247,000 3.0
Temporary and Permanent Seeding (TS/PS) EC-2
June 2012 Urban Drainage and Flood Control District TS/PS-5
Urban Storm Drainage Criteria Manual Volume 3
Table TS/PS-2. Minimum Drill Seeding Rates for Perennial Grasses
(cont.)
Common
Name
Botanical
Name
Growth
Season
b
Growth
Form
Seeds/
Pound
Pounds of
PLS/acre
Sandy Soil Seed Mix
Blue grama Bouteloua gracilis Warm
Sod-forming
bunchgrass
825,000 0.5
Camper little bluestem
Schizachyrium scoparium
'Camper'
Warm Bunch 240,000 1.0
Prairie sandreed Calamovilfa longifolia Warm Open sod 274,000 1.0
Sand dropseed Sporobolus cryptandrus Cool Bunch 5,298,000 0.25
Vaughn sideoats grama
Bouteloua curtipendula
'Vaughn'
Warm Sod 191,000 2.0
Arriba western wheatgrass Agropyron smithii 'Arriba' Cool Sod 110,000 5.5
Total 10.25
Heavy Clay, Rocky Foothill Seed Mix
Ephriam crested wheatgrassd
Agropyron cristatum
'Ephriam'
Cool Sod 175,000 1.5
Oahe Intermediate wheatgrass
Agropyron intermedium
'Oahe'
Cool Sod 115,000 5.5
Vaughn sideoats gramae
Bouteloua curtipendula
'Vaughn'
Warm Sod 191,000 2.0
Lincoln smooth brome
Bromus inermis leyss
'Lincoln'
Cool Sod 130,000 3.0
Arriba western wheatgrass Agropyron smithii 'Arriba' Cool Sod 110,000 5.5
Total 17.5
a
All of the above seeding mixes and rates are based on drill seeding followed by crimped straw mulch. These rates should be
doubled if seed is broadcast and should be increased by 50 percent if the seeding is done using a Brillion Drill or is applied
through hydraulic seeding. Hydraulic seeding may be substituted for drilling only where slopes are steeper than 3:1. If
hydraulic seeding is used, hydraulic mulching should be done as a separate operation.
b See Table TS/PS-3 for seeding dates.
EC-2 Temporary and Permanent Seeding (TS/PS)
TS/PS-6 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
Table TS/PS-3. Seeding Dates for Annual and Perennial Grasses
Annual Grasses
(Numbers in table reference
species in Table TS/PS-1)
Perennial Grasses
Seeding Dates Warm Cool Warm Cool
January 1–March 15
March 16–April 30 4 1,2,3
May 1–May 15 4
May 16–June 30 4,5,6,7
July 1–July 15 5,6,7
July 16–August 31
September 1–September 30 8,9,10,11
October 1–December 31
Mulch
Cover seeded areas with mulch or an appropriate rolled erosion control product to promote establishment
of vegetation. Anchor mulch by crimping, netting or use of a non-toxic tackifier. See the Mulching BMP
Fact Sheet for additional guidance.
Maintenance and Removal
Monitor and observe seeded areas to identify areas of poor growth or areas that fail to germinate. Reseed
and mulch these areas, as needed.
An area that has been permanently seeded should have a good stand of vegetation within one growing
season if irrigated and within three growing seasons without irrigation in Colorado. Reseed portions of
the site that fail to germinate or remain bare after the first growing season.
Seeded areas may require irrigation, particularly during extended dry periods. Targeted weed control may
also be necessary.
Protect seeded areas from construction equipment and vehicle access.
Protection of Existing Vegetation (PV) SM-2
November 2010 Urban Drainage and Flood Control District PV-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph PV-1. Protection of existing vegetation and a sensitive
area. Photo courtesy of CDOT.
Description
Protection of existing vegetation on a
construction site can be accomplished
through installation of a construction
fence around the area requiring protection.
In cases where upgradient areas are
disturbed, it may also be necessary to
install perimeter controls to minimize
sediment loading to sensitive areas such as
wetlands. Existing vegetation may be
designated for protection to maintain a
stable surface cover as part of construction
phasing, or vegetation may be protected in
areas designated to remain in natural
condition under post-development
conditions (e.g., wetlands, mature trees,
riparian areas, open space).
Appropriate Uses
Existing vegetation should be preserved for the maximum practical duration on a construction site
through the use of effective construction phasing. Preserving vegetation helps to minimize erosion and
can reduce revegetation costs following construction.
Protection of wetland areas is required under the Clean Water Act, unless a permit has been obtained from
the U.S. Army Corps of Engineers (USACE) allowing impacts in limited areas.
If trees are to be protected as part of post-development landscaping, care must be taken to avoid several
types of damage, some of which may not be apparent at the time of injury. Potential sources of injury
include soil compaction during grading or due to construction traffic, direct equipment-related injury such
as bark removal, branch breakage, surface grading and trenching, and soil cut and fill. In order to
minimize injuries that may lead to immediate or later death of the tree, tree protection zones should be
developed during site design, implemented at the beginning of a construction project, as well as continued
during active construction.
Design and Installation
General
Once an area has been designated as a preservation area, there should be no construction activity allowed
within a set distance of the area. Clearly mark the area with construction fencing. Do not allow
stockpiles, equipment, trailers or parking within the
protected area. Guidelines to protect various types of
existing vegetation follow.
Protection of Existing Vegetation
Functions
Erosion Control Yes
Sediment Control Moderate
Site/Material Management Yes
SM-2 Protection of Existing Vegetation (PV)
PV-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Surface Cover During Phased Construction
Install construction fencing or other perimeter controls around areas to be protected from clearing and
grading as part of construction phasing.
Maintaining surface cover on steep slopes for the maximum practical duration during construction is
recommended.
Open Space Preservation
Where natural open space areas will be preserved as part of a development, it is important to install
construction fencing around these areas to protect them from compaction. This is particularly important
when areas with soils with high infiltration rates are preserved as part of LID designs. Preserved open
space areas should not be used for staging and equipment storage.
Wetlands and Riparian Areas
Install a construction fence around the perimeter of the wetland or riparian (streamside vegetation) area to
prevent access by equipment. In areas downgradient of disturbed areas, install a perimeter control such as
silt fence, sediment control logs, or similar measure to minimize sediment loading to the wetland.
Tree Protection
1
Before beginning construction operations, establish a tree protection zone around trees to be
preserved by installing construction fences. Allow enough space from the trunk to protect the root
zone from soil compaction and mechanical damage, and the branches from mechanical damage (see
Table PV-1). If low branches will be kept, place the fence outside of the drip line. Where this is not
possible, place fencing as far away from the trunk as possible. In order to maintain a healthy tree, be
aware that about 60 percent of the tree's root zone extends beyond the drip line.
Table PV-1
Guidelines for Determining the Tree Protection Zone
(Source: Matheny and Clark, 1998; as cited in GreenCO and WWE 2008)
Distance from Trunk (ft) per inch of DBH
Species Tolerance to Damage Young Mature Over mature
Good 0.5' 0.75' 1.0'
Moderate 0.75' 1.0' 1.25'
Poor 1.0' 1.25' 1.5'
Notes: DBH = diameter at breast height (4.5 ft above grade); Young = <20% of
life expectancy; Mature = 20%-80% of life expectancy; Over mature =>80% of
life expectancy
Most tree roots grow within the top 12 to 18 inches of soil. Grade changes within the tree protection
zone should be avoided where possible because seemingly minor grade changes can either smother
1 Tree Protection guidelines adapted from GreenCO and WWE (2008). Green Industry Best Management Practices (BMPs) for
the Conservation and Protection of Water Resources in Colorado: Moving Toward Sustainability, Third Release. See
www.greenco.org for more detailed guidance on tree preservation.
Protection of Existing Vegetation (PV) SM-2
November 2010 Urban Drainage and Flood Control District PV-3
Urban Storm Drainage Criteria Manual Volume 3
roots (in fill situations) or damage roots (in cut situations). Consider small walls where needed to
avoid grade changes in the tree protection zone.
Place and maintain a layer of mulch 4 to 6-inch thick from the tree trunk to the fencing, keeping a
6-inch space between the mulch and the trunk. Mulch helps to preserve moisture and decrease soil
compaction if construction traffic is unavoidable. When planting operations are completed, the mulch
may be reused throughout planting areas.
Limit access, if needed at all, and appoint one route as the main entrance and exit to the tree
protection zone. Within the tree protection zone, do not allow any equipment to be stored, chemicals
to be dumped, or construction activities to take place except fine grading, irrigation system
installation, and planting operations. These activities should be conducted in consultation with a
landscaping professional, following Green Industry BMPs.
Be aware that soil compaction can cause extreme damage to tree health that may appear gradually
over a period of years. Soil compaction is easier to prevent than repair.
Maintenance and Removal
Repair or replace damaged or displaced fencing or other protective barriers around the vegetated area.
If damage occurs to a tree, consult an arborist for guidance on how to care for the tree. If a tree in a
designated preservation area is damaged beyond repair, remove and replace with a 2-inch diameter tree of
the same or similar species.
Construction equipment must not enter a wetland area, except as permitted by the U.S. Army Corps of
Engineers (USACE). Inadvertent placement of fill in a wetland is a 404 permit violation and will require
notification of the USACE.
If damage to vegetation occurs in a protected area, reseed the area with the same or similar species,
following the recommendations in the USDCM Revegetation chapter.
Stockpile Management (SP) MM-2
November 2010 Urban Drainage and Flood Control District SP-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph SP-1. A topsoil stockpile that has been partially
revegetated and is protected by silt fence perimeter control.
Description
Stockpile management includes
measures to minimize erosion and
sediment transport from soil stockpiles.
Appropriate Uses
Stockpile management should be used
when soils or other erodible materials
are stored at the construction site.
Special attention should be given to
stockpiles in close proximity to natural
or manmade storm systems.
Design and Installation
Locate stockpiles away from all drainage system components including storm sewer inlets. Where
practical, choose stockpile locations that that will remain undisturbed for the longest period of time as the
phases of construction progress. Place sediment control BMPs around the perimeter of the stockpile, such
as sediment control logs, rock socks, silt fence, straw bales and sand bags. See Detail SP-1 for guidance
on proper establishment of perimeter controls around a stockpile. For stockpiles in active use, provide a
stabilized designated access point on the upgradient side of the stockpile.
Stabilize the stockpile surface with surface roughening, temporary seeding and mulching, erosion control
blankets, or soil binders. Soils stockpiled for an extended period (typically for more than 60 days) should
be seeded and mulched with a temporary grass cover once the stockpile is placed (typically within 14
days). Use of mulch only or a soil binder is acceptable if the stockpile will be in place for a more limited
time period (typically 30-60 days). Timeframes for stabilization of stockpiles noted in this fact sheet are
"typical" guidelines. Check permit requirements for specific federal, state, and/or local requirements that
may be more prescriptive.
Stockpiles should not be placed in streets or paved areas unless no other practical alternative exists. See
the Stabilized Staging Area Fact Sheet for guidance when staging in roadways is unavoidable due to
space or right-of-way constraints. For paved areas, rock socks must be used for perimeter control and all
inlets with the potential to receive sediment from the stockpile (even from vehicle tracking) must be
protected.
Maintenance and Removal
Inspect perimeter controls and inlet protection in accordance with their respective BMP Fact Sheets.
Where seeding, mulch and/or soil binders are used, reseeding or reapplication of soil binder may be
necessary.
When temporary removal of a perimeter BMP is necessary
to access a stockpile, ensure BMPs are reinstalled in
accordance with their respective design detail section.
Stockpile Management
Functions
Erosion Control Yes
Sediment Control Yes
Site/Material Management Yes
MM-2 Stockpile Management (SM)
SP-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
When the stockpile is no longer needed, properly dispose of excess materials and revegetate or otherwise
stabilize the ground surface where the stockpile was located.
Stockpile Management (SP) MM-2
November 2010 Urban Drainage and Flood Control District SP-3
Urban Storm Drainage Criteria Manual Volume 3
MM-2 Stockpile Management (SM)
SP-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Stockpile Management (SP) MM-2
November 2010 Urban Drainage and Flood Control District SP-5
Urban Storm Drainage Criteria Manual Volume 3
MM-2 Stockpile Management (SM)
SP-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Mulching (MU) EC-4
June 2012 Urban Drainage and Flood Control District MU-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph MU-1. An area that was recently seeded, mulched,
and crimped.
Description
Mulching consists of evenly applying
straw, hay, shredded wood mulch, rock,
bark or compost to disturbed soils and
securing the mulch by crimping, tackifiers,
netting or other measures. Mulching helps
reduce erosion by protecting bare soil
from rainfall impact, increasing
infiltration, and reducing runoff.
Although often applied in conjunction
with temporary or permanent seeding, it
can also be used for temporary
stabilization of areas that cannot be
reseeded due to seasonal constraints.
Mulch can be applied either using
standard mechanical dry application
methods or using hydromulching equipment
that hydraulically applies a slurry of water,
wood fiber mulch, and often a tackifier.
Appropriate Uses
Use mulch in conjunction with seeding to help protect the seedbed and stabilize the soil. Mulch can also
be used as a temporary cover on low to mild slopes to help temporarily stabilize disturbed areas where
growing season constraints prevent effective reseeding. Disturbed areas should be properly mulched and
tacked, or seeded, mulched and tacked promptly after final grade is reached (typically within no longer
than 14 days) on portions of the site not otherwise permanently stabilized.
Standard dry mulching is encouraged in most jurisdictions; however, hydromulching may not be allowed
in certain jurisdictions or may not be allowed near waterways.
Do not apply mulch during windy conditions.
Design and Installation
Prior to mulching, surface-roughen areas by rolling with a crimping or punching type roller or by track
walking. Track walking should only be used where other methods are impractical because track walking
with heavy equipment typically compacts the soil.
A variety of mulches can be used effectively at construction
sites. Consider the following:
Mulch
Functions
Erosion Control Yes
Sediment Control Moderate
Site/Material Management No
EC-4 Mulching (MU)
MU-2 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
Clean, weed-free and seed-free cereal grain straw should be applied evenly at a rate of 2 tons per acre and
must be tacked or fastened by a method suitable for the condition of the site. Straw mulch must be
anchored (and not merely placed) on the surface. This can be accomplished mechanically by crimping or
with the aid of tackifiers or nets. Anchoring with a crimping implement is preferred, and is the
recommended method for areas flatter than 3:1. Mechanical crimpers must be capable of tucking the long
mulch fibers into the soil to a depth of 3 inches without cutting them. An agricultural disk, while not an
ideal substitute, may work if the disk blades are dull or blunted and set vertically; however, the frame may
have to be weighted to afford proper soil penetration.
Grass hay may be used in place of straw; however, because hay is comprised of the entire plant including
seed, mulching with hay may seed the site with non-native grass species which might in turn out-compete
the native seed. Alternatively, native species of grass hay may be purchased, but can be difficult to find
and are more expensive than straw. Purchasing and utilizing a certified weed-free straw is an easier and
less costly mulching method. When using grass hay, follow the same guidelines as for straw (provided
above).
On small areas sheltered from the wind and heavy runoff, spraying a tackifier on the mulch is satisfactory
for holding it in place. For steep slopes and special situations where greater control is needed, erosion
control blankets anchored with stakes should be used instead of mulch.
Hydraulic mulching consists of wood cellulose fibers mixed with water and a tackifying agent and should
be applied at a rate of no less than 1,500 pounds per acre (1,425 lbs of fibers mixed with at least 75 lbs of
tackifier) with a hydraulic mulcher. For steeper slopes, up to 2000 pounds per acre may be required for
effective hydroseeding. Hydromulch typically requires up to 24 hours to dry; therefore, it should not be
applied immediately prior to inclement weather. Application to roads, waterways and existing vegetation
should be avoided.
Erosion control mats, blankets, or nets are recommended to help stabilize steep slopes (generally 3:1 and
steeper) and waterways. Depending on the product, these may be used alone or in conjunction with grass
or straw mulch. Normally, use of these products will be restricted to relatively small areas.
Biodegradable mats made of straw and jute, straw-coconut, coconut fiber, or excelsior can be used instead
of mulch. (See the ECM/TRM BMP for more information.)
Some tackifiers or binders may be used to anchor mulch. Check with the local jurisdiction for allowed
tackifiers. Manufacturer's recommendations should be followed at all times. (See the Soil Binder BMP
for more information on general types of tackifiers.)
Rock can also be used as mulch. It provides protection of exposed soils to wind and water erosion and
allows infiltration of precipitation. An aggregate base course can be spread on disturbed areas for
temporary or permanent stabilization. The rock mulch layer should be thick enough to provide full
coverage of exposed soil on the area it is applied.
Maintenance and Removal
After mulching, the bare ground surface should not be more than 10 percent exposed. Reapply mulch, as
needed, to cover bare areas.
Wind Erosion/Dust Control (DC) EC-14
November 2010 Urban Drainage and Flood Control District DC-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph DC-1. Water truck used for dust suppression. Photo
courtesy of Douglas County.
Description
Wind erosion and dust control BMPs
help to keep soil particles from entering
the air as a result of land disturbing
construction activities. These BMPs
include a variety of practices generally
focused on either graded disturbed areas
or construction roadways. For graded
areas, practices such as seeding and
mulching, use of soil binders, site
watering, or other practices that provide
prompt surface cover should be used.
For construction roadways, road
watering and stabilized surfaces should
be considered.
Appropriate Uses
Dust control measures should be used on any site where dust poses a problem to air quality. Dust control
is important to control for the health of construction workers and surrounding waterbodies.
Design and Installation
The following construction BMPs can be used for dust control:
An irrigation/sprinkler system can be used to wet the top layer of disturbed soil to help keep dry soil
particles from becoming airborne.
Seeding and mulching can be used to stabilize disturbed surfaces and reduce dust emissions.
Protecting existing vegetation can help to slow wind velocities across the ground surface, thereby
limiting the likelihood of soil particles to become airborne.
Spray-on soil binders form a bond between soil particles keeping them grounded. Chemical
treatments may require additional permitting requirements. Potential impacts to surrounding
waterways and habitat must be considered prior to use.
Placing rock on construction roadways and entrances will help keep dust to a minimum across the
construction site.
Wind fences can be installed on site to reduce wind
speeds. Install fences perpendicular to the prevailing
wind direction for maximum effectiveness.
Maintenance and Removal
When using an irrigation/sprinkler control system to aid in
dust control, be careful not to overwater. Overwatering will
cause construction vehicles to track mud off-site.
Wind Erosion Control/
Dust Control
Functions
Erosion Control Yes
Sediment Control No
Site/Material Management Moderate
Street Sweeping and Vacuuming (SS) SM-7
November 2010 Urban Drainage and Flood Control District SS-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph SS-1. A street sweeper removes sediment and potential
pollutants along the curb line at a construction site. Photo courtesy of
Tom Gore.
Description
Street sweeping and vacuuming remove
sediment that has been tracked onto
roadways to reduce sediment transport
into storm drain systems or a surface
waterway.
Appropriate Uses
Use this practice at construction sites
where vehicles may track sediment
offsite onto paved roadways.
Design and Installation
Street sweeping or vacuuming should be
conducted when there is noticeable
sediment accumulation on roadways adjacent to the construction site. Typically, this will be concentrated
at the entrance/exit to the construction site. Well-maintained stabilized construction entrances, vehicle
tracking controls and tire wash facilities can help reduce the necessary frequency of street sweeping and
vacuuming.
On smaller construction sites, street sweeping can be conducted manually using a shovel and broom.
Never wash accumulated sediment on roadways into storm drains.
Maintenance and Removal
Inspect paved roads around the perimeter of the construction site on a daily basis and more
frequently, as needed. Remove accumulated sediment, as needed.
Following street sweeping, check inlet protection that may have been displaced during street
sweeping.
Inspect area to be swept for materials that may be hazardous prior to beginning sweeping operations.
Street Sweeping/ Vacuuming
Functions
Erosion Control No
Sediment Control Yes
Site/Material Management Yes
Paving and Grinding Operations (PGO) SM-12
November 2010 Urban Drainage and Flood Control District PGO-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph PGO-1. Paving operations on a Colorado highway. Photo
courtesy of CDOT.
Description
Manage runoff from paving and grinding
operations to reduce pollutants entering
storm drainage systems and natural
drainageways.
Appropriate Uses
Use runoff management practices during
all paving and grinding operations such
as surfacing, resurfacing, and saw
cutting.
Design and Installation
There are a variety of management
strategies that can be used to manage runoff from paving and grinding operations:
Establish inlet protection for all inlets that could potentially receive runoff.
Schedule paving operations when dry weather is forecasted.
Keep spill kits onsite for equipment spills and keep drip pans onsite for stored equipment.
Install perimeter controls when asphalt material is used on embankments or shoulders near
waterways, drainages, or inlets.
Do not wash any paved surface into receiving storm drain inlets or natural drainageways. Instead,
loose material should be swept or vacuumed following paving and grinding operations.
Store materials away from drainages or waterways.
Recycle asphalt and pavement material when feasible. Material that cannot be recycled must be
disposed of in accordance with applicable regulations.
See BMP Fact Sheets for Inlet Protection, Silt Fence and other perimeter controls selected for use during
paving and grinding operations.
Maintenance and Removal
Perform maintenance and removal of inlet protection and perimeter controls in accordance with their
respective fact sheets.
Promptly respond to spills in accordance with the spill
prevention and control plan.
Paving and Grinding Operations
Functions
Erosion Control No
Sediment Control No
Site/Material Management Yes
Good Housekeeping Practices (GH) MM-3
November 2010 Urban Drainage and Flood Control District GH-1
Urban Storm Drainage Criteria Manual Volume 3
Photographs GH-1 and GH-2. Proper materials
storage and secondary containment for fuel tanks
are important good housekeeping practices. Photos
courtesy of CDOT and City of Aurora.
Description
Implement construction site good housekeeping practices to
prevent pollution associated with solid, liquid and hazardous
construction-related materials and wastes. Stormwater
Management Plans (SWMPs) should clearly specify BMPs
including these good housekeeping practices:
Provide for waste management.
Establish proper building material staging areas.
Designate paint and concrete washout areas.
Establish proper equipment/vehicle fueling and
maintenance practices.
Control equipment/vehicle washing and allowable non-
stormwater discharges.
Develop a spill prevention and response plan.
Acknowledgement: This Fact Sheet is based directly on
EPA guidance provided in Developing Your Stormwater
Pollution Prevent Plan (EPA 2007).
Appropriate Uses
Good housekeeping practices are necessary at all construction sites.
Design and Installation
The following principles and actions should be addressed in SWMPs:
Provide for Waste Management. Implement management procedures and practices to prevent or
reduce the exposure and transport of pollutants in stormwater from solid, liquid and sanitary wastes
that will be generated at the site. Practices such as trash disposal, recycling, proper material handling,
and cleanup measures can reduce the potential for stormwater runoff to pick up construction site
wastes and discharge them to surface waters. Implement a comprehensive set of waste-management
practices for hazardous or toxic materials, such as paints, solvents, petroleum products, pesticides,
wood preservatives, acids, roofing tar, and other materials. Practices should include storage,
handling, inventory, and cleanup procedures, in case of spills. Specific practices that should be
considered include:
Solid or Construction Waste
o Designate trash and bulk waste-collection areas on-
site.
Good Housekeeping
Functions
Erosion Control No
Sediment Control No
Site/Material Management Yes
MM-3 Good Housekeeping Practices (GH)
GH-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Photograph GH-3. Locate portable toilet facilities on level
surfaces away from waterways and storm drains. Photo
courtesy of WWE.
o Recycle materials whenever possible (e.g., paper, wood, concrete, oil).
o Segregate and provide proper disposal options for hazardous material wastes.
o Clean up litter and debris from the construction site daily.
o Locate waste-collection areas away from streets, gutters, watercourses, and storm drains. Waste-
collection areas (dumpsters, and such) are often best located near construction site entrances to
minimize traffic on disturbed soils. Consider secondary containment around waste collection
areas to minimize the likelihood of contaminated discharges.
o Empty waste containers before they are full and overflowing.
Sanitary and Septic Waste
o Provide convenient, well-maintained, and properly located toilet facilities on-site.
o Locate toilet facilities away from storm drain inlets and waterways to prevent accidental spills
and contamination of stormwater.
o Maintain clean restroom facilities and empty portable toilets regularly.
o Where possible, provide secondary containment pans under portable toilets.
o Provide tie-downs or stake-downs for portable toilets.
o Educate employees, subcontractors, and suppliers on locations of facilities.
o Treat or dispose of sanitary and septic waste in accordance with state or local regulations. Do not
discharge or bury wastewater at the construction site.
o Inspect facilities for leaks. If found, repair or replace immediately.
o Special care is necessary during maintenance (pump out) to ensure that waste and/or biocide are
not spilled on the ground.
Hazardous Materials and Wastes
o Develop and implement employee and
subcontractor education, as needed, on
hazardous and toxic waste handling,
storage, disposal, and cleanup.
o Designate hazardous waste-collection
areas on-site.
o Place all hazardous and toxic material
wastes in secondary containment.
Good Housekeeping Practices (GH) MM-3
November 2010 Urban Drainage and Flood Control District GH-3
Urban Storm Drainage Criteria Manual Volume 3
o Hazardous waste containers should be inspected to ensure that all containers are labeled properly
and that no leaks are present.
Establish Proper Building Material Handling and Staging Areas. The SWMP should include
comprehensive handling and management procedures for building materials, especially those that are
hazardous or toxic. Paints, solvents, pesticides, fuels and oils, other hazardous materials or building
materials that have the potential to contaminate stormwater should be stored indoors or under cover
whenever possible or in areas with secondary containment. Secondary containment measures prevent
a spill from spreading across the site and may include dikes, berms, curbing, or other containment
methods. Secondary containment techniques should also ensure the protection of groundwater.
Designate staging areas for activities such as fueling vehicles, mixing paints, plaster, mortar, and
other potential pollutants. Designated staging areas enable easier monitoring of the use of materials
and clean up of spills. Training employees and subcontractors is essential to the success of this
pollution prevention principle. Consider the following specific materials handling and staging
practices:
o Train employees and subcontractors in proper handling and storage practices.
o Clearly designate site areas for staging and storage with signs and on construction drawings.
Staging areas should be located in areas central to the construction site. Segment the staging area
into sub-areas designated for vehicles, equipment, or stockpiles. Construction entrances and exits
should be clearly marked so that delivery vehicles enter/exit through stabilized areas with vehicle
tracking controls (See Vehicle Tracking Control Fact Sheet).
o Provide storage in accordance with Spill Protection, Control and Countermeasures (SPCC)
requirements and plans and provide cover and impermeable perimeter control, as necessary, for
hazardous materials and contaminated soils that must be stored on site.
o Ensure that storage containers are regularly inspected for leaks, corrosion, support or foundation
failure, or other signs of deterioration and tested for soundness.
o Reuse and recycle construction materials when possible.
Designate Concrete Washout Areas. Concrete contractors should be encouraged to use the washout
facilities at their own plants or dispatch facilities when feasible; however, concrete washout
commonly occurs on construction sites. If it is necessary to provide for concrete washout areas on-
site, designate specific washout areas and design facilities to handle anticipated washout water.
Washout areas should also be provided for paint and stucco operations. Because washout areas can
be a source of pollutants from leaks or spills, care must be taken with regard to their placement and
proper use. See the Concrete Washout Area Fact Sheet for detailed guidance.
Both self-constructed and prefabricated washout containers can fill up quickly when concrete, paint,
and stucco work are occurring on large portions of the site. Be sure to check for evidence that
contractors are using the washout areas and not dumping materials onto the ground or into drainage
facilities. If the washout areas are not being used regularly, consider posting additional signage,
relocating the facilities to more convenient locations, or providing training to workers and
contractors.
When concrete, paint, or stucco is part of the construction process, consider these practices which will
help prevent contamination of stormwater. Include the locations of these areas and the maintenance
and inspection procedures in the SWMP.
MM-3 Good Housekeeping Practices (GH)
GH-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
o Do not washout concrete trucks or equipment into storm drains, streets, gutters, uncontained
areas, or streams. Only use designated washout areas.
o Establish washout areas and advertise their locations with signs. Ensure that signage remains in
good repair.
o Provide adequate containment for the amount of wash water that will be used.
o Inspect washout structures daily to detect leaks or tears and to identify when materials need to be
removed.
o Dispose of materials properly. The preferred method is to allow the water to evaporate and to
recycle the hardened concrete. Full service companies may provide dewatering services and
should dispose of wastewater properly. Concrete wash water can be highly polluted. It should
not be discharged to any surface water, storm sewer system, or allowed to infiltrate into the
ground in the vicinity of waterbodies. Washwater should not be discharged to a sanitary sewer
system without first receiving written permission from the system operator.
Establish Proper Equipment/Vehicle Fueling and Maintenance Practices. Create a clearly
designated on-site fueling and maintenance area that is clean and dry. The on-site fueling area should
have a spill kit, and staff should know how to use it. If possible, conduct vehicle fueling and
maintenance activities in a covered area. Consider the following practices to help prevent the
discharge of pollutants to stormwater from equipment/vehicle fueling and maintenance. Include the
locations of designated fueling and maintenance areas and inspection and maintenance procedures in
the SWMP.
o Train employees and subcontractors in proper fueling procedures (stay with vehicles during
fueling, proper use of pumps, emergency shutoff valves, etc.).
o Inspect on-site vehicles and equipment regularly for leaks, equipment damage, and other service
problems.
o Clearly designate vehicle/equipment service areas away from drainage facilities and watercourses
to prevent stormwater run-on and runoff.
o Use drip pans, drip cloths, or absorbent pads when replacing spent fluids.
o Collect all spent fluids, store in appropriate labeled containers in the proper storage areas, and
recycle fluids whenever possible.
Control Equipment/Vehicle Washing and Allowable Non-Stormwater Discharges. Implement
practices to prevent contamination of surface and groundwater from equipment and vehicle wash
water. Representative practices include:
o Educate employees and subcontractors on proper washing procedures.
o Use off-site washing facilities, when available.
o Clearly mark the washing areas and inform workers that all washing must occur in this area.
o Contain wash water and treat it using BMPs. Infiltrate washwater when possible, but maintain
separation from drainage paths and waterbodies.
Good Housekeeping Practices (GH) MM-3
November 2010 Urban Drainage and Flood Control District GH-5
Urban Storm Drainage Criteria Manual Volume 3
o Use high-pressure water spray at vehicle washing facilities without detergents. Water alone can
remove most dirt adequately.
o Do not conduct other activities, such as vehicle repairs, in the wash area.
o Include the location of the washing facilities and the inspection and maintenance procedures in
the SWMP.
Develop a Spill Prevention and Response Plan. Spill prevention and response procedures must be
identified in the SWMP. Representative procedures include identifying ways to reduce the chance of
spills, stop the source of spills, contain and clean up spills, dispose of materials contaminated by
spills, and train personnel responsible for spill prevention and response. The plan should also specify
material handling procedures and storage requirements and ensure that clear and concise spill cleanup
procedures are provided and posted for areas in which spills may potentially occur. When developing
a spill prevention plan, include the following:
o Note the locations of chemical storage areas, storm drains, tributary drainage areas, surface
waterbodies on or near the site, and measures to stop spills from leaving the site.
o Provide proper handling and safety procedures for each type of waste. Keep Material Safety Data
Sheets (MSDSs) for chemical used on site with the SWMP.
o Establish an education program for employees and subcontractors on the potential hazards to
humans and the environment from spills and leaks.
o Specify how to notify appropriate authorities, such as police and fire departments, hospitals, or
municipal sewage treatment facilities to request assistance. Emergency procedures and contact
numbers should be provided in the SWMP and posted at storage locations.
o Describe the procedures, equipment and materials for immediate cleanup of spills and proper
disposal.
o Identify personnel responsible for implementing the plan in the event of a spill. Update the spill
prevention plan and clean up materials as changes occur to the types of chemicals stored and used
at the facility.
MM-3 Good Housekeeping Practices (GH)
GH-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Maintenance and Removal
Effective implementation of good housekeeping practices is dependent on clear designation of personnel
responsible for supervising and implementing good housekeeping programs, such as site cleanup and
disposal of trash and debris, hazardous material management and disposal, vehicle and equipment
maintenance, and other practices. Emergency response "drills" may aid in emergency preparedness.
Checklists may be helpful in good housekeeping efforts.
Staging and storage areas require permanent stabilization when the areas are no longer being used for
construction-related activities.
Construction-related materials, debris and waste must be removed from the construction site once
construction is complete.
Design Details
See the following Fact Sheets for related Design Details:
MM-1 Concrete Washout Area
MM-2 Stockpile Management
SM-4 Vehicle Tracking Control
Design details are not necessary for other good housekeeping practices; however, be sure to designate
where specific practices will occur on the appropriate construction drawings.
APPENDIX C
LANDSCAPE PLAN
APPENDIX D
COPIES OF PERMITS/APPLICATIONS
APPENDIX E
INSPECTION LOGS
APPENDIX F
CONTRACTOR INSERTS
APPENDIX G
CONTRACTOR INSERTS
c If site is to be irrigated, the transition turf seed rates should be doubled.
d Crested wheatgrass should not be used on slopes steeper than 6H to 1V.
e Can substitute 0.5 lbs PLS of blue grama for the 2.0 lbs PLS of Vaughn sideoats grama.
Lincoln smooth brome
Bromus inermis leyss
'Lincoln'
Cool Sod 130,000 3.0
Total 7.5
5:1
0.25 lbs/ft2
(12 Pa)
25 lbs/ft
(0.36 kN/m)
24 months
Erosion Control
Blankets & Open
Weave Textiles
(slowly degrading)
1.5:1 (H:V)
≤0.25 @
1.5:1
2.00 lbs/ft2
(96 Pa)
100 lbs/ft
(1.45 kN/m)
24 months
Erosion Control
Blankets & Open
Weave Textiles
1:1 (H:V)
≤0.25 @
1:1
2.25 lbs/ft2
(108 Pa)
125 lbs/ft
(1.82 kN/m)
36 months
* C Factor and shear stress for mulch control nettings must be obtained with netting used in conjunction
with pre-applied mulch material. (See Section 5.3 of Chapter 7 Construction BMPs for more information
on the C Factor.)
1 Minimum Average Roll Values, Machine direction using ECTC Mod. ASTM D 5035.
2 C Factor calculated as ratio of soil loss from RECP protected slope (tested at specified or greater
gradient, H:V) to ratio of soil loss from unprotected (control) plot in large-scale testing.
3 Required minimum shear stress RECP (unvegetated) can sustain without physical damage or excess
erosion (> 12.7 mm (0.5 in) soil loss) during a 30-minute flow event in large-scale testing.
4 The permissible shear stress levels established for each performance category are based on historical
experience with products characterized by Manning's roughness coefficients in the range of 0.01 - 0.05.
5 Acceptable large-scale test methods may include ASTM D 6459, or other independent testing deemed
acceptable by the engineer.
6 Per the engineer’s discretion. Recommended acceptable large-scale testing protocol may include ASTM
D 6460, or other independent testing deemed acceptable by the engineer.
WATTLE "A" WATTLE "B"
1' 2'
TYP.
1' 1'
W2 NOTES:
INSTALLATION:
STAKES SHOULD BE DRIVEN ACROSS FROM EACH OTHER
AND ON EACH SIDE OF THE WATTLE. LEAVING 4"-6" OF
STAKE PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR
NYLON ROPE SHOULD BE TIED TO THE STAKES ACROSS
THE WATTLE. STAKES SHOULD THEN BE DRIVEN UNTIL THE
BAILING WIRE OR NYLON ROPE IS SUFFICIENTLY SNUG TO
THE WATTLE.
WHEN INSTALLING RUNNING LENGTHS OF WATTLES, TO
PREVENT SHIFTING, BUTT THE SECOND WATTLE TIGHTLY
AGAINST THE FIRST. DO NOT OVERLAP THE ENDS. STAKES
SHOULD BE DRIVEN 1 FT. FROM END, ACROSS FROM AND
ON EACH SIDE OF WATTLE LEAVING 4"-6" OF STAKE
PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR
NYLON ROPE SHOULD BE TIED TO STAKES IN AN HOUR
GLASS FORMATION (FRONT TO BACK OF WATTLE "A",
ACROSS TO FRONT OF WATTLE "B", ACROSS TO BACK AND
BACK TO FRONT OF WATTLE "A"). STAKES SHOULD THEN BE
DRIVEN IN UNTIL BAILING WIRE OR NYLON ROPE IS
SUFFICIENTLY SNUG TO THE WATTLE.
W1 & W2 INSTALLATION NOTES:
1. THE LOCATION AND LENGTH OF WATTLE IS DEPENDENT ON THE CONDITIONS OF EACH SITE.
2. WATTLES SHALL BE INSTALLED PRIOR TO ANY LAND-DISTURBING ACTIVITIES.
3. WATTLES SHALL CONSIST OF STRAW, COMPOST, EXCELSIOR, OR COCONUT FIBER.
4. NOT FOR USE IN CONCENTRATED FLOW AREAS.
5. THE WATTLES SHALL BE TRENCHED INTO THE GROUND A MINIMUM OF TWO (2) INCHES.
6. WATTLES SHALL BE INSTALLED PER MANUFACTURERS SPECIFICATIONS.
7. ON SLOPES, WATTLES SHOULD BE INSTALLED ON CONTOUR WITH A SLIGHT DOWNWARD ANGLE AT THE END OF THE ROW IN ORDER TO PREVENT
PONDING AT THE MID SECTION.
8. RUNNING LENGTHS OF WATTLES SHOULD BE ABUTTED FIRMLY TO ENSURE NO LEAKAGE AT THE ABUTMENTS.
9. SPACING - DOWNSLOPE:
10. VERTICAL SPACING FOR SLOPE INSTALLATIONS SHOULD BE DETERMINED BY SITE CONDITIONS. SLOPE GRADIENT AND SOIL TYPE ARE THE MAIN
FACTORS. A GOOD RULE OF THUMB IS:
1:1 SLOPES = 10 FEET APART
2:1 SLOPES = 20 FEET APART
3:1 SLOPES = 30 FEET APART
4:1 SLOPES = 40 FEET APART, ETC.
11. HOWEVER, ADJUSTMENTS MAY HAVE TO BE MADE FOR THE SOIL TYPE: FOR SOFT, LOAMY SOILS - ADJUST THE ROWS CLOSER TOGETHER; FOR HARD,
ROCKY SOILS - ADJUST THE ROWS FURTHER APART. A SECONDARY WATTLE PLACED BEHIND THE ABUTMENT OF TWO WATTLES IS ENCOURAGED ON
STEEP SLOPES OR WHERE JOINTS HAVE FAILED IN THE PAST.
12. STAKING: THE CITY RECOMMENDS USING WOOD STAKES TO SECURE THE WATTLES. 1/2" TO 5/8" REBAR IS ALSO ACCEPTABLE. BE SURE TO USE A
STAKE THAT IS LONG ENOUGH TO PROTRUDE SEVERAL INCHES ABOVE THE WATTLE: 18" IS A GOOD LENGTH FOR HARD, ROCKY SOIL. FOR SOFT LOAMY
SOIL USE A 24" STAKE.
1"x 1" WOOD STAKES
18"-24"
ENDS OF ADJACENT WATTLES
SHALL BE TIGHTLY ABUTTED
TO PREVENT SEDIMENT BYPASS
W2 NOTE:
ONLY WATTLES MADE WITH COCONUT
FIBERS SHALL BE USED WHEN
INSTALLATION COMES IN CONTACT WITH A
WATER BODY.
WP
CONCRETE WASHOUT AREA
CWA
2 3 ROCK SOCK DETAIL
ROCK SOCK SECTION ROCK SOCK PLAN
ROCK SOCK JOINTING
GRADATION TABLE
SIEVE SIZE
MASS PERCENT
PASSING SQUARE
MESH SIEVES
NO. 4
2" 100
1-1/2" 90-100
1" 20-55
3/4" 0-15
3/8" 0-5
MATCHES SPECIFICATIONS FOR NO. 4 COARSE AGGREGATE FOR
CONCRETE PER AASHTO M43. ALL ROCK SHALL BE FRACTURED FACE,
ALL SIDES
RS
VEHICLE CONTROL TRACKING PAD
VTC
4
AT PIPE OUTLET AREAS OF STREAMS AND
DRAINAGE CHANNELS - DETAIL A
IN DIVERSION DITCH OR SMALL DITCH DRAINAGE WAY - DETAIL B
OUTSIDE OF STREAMS AND DRAINAGE CHANNELS - DETAIL C
ANCHOR DETAILS
PERIMETER ANCHOR TRENCH
JOINT ANCHOR TRENCH
INTERMEDIATE ANCHOR TRENCH
OVERLAPPING JOINT
WOOD STAKE DETAIL
MINIMUM THICKNESS 1"
USE 2x4 MATERIAL FOR STAKES
JOINT ANCHOR
TRENCH, TYP.
PERIMETER
ANCHOR
TRENCH, TYP.
TOP OF
CHANNEL BANK
TYPE OF BLANKET AS INDICATED IN PLAN VIEW, IN ALL DISTURBED AREAS OF
STREAMS AND DRAINAGE CHANNELS TO DEPTH "D" ABOVE CHANNEL INVERT.
BLANKET SHALL GENERALLY BE ORIENTED PARALLEL TO FLOW DIRECTION.
STAKING PATTERN SHALL MATCH BLANKET TYPE.
UNDISTURBED
SOIL
TYPE OF BLANKET,
PER MANUFACTURER SPEC. OR TYPE 2 OR 3 STAKING INDICATED IN PLAN VIEW
(MATCH SPECIFIED BLANKET TYPE) SEE THE STAKING
PATTERNS DETAIL ON NEXT SHEET
PERIMETER
ANCHOR TRENCH, TYP.
JOINT ANCHOR TRENCH, TYP.
COMPACTED
SUBGRADE
1
>3
THE BLANKET SHALL
BE EXTENDED TO THE
TOP OF CHANNEL
"D"
6"
TOPSOIL
"M"
OVERLAPPING JOINT, SEE
DETAIL ON THIS SHEET
STAGGER
OVERLAPS
PERIMETER ANCHOR TRENCH
SEE DETAIL ON THIS SHEET
PER MANUFACTURER SPEC.
OR TYPE 1 STAKING SEE
THE STAKING PATTERN
DETAIL ON NEXT SHEET
BLANKET SHALL BE
100% STRAW MIN.
DIVERSION DITCH
TYPICALLY AT
TOP OF SLOPE
6"
TOPSOIL
6" MIN.
(TYP.)
3" MIN.
(TYP.)
SINGLE EDGE
EROSION CONTROL
BLANKET (TYP.)
COMPACTED
BACKFILL (TYP.)
STAKE (TYP.)
TWO EDGES OF
TWO ADJACENT
ROLLS
LOOP FROM
MIDDLE OF
ROLL
FLOW 6"
3" MIN.
12"
MIN.
STAKING PATTERNS
SHALL BE IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATION. IF NO MANUFACTURER'S
SPECIFICATION IS AVAILABLE USE THE ACCEPTABLE STAKING PATTERN (AS SHOWN ABOVE)
PERIMETER ANCHOR
TRENCH OR JOINT
ANCHOR TRENCH, TYP.
STRAW-COCONUT
COCONUT OR EXCELSIOR
STRAW
ROLL WIDTH
"W" (TYP.)
6'
3'
1/2 "W"
1/2 "W"
1/2 "W"
1/2 "W"
1/2 "W"
4'
3'
2'
ECB
EROSION CONTROL BLANKET TYPE
TYPE
STRAW*
STRAW-COCONUT
EXCELSIOR
COCONUT
CONTENT
-
30% MIN.
-
STRAW
CONTENT
100%
-
NETTING MIN.
DOUBLE/NATURAL
100%
-
-
EXCELSIOR
CONTENT
COCONUT 100% - -
* FOR OUTSIDE OF STREAMS AND DRAINAGE CHANNELS
DOUBLE/NATURAL
DOUBLE/NATURAL
DOUBLE/NATURAL
70% MAX.
10 RIP-RAP
1 WATTLE INSTALLATION
A A
PLAN VIEW
SECTION A-A
2:1
OP
WQCV
8 OUTFALL PROTECTION
5 SILT FENCE
9 INLET PROTECTION
ILP
IP1
6 INDIVIDUAL LOT PROTECTION
3.
BY VOLUME PRIOR TO PLACEMENT.
VOLUME WITH 35% OF APPROVED SOIL
MIX UNIFORM ALLY 65% RIPRAP BY
ABOVE DESIGN RIPRAP TOP GRADE.
VOIDS AND ROCKS PROJECTING
COMPACT AND LEVEL TO ELIMINATE ALL
DESIGN THICKNESS AND GRADE.
SECURELY INTERLOCKED ROCK AT THE
PLACE STONE-SOIL MIX TO RESULT IN
2.
ACTUAL LOCATION AND LIMITS.
SLOPED AREAS. REFER TO THE SITE PLAN
1. SOIL RIPRAP DETAILS ARE APPLICABLE TO
NOTES:
12" min
3" min
ONE-INCH THICK
WOOD STAKE DETAIL
Use 2x4
material
for stakes
4.
CRIMP OR TACKIFY MULCH OR USE
APPROVED HYDROMULCH AS CALLED
FOR IN THE PLANS AND SPECIFICATIONS.
SOIL RIPRAP.
MIX SOIL AND RIPRAP
COMPLETELY (SEE NOTES)
SOIL RIPRAP.
MIX SOIL AND RIPRAP
COMPLETELY (SEE NOTES)
10" MIN.
TOPSOIL LAYER AND SEED AND MULCH
AS REQUIRED BY PLANS AND SPECIFICATIONS
TOPSOIL LAYER AND SEED AND MULCH
AS REQUIRED BY PLANS AND SPECIFICATIONS
FINISHED GRAD
DESIGN RIPRAP GRADE
FINISHED GRAD
DESIGN RIPRAP GRADE
2*D50 4" - 6" (TYP.)
2*D50
SLOPE VARIES (SEE PLANS)
PREPARE COMPACTED
SUBGRADE PER SPECIFICATIONS
OR PLACE ON UNDISTURBED SUGRADE
SLOPE VARIES (SEE PLANS)
PREPARE COMPACTED
SUBGRADE PER SPECIFICATIONS
TYPICAL SECTION - OR PLACE ON UNDISTURBED SUGRADE
SOIL RIPRAP WITH MUCLH
TYPICAL SECTION -
SOIL RIPRAP WITH EROSION CONTROL FABRIC
STAKE BLANKET TO
GROUND BETWEEN STONES
EROSION CONTROL BLANAKET
AS SPECIFIED OR CALLED FOR
ON THE PLANS
4" - 6" (TYP.)
7 EROSION CONTROL BLANKET
RIPRAP SCHEDULE
Storm Line Pipe
Diameter
(ft)
Ordinary
Riprap
Type
Length
of Riprap
(ft)
Width
of Riprap
(ft)
2*d50,
Depth of
Riprap
(ft)
Storm Line A 2.00 Type L 7.00 9.00 1.5
Storm Line B 2.00 Type L 8.00 9.00 1.5
Storm Line C 1.25 Type L 5.00 7.00 1.5
Storm Line D 1.25 Type L 5.00 7.00 1.5
LOD
LOD
LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
15" SS 15" SS 15" SS
15" SS
15" SS 15" SS 15" SS
15" SS
15" SS 15" SS 15" SS
UD UD
2' CONCRETE
PAN
OUTFALL
ROYAL TROON AVE.
ARNOUSTIE DR.
POND 2
RAIN GARDEN 2
LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD LOD
LOD LOD LOD
LOD LOD
LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD LOD
LOD LOD
LOD LOD
LOD LOD
LOD LOD
LOD
PROPOSED FES
CONCRETE
CULVERT
FES
POND 1
SITE OUTFALL
SF
SF
SF
SF
SF SF SF
SF
SF SF
SIDEWALK AND
CONCRETE CHASE
EXISTING 24" CMP
TURNBERRY ROAD
PROPOSED
OUTFALL FES
EC6
DYNAMIC EROSION CONTROL PLAN 4
##
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
( IN FEET )
0
1 INCH = 30 FEET
30 30 60 90
BENCHMARK/BASIS OF BEARING
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
SILT FENCE SF
WATTLE PROTECTION W
VEHICLE TRACKING PAD VTC
SF
ILP
INDIVIDUAL LOT PROTECTION
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 2.69 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE SEE FINAL STORM WATER MANAGMENT PLAN BY NORTHERN
ENGINEERING SERVICES, DATED NOVEMBER 13, 2017 FOR ADDITIONAL
INFORMATION.
GENERAL NOTES:
PROJECT DATUM: NAVD88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 34-92: WEST SIDE OF TAFT HILL RD. NORTH OF
STUART ST. ON A STORM WATER DIVERSION STRUCTURE.
ELEVATION: 5088.78
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 12-97: ON WEST STUART ST. BETWEEN ZENITH
COURT AND RYELAND LANE, ON THE SOUTH END OF THE EAST HEADWALL OF THE CANAL
BRIDGE.
ELEVATION: 5116.62
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING
EQUATION SHOULD BE USED:
NGVD29 UNADJUSTED = NAVD88 - 3.18.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE OF THE SOUTHWEST QUARTER OF SECTION
22-T7N-R69W AS BEARING SOUTH 00°06'35" WEST
LEGEND:
ROCK SOCK WITH MARKER RS
EROSION CONTROL BLANKET ECB
CONCRETE WASHOUT AREA CWA
OP
OUTFALL PROTECTION
1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE
CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED.
ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY
DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT
BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT,
ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY
MAINTAINED AND FOLLOWED.
4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING
THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORMWATER
FACILITIES UNTIL SITE IS FULLY STABILIZED.
6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT
CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH
DOWNSPOUT.
7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND
CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN
6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND
ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND
STABILIZE THE SLOPE.
9. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT
EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE
ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING
DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE
SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR
SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY
OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS
AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO
DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE
WAY.
12. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION
TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND,
OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW
POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER,
WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND
CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
13. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION
INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE
BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND
WELFARE.
14. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT
SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR
OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
15. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE
AND OTHER PERMANENT SITE STABILIZATION METHODS.
EROSION CONTROL NOTES:
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION/REMOVAL
Project: BRICK STONE APARTMENTS ON HARMONY Date: 11.30.17
Contractor to utilize this table to indicate when construction activities occur and when each associated BMP is installed or removed.
CONSTRUCTION PHASE (Monthly) 1 2 3 4 5 6 7 8 9 10 11 12 Comments
Grading
Overlot
Swales, Drainageways
Pipeline Installation
Stormwater
Concrete Installation
Building Structure
Miscellaneous
Hardscape Amenities
BEST MANAGEMENT PRACTICES
Temporary
Contour Furrows and Diversion Dikes (Ripping/Disking)
Inlet Protection (IP)
Vehicle Tracking Control (VTC)
Flow Barriers (Bales, Wattles, Etc) (WD)
Concrete Washout Area (CWA)
Preventative Maintenance Activities/Meetings/ etc.
Permanent
Mulching/Sealant
Permanent Seed Planting
Water Service
Sanitary Sewer Service
Curb and Gutter
Concrete Parking and Drive Aisle
Bio-Swale
Permeable Pavers
KEYMAP
DOUGLAS RD
TURNBERRY RD
DEC1 DEC2
DEC3 DEC4
X
X
X X X
X
X X
X
X X
X X X X X
X
B
B
A.V.
LOD LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
CARNOUSTIE DR.
BALTUSROL DR.
BALTUSROL CT.
LOD LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
EC5
DYNAMIC EROSION CONTROL PLAN 3
##
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
( IN FEET )
0
1 INCH = 30 FEET
30 30 60 90
BENCHMARK/BASIS OF BEARING
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
SILT FENCE SF
WATTLE PROTECTION W
VEHICLE TRACKING PAD VTC
SF
ILP
INDIVIDUAL LOT PROTECTION
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 2.69 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE SEE FINAL STORM WATER MANAGMENT PLAN BY NORTHERN
ENGINEERING SERVICES, DATED NOVEMBER 13, 2017 FOR ADDITIONAL
INFORMATION.
GENERAL NOTES:
PROJECT DATUM: NAVD88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 34-92: WEST SIDE OF TAFT HILL RD. NORTH OF
STUART ST. ON A STORM WATER DIVERSION STRUCTURE.
ELEVATION: 5088.78
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 12-97: ON WEST STUART ST. BETWEEN ZENITH
COURT AND RYELAND LANE, ON THE SOUTH END OF THE EAST HEADWALL OF THE CANAL
BRIDGE.
ELEVATION: 5116.62
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING
EQUATION SHOULD BE USED:
NGVD29 UNADJUSTED = NAVD88 - 3.18.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE OF THE SOUTHWEST QUARTER OF SECTION
22-T7N-R69W AS BEARING SOUTH 00°06'35" WEST
LEGEND:
ROCK SOCK WITH MARKER RS
EROSION CONTROL BLANKET ECB
CONCRETE WASHOUT AREA CWA
OP
OUTFALL PROTECTION
1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE
CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED.
ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY
DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT
BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT,
ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY
MAINTAINED AND FOLLOWED.
4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING
THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORMWATER
FACILITIES UNTIL SITE IS FULLY STABILIZED.
6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT
CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH
DOWNSPOUT.
7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND
CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN
6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND
ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND
STABILIZE THE SLOPE.
9. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT
EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE
ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING
DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE
SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR
SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY
OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS
AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO
DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE
WAY.
12. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION
TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND,
OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW
POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER,
WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND
CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
13. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION
INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE
BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND
WELFARE.
14. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT
SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR
OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
15. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE
AND OTHER PERMANENT SITE STABILIZATION METHODS.
EROSION CONTROL NOTES:
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION/REMOVAL
Project: BRICK STONE APARTMENTS ON HARMONY Date: 11.30.17
Contractor to utilize this table to indicate when construction activities occur and when each associated BMP is installed or removed.
CONSTRUCTION PHASE (Monthly) 1 2 3 4 5 6 7 8 9 10 11 12 Comments
Grading
Overlot
Swales, Drainageways
Pipeline Installation
Stormwater
Concrete Installation
Building Structure
Miscellaneous
Hardscape Amenities
BEST MANAGEMENT PRACTICES
Temporary
Contour Furrows and Diversion Dikes (Ripping/Disking)
Inlet Protection (IP)
Vehicle Tracking Control (VTC)
Flow Barriers (Bales, Wattles, Etc) (WD)
Concrete Washout Area (CWA)
Preventative Maintenance Activities/Meetings/ etc.
Permanent
Mulching/Sealant
Permanent Seed Planting
Water Service
Sanitary Sewer Service
Curb and Gutter
Concrete Parking and Drive Aisle
Bio-Swale
Permeable Pavers
KEYMAP
DOUGLAS RD
TURNBERRY RD
DEC1 DEC2
DEC3 DEC4
15" SS 15" SS 15" SS
UD
UD
ED FOOT DR.
KIAWAH DR.
SF SF
SF
SF
SF
SF
SF SF SF
SF SF
SF
SF SF
SF SF
SF
SF SF
SF
SF
SF
SF
LOD LOD LOD LOD
LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD LOD LOD
LOD
LOD LOD LOD
LOD LOD
LOD
PROPOSED FES
SITE OUTFALL
SF SF
NATURAL HABITAT
BUFFER ZONE
PROPOSED FES
INLET (2)
SF SF SF SF SF
SF
SF
SF
SF SF
INLET OUTFALL
INLET
RAIN GARDEN 1
PROPOSED
OUTFALL FES
EC4
DYNAMIC EROSION CONTROL PLAN 2
##
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
( IN FEET )
0
1 INCH = 60 FEET
60 60 120 180
BENCHMARK/BASIS OF BEARING
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
SILT FENCE SF
WATTLE PROTECTION W
VEHICLE TRACKING PAD VTC
SF
ILP
INDIVIDUAL LOT PROTECTION
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 2.69 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE SEE FINAL STORM WATER MANAGMENT PLAN BY NORTHERN
ENGINEERING SERVICES, DATED NOVEMBER 13, 2017 FOR ADDITIONAL
INFORMATION.
GENERAL NOTES:
PROJECT DATUM: NAVD88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 34-92: WEST SIDE OF TAFT HILL RD. NORTH OF
STUART ST. ON A STORM WATER DIVERSION STRUCTURE.
ELEVATION: 5088.78
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 12-97: ON WEST STUART ST. BETWEEN ZENITH
COURT AND RYELAND LANE, ON THE SOUTH END OF THE EAST HEADWALL OF THE CANAL
BRIDGE.
ELEVATION: 5116.62
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING
EQUATION SHOULD BE USED:
NGVD29 UNADJUSTED = NAVD88 - 3.18.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE OF THE SOUTHWEST QUARTER OF SECTION
22-T7N-R69W AS BEARING SOUTH 00°06'35" WEST
LEGEND:
ROCK SOCK WITH MARKER RS
EROSION CONTROL BLANKET ECB
CONCRETE WASHOUT AREA CWA
OP
OUTFALL PROTECTION
1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE
CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED.
ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY
DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT
BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT,
ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY
MAINTAINED AND FOLLOWED.
4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING
THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORMWATER
FACILITIES UNTIL SITE IS FULLY STABILIZED.
6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT
CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH
DOWNSPOUT.
7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND
CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN
6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND
ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND
STABILIZE THE SLOPE.
9. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT
EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE
ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING
DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE
SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR
SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY
OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS
AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO
DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE
WAY.
12. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION
TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND,
OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW
POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER,
WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND
CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
13. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION
INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE
BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND
WELFARE.
14. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT
SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR
OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
15. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE
AND OTHER PERMANENT SITE STABILIZATION METHODS.
EROSION CONTROL NOTES:
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION/REMOVAL
Project: BRICK STONE APARTMENTS ON HARMONY Date: 11.30.17
Contractor to utilize this table to indicate when construction activities occur and when each associated BMP is installed or removed.
CONSTRUCTION PHASE (Monthly) 1 2 3 4 5 6 7 8 9 10 11 12 Comments
Grading
Overlot
Swales, Drainageways
Pipeline Installation
Stormwater
Concrete Installation
Building Structure
Miscellaneous
Hardscape Amenities
BEST MANAGEMENT PRACTICES
Temporary
Contour Furrows and Diversion Dikes (Ripping/Disking)
Inlet Protection (IP)
Vehicle Tracking Control (VTC)
Flow Barriers (Bales, Wattles, Etc) (WD)
Concrete Washout Area (CWA)
Preventative Maintenance Activities/Meetings/ etc.
Permanent
Mulching/Sealant
Permanent Seed Planting
Water Service
Sanitary Sewer Service
Curb and Gutter
Concrete Parking and Drive Aisle
Bio-Swale
Permeable Pavers
KEYMAP
DOUGLAS RD
TURNBERRY RD
DEC1 DEC2
DEC3 DEC4
M
M
F
E
S
X
X
T
ELE
F.O.
TELE
X
X
X X
F
E
S
M
F
E
S
TELE
B
B
AW
10"W 1976 (AC)
000
10"W 1976 (AC) 4" (AC)
4" (AC)
W
LOD
LOD LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
UD UD UD UD
WINGED FOOT DR.
CARNOUSTIE DR.
BETHPAGE DR.
SF SF SF SF SF SF SF SF SF
LOD
LOD LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD LOD LOD
LOD
LOD
LOD
LOD LOD LOD
LOD LOD LOD LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD LOD LOD LOD
LOD LOD LOD LOD
SIDEWALK CHASE
POND 3
RAIN GARDEN 3
SF SF SF SF SF SF SF SF SF SF SF SF SF
SF
SF SF SF SF SF SF
SF
SF
INLET
E. DOUGLAS ROAD
EC3
DYNAMIC EROSION CONTROL PLAN 1
##
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
( IN FEET )
0
1 INCH = 60 FEET
60 60 120 180
BENCHMARK/BASIS OF BEARING
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
SILT FENCE SF
WATTLE PROTECTION W
VEHICLE TRACKING PAD VTC
SF
ILP
INDIVIDUAL LOT PROTECTION
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 2.69 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE SEE FINAL STORM WATER MANAGMENT PLAN BY NORTHERN
ENGINEERING SERVICES, DATED NOVEMBER 13, 2017 FOR ADDITIONAL
INFORMATION.
GENERAL NOTES:
PROJECT DATUM: NAVD88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 34-92: WEST SIDE OF TAFT HILL RD. NORTH OF
STUART ST. ON A STORM WATER DIVERSION STRUCTURE.
ELEVATION: 5088.78
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 12-97: ON WEST STUART ST. BETWEEN ZENITH
COURT AND RYELAND LANE, ON THE SOUTH END OF THE EAST HEADWALL OF THE CANAL
BRIDGE.
ELEVATION: 5116.62
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING
EQUATION SHOULD BE USED:
NGVD29 UNADJUSTED = NAVD88 - 3.18.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE WEST LINE OF THE SOUTHWEST QUARTER OF SECTION
22-T7N-R69W AS BEARING SOUTH 00°06'35" WEST
LEGEND:
ROCK SOCK WITH MARKER RS
EROSION CONTROL BLANKET ECB
CONCRETE WASHOUT AREA CWA
OP
OUTFALL PROTECTION
1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE
CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED.
ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY
DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT
BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT,
ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY
MAINTAINED AND FOLLOWED.
4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING
THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION.
5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORMWATER
FACILITIES UNTIL SITE IS FULLY STABILIZED.
6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT
CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH
DOWNSPOUT.
7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND
CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.)
8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN
6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND
ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND
STABILIZE THE SLOPE.
9. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT
EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE
ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING
DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE
SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR
SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY
OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS
AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO
DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE
WAY.
12. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION
TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND,
OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW
POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER,
WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND
CONSTRUCTION TOILETS SHALL BE STAKED DOWN.
13. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION
INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE
BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND
WELFARE.
14. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT
SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR
OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION.
15. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE
AND OTHER PERMANENT SITE STABILIZATION METHODS.
EROSION CONTROL NOTES:
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION/REMOVAL
Project: BRICK STONE APARTMENTS ON HARMONY Date: 11.30.17
Contractor to utilize this table to indicate when construction activities occur and when each associated BMP is installed or removed.
CONSTRUCTION PHASE (Monthly) 1 2 3 4 5 6 7 8 9 10 11 12 Comments
Grading
Overlot
Swales, Drainageways
Pipeline Installation
Stormwater
Concrete Installation
Building Structure
Miscellaneous
Hardscape Amenities
BEST MANAGEMENT PRACTICES
Temporary
Contour Furrows and Diversion Dikes (Ripping/Disking)
Inlet Protection (IP)
Vehicle Tracking Control (VTC)
Flow Barriers (Bales, Wattles, Etc) (WD)
Concrete Washout Area (CWA)
Preventative Maintenance Activities/Meetings/ etc.
Permanent
Mulching/Sealant
Permanent Seed Planting
Water Service
Sanitary Sewer Service
Curb and Gutter
Concrete Parking and Drive Aisle
Bio-Swale
Permeable Pavers
KEYMAP
DOUGLAS RD
TURNBERRY RD
DEC1 DEC2
DEC3 DEC4
E
E
E
E
E
E E
E
E
E
E
E
E
E
WV
WV WV
WV
WV
WV
X
X
X
X
X
V.P.
WV
H
Y
D
WV
WV
X X X
X X
X X
X X
X
X X
X X X X X X
X
M
X X X
X
F
E
S
M
M
F
E
S
F
E
S
MM
X
TELE
F.O.
TELE
F
E
S
MGAS
X X
F
E
S
M
F
E
S
TELE
X
F
E
S
M
F
E
S
X
X X X
X
W
S
O
X
V.P. X
VAULT
CABLE
BOX
CABLE
H2O
V.GAS P.
GAS
OHE
OHE
OHE
OHE
OHE
OHE
OHE OHE
OHE
B
B
B
B
B
B
B
B
ST ST
A.V.
AW
10"W 1976 (AC)
000
10"W 1976 (AC) 4" (AC)
4" (AC)
10"W 1976 (AC)
4" (AC)
10"W 1976 (AC)
4" (AC)
W
W
W W
W W W
W W
W W W
1
14"W 1976 (AC) 4"W 1976 (AC)
14"W 1976 (AC)
LOD LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
15" SS 15" SS 15" SS 15" SS 15" SS 15" SS
UD
UD
UD
UD
2' CONCRETE
PAN
OUTFALL
WINGED FOOT DR.
KIAWAH DR.
ROYAL TROON AVE.
CARNOUSTIE DR.
BALTUSROL DR.
BETHPAGE DR.
POND 2
RAIN GARDEN 2
BALTUSROL CT.
SF
SF
SF SF
SF
SF SF
W W
W
W
W
W
W
IP
W
IP
OP
SF
SF
SF SF SF SF SF
SF
SF
SF SF
W
W
LOD LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD
LOD LOD
LOD
LOD
LOD LOD LOD
LOD LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
LOD LOD LOD LOD
LOD LOD LOD LOD LOD
LOD LOD LOD
LOD
LOD
LOD LOD LOD
LOD
LOD LOD
PROPOSED FES
CONCRETE
CULVERT
FES
POND 1
SITE OUTFALL
OP
SF
SF
SF
SIDEWALK CHASE
NATURAL HABITAT
BUFFER ZONE
PROPOSED FES
POND 3
RAIN GARDEN 3
INLET (2)
CWA IP IP IP
OP
SF SF
SF
W
IP
SF
RS
RS RS
OUTFALL
INLET
INLET
INLET
E. DOUGLAS ROAD
VTC
VTC IP IP IP
S
F SF SF SF SF
SF
SF
SF
SF
SF
SF SF SF SF
SF
RS RS RS
RS
VTC
W
RS
RS
RAIN GARDEN 1
RS
SIDEWALK AND
CONCRETE CHASE
EXISTING 24" CMP
TURNBERRY ROAD
IP OP
SF SF
SF
SF
IP
IP
RS
RS
PROPOSED
OUTFALL FES
OP
W
W
ECB
ECB
W W
EC1
EROSION CONTROL PLAN
13
Sheet
of 65
COUNTRY CLUB RESERVE These drawings are
instruments of service
provided by Northern
Engineering Services, Inc.
and are not to be used for
any type of construction
unless signed and sealed by
a Professional Engineer in
the employ of Northern
Engineering Services, Inc.
NOT FOR CONSTRUCTION
REVIEW SET
301 North Howes Street, Suite 100
Fort Collins, Colorado 80521
E NGINEER ING
N O R T H E RN
PHONE: 970.221.4158
www.northernengineering.com
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
Call before you dig.
R
BENCHMARK/BASIS OF BEARING
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
SILT FENCE
WATTLE PROTECTION
VEHICLE TRACKING PAD
SF
INLET PROTECTION
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 2.69 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE
WASHOUT AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE FINAL STORM WATER MANAGMENT PLAN BY NORTHERN
ENGINEERING SERVICES, DATED 12/12/18 FOR ADDITIONAL INFORMATION.
6. ALL DISTURBED AREAS SHOULD BE REVEGETATED PER THE APPROVED
LANDSCAPING PLANS.
GENERAL NOTES:
LEGEND:
ROCK SOCK WITH MARKER
EROSION CONTROL BLANKET
1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES
ONLY AS A GUIDELINE TO THE CONTRACTOR. STAGING AND/OR
PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED.
ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY
DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO
CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH,
GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR ARE THEY
NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING
(CITY, STATE DISCHARGE PERMIT, ETC.) AND COMPLIANCE WITH
GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF
THE CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION
CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED.
4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION
CONTROL MEASURES ACCORDING THE THE CONSTRUCTION
SEQUENCING AND LEVEL OF SITE STABILIZATION.
5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION
FOR ALL STORM DRAINS, SWALES, PONDS AND RAIN GARDENS UNTIL
SITE IS FULLY STABILIZED.
6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION
FOR DOWNSPOUT CONNECTIONS, TO THE STORM DRAIN SYSTEM,
UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT.
7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE
SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN
WATTLES FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR
PAVEMENT, ETC.)
8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES,
PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP MULCHING,
HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND
ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO
ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE.
9. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE
NECESSARY TO INSURE THAT EACH BUILDING PAD IS STABILIZED
THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE
ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER
PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE.
PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO
THE SURROUNDING SURFACE TYPE AND CONDITION (i.e.,
STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE
SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED
(100) FEET FROM NATURAL BODY OF WATER, WETLAND, NATURAL
DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS
AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT
WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF,
OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE
WAY.
12. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE
SANITATION UNITS (CONSTRUCTION TOILETS) SHALL BE LOCATED AT
LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND,
OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A
CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO
DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF
WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE
LOCATED ON FLAT, STABLE GROUND, AND CONSTRUCTION TOILETS
SHALL BE STAKED DOWN.
13. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE
WITH THE CITY'S CONSTRUCTION INSPECTORS BY CEASING
OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO
CREATE BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS
HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE.
14. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND
WINTER MONTHS) INHIBIT PERMANENT SEEDING OPERATIONS,
DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH
TACKIFIER OR OTHER MATERIALS APPROVED BY EROSION CONTROL
STAFF TO PREVENT EROSION.
15. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON
PLANTING, REVEGETATION, HARDSCAPE AND OTHER PERMANENT
SITE STABILIZATION METHODS.
16. ALL DOWNSTREAM INLETS ALONG DOUGLAS ROAD AND TURNBERRY
ROAD SHOULD HAVE INLET PROTECTION.
TABLE OF CONSTRUCTION SEQUENCE AND BMP EROSION CONTROL NOTES:
APPLICATION
CONSTRUCTION PHASE
(DESCRIPTION)
PHASE I
(GRADING)
PHASE II
(INFRASTRUCTURE)
PHASE III
(VERTICAL
CONSTRUCITON)
PHASE IV
(PERMANENT
BMP'S)
Grading (Include Offsite)
Overlot
Pipeline Installation
Stormwater
Concrete Installation
Site Walls
Building Structure
Miscellaneous
Hardscape Amenities
BEST MANAGEMENT PRACTICES
Temporary
Inlet Protection (IP)
Vehicle Tracking Control (VTC)
Flow Barriers (Wattles, Rock Socks, etc.) (WD)
Concrete Washout Area (CWA)
Preventative Maintenance Activities/Meetings/etc.
Silt Fence (SF)
Permanent
Mulching/Sealant
Permanent Seed Planting
Sewer Service
Water Service
Curb and Gutter
CONCRETE WASHOUT AREA
OUTFALL PROTECTION
INDIVIDUAL LOT PROTECTION
LIMITS OF DISTURBANCE LOD
( IN FEET )
1 inch = ft.
120 0 120 Feet
120
240 360
SF
W
VTC
IP
RS
ECB
CWA
OP
ILP
OVERLAND FLOW
DIRECT FLOW
PROJECT DATUM: NAVD 88
BENCHMARK #1: CITY OF FORT COLLINS BENCHMARK 92-14
NORTHEAST CORNER OF DOUGLAS ROAD AND TURNBERRY ROAD, ON THE SOUTHWEST
CORNER OF A BRIDGE OVER LARIMER CANAL DITCH.
ELEVATION = 5075.10
BENCHMARK #2: CITY OF FORT COLLINS BENCHMARK 92-15
DOUGLAS ROAD AND COUNTY ROAD 13, ON A LARIMER COUNTRY BRASS CAP, ON THE
SOUTHWEST CORNER OF A BRIDGE OVER LARIMER CANAL DITCH.
ELEVATION = 5123.89
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED (PRIOR CITY OF FORT COLLINS DATUM)
FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS) IS REQUIRED FOR ANY
PURPOSE, THE FOLLOWING EQUATION SHOULD BE USED:
NGVD29 UNADJUSTED(PRIOR CITY OF FORT COLLINS DATUM) = NAVD88 - 3.17
BASIS OF BEARING:
THE BASIS OF BEARINGS IS THE WEST LINE OF THE NORTHEAST QUARTER OF SECTION
30-T8N-R68W AS BEARING SOUTH 89°21'11" WEST.