HomeMy WebLinkAboutALLIED BUILDING PRODUCTS - PDP - PDP180015 - SUBMITTAL DOCUMENTS - ROUND 2 - GEOTECHNICAL (SOILS) REPORTGEOTECHNICAL SUBSURFACE EXPLORATION REPORT
ALLIED BUILDING PRODUCTS STORAGE BUILDING
LOT 2, CENTERPOINT PLAZA
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
SOILOGIC # 18-1265
September 26, 2018
Soilogic, Inc.
3522 Draft Horse Court Loveland, CO 80538 (970) 535-6144
P.O. Box 1121 Hayden, CO 81639 (970) 276-2087
September 26, 2018
Baseline Engineering
1950 Ford Street
Golden, Colorado 80401
Attn: Ms. Deanne Frederickson, RLA
Re: Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building
(Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Project # 18-1265
Ms. Frederickson:
Soilogic, Inc. (Soilogic) personnel have completed the geotechnical subsurface
exploration you requested for the proposed Allied Building Products storage building to
be constructed on Lot 2 of the Centerpoint Plaza industrial/commercial development in
Fort Collins, Colorado. The results of our subsurface exploration and pertinent
geotechnical engineering recommendations are included with this report.
The subsurface materials encountered in the completed site borings consisted of a thin
mantle of vegetation and topsoil or gravel surfacing underlain by brown/rust, medium
stiff to very stiff lean clay at the location of borings B-1 and B-2 and loose to medium
dense, brown/rust/grey silty to clayey sand and gravel at the location of borings B-3 and
B-4. The near-surface sand and gravel encountered at the location of boring B-4 was
identified as possible existing fill material which may have been placed to develop finish
site grades and extended to a depth of approximately two (2) feet below ground surface,
where it was underlain by lean clay. The lean clay soils encountered in boring B-1 were
relatively dry at the time of drilling and exhibited moderate swell potential at current
moisture and density conditions. Higher moisture content lean clay soils exhibiting no
swell potential were encountered in borings B-2 and B-4. At the location of borings B-1,
B-2 and B-4, the lean clay extended to a depth of approximately eight (8) feet below
ground surface, where it was underlain by reddish brown silty sand and gravel. The sand
and gravel varied from loose to dense in terms of relative density, would be expected to
be non-expansive based on the material’s physical properties and engineering
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
2
characteristics and extended to the bottom of all borings at depths ranging from
approximately 10 to 15 feet below present site grade.
Groundwater was measured in borings B-1 and B-2 at a depth of approximately 12 feet
below ground surface when checked immediately after completion of drilling.
Groundwater was not encountered in borings B-3 and B-4 terminated at a depth of
approximately 10 feet below ground surface at that time.
Based on the subsurface conditions encountered, results of laboratory testing and
proposed construction, it is our opinion the proposed storage building could be
constructed with conventional spread footing foundations bearing on natural, undisturbed
lean clay with no to low swell potential and/or properly placed and compacted
overexcavation/backfill (if/where required). Although most of the lean clay soils
encountered in the test borings drilled for this exploration exhibited no swell potential at
current moisture and density conditions, one sample obtained from boring B-1 at a depth
of about 4 feet below ground surface exhibited moderate swell potential. Additionally,
approximately two (2) feet of apparent undocumented fill was encountered near-surface
at the location of boring B-4. Overexcavation/backfill procedures are recommended
beneath footing foundations and floor slabs in the northern portion of the building area
where expansive lean clay soils were identified. Similar methods should be used in order
to develop LVC-potential pavement and exterior flatwork subgrades if/where
undocumented fill and/or expansive lean clay soils are identified underlying these
improvements. The overexcavation/backfill procedures would help develop LVC-
potential foundation, floor slab support across the building footprint, reducing the
potential for total and differential movement of those supported elements subsequent to
construction.
Based on the results of completed laboratory testing, the existing fill and natural site lean
clay soils appear suitable for use as low volume change (LVC) fill and
overexcavation/backfill (if/where required) to develop the site. Other opinions and
recommendations concerning design criteria and construction details for the proposed site
improvements are included with this report. Pavement section design options are also
included.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
3
We appreciate the opportunity to be of service to you on this project. If you have any
questions concerning the enclosed information or if we can be of further service to you in
any way, please do not hesitate to contact us.
Very Truly Yours,
Soilogic, Inc. Reviewed by:
Wolf von Carlowitz, P.E. Darrel DiCarlo, P.E.
Principal Engineer Senior Project Engineer
36746
44271
GEOTECHNICAL SUBSURFACE EXPLORATION REPORT
ALLIED BUILDING PRODUCTS STORAGE BUILDING
LOT 2 – CENTERPOINT PLAZA
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
SOILOGIC # 18-1265
September 26, 2018
INTRODUCTION
This report contains the results of the completed geotechnical subsurface exploration for
the proposed Allied Building Products storage building to be constructed on Lot 2 of the
Centerpoint Plaza industrial/commercial development in Fort Collins, Colorado. The
purpose of our exploration was to describe the subsurface conditions encountered in the
completed site borings and develop the test data necessary to provide recommendations
concerning design and construction of the proposed building foundations and support of
floor slabs, exterior flatwork and site pavements. The conclusions and recommendations
outlined in this report are based on the results of the completed field and laboratory
testing and our experience with subsurface conditions in this area.
PROPOSED CONSTRUCTION
We understand the proposed storage building will be a three-sided pre-engineered steel
structure constructed as slab-on-grade, encompassing a plan area of approximately 6,600
square feet. Foundations loads for the building are anticipated to be relatively light, with
maximum continuous wall loads on the order of 3 to 4 kips per lineal foot and individual
column loads less than 100 kips. Paved drive and parking areas are also anticipated as
part of the proposed site improvements. Small grade changes are anticipated to develop
finish site grades in building and pavement areas. If proposed construction or assumed
loadings differ significantly from those assumed, Soilogic should be notified to
reevaluate the recommendations in this report.
SITE DESCRIPTION
The development parcel includes approximately an approximate 1.9-acre parcel of land
identified as Lot 2 of the Centerpoint Plaza industrial/commercial development, located
at 2155 Midpoint Drive in Fort Collins, Colorado. At the time of our exploration, the site
contained a sparse to moderate growth of grass and weed vegetation and gravel-surfaced
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
2
drive and parking areas. The site was relatively level, with the maximum difference in
ground surface elevation across the property estimated to be less than 4 feet. Evidence of
prior building construction was not observed in the proposed construction areas by
Soilogic personnel at the time of our site exploration.
SITE EXPLORATION
Field Exploration
To develop subsurface information for the proposed site improvements, a total of four (4)
soil borings were completed. Two (2) borings were advanced in the area of the proposed
storage building to a depth of approximately 15 feet below present site grade. Two (2)
additional borings were completed in site pavement areas to a depth of approximately 10
feet below ground surface. The boring locations were established in the field by Soilogic,
Inc. (Soilogic) personnel based on a provided site plan, using a mechanical surveyor's
wheel and estimating angles from identifiable site references. A diagram indicating the
approximate boring locations is included with this report. The boring locations outlined
on the attached diagram should be considered accurate only to the degree implied by the
methods used to make the field measurements. Graphic logs of each of the auger borings
are also included.
The test holes were advanced using 4-inch diameter continuous flight auger powered by a
truck-mounted CME-45 drill rig. Samples of the subsurface materials were obtained at
regular intervals using California barrel sampling procedures in general accordance with
ASTM specification D-1586. As part of the D-1586 sampling procedure, the standard
sampling barrel is driven into the substrata using a 140-pound hammer falling a distance
of 30 inches. The number of blows required to advance the sampler a distance of 12
inches is recorded and helpful in estimating the consistency or relative density of the soils
encountered. In the California barrel sampling procedure, lesser disturbed samples are
obtained in removable brass liners. Samples of the subsurface materials obtained in the
field were sealed and returned to the laboratory for further evaluation, classification and
testing.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
3
Laboratory Testing
The samples collected were tested in the laboratory to measure natural moisture content
and were visually and/or manually classified in accordance with the Unified Soil
Classification System (USCS). The USCS group symbols are indicated on the attached
boring logs. An outline of the USCS classification system is included with this report.
As part of the laboratory testing, a calibrated hand penetrometer (CHP) was used to
estimate the unconfined compressive strength of essentially-cohesive specimens. The
CHP also provides a more reliable estimate of soil/bedrock consistency than tactual
observation alone. Dry density, Atterberg limits, -200 wash and swell/consolidation tests
were completed on selected samples to help establish specific soil/bedrock
characteristics. Atterberg limits tests are used to determine soil/bedrock plasticity. The
percent passing the #200 size sieve (-200 wash) test is used to determine the percentage
of fine-grained materials (clay and silt) in a sample. Swell/consolidation tests are
performed to evaluate soil/bedrock volume change potential with variation in moisture
content. Water Soluble Sulfates (WSS) tests were completed on two (2) selected soil
samples to evaluate corrosive soil characteristics with respect to buried concrete. The
results of the completed laboratory tests are outlined on the attached boring logs and
swell/ consolidation test summaries and/or discussed subsequently in this report.
SUBSURFACE CONDITIONS
The subsurface materials encountered in the completed site borings consisted of a thin
mantle of vegetation and topsoil or gravel surfacing underlain by brown/rust, medium
stiff to very stiff lean clay at the location of borings B-1 and B-2 and loose to medium
dense, brown/rust/grey silty to clayey sand and gravel at the location of borings B-3 and
B-4. The near-surface sand and gravel encountered at the location of boring B-4 was
identified as possible existing fill material which may have been placed to develop finish
site grades and extended to a depth of approximately two (2) feet below ground surface,
where it was underlain by lean clay. The lean clay soils encountered in boring B-1 were
relatively dry at the time of drilling and exhibited moderate swell potential at current
moisture and density conditions. Higher moisture content lean clay soils exhibiting no
swell potential were encountered in borings B-2 and B-4. At the location of borings B-1,
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
4
B-2 and B-4, the lean clay extended to a depth of approximately eight (8) feet below
ground surface, where it was underlain by reddish brown silty sand and gravel. The sand
and gravel varied from loose to dense in terms of relative density, would be expected to
be non-expansive based on the material’s physical properties and engineering
characteristics and extended to the bottom of all borings at depths ranging from
approximately 10 to 15 feet below present site grade.
The stratigraphy indicated on the included boring logs represents the approximate
location of changes in soil types. Actual changes may be more gradual than those
indicated.
Groundwater was measured in borings B-1 and B-2 at a depth of approximately 12 feet
below ground surface when checked immediately after completion of drilling.
Groundwater was not encountered in borings B-3 and B-4 terminated at a depth of
approximately 10 feet below ground surface at that time.
Groundwater levels will vary due to seasonal variations in precipitation, site
development, irrigation practices and other hydrologic conditions. Perched and/or
trapped groundwater conditions may also be encountered at times throughout the year.
Perched water is commonly encountered in soils overlying less permeable soil layers
and/or bedrock. Trapped water is typically encountered within more permeable zones of
layered soil and bedrock systems. The location and amount of perched and/or trapped
water can also vary over time.
ANALYSIS AND RECOMMENDATIONS
General
Lean clay soils exhibiting moderate swell potential were encountered relatively near-
surface at the location of boring B-1 completed at the approximate northwest corner of
the proposed building. Total and differential heaving of site improvements placed
directly on or immediately above the expansive lean clay soils would be expected as the
moisture content of those materials increases subsequent to construction.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
5
Based on the subsurface conditions encountered in the completed site borings, results of
laboratory testing and type of construction proposed, it is our opinion overexcavation/
backfill procedures could be completed beneath the building foundation and floor slab in
this area to reduce the potential for movement of those supported elements subsequent to
construction. Similar overexcavation/backfill procedures could be completed beneath
pavements and exterior flatwork if planned for this area. Recommendations concerning
overexcavation/backfill procedures to redevelop low volume change (LVC) foundation
and floor slab support for the northern portion of the building are outlined below.
Drilled pier foundations could also be considered for support of the structure and in order
to reduce the potential for total and differential movement of the storage building
subsequent to construction in the expansive soils environment. Drilled piers would
anchor the building into bedrock underlying the site, significantly reducing the potential
for movement of the structure. Deeper subsurface exploration would be required to
develop soil design parameters for use in drilled pier design. If drilled pier foundations
are to be used, structural flooring systems or overexcavation/backfill procedures to
develop LVC floor slab subgrades would be required. Recommendations concerning the
design and construction of drilled pier foundations and structural flooring systems can be
provided at your request.
Building, Exterior Flatwork and Pavement Subgrade Development
To develop low-volume-change (LVC) potential foundation bearing and floor slab
support (if expansive lean clay soils are observed within close proximity to finish floor
slab subgrade levels), and reduce the potential for total and differential movement of the
northern portion of the building and building floor slab subsequent to construction, we
recommend a zone of reconditioned soil be developed beneath those supported elements.
The reconditioned mat will provide a zone of material immediately beneath the building
foundation and floor slab in the northern portion of the structure which will have low
potential for volume change subsequent to construction. At this time, overexcavation/
backfill procedures do not appear to be warranted for the south portion of the building
where lean clay soils with elevated moisture content and no swell potential were
identified. The LVC mat and surcharge loads placed on the underlying soils by the
reconditioned mat would reduce the potential for total and differential movement of the
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
6
supported improvements subsequent to construction. The reconditioned zone would also
assist in distributing movement in the event that some swelling of the materials
underlying the reconditioned zone occurs.
The overexcavation zone should extend to a depth of four (4) feet below foundation
bearing and finish floor slab subgrade elevation or to moist lean clay with low swell
potential, whichever results in the lesser overexcavation depth. Complete removal of the
expansive lean clay anticipated to extend up to a depth of approximately eight (8) feet
below present site grade in the northern portion of the building could also be considered
to further reduce the amount of anticipated post-construction heave of the building
foundation and floor slab. The overexcavation area should extend a minimum of 8 inches
laterally past all four edges of column pad foundations for every 12 inches of
overexcavation depth (32 inches).
Since movement of site pavements and exterior flatwork is generally considered to be
less consequential than structural and floor slab movement, it is our opinion the
overexcavation zone beneath site pavements and exterior flatwork could be reduced to a
minimum of 24 inches below finish subgrade levels (if/where expansive lean clay soils
are identified underlying these improvements at the time of site development), with the
understanding that some movement of exterior flatwork and site pavements will occur
subsequent to construction. The 24-inch LVC zone beneath flatwork and site pavements
could be developed through any combination of overexcavation/backfill procedures,
subgrade reconditioning and new fill placement.
Soils used as fill and overexcavation/backfill should consist of approved materials free
from organic matter, debris and other objectionable materials. Based on results of the
completed laboratory testing, it is our opinion existing fill (if any) free from organic
matter and deleterious materials and natural site lean clay could be used as
overexcavation/backfill provided care is taken to develop the proper moisture content in
those materials at the time of placement and compaction. Essentially-granular structural
fill materials should not be used as overexcavation/backfill due to the ability of those
materials to pond and transmit water.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
7
All existing topsoil and vegetation should be removed from the proposed building,
exterior flatwork, pavement and any proposed fill areas. All existing undocumented fill
should also be completely removed from these areas at this time. After stripping and
completing all cuts and overexcavation procedures and prior to placement of any new fill
or overexcavation/backfill, we recommend the exposed subgrades be scarified to a depth
of 9 inches, adjusted in moisture content and compacted to at least 95% of the materials
standard Proctor maximum dry density. The moisture content of the scarified soils
should be adjusted to be within the range of -1 to +3% of standard Proctor optimum
moisture content at the time of compaction. Fill and overexcavation/backfill materials
consisting of existing fill, site lean clay and/or similar soils should be placed in loose lifts
not to exceed 9 inches thick, adjusted in moisture content and compacted as outlined for
the scarified soils above. At the high end of the above recommended moisture content
range, some pumping of the lean to fat clay overexcavation/backfill soils may be
observed and would be expected.
Care should be taken to maintain the proper moisture content in the bearing/subgrade
soils prior to foundation and floor slab concrete placement and/or paving. The prepared
structural mat should not be left exposed for extended periods of time. In the event that
the reconditioned soils are allowed to dry out or if rain, snowmelt or water from any
source is allowed to infiltrate the bearing/subgrade soils, reworking of those materials or
removal/replacement procedures may be required.
Inherent risks exist when building in areas of expansive soils. The overexcavation/
backfill procedures outlined above will reduce but not eliminate the potential for
movement of the building foundation, floor slab, exterior flatwork and site pavements
subsequent to construction. The in-place materials below the moisture conditioned zone
can increase in moisture content causing movement of the overlying improvements.
Some movement of the lightly-loaded building floor slab, exterior flatwork and site
pavements should be expected. If some structural and floor slab movement and
associated distress cannot be tolerated, drilled pier foundations and structural floor
systems should be employed.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
8
Foundations
For design of spread footing foundations bearing on natural undisturbed medium stiff to
very stiff lean clay with no to low swell potential and/or a suitable zone of
overexcavation/backfill soils placed and compacted as outlined above, we recommend
using a maximum net allowable soil bearing pressure of 1,500 psf. As a precaution, we
recommend continuous spread footing and isolated pad foundations be designed to
maintain a minimum dead-load pressure of 500 psf (or as high as practical) on the
supporting soils.
Exterior footings should bear a minimum of 30 inches below finished adjacent exterior
grade to provide frost protection. We recommend formed strip footings have a minimum
width of 12 inches and isolated pad foundations have a minimum width of 24 inches in
order to facilitate construction and reduce the potential for development of eccentrically
loaded footings. Actual footing widths should be designed by a structural engineer.
For design of spread footing foundations and foundation walls to resist lateral movement,
a passive equivalent fluid pressure value of 250 pcf could be used. The top 30 inches of
subgrade could be considered a surcharge load but should not be used in the passive
resistance calculations. A coefficient of friction of 0.35 could be used between
foundation and floor slab concrete and the bearing/subgrade soils to resist sliding. The
recommended passive equivalent fluid pressure value and coefficient of friction do not
include a factor of safety.
We estimate settlement of footing foundations supported on a suitable mat of properly-
placed and compacted overexcavation/backfill and resulting from the assumed structural
loads would be less than 1 inch. Differential settlement could approach the amount of
total settlement estimated above. If water from any source is allowed to infiltrate the
foundation bearing soils, additional movement of those supported elements could occur.
Seismicity
Based on the results of our exploration and our review of the International Building Code
(2003), a soil profile type D could be used for the site strata. Based on our review of
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
9
United States Geologic Survey (USGS) mapped information, design spectral response
acceleration values of SDS = .218 (21.8%) and S
D1 = .092 (9.2%) could be used.
Floor Slabs
The building floor slab could be supported directly on reconditioned lean clay with no to
low swell potential and/or properly placed and compacted fill or overexcavation/backfill
(if/where required) developed as outlined above. A modulus of subgrade reaction (k)
value of 150 pci could be used for design of floor slabs supported on reconditioned site
lean clay or similar soils. Disturbed subgrades or subgrade materials that have been
allowed to dry out or become wet and softened should be removed and replaced or
reconditioned in place prior to concrete placement.
The structure floor slab will be located in an unheated area and subject to movement
associated with freezing soils. Placement of a low frost susceptible material immediately
beneath the building floor slab could be considered to reduce the amount of frost heave.
If completed, care should be taken to crown lean clay subgrade soils and develop positive
free drainage of structural fill soils placed beneath the building floor slab.
The floor slab should be designed and constructed as a floating slab, separated from
foundation walls, columns and plumbing and mechanical penetrations by the use of block
outs or appropriate isolation material. In addition, we recommend all partition walls
supported above isolated slabs-on-grade be constructed as floating walls to help reduce
the potential for differential slab-to-foundation movement causing distress in upper
sections of the structure. A minimum one and one-half (1½) inch void space is
recommended beneath all floating walls. Special attention to door and stair framing,
drywall installation and trim carpentry should be taken to isolate those elements from the
floor slab, allowing for some differential floor slab-to-foundation movement to occur
without transmitting stresses to the overlying structure.
Depending on the type of floor covering and floor covering adhesive used, a vapor barrier
may be required immediately beneath the floor slab in order to maintain flooring product
manufacturer warranties. A vapor barrier would help reduce the transmission of moisture
through the floor slabs. However, the unilateral moisture release caused by placing
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
10
concrete on an impermeable surface can increase slab curl. The amount of slab curl can
be reduced by careful selection of an appropriate concrete mix. Slab curl cannot be
eliminated. We recommend the owner, architect and flooring contractor consider the
performance of the slab in conjunction with the proposed flooring products to help
determine if a vapor barrier will be required and where best to position the vapor barrier
in relation to the floor slab. Additional guidance and recommendations concerning slab
on grade design can be found in American Concrete Institute (ACI) section 302.
Pavement and Exterior Flatwork Subgrades
Pavement and exterior flatwork subgrades should be developed as outlined in the
“Building, Exterior Flatwork and Pavement Subgrade Development” section of this
report. Site pavements could be supported directly on reconditioned natural site soils
and/or suitable overexcavation/backfill soils placed and compacted as outlined in that
section (if warranted). Care should be taken to avoid disturbing the overexcavation/
backfill soils prior to placement of exterior flatwork and site pavements. In addition,
efforts to maintain the proper moisture content in the subgrade soils should be made. If
subgrade soils are disturbed or allowed to dry out or become elevated in moisture
content, those materials should be reworked in place or removed and replaced prior to
paving or concrete placement.
Some movement of exterior flatwork and site pavements should be expected as the
moisture content of the subgrade soils increases subsequent to construction. Care should
be taken to ensure that when exterior flatwork and site pavements move, positive
drainage will be maintained away from the structure.
Site Pavements
Based on the materials encountered in the completed site borings and results of
laboratory testing, pavement subgrades are expected to consist of reconditioned lean clay.
These soils classify as A-6 soils in accordance with the American Association of State
and Highway Transportation Officials (AASHTO) classification system and exhibit low
remolded shear strength. A resistance value (R-value) of 5 was estimated for the
subgrade soils and used in the pavement section design.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
11
Traffic loading on the site pavements is expected to consist of areas of low volumes of
automobiles and light trucks, as well as areas of higher light vehicle traffic volumes and
occasional heavier trash and delivery trucks. Equivalent 18-kip single axle loads
(ESAL’s) were estimated for the quantity of site traffic anticipated. Two (2) general
pavement design categories are outlined below in Table I. Standard duty pavements
could be considered in automobile drive and parking areas. Heavy duty pavements
should be considered for access drives and other areas of the site expected to receive
higher traffic volumes or heavy truck traffic. Thicker pavement sections may be
warranted if high volumes of heavy truck traffic are anticipated in areas of the site. we
would be happy to complete a pavement section design based on the actual type and
quantity of heavy trucks anticipated to utilize these areas.
Proofrolling of the pavement subgrades should be completed to help identify unstable
areas. Depending on the in-place moisture content of the subgrade soils immediately
prior to paving, the time of year when construction occurs and other hydrologic
conditions, stabilization of the subgrade soils may become necessary to develop a
suitable paving platform. Isolated areas of subgrade instability can be mended on a case
by case basis. If more widespread subgrade instability is observed at the time of
proofrolling, we recommend consideration be given to stabilization of the pavement
subgrades with Class C fly ash. With the increase in support strength developed by the
fly ash stabilization procedures, it is our opinion some credit for the stabilized zone could
be included in the pavement section design, reducing the required thickness of overlying
asphaltic concrete and aggregate base course. Pavement section design options
incorporating some structural credit for the stabilized subgrade soils are outlined below in
Table 1. Fly ash-stabilization can also eliminate some of the uncertainty associated with
attempting to pave late in the season and during periods of inclement weather.
It has been our experience that full-depth asphaltic concrete pavement sections typically
do not perform as well as structurally equivalent composite pavement sections
constructed upon clay subgrade soils and we do not recommend full-depth asphalt
sections be constructed for this project. Pavement section design options are outline
below in Table 1. Alternative pavement sections could be considered and we would be
happy to discuss any alternatives at your request.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
12
TABLE 1 – PAVEMENT SECTION DESIGN
Standard Duty Heavy Duty
Option A – Composite
Asphaltic Concrete (Grading S or SX)
Aggregate Base (Class 5 or 6)
4”
6”
5”
8”
Option B – Composite on Stabilized Subgrade
Asphaltic Concrete (Grading S or SX)
Aggregate Base (Class 5 or 6)
Fly Ash Stabilized Subgrade
3”
4”
12”
4”
6”
12”
Option C – Portland Cement Concrete Pavement 5” 6”
Asphaltic concrete should consist of a bituminous plant mix composed of a mixture of
aggregate, filler, binders and additives (if required) meeting the design requirements of
the City of Fort Collins. Aggregate used in the asphaltic concrete should meet specific
gradation requirements such as Colorado Department of Transportation (CDOT) grading
S (¾-inch minus) or SX (½-inch minus) specifications. Hot mix asphalt designed using
“Superpave” criteria should be compacted to within 92 to 96% of the materials Maximum
Theoretical Density. Aggregate base should be consistent with CDOT requirements for
Class 5 or Class 6 aggregate base, placed in loose lifts not to exceed 9 inches thick and
compacted to at least 95% of the materials standard Proctor maximum dry density.
If fly ash stabilization procedures will be completed, we recommend the addition of 12%
Class ‘C’ fly ash based on component dry unit weights. A 12-inch thick stabilized zone
should be constructed by thoroughly blending the fly ash with the in-place subgrade soils.
Some “fluffing” of the finish subgrade level should be expected with the stabilization
procedures. The blended materials should be adjusted in moisture content to within the
range of ±2% of standard Proctor optimum moisture content and compacted to at least
95% of the material’s standard Proctor maximum dry density within two (2) hours of fly
ash addition.
For areas subjected to truck turning movements and/or concentrated and repetitive
loading such as dumpster or truck parking and loading areas, we recommend
consideration be given to the use of Portland cement concrete pavement with a minimum
thickness of 6 inches. The concrete used for site pavements should be air entrained and
have a minimum 28-day compressive strength of 4,000 psi. Woven wire mesh or fiber
entrained concrete should be considered to help in the control of shrinkage cracking.
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
13
The proposed pavement section designs do not include an allowance for excessive
loading conditions imposed by heavy construction vehicles or equipment. Heavily
loaded concrete or other building material trucks and construction equipment can cause
some localized distress to site pavements. The recommended pavement sections are
minimums and periodic maintenance efforts should be expected. A preventative
maintenance program can help increase the service life of site pavements.
Corrosive Soil Characteristics
We measured the soluble sulfate concentration of two (2) representative samples of the
subsoils which will likely be in contact with structural concrete. The sulfate
concentrations measured in the samples fell within the ‘negligible’ risk category with
respect to concrete sulfate attack; therefore Type I cement should be suitable for concrete
members on and below grade. As an added precaution, Type I/II Portland cement could
be considered for additional sulfate resistance of construction concrete. Foundation
concrete should be designed in accordance with the provisions of the ACI Design
Manual, Section 318, Chapter 4.
Drainage
Positive drainage is imperative for satisfactory long-term performance of the proposed
building and associated site improvements. We recommend positive drainage be
developed away from the structure during construction and maintained throughout the
life of the site improvements, with twelve (12) inches of fall in the first 10 feet away from
the building. Shallower slopes could be considered in hardscape areas. In the event that
poor or negative drainage develops adjacent to the building over time, the original grade
and associated positive drainage outlined above should be immediately restored.
Care should be taken in the planning of landscaping to avoid features which could result
in the fluctuation of the moisture content of the foundation bearing and flatwork and
pavement subgrade soils. We recommend watering systems be placed a minimum of 5
feet away from the perimeter of the site structure and be designed to discharge away from
all site improvements. Gutter systems should be considered to help reduce the potential
Geotechnical Subsurface Exploration Report
Allied Building Products Storage Building (Lot 2 – Centerpoint Plaza)
2155 Midpoint Drive, Fort Collins, Colorado
Soilogic Job No. 18-1265
14
for water ponding adjacent to the structure, with the gutter downspouts, roof drains or
scuppers extended to discharge a minimum of 5 feet away from structural, flatwork and
pavement elements. Water which is allowed to pond adjacent to site improvements can
result in unsatisfactory performance of those improvements over time.
LIMITATIONS
This report was prepared based upon the data obtained from the completed site
exploration, laboratory testing, engineering analysis and any other information discussed.
The completed borings provide an indication of subsurface conditions at the boring
locations only. Variations in subsurface conditions can occur in relatively short distances
away from the borings. This report does not reflect any variations which may occur
across the site or away from the borings. If variations in the subsurface conditions
anticipated become evident, the geotechnical engineer should be notified immediately so
that further evaluation and supplemental recommendations can be provided.
The scope of services for this project does not include either specifically or by
implication any biological or environmental assessment of the site or identification or
prevention of pollutants or hazardous materials or conditions. Other studies should be
completed if concerns over the potential of such contamination or pollution exist.
The geotechnical engineer should be retained to review the plans and specifications so
that comments can be made regarding the interpretation and implementation of our
geotechnical recommendations in the design and specifications. The geotechnical
engineer should also be retained to provide testing and observation services during
construction to help determine that the design requirements are fulfilled.
This report has been prepared for the exclusive use of our client for specific application
to the project discussed and has been prepared in accordance with the generally accepted
standard of care for the profession. No warranties express or implied, are made. The
conclusions and recommendations contained in this report should not be considered valid
in the event that any changes in the nature, design or location of the project as outlined in
this report are planned, unless those changes are reviewed and the conclusions of this
report modified and verified in writing by the geotechnical engineer.
LOG OF BORING B-1
1/1 CME 45
4" CFA
Automatic
ZG/BM
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0-6" VEGETATION AND TOPSOIL -
1
-
CL SANDY LEAN CLAY 2
brown/rust -
very stiff 3
With Scattered Gravel -
4
-
5 CS 22 11.2 117.8 9000+ 3.9% 5300 - - -
-
6
-
7
-
8
-
9
-
SM-GM SILTY SAND with GRAVEL 10 CS 16 2.7 - N/A - - - - 8.7%
reddish brown -
medium dense to dense 11
-
12
-
Gravel and Possible Cobble with Depth 13
-
14
-
15 CS 50 4.8 - N/A - - - - -
BOTTOM OF BORING @ 15.0' -
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
USCS
Sampler
LOG OF BORING B-2
1/1 CME 45
4" CFA
Automatic
ZG/BM
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0-6" GRAVEL SURFACING -
1
-
CL SANDY LEAN CLAY 2
brown/rust -
medium stiff 3 CS 7 19.3 104.7 4000 None <500 - - -
-
4
-
5 CS 8 17.1 103.1 2000 None <500 - - -
-
6
-
7
-
8
-
9
SM-GM SILTY SAND with GRAVEL -
reddish brown 10 CS 14 16.7 - N/A - - - - -
loose to dense -
11
-
12
-
Gravel and Possible Cobble with Depth 13
-
14
-
15 CS 50/10 4.6 122.9 N/A - - - - -
BOTTOM OF BORING @ 15.0' -
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
24 Hours After Drilling -
USCS
LOG OF BORING B-3
1/1 CME 45
4" CFA
Automatic
ZG/BM
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0-6" VEGETATION AND TOPSOIL -
1
-
2
SM-GM SILTY to CLAYEY SAND with GrAVEL -
brown/rust 3 CS 14 2.4 - N/A - - - - 8.7%
loose to medium dense -
4
-
5 CS 7 7.5 103.8 N/A - - - - -
-
6
-
7
-
Increasing Gravel with Depth 8
-
9
-
10 CS 17 5.0 - N/A - - - - -
BOTTOM OF BORING @ 10.0' -
11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
24 Hours After Drilling -
USCS
LOG OF BORING B-4
1/1 CME 45
4" CFA
Automatic
ZG/BM
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0-6" GRAVEL SURFACING -
FILL - SILTY SAND AND GRAVEL 1
brown/grey -
2
-
3 CS 9 19.2 101.6 4000 None <500 - - -
CL SANDY LEAN CLAY -
brown/rust 4
medium stiff -
5 CS 10 16.0 119.1 5000 - - 37 18 69.7%
-
6
-
7
-
8
SM-GM SILTY SAND AND GRAVEL -
brown/rust 9
loose -
10 CS 12 6.3 - N/A - - - - -
BOTTOM OF BORING @ 10.0' -
11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
24 Hours After Drilling -
USCS
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 117.8
500
Final Moisture 16.3%
% Swell @ 500 psf 3.9%
Swell Pressure (psf) 5,300
Sample ID: B-1 @ 4
Sample Description: Brown/Rust Sandy Lean Clay (CL)
Initial Moisture 11.2%
SWELL/CONSOLIDATION TEST SUMMARY
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 104.7
500
Final Moisture 20.8%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Initial Moisture 19.3%
Sample ID: B-2 @ 2
Sample Description: Brown/Rust Sandy Lean Clay (CL)
(Swell Only)
SWELL/CONSOLIDATION TEST SUMMARY
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 103.1
500
Final Moisture 22.2%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Initial Moisture 17.1%
Sample ID: B-2 @ 4
Sample Description: Brown/Rust Sandy Lean Clay (CL)
SWELL/CONSOLIDATION TEST SUMMARY
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 101.6
500
Final Moisture 16.5%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Initial Moisture 19.2%
Sample ID: B-4 @ 2
Sample Description: Brown/Rust Sandy Lean Clay (CL)
(Swell Only)
SWELL/CONSOLIDATION TEST SUMMARY
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory TestsA Soil Classification
Group
Symbol
Group NameB
Clean Gravels Cu ! 4 and 1 " Cc " 3E GW Well graded gravelF
Less than 5% finesC Cu
< 4 and/or 1 > Cc > 3E GP Poorly graded gravelF
Fines classify as ML or MH GM Silty gravelF,G, H
Coarse Grained Soils
More than 50% retained
on No. 200 sieve
Gravels
More than 50% of coarse
fraction retained on
No. 4 sieve Gravels with Fines More
than 12% finesC Fines classify as CL or CH GC Clayey gravelF,G,H
Clean Sands Cu ! 6 and 1 " Cc " 3E SW Well graded sandI
Less than 5% finesD Cu
< 6 and/or 1 > Cc > 3E SP Poorly graded sandI
Fines classify as ML or MH SM Silty sandG,H,I
Sands
50% or more of coarse
fraction passes
No. 4 sieve Sands with Fines
More than 12% finesD Fines classify as CL or CH SC Clayey sandG,H,I
Silts and Clays PI > 7 and plots on or above “A” lineJ CL Lean clayK,L,M
Liquid limit less than 50
Inorganic
PI < 4 or plots below “A” lineJ ML SiltK,L,M
Liquid limit - oven
dried
Organic clayK,L,M,N
Fine-Grained Soils
50% or more passes the
No. 200 sieve
Organic
Liquid limit - not
dried
< 0.75 OL
Organic siltK,L,M,O
Inorganic PI plots on or above “A” line CH Fat clayK,L,M
Silts and Clays
Liquid limit 50 or more
PI plots below “A” line MH Elastic siltK,L,M
Organic Liquid limit - oven dried Organic clayK,L,M,P
Liquid limit - not dried
< 0.75 OH
Organic siltK,L,M,Q
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-in. (75-mm) sieve
B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name.
C Gravels with 5 to 12% fines require dual symbols: GW-GM well graded
gravel with silt, GW-GC well graded gravel with clay, GP-GM poorly
graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well graded
sand with silt, SW-SC well graded sand with clay, SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon - 1⅜" I.D., 2" O.D., unless otherwise noted HS: Hollow Stem Auger
ST: Thin-Walled Tube – 2.5" O.D., unless otherwise noted PA: Power Auger
RS: Ring Sampler - 2.42" I.D., 3" O.D., unless otherwise noted HA: Hand Auger
CS: California Barrel - 1.92" I.D., 2.5" O.D., unless otherwise noted RB: Rock Bit
BS: Bulk Sample or Auger Sample WB: Wash Boring or Mud Rotary
The number of blows required to advance a standard 2-inch O.D. split-spoon sampler (SS) the last 12 inches of the total 18-inch
penetration with a 140-pound hammer falling 30 inches is considered the “Standard Penetration” or “N-value”. For 2.5” O.D.
California Barrel samplers (CB) the penetration value is reported as the number of blows required to advance the sampler 12
inches using a 140-pound hammer falling 30 inches, reported as “blows per inch,” and is not considered equivalent to the
“Standard Penetration” or “N-value”.
WATER LEVEL MEASUREMENT SYMBOLS:
WL: Water Level WS: While Sampling
WCI: Wet Cave in WD: While Drilling
DCI: Dry Cave in BCR: Before Casing Removal
AB: After Boring ACR: After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other
times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater.
In low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils
have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand.
Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they
are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents
may be added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined
on the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
FINE-GRAINED SOILS COARSE-GRAINED SOILS BEDROCK
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Consistency
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Relative
Density
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Consistency
< 3 0-2 Very Soft 0-5 < 3 Very Loose < 24 < 20 Weathered
3-5 3-4 Soft 6-14 4-9 Loose 24-35 20-29 Firm
6-10 5-8 Medium Stiff 15-46 10-29 Medium Dense 36-60 30-49 Medium Hard
11-18 9-15 Stiff 47-79 30-50 Dense 61-96 50-79 Hard
19-36 16-30 Very Stiff > 79 > 50 Very Dense > 96 > 79 Very Hard
> 36 > 30 Hard
RELATIVE PROPORTIONS OF SAND AND
GRAVEL
GRAIN SIZE TERMINOLOGY
Descriptive Terms of
Other Constituents
Percent of
Dry Weight
Major Component
of Sample
Particle Size
Trace < 15 Boulders Over 12 in. (300mm)
With 15 – 29 Cobbles 12 in. to 3 in. (300mm to 75 mm)
Modifier > 30 Gravel 3 in. to #4 sieve (75mm to 4.75 mm)
Sand
Silt or Clay
#4 to #200 sieve (4.75mm to 0.075mm)
Passing #200 Sieve (0.075mm)
RELATIVE PROPORTIONS OF FINES PLASTICITY DESCRIPTION
Descriptive Terms of
Other Constituents
Percent of
Dry Weight
Term Plasticity Index
Trace
With
Modifiers
< 5
5 – 12
> 12
Non-plastic
Low
Medium
High
0
1-10
11-30
30+
F If soil contains ! 15% sand, add “with sand” to group name.
G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
HIf fines are organic, add “with organic fines” to group name.
I If soil contains ! 15% gravel, add “with gravel” to group name.
J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add “with sand” or “with
gravel,” whichever is predominant.
L If soil contains ! 30% plus No. 200 predominantly sand, add
“sandy” to group name.
M If soil contains ! 30% plus No. 200, predominantly gravel, add
“gravelly” to group name.
N PI ! 4 and plots on or above “A” line.
O PI < 4 or plots below “A” line.
P PI plots on or above “A” line.
Q PI plots below “A” line.
Sampler
Atterberg Limits
Start Date 8/30/2018 Auger Type: During Drilling None
Finish Date 8/30/2018 Hammer Type: After Drilling None
Surface Elev. - Field Personnel:
Sheet Drilling Rig: Water Depth Information
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
Sampler
Atterberg Limits
Start Date 8/30/2018 Auger Type: During Drilling None
Finish Date 8/30/2018 Hammer Type: After Drilling None
Surface Elev. - Field Personnel:
Sheet Drilling Rig: Water Depth Information
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
Sampler
Atterberg Limits
Start Date 8/30/2018 Auger Type: During Drilling 12'
Finish Date 8/30/2018 Hammer Type: After Drilling 12'
Surface Elev. - Field Personnel:
Sheet Drilling Rig: Water Depth Information
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018
Atterberg Limits
Surface Elev. - Field Personnel: 24 Hours After Drilling -
Finish Date 8/30/2018 Hammer Type: After Drilling 12'
Sheet Drilling Rig: Water Depth Information
Start Date 8/30/2018 Auger Type: During Drilling 12'
ALLIED BUILDING PRODUCTS STORAGE BUILDING
2155 MIDPOINT DRIVE, FORT COLLINS, COLORADO
Project # 18-1265
September 2018