September 04, 2018
Kris Lee
Kenney Lee Architecture Group, Inc
209 E 4th St
Loveland, CO 80537
RE: Spradley Barr Ford Expansion, MA180062/BDR180025, Round Number 1
Please see the following summary of comments from City staff and outside reviewing agencies for your
submittal of the Spradley Barr Ford Expansion. If you have questions about any comments, you may contact the
individual commenter or direct your questions through your Development Review Coordinator, Brandy Bethurem
Harras, at 970-416-6689 or bbethuremharras@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray@fcgov.com
Topic: Building Elevations MA
Comment Number: 1
Building Elevations. Update Elevation titles. Reference building material colors. Do they match existing building
colors?
Response - Elevations are titles are correct. Building material colors are noted and intended to match
existing stucco on existing main building.
Topic: Site Plan MA
Comment Number: 2
Show and distinguish what is existing and proposed changes on plans.
Response – Dark black building outline with gray hatching is proposed addition as indicated with
“proposed” note. All other area that are lighter, thinner lines indicate existing. No site changes
proposed outside immediate vicinity of addition.
Comment Number: 3
Site Plan add planning signature block.
Response – Planning signature block added to sheet A2.0.
Topic: Plat BDR
2
Comment Number: 4
No comments on plat.
Response – Acknowledged
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General MA
Comment Number: 1
09/05/2018: Is there any roof top mechanical equipment?
Response – Yes, they will be behind the parapet wall and away from street view.
Comment Number: 2
09/05/2018: Is there any exterior lighting to be added?
Response – Yes, only building mounted lights over the proposed walk doors.
Comment Number: 3
09/05/2018: On the site plan the Owner signature block is not necessary and
can be removed.
Response – Owner signature block has been removed from site plan.
Please include a sheet index for the Minor Amendment that includes all sheets not in the Utility Plan set.
Response – A sheet index has been added to sheet A2.0.
Topic: General BDR
Comment Number: 1
09/05/2018: The signature line for the City please change from "Director of Planning" to "CDNS Director"
Response - Signature Block has been updated.
Department: Engineering Development Review
Contact: Morgan Uhlman, 970-416-4344, muhlman@fcgov.com
Topic: General MA
Comment Number: 1
09/04/2018: Please provide elevations for the existing curb ramp along College Ave to show its ADA compliance.
If the current configuration and slopes of the curb ramp does not meet ADA requirements, it will need to be
brought up into compliance.
Response – Plans have been revised to show the reconstruction of this ramp.
Topic: General BDR
Comment Number: 1
09/06/2018: For final plat submission please use the following links, the first is a check list of what needs to be
submitted with the plat, and the second are the AutoCAD drawing requirements :
https://www.fcgov.com/developmentreview/pdf/electronic_final_plat_submittal_req.pdf
https://www.fcgov.com/developmentreview/files/digitalsubmittalstandards.pdf
Response – Is this comment for information? Is there some reason the City would want a CAD file of the plat
3
prior to approval?
Department: Stormwater Engineering
Contact: Heather McDowell, 970-224-6065, hmcdowell@fcgov.com
Topic: General MA/General BDR
Comment Number: 2
09/03/2018: With the dedication of the additional ROW and access easement along College Avenue, and with
the future public sidewalk shifting into the new easement, this will potentially impact the existing detention basin
and reduce the required volume. With the future sidewalk installation, a drainage report will be required and will
need to show how the impacted detention basin will be mitigated. (This comment is also provided in the
BDR180025).
Response – Understood – at this time no changes are planned to the pond.
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control MA / Erosion Control BDR
Comment Number: 1
08/22/2018: Based upon the truck traffic and lift traffic on this building addition the control measures proposed
here are not going to be very effective and would recommend looking at some other types of inlet protection or
vehicle tracking control devices to handle the unique aspects of this site already being majority built out. Plans,
Details and Escrow will all need to be updated based upon the controls chosen. If you need clarification
concerning the Erosion Control Material Requirements or Comments presented above, please contact myself.
Jesse Schlam (970) 224-6015 jschlam@fcgov.com
Response – Since our initial submittal we have worked these comments out directly with Jesse.
Department: Light and Power
Contact: Rob Irish, 970-224-6167, rirish@fcgov.com
Topic: General MA/ General BDR
Comment Number: 1
09/04/2018: If the applicant anticipates a change to the existing electric infrastructure, or an increase in
capacity, please contact Rob Irish @ 970-224-6167 or rirish@fcgov.com.
Response – No change in electrical infrastructure anticipated. All power coming from existing panels.
PLANNING APPROVAL
By the Director of Community and Neighborhood Services the City of Fort Collins, Colorado this
_____day of ________A.D., 20___.
__________________
Director of Community and Neighborhood Services
_____________
City Clerk
Topic: General MA
Comment Number: 2
09/04/2018: The existing 500kva transformer may have the CT's (current transformers) mounted inside the
transformer. Any change to the existing electric service will require the installation of a CT cabinet and the
removal of the existing CT's from the transformer. Placing CT's in the transformer is a practice that is no longer
allowed.
Response – Will update affected CTs.
4
Comment Number: 3
09/04/2018: A C-1 Form and a One-line diagram will need to be submitted to Light & Power for any change to
the existing electric service.
Response – Acknowledged
Comment Number: 4
Any modification or relocation to the existing electric facilities will be subject to system modification charges.
Response – Acknowledged
Comment Number: 5
09/04/2018: Electric Capacity Fee & Building Site charges may apply to this development.
Response – Acknowledged
Topic: General BDR
Comment Number: 1
09/04/2018: Light & Power has no comments, for the platting of this property, at this time.
Response – Acknowledged
Department: Forestry
Contact: Molly Roche, mroche@fcgov.com
Topic: Landscape Plans MA/ Landscape Plans BDR
Comment Number: 1
9/4/2018:Please confirm, was a tree already removed from the site, or is it planned to be removed? On-site
mitigation will need to be provided for the loss of this tree. If the tree was already removed, please include
specimen details including species, size, and condition, since a tree inventory meeting with City Forestry did not
occur. City Forestry will assign the appropriate amount of mitigation trees to be planted back on-site.
Response – After on-site meeting 9-24018 with Molly the single tree proposed to be removed is not in
good shape and does not need to be mitigated.
2/5/2018:
There appears to be existing trees on-site. Please schedule an on-site meeting with City Forestry (Molly
Roche - mroche@fcgov.com) to obtain tree inventory and mitigation information. Please confirm if trees will be
impacted by building expansion and construction activities.
Comment Number: 2
9/4/2018:Please address: will additional landscaping be planted on-site? If so, please
provide a plant list following LUC 3.2.1 guidelines.
Response – Notes added to additional sheet A2.1
Comment Number: 3
9/4/2018:Please provide a note on the site plans that states: EXISITING LANDSCAPE TO REMAIN.
Response – All existing landscaping to remain unless noted otherwise as shown on site/landscape plan.
5
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak@fcgov.com
Topic: General MA/ General BDR
Comment Number: 1
09/03/2018: Refer to comments from Forestry regarding mitigation required for
tree removal.
Response – After on-site meeting 9-24018 with Molly the single tree proposed to be removed is not in
good shape and does not need to be mitigated.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations MA
Comment Number: 6
09/05/2018: There is text that needs to be masked. Mask all text in hatched areas. See redlines.
Response – Redlines have been addressed.
Comment Number: 7
09/05/2018: There is text that needs to be masked. Mask all text in hatched areas. See redlines.
Response – Redlines have been addressed.
Topic: Construction Drawings
Comment Number: 8
09/05/2018: Please revise the sub-title as marked. See redlines.
Response – Redlines have been addressed.
Comment Number: 9
09/05/2018: The Benchmark Statement has been updated. Please provide the following information for the
Benchmark Statement in the EXACT format shown below.
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION ELEVATION:
BENCHMARK # w/ DESCRIPTION ELEVATION:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING
DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED (PRIOR CITY OF FORT COLLINS DATUM) FOR
THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY
PURPOSE, THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED (PRIOR CITY OF
FORT COLLINS DATUM) = NAVD88 - X.XX’.
Response – Redlines have been addressed.
Comment Number: 10
09/05/2018: Please verify that the right of way & easement descriptions shown match the Subdivision Plat
6
(BDR180025). There is one (marked) that will be changing on the Subdivision Plat. See redlines.
Response – Redlines have been addressed.
Comment Number: 11
09/05/2018: There are line over text issues. See redlines.
Response – Redlines have been addressed.
Comment Number: 12
09/05/2018: There is text that needs to be rotated 180°. See redlines.
Response – Redlines have been addressed.
Topic: General MA
Comment Number: 1
09/05/2018: Please verify the address in the title blocks. With the project being replatted, the address could
change.
Response – Acknowledged
Topic: Site Plan MA
Comment Number: 2
09/05/2018: There are line over text issues. See redlines.
Response – Redlines have been addressed.
Comment Number: 3
09/05/2018: The smaller text does not scan or reproduce well. The text needs to increase in size & changed to
normal text. See examples of problem text on redlines.
Response – Redlines have been addressed, text size increased.
Comment Number: 4
09/05/2018: Please verify that the right of way & easement descriptions shown match the Subdivision Plat
(BDR180025). Some of them are affected by the line over text issues.
Response – Redlines have been addressed.
Comment Number: 5
09/05/2018: Please add a legal description for the project property.
Response – Legal description and address have been added.
Topic: Plat BDR
Comment Number: 1
09/03/2018: Please make changes as marked. If changes are not made or you disagree with comments, please
provide written response of why corrections were not made. Please provide any responses on redlined sheets
and/or in response letter.
Response – Redlines have been addressed – comment responses on your redlines are included in this
submittal.
7