Loading...
HomeMy WebLinkAboutOASIS ON OLIVE - FDP - FDP180018 - SUBMITTAL DOCUMENTS - ROUND 2 - DRAINAGE RELATED DOCUMENT1218 W. ASH, STE. A, WINDSOR, COLORADO 80550 TEL. 970.674.3300 – FAX 970.674.3303 September 26, 2018 Mr. Wes Lamarque Fort Collins Utilities – Stormwater 700 Wood Street Fort Collins, CO 80522 Re: Oasis on Olive – 310 W. Olive Street Final Storm Drainage Letter Dear Wes, Please accept the following letter describing the storm drainage intent demonstrating the proposed site improvement’s ability to comply with the City’s stormwater requirements. INTRODUCTION The Oasis on Olive proposes to construct a condominium building with supporting utility infrastructure, site accesses (pedestrian/vehicular). The site is located along the north side of W. Olive St., between S. Howes St. and S. Meldrum St., addressed as 310 W. Olive Street. A vicinity map is attached for reference. EXISTING CONDITIONS The project site is located within the Udall drainage basin and standard water quality is not required. The existing site consists of two (2) parking garages, pedestrian pathways, driveways, and gardens. The total site is approximately 0.22 acres and currently site has approximately 3,844 sq-ft of impervious area and is 35.5% impervious. There are two (2) drainage basins to describe the drainage paths. The larger basin (Basin H1) surface drains south to W. Olive St. A narrow basin (Basin H2) describes the private drive that surface drains west to Canyon Ave. The garages, driveways, and pathways are all to be removed to accommodate the proposed improvements. The Owner would like to preserve as much of the existing gardens as possible. The gardens are generally located in the southeast corner of the site. We are not aware of any site-specific drainage studies for this lot. The project is located within the City regulated 100-yr Old Town Basin floodplain. The Master Plan was prepared by Anderson Consulting Engineers, dated July 15, 2003. The project is not located within a FEMA mapped 100-yr floodplain as shown within FIRM Map No. 08069C0979H though is within a defined City of Fort Collins floodplain. Refer to the attached exhibits. PROPOSED DEVELOPMENT The improvements proposed will consist of a 3 story multi-family building, with tuck under parking, and will include the supporting utility infrastructure and pedestrian/vehicle accesses. The project is planned to be constructed in a single phase. Oasis on Olive Final Storm Drainage Letter September 26, 2018 Page 2 of 4 The proposed improvements will increase the impervious area to 7,401 sq-ft and will be approximately 70.3% impervious. Similar to the existing conditions, the site is divided into two (2) major drainage basins to describe the drainage paths. Basin D1 consists of the area draining to W. Olive St. and is divided into three (3) sub-basins for conveyance and Low Impact Development calculations. Runoff within these basins are directed to bioretention / rain garden planters for treatment and surface flows either sheet flow or are conveyed by a storm drain to W. Olive St. Basin D2 consists of the improved east-west private drive. Runoff is collected in a curb and gutter and directed to Canyon Ave, similar to the historic drainage path. The proposed improvements create an increase in impervious area 3,558 sq-ft and is under the increase of 5,000 sq-ft which would require onsite detention. Standard water quality is provided downstream within the Udall Basin and is not required onsite. A combination of the bioretention / rain garden planters are proposed to provide water quality enhancement and are designed to satisfy the Low Impact Development (LID) requirements. All calculations and exhibits are attached for reference. CITY FLOODPLAIN/FLOODWAY An existing floodplain/floodway exists within and along W. Olive St. The driveway extending from W. Olive St into the site is proposed to be improved. The elevations along the driveway are designed to match or be slightly less that the existing grades within this area, with the intent to not effect or change the floodplain/floodway elevations. Per the City’s flood maps, cross-section 3164 extends through the site near the upstream corner of the site. The base flood elevation is 5001.48 ft (NAVD88). No portions of the proposed structure is within the flood plain or floodway. To ensure that we are compliant with the no-rise requirement, the driveway elevations are unable to be raised and the garage entries are at 5001.85 ft. Floodplain use permits are anticipated for the completion of the improvements with the floodplain/floodway and a no-rise certification will be required for the certificate of occupancy. LOW IMPACT DEVELOPMENT TECHNIQUES In reference to the code requirements for implementation of Low Impact Development (LID) techniques, the use of a bioretention / rain garden planters are necessary to satisfy these requirements. The rain garden will promote infiltration while capturing fine sediment that drains off of the impervious areas. The bioretention / rain garden planters will be lined due to the vicinity to the proposed building and will provide filtration to remove fine sediment. A Standard Operations Procedure will be provided at final design to assist in ensuring that these BMPs will adequately perform over time. Due to the historical value of this site along with consideration of the adjacent historic buildings and the heritage garden on site, it was approved with the City and the Landmark Preservation Commission, that only 50% of the proposed impervious area is required for treatment with bioretention / rain garden planters. Due to the roof configuration we are able to treat 48.5% of the overall proposed impervious area. Below is a description of the 4 step process for selecting structural BMPs: Urban Drainage and Flood Control District (UDFCD) recommends a Four Step Process for receiving water protection that focuses on reducing runoff volumes, treating the water quality capture volume (WQCV), stabilizing drainageways and implementing long-term source controls. The Four Step Process applies to the management of smaller, frequently occurring events. Oasis on Olive Final Storm Drainage Letter September 26, 2018 Page 3 of 4 Step 1: Employ Runoff Reduction Practices To reduce runoff peaks, volumes, and pollutant loads from urbanizing areas, implement Low Impact Development (LID) strategies, including Minimizing Directly Connected Impervious Areas (MDCIA). Runoff from the building roof will be conveyed to the bioretention / rain garden planters via roof drains. The rain garden planters will slow runoff, and filter runoff prior to being released into the adjacent storm drain system. Step 2: Implement BMPs that Provide a Water Quality Capture Volume with Slow Release The rain garden planters are designed to provide water quality capture volume per Urban Drainage’s recommendations and calculations. The captured runoff is design for a 12-hr drain time. Step 3: Stabilize Drainageways Natural Drainageways are subject to bed and bank erosion due to increases in frequency, duration, rate and volume of runoff during and following development. Because the site will drain to an existing roadway and storm system, bank stabilization is unnecessary with this project. Step 4: Implement Site Specific and Other Source Control BMPs Proactively controlling pollutants at their source by preventing pollution rather than removing contaminants once they have entered the stormwater system or receiving waters is important when protecting storm systems and receiving waters. This can be accomplished through site specific needs such as construction site runoff control, post-construction runoff control and pollution prevention / good housekeeping. It will be the responsibility of the contractor to develop a procedural best management practice for the site. All calculations are attached for reference. EROSION CONTROL Erosion and sedimentation will be controlled on-site by use of sediment control logs, inlet protection, a gravel construction entrance, seeding, mulch, and turf. The measures are designed to limit the overall sediment yield increase due to construction as required by the City of Fort Collins. During overlot and final grading the soil will be roughened and furrowed perpendicular to the prevailing winds. During the performance of the work required by these specifications or any operations appurtenant thereto, whether on right-of-way provided by the City or elsewhere, the contractor shall furnish all labor, equipment, materials, and means required. The Contractor shall carry out proper efficient measures wherever and as necessary to reduce dust nuisance, and to prevent dust nuisance that has originated from his operations from damaging crops, orchards, cultivated fields, and dwellings, or causing naissance to persons. The Contractor will be held liable for any damage resulting from dust originating from his operations under these specifications on right-of-way or elsewhere. It is unlawful to track or cause to be tracked mud or other debris onto city streets or rights-of-way. Wherever construction vehicles access routes or intersect paved public roads, previsions must be made to Oasis on Olive Final Storm Drainage Letter September 26, 2018 Page 4 of 4 minimize the transport of sediment by runoff or vehicles tracking onto the paved surface. Stabilized construction entrances are required with base material consisting of 6” coarse aggregate. The contractor will be responsible for clearing mud tracked onto city streets on a daily basis. All temporary and permanent erosion and sediment control practices must be maintained and repaired as needed to assure continued performance of their intended function. Silt fence and sediment control logs will require periodic replacement. Maintenance is the responsibility of the contractor. All disturbed areas must be seeded and mulched within 30 days of project start. Vegetation shall not be considered established until a ground cover is achieved which is demonstrated to be mature enough to control soil erosion to the satisfaction of the City Inspector and to survive severe weather condition. Thank you in advance for your time and if you have any questions or comments please contact me at (970) 347-8917. Sincerely, Jason T. Claeys, P.E., LEED AP Interwest Consulting Group Attachments SITE Vicinity Map Scale: 1" = 1000' PROJECT DATUM: NAVD88 CITY OF FORT COLLINS BENCHMARK #1-12 SOUTHEAST CORNER OF LAPORTE AVENUE AND WHITCOMB STREET, ON A STORM INLET ON WHITCOMB STREET ELEV= 5004.15 CITY OF FORT COLLINS BENCHMARK #6-00 ON A CATCH BASIN AT THE NORTHWEST CORNER OF MULBERRY ST. AND COLLEGE AVENUE ELEV= 4993.85 PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. IF NGVD29 UNADJUSTED IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATIONS SHOULD BE USED: NGVD UNADJUSTED = 5004.15 (NAVD88) - 3.18 NGVD UNADJUSTED = 4993.85 (NAVD88) - 3.17 Vicinity Map 1,128 188.1 Olive Street Condos This map is a user generated static output from the City of Fort Collins FCMaps Internet mapping site and is for reference only. Data layers that appear on this map may or may not be accurate, current, or otherwise reliable. City of Fort Collins - GIS 143.0 1: WGS_1984_Web_Mercator_Auxiliary_Sphere 0 71.50 143.0 Feet Notes Legend 857 FEMA Floodplain FEMA High Risk - Floodway FEMA High Risk - 100 Year FEMA Moderate Risk - 100 / 500 Year FEMA Map Panel City Floodplains City High Risk - Floodway City High Risk - 100 Year City Moderate Risk - 100 Year City Limits Site Location Oasis on Olive Oasis on Olive (approx site location) Oasis on Olive DRAINAGE SUMMARY Design Engineer: Design Firm: Project Number: Date: IMPERVIOUS SUMMARY: Description Impervious Area % Impervious Existing 3,844 35.5% Proposed 7,401 70.3% Difference 3,558 34.8% J.Claeys Interwest Consulting Group 1335-176-00 July 18, 2018 1335-176-00 Rational Calcs (FC).xlsx Page 1 of 1 Interwest Consulting Group WEST OLIVE STREET CANYON AVENUE LOT 3 LOT 2 LOT 1 SOUTH HOWES STREET 1218 W. Ash, Suite A Windsor , Colorado 80550 Phone: (970) 674-3300 Fax: (970) 674-3303 I N T E R W E S T C O N S U L T I N G G R O U P PREPARED FOR PROJ. NO. DATE: SCALE (H): SCALE (V): CHECKED BY: DESIGNED BY: PROJECT NAME OASIS ON OLIVE HISTORIC DRAINAGE EXHIBIT 03/14/18 1" = 20' N/A JTC JTC 1335-176-00 1 of 1 THIS OLD HOWES, LLC 561 YORK STREET DENVER, CO 80209 PHONE: 970.484.5907 Design Engineer: Design Firm: Project Number: Date: % Impervious Runoff Coefficient C Return Period Frequency Adjustment Factor (Cf) 100% 0.95 2-year to 10-year 1.00 90% 0.95 100-year 1.25 90% 0.95 40% 0.50 0% 0.25 C2 to C10 C100 H1 8,922 0.205 0 1,090 1,945 0 5,888 30.6% 0.49 0.61 H2 809 0.019 0 0 809 0 0 90.0% 0.95 1.00 Overall 9,731 0.223 0 1,090 2,754 0 5,888 35.5% 0.53 0.66 Apavers (sq feet) Alawn (sq feet) Weighted % Impervious COMPOSITE Oasis on Olive EXISTING IMPERVIOUS AREA CALCULATION Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) DESIGN CRITERIA: BASINS: % Impervious values from Table RO-3 in the Urban Storm Drainage Criteria Manual Sub-basin Designation Atotal (sq feet) Atotal (acres) Apaved (sq feet) Aroof (sq feet) Awalk/RAP (sq feet) Lawns (Heavy, 2-7% Slope) J.Claeys Interwest Consulting Group 1335-176-00 July 18, 2018 Runoff Coefficients and Frequency Adjustment Factors for City of Fort Collins - Storm Water Criteria Manual Land Use Paved Roof Design Engineer: Design Firm: Project Number: Date: % Impervious Runoff Coefficient C Return Period Frequency Adjustment Factor (Cf ) 100% 0.95 2-year to 10-year 1.00 90% 0.95 100-year 1.25 90% 0.95 40% 0.50 0% 0.25 C2 to C10 C100 D1a 1,421 0.03 0 1,421 0 0 0 90.0% 0.95 1.00 D1b 1,364 0.03 0 1,132 0 0 232 74.7% 0.83 1.00 D1c 6,014 0.14 0 3,153 928 0 1,933 61.1% 0.72 0.91 D2 780 0.02 767 0 0 0 13 98.4% 0.94 1.00 Overall 9,579 0.22 767 5,706 928 0 2,177 70.3% 0.79 0.99 Oasis on Olive DEVELOPED IMPERVIOUS AREA CALCULATION DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) BASINS: % Impervious values from Table RO-3 in the Urban Storm Drainage Criteria Manual J.Claeys Interwest Consulting Group 1335-176-00 July 18, 2018 Land Use Paved Roof Walks Runoff Coefficients and Frequency Adjustment Factors for City of Fort Collins - Storm Water Criteria Manual Gravel/Pavers Lawns (Heavy, 2-7% Slope) Sub-basin Designation Atotal (sq feet) Atotal (acres) Weighted % Impervious A COMPOSITE paved (sq feet) Aroof Design Engineer: Design Firm: Project Number: Date: EQUATIONS: -Equation 6-2 -Equation 6-4 -Urbanized Check Equation 6-5 - CoFC Overland Flow CONSTRAINTS: 300 ft - Overland flow shall not exceed for developed condition 500 ft - Overland flow shall not exceed for undeveloped condition Final t c = minimum of t i + t t and urbanized basin check recommended minimum t c = 5 min for urbanized basins Time of Concentration (2-yr to 10-yr) Type of Travel Surface Cv 1a D1a 90.0% 0.95 0.033 26 0.3000 0.46 69 0.0195 Paved Areas 20 2.79 0.41 5.00 0.0959 5.00 5.00 1b D1b 74.7% 0.83 0.031 37 0.3000 0.98 145 0.0040 Paved Areas 20 1.26 1.91 5.00 0.0635 7.20 5.00 1c D1c 61.1% 0.72 0.138 53 0.0186 4.15 166 0.0100 Paved Areas 20 2.00 1.38 5.53 0.0121 10.08 5.53 2 D2 98.4% 0.94 0.018 17 0.0266 0.90 43 0.0191 Paved Areas 20 2.76 0.26 5.00 0.0212 5.00 5.00 July 18, 2018 Oasis on Olive DEVELOPED TIME OF CONCENTRATION J.Claeys Interwest Consulting Group 1335-176-00 LENGTH (ft) DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) Overland Flow Equations for City of Fort Collins - Storm Water Criteria Manual SUB-BASIN DATA INITIAL/OVERLAND TIME (ti ) TRAVEL TIME (tt ) tc =ti +tt (min) Urban Check Final tc (min) DESIGN POINT Sub-basin % Impervious C2-10 AREA (acres) tt (min) OVERALL SLOPE (ft/ft) tc (min) SLOPE (ft/ft) Design Engineer: Design Firm: Project Number: Date: EQUATIONS: -Equation 6-2 -Equation 6-4 -Urbanized Check Equation 6-5 - CoFC Overland Flow CONSTRAINTS: 300 ft - Overland flow shall not exceed for developed condition 500 ft - Overland flow shall not exceed for undeveloped condition Final t c = minimum of t i + t t and urbanized basin check recommended minimum t c = 5 min for urbanized basins Time of Concentration (100-yr) Type of Travel Surface Cv 1A D1a 90.0% 1.00 0.033 26 0.3000 0.31 69 0.0195 Paved Areas 20 2.79 0.41 5.00 0.0959 5.00 5.00 1B D1b 74.7% 1.00 0.031 37 0.3000 0.36 145 0.0040 Paved Areas 20 1.26 1.91 5.00 0.0635 7.20 5.00 2A D1c 61.1% 0.91 0.138 53 0.0186 2.15 166 0.0100 Paved Areas 20 2.00 1.38 5.00 0.0121 10.08 5.00 2B D2 98.4% 1.00 0.018 17 0.0266 0.55 43 0.0191 Paved Areas 20 2.76 0.26 5.00 0.0212 5.00 5.00 July 18, 2018 Oasis on Olive DEVELOPED TIME OF CONCENTRATION J.Claeys Interwest Consulting Group 1335-176-00 LENGTH (ft) DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) Overland Flow Equations for City of Fort Collins - Storm Water Criteria Manual SUB-BASIN DATA INITIAL/OVERLAND TIME (ti ) TRAVEL TIME (tt ) tc =ti +tt (min) Urban Check Final tc (min) DESIGN POINT Sub-basin % Impervious C100 AREA (acres) tt (min) OVERALL SLOPE (ft/ft) tc (min) SLOPE (ft/ft) Design Engineer: Design Firm: Project Number: Date: EQUATIONS: I = rainfall intensity (in/hr) Q n = n -yr peak discharge (cfs) P 1 = one-hour point rainfall depth (in) C n = n -yr runoff coefficient t c = time of concentration (min) I n = n -yr rainfall intensity (in/hr) P 1-2yr = 0.82 in A n = Basin drainage area (ac) P 1-10yr = 1.40 in P 1-100yr = 2.86 in BASIN SUMMARY: tc (min) Runoff Coeff (C2-10) C(A) (acres) Intensity (in/hr) Q (ft3/s) tc (min) Runoff Coeff (C2-10) C(A) (acres) Intensity (in/hr) Q (ft3/s) tc (min) Runoff Coeff. (C100) C(A) (acres) Intensity (in/hr) Q (ft3/s) 1a D1a 0.033 5.00 0.95 0.03 2.78 0.09 5.00 0.95 0.03 4.87 0.15 5.00 1.00 0.03 9.95 0.32 1b D1b 0.031 5.00 0.83 0.03 2.78 0.07 5.00 0.83 0.03 4.87 0.13 5.00 1.00 0.03 9.95 0.31 1c D1c 0.138 5.53 0.72 0.10 2.70 0.27 5.53 0.72 0.10 4.61 0.46 5.00 0.91 0.13 9.95 1.24 2 D2 0.018 5.00 0.94 0.02 2.78 0.05 5.00 0.94 0.02 4.87 0.08 5.00 1.00 0.02 9.95 0.18 10-yr Peak Runoff 100-yr Peak Runoff Oasis on Olive DEVELOPED PEAK RUNOFF Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised August 2006) DESIGN CRITERIA: Design Point Sub-basin Area (acres) J.Claeys Interwest Consulting Group 1335-176-00 July 18, 2018 2-yr Peak Runoff Q n = C n I n A n 0.786651) 1 ( 10 ) 28 . 5 t c P I + = 1335-176-00 Rational Calcs (FC).xlsx Page 4 of 4 Interwest Consulting Group Oasis on Olive Low Impact Development Design Engineer: Design Firm: Project Number: Date: DESIGN CRITERIA Low Impact Development Summary Pavement Area Summary 767 sqft 0 sqft 0.0% Developed Area Summary 7,401 sqft Total Area required for Treatment (50%): 3,701 sqft 0 sqft 0 sqft 0 sqft 3,588 sqft 3,588 sqft 48.5% Total New Impervious Area: J.Claeys Interwest Consulting Group 1335-176-00 July 18, 2018 City of Fort Collins - Ordinance No. 007, 2016 - Treat at least 75% of any newly developed or redeveloped impervious area using one or a combination of LID techniques, or - Treat at least 50% of any newly developed or redeveloped impervious area using one or a combination of LID techniques when 25% of private driveable surfaces are permeable. - Per Landmark Preservation Committee coordination & acceptance, LID treated area may be reduced to 50% of impervious area. Urban Storm Drainage Criteria Manual, Urban Drainage and Flood Control District, January 2010 Total New Paved Area: Permeable Paver Area: Percent Pavement Area as Permeable Pavers: Proposed Area of Pavers: Additional Area Treated by Pavers: Total Area Treated by Pavers: Impervious Area Treated by Rain Garden Planters: Total Area Treated by LID: Percent Site Area Treated by LID: 1 & 2, BLOCK 92 LOT 2 LOT 1 LOT 3 310 W. OLIVE ST. 1218 W. Ash, Suite A Windsor , Colorado 80550 Phone: (970) 674-3300 Fax: (970) 674-3303 I N T E R W E S T C O N S U L T I N G G R O U P PREPARED FOR PROJ. NO. DATE: SCALE (H): SCALE (V): CHECKED BY: DESIGNED BY: PROJECT NAME OASIS ON OLIVE 310 W. OLIVE STREET LID EXHIBIT 07/18/18 1"= 5' N/A JTC RA 1335-176-00 1 of 1 THIS OLD HOWES, LLC 561 YORK STREET DENVER, CO 80209 PHONE: 970.484.5907 CONTACT: STEVE SLEZAK SCALE: 1" = 0 5' 5 2.5 5 10 Sheet 1 of 2 Designer: Company: Date: Project: Location: 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, Ia Ia = 90.0 % (100% if all paved and roofed areas upstream of rain garden) B) Tributary Area's Imperviousness Ratio (i = Ia/100) i = 0.900 C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV = 0.32 watershed inches (WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i) D) Contributing Watershed Area (including rain garden area) Area = 1,421 sq ft E) Water Quality Capture Volume (WQCV) Design Volume VWQCV = cu ft Vol = (WQCV / 12) * Area F) For Watersheds Outside of the Denver Region, Depth of d6 = 0.43 in Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, VWQCV OTHER = 38.0 cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER = cu ft (Only if a different WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth (12-inch maximum) DWQCV = 12 in B) Rain Garden Side Slopes (Z = 4 min., horiz. dist per unit vertical) Z = 0.00 ft / ft (Use "0" if rain garden has vertical walls) C) Mimimum Flat Surface Area AMin = 26 sq ft D) Actual Flat Surface Area AActual = 38.75 sq ft E) Area at Design Depth (Top Surface Area) ATop = 38.75 sq ft F) Rain Garden Total Volume VT= 38.75 cu ft (VT= ((ATop + AActual) / 2) * Depth) 3. Growing Media Modified CoFC Rain Garden Section (12" Growing Media, 4" Pea Gravel, 8" AASHTO Class 2) 4. Underdrain System A) Are underdrains provided? B) Underdrain system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y = ft Volume to the Center of the Orifice ii) Volume to Drain in 12 Hours Vol12 = N/A cu ft iii) Orifice Diameter, 3/8" Minimum DO = N/A in Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (West - Basin D1a) UD-BMP (Version 3.06, November 2016) Choose One Choose One 18" Rain Garden Growing Media Other (Explain): YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - West).xlsm, RG 7/19/2018, 8:51 AM Sheet 2 of 2 Designer: Company: Date: Project: Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric A) Is an impermeable liner provided due to proximity of structures or groundwater contamination? PROVIDE A 30 MIL (MIN) PVC LINER WITH CDOT CLASS B GEOTEXTILE ABOVE IT. USE THE SAME GEOTEXTILE BELOW THE LINER IF THE SUBGRADE IS ANGULAR 6. Inlet / Outlet Control A) Inlet Control 7. Vegetation 8. Irrigation A) Will the rain garden be irrigated? Notes: Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (West - Basin D1a) Choose One Choose One Choose One Sheet Flow- No Energy Dissipation Required Concentrated Flow- Energy Dissipation Provided Plantings Seed (Plan for frequent weed control) Sand Grown or Other High Infiltration Sod Choose One YES NO YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - West).xlsm, RG 7/19/2018, 8:51 AM Sheet 1 of 2 Designer: Company: Date: Project: Location: 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, Ia Ia = 90.0 % (100% if all paved and roofed areas upstream of rain garden) B) Tributary Area's Imperviousness Ratio (i = Ia/100) i = 0.900 C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV = 0.32 watershed inches (WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i) D) Contributing Watershed Area (including rain garden area) Area = 1,129 sq ft E) Water Quality Capture Volume (WQCV) Design Volume VWQCV = cu ft Vol = (WQCV / 12) * Area F) For Watersheds Outside of the Denver Region, Depth of d6 = 0.43 in Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, VWQCV OTHER = 30.2 cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER = cu ft (Only if a different WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth (12-inch maximum) DWQCV = 12 in B) Rain Garden Side Slopes (Z = 4 min., horiz. dist per unit vertical) Z = 0.00 ft / ft (Use "0" if rain garden has vertical walls) C) Mimimum Flat Surface Area AMin = 20 sq ft D) Actual Flat Surface Area AActual = 31.25 sq ft E) Area at Design Depth (Top Surface Area) ATop = 31.25 sq ft F) Rain Garden Total Volume VT= 31.25 cu ft (VT= ((ATop + AActual) / 2) * Depth) 3. Growing Media Modified CoFC Rain Garden Section (12" Growing Media, 4" Pea Gravel, 8" AASHTO Class 2) 4. Underdrain System A) Are underdrains provided? B) Underdrain system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y = ft Volume to the Center of the Orifice ii) Volume to Drain in 12 Hours Vol12 = N/A cu ft iii) Orifice Diameter, 3/8" Minimum DO = N/A in Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (North - Basin D1b) UD-BMP (Version 3.06, November 2016) Choose One Choose One 18" Rain Garden Growing Media Other (Explain): YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - North).xlsm, RG 7/19/2018, 8:51 AM Sheet 2 of 2 Designer: Company: Date: Project: Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric A) Is an impermeable liner provided due to proximity of structures or groundwater contamination? PROVIDE A 30 MIL (MIN) PVC LINER WITH CDOT CLASS B GEOTEXTILE ABOVE IT. USE THE SAME GEOTEXTILE BELOW THE LINER IF THE SUBGRADE IS ANGULAR 6. Inlet / Outlet Control A) Inlet Control 7. Vegetation 8. Irrigation A) Will the rain garden be irrigated? Notes: Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (North - Basin D1b) Choose One Choose One Choose One Sheet Flow- No Energy Dissipation Required Concentrated Flow- Energy Dissipation Provided Plantings Seed (Plan for frequent weed control) Sand Grown or Other High Infiltration Sod Choose One YES NO YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - North).xlsm, RG 7/19/2018, 8:51 AM Sheet 1 of 2 Designer: Company: Date: Project: Location: 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, Ia Ia = 90.0 % (100% if all paved and roofed areas upstream of rain garden) B) Tributary Area's Imperviousness Ratio (i = Ia/100) i = 0.900 C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV = 0.32 watershed inches (WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i) D) Contributing Watershed Area (including rain garden area) Area = 586 sq ft E) Water Quality Capture Volume (WQCV) Design Volume VWQCV = cu ft Vol = (WQCV / 12) * Area F) For Watersheds Outside of the Denver Region, Depth of d6 = 0.43 in Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, VWQCV OTHER = 15.7 cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER = cu ft (Only if a different WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth (12-inch maximum) DWQCV = 12 in B) Rain Garden Side Slopes (Z = 4 min., horiz. dist per unit vertical) Z = 0.00 ft / ft (Use "0" if rain garden has vertical walls) C) Mimimum Flat Surface Area AMin = 11 sq ft D) Actual Flat Surface Area AActual = 16.25 sq ft E) Area at Design Depth (Top Surface Area) ATop = 16.25 sq ft F) Rain Garden Total Volume VT= 16.25 cu ft (VT= ((ATop + AActual) / 2) * Depth) 3. Growing Media Modified CoFC Rain Garden Section (12" Growing Media, 4" Pea Gravel, 8" AASHTO Class 2) 4. Underdrain System A) Are underdrains provided? B) Underdrain system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y = ft Volume to the Center of the Orifice ii) Volume to Drain in 12 Hours Vol12 = N/A cu ft iii) Orifice Diameter, 3/8" Minimum DO = N/A in Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (East - Basin D1c) UD-BMP (Version 3.06, November 2016) Choose One Choose One 18" Rain Garden Growing Media Other (Explain): YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - East).xlsm, RG 7/19/2018, 8:54 AM Sheet 2 of 2 Designer: Company: Date: Project: Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric A) Is an impermeable liner provided due to proximity of structures or groundwater contamination? PROVIDE A 30 MIL (MIN) PVC LINER WITH CDOT CLASS B GEOTEXTILE ABOVE IT. USE THE SAME GEOTEXTILE BELOW THE LINER IF THE SUBGRADE IS ANGULAR 6. Inlet / Outlet Control A) Inlet Control 7. Vegetation 8. Irrigation A) Will the rain garden be irrigated? Notes: Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (East - Basin D1c) Choose One Choose One Choose One Sheet Flow- No Energy Dissipation Required Concentrated Flow- Energy Dissipation Provided Plantings Seed (Plan for frequent weed control) Sand Grown or Other High Infiltration Sod Choose One YES NO YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - East).xlsm, RG 7/19/2018, 8:54 AM Sheet 1 of 2 Designer: Company: Date: Project: Location: 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, Ia Ia = 90.0 % (100% if all paved and roofed areas upstream of rain garden) B) Tributary Area's Imperviousness Ratio (i = Ia/100) i = 0.900 C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV = 0.32 watershed inches (WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i) D) Contributing Watershed Area (including rain garden area) Area = 452 sq ft E) Water Quality Capture Volume (WQCV) Design Volume VWQCV = cu ft Vol = (WQCV / 12) * Area F) For Watersheds Outside of the Denver Region, Depth of d6 = 0.43 in Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, VWQCV OTHER = 12.1 cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER = cu ft (Only if a different WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth (12-inch maximum) DWQCV = 12 in B) Rain Garden Side Slopes (Z = 4 min., horiz. dist per unit vertical) Z = 0.00 ft / ft (Use "0" if rain garden has vertical walls) C) Mimimum Flat Surface Area AMin = 8 sq ft D) Actual Flat Surface Area AActual = 12.50 sq ft E) Area at Design Depth (Top Surface Area) ATop = 12.50 sq ft F) Rain Garden Total Volume VT= 12.50 cu ft (VT= ((ATop + AActual) / 2) * Depth) 3. Growing Media Modified CoFC Rain Garden Section (12" Growing Media, 4" Pea Gravel, 8" AASHTO Class 2) 4. Underdrain System A) Are underdrains provided? B) Underdrain system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y = ft Volume to the Center of the Orifice ii) Volume to Drain in 12 Hours Vol12 = N/A cu ft iii) Orifice Diameter, 3/8" Minimum DO = N/A in Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (East Tower - Basin D1c) UD-BMP (Version 3.06, November 2016) Choose One Choose One 18" Rain Garden Growing Media Other (Explain): YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - East Tower).xlsm, RG 7/19/2018, 8:56 AM Sheet 2 of 2 Designer: Company: Date: Project: Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric A) Is an impermeable liner provided due to proximity of structures or groundwater contamination? PROVIDE A 30 MIL (MIN) PVC LINER WITH CDOT CLASS B GEOTEXTILE ABOVE IT. USE THE SAME GEOTEXTILE BELOW THE LINER IF THE SUBGRADE IS ANGULAR 6. Inlet / Outlet Control A) Inlet Control 7. Vegetation 8. Irrigation A) Will the rain garden be irrigated? Notes: Design Procedure Form: Rain Garden (RG) J.Claeys Interwest Consulting Group July 18, 2018 Oasis on Olive Rain Garden Planters (East Tower - Basin D1c) Choose One Choose One Choose One Sheet Flow- No Energy Dissipation Required Concentrated Flow- Energy Dissipation Provided Plantings Seed (Plan for frequent weed control) Sand Grown or Other High Infiltration Sod Choose One YES NO YES NO 1335-176-00 UD-BMP_v3.06 (RG Planters - East Tower).xlsm, RG 7/19/2018, 8:56 AM ti (min) LENGTH (ft) SLOPE (ft/ft) Table RO-2 VELOCITY (ft/s) t c = t i + t t 0 . 5 V = C v S w V L tt 60 = �� = 18 − 15� + � 60 24� + 12 � �� = 1.87(1.1 − �� �� ) � � � 1335-176-00 Rational Calcs (FC).xlsx Page 3 of 4 Interwest Consulting Group ti (min) LENGTH (ft) SLOPE (ft/ft) Table RO-2 VELOCITY (ft/s) t c = t i + t t 0 . 5 V = C v S w V L tt 60 = �� = 18 − 15� + � 60 24� + 12 � �� = 1.87(1.1 − �� �� ) � � � 1335-176-00 Rational Calcs (FC).xlsx Page 2 of 4 Interwest Consulting Group (sq feet) Awalk (sq feet) Agravel/pavers (sq feet) Alawn (sq feet) 1335-176-00 Rational Calcs (FC).xlsx Page 1 of 4 Interwest Consulting Group Walks/RAP Gravel/Pavers 1335-176-00 Rational Calcs (FC).xlsx Page 1 of 1 Interwest Consulting Group