HomeMy WebLinkAboutMASON PLACE - MAJOR AMENDMENT - MJA180003 - SUBMITTAL DOCUMENTS - ROUND 2 - GEOTECHNICAL (SOILS) REPORT400 North Link Lane | Fort Collins, Colorado 80524
Telephone: 970-206-9455 Fax: 970-206-9441
GEOTECHNICAL INVESTIGATION
PROPOSED MIDTOWN ON THE MAX PSH
Aka MASON PLACE
3750 SOUTH MASON STREET
FORT COLLINS, COLORADO
HOUSING CATALYST
1715 West Mountain Avenue
Fort Collins, Colorado 80521
Attention: Kristin Fritz
Project No. FC08258-120
April 23, 2018
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
TABLE OF CONTENTS
SCOPE 1
SUMMARY OF CONCLUSIONS 1
SITE CONDITIONS 3
PROPOSED CONSTRUCTION 3
PREVIOUS INVESTIGATIONS 3
INVESTIGATION 3
SUBSURFACE CONDITIONS 4
Groundwater 4
GEOLOGIC HAZARDS 5
Expansive Soils 5
Seismicity 5
SITE DEVELOPMENT 6
Demolition 6
Excavations 6
Fill Placement 7
FOUNDATIONS 8
Drilled Piers Bottomed in Bedrock 8
Micropiles 9
BELOW GRADE AREAS 11
FLOOR SYSTEMS 11
WATER-SOLUBLE SULFATES 14
SURFACE DRAINAGE 15
CONSTRUCTION OBSERVATIONS 15
GEOTECHNICAL RISK 15
LIMITATIONS 16
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
FIGURE 1 – LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2 – SUMMARY LOGS OF EXPLORATORY BORINGS
APPENDIX A – RESULTS OF LABORATORY TESTING
APPENDIX B – SAMPLE SITE GRADING SPECIFICATIONS
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
1
SCOPE
This report presents the results of our Geotechnical Investigation for the
proposed Midtown on the Max Permanent Supportive Housing (PSH) project also
known as Mason Place in Fort Collins, Colorado. The purpose of the investiga-
tion was to evaluate the subsurface conditions to provide geotechnical design cri-
teria and construction recommendations for the proposed renovations. The
scope was described in our Service Agreement (Proposal No. DN 18-0083Rev)
dated February 21, 2018.
The report was prepared from data developed during field exploration, la-
boratory testing, engineering analysis and experience with similar conditions.
The report includes a description of subsurface conditions found in our explora-
tory borings and discussions of site development as influenced by geotechnical
considerations. Our opinions and recommendations regarding design criteria
and construction details for site development, foundations, floor systems, slabs-
on-grade, lateral earth loads and drainage are provided. The report was pre-
pared for the exclusive use of Housing Catalyst in design and construction of pro-
posed Midtown on the Max PSH. If the proposed construction changes, we
should be requested to review our recommendations. Our conclusions are sum-
marized in the following paragraphs.
SUMMARY OF CONCLUSIONS
1. Subsurface conditions encountered in our borings generally con-
sisted of 0 to 12 feet of sandy clay overlying sandstone bedrock to
the depths explored. Borings TH-3 and TH-5 had a 1 to 1½ foot
layer of gravel and sand at depths of 6 and 4 feet respectively. The
upper 3 to 6 feet of soil in three borings was determined to be fill.
Approximately 5 inches of asphaltic concrete overlay borings TH-1,
TH-4 and TH-5. The pertinent engineering characteristics of the
subsoils and bedrock are described in more detail in the report.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
2
2. Groundwater was encountered at depths of 8 to 29 feet in all the
borings during drilling. When measured several days later, ground-
water was at depths of 4½ to 8½ feet in borings TH-2 and TH-3.
The remaining borings were backfilled before secondary groundwa-
ter measurements could be taken. Existing groundwater levels
may affect site development including the elevator shaft and pier in-
stallation. We recommend a minimum 3-foot separation between
the lowest proposed floor elevation and groundwater.
3. Existing fill was encountered in three borings (TH-2, TH-3 and TH-
4), to depths of up to 5 feet. The fill was likely placed during previ-
ous site grading activities. Existing fill should not support floor
slabs. We recommend removal and recompaction of the existing fill
beneath improvements.
4. The presence of expansive soils constitutes a geologic hazard.
There is risk that slabs-on-grade and foundations will heave or set-
tle and be damaged. We judge the risk is low. We believe the rec-
ommendations presented in this report will help to control risk of
damage; they will not eliminate that risk. Slabs-on-grade and, in
some instances, foundations may be damaged.
5. The existing foundation is founded on a drilled pier system. It has
been determined by the structural engineer that the existing foun-
dation is insufficient to support new loads. Additional drilled piers
and/or micropiles, bottomed into bedrock, are recommended to un-
derpin the existing foundation and to allow for additional loads. De-
sign and construction criteria for foundations are presented in the
report.
6. Structural floors will be used for a pier system. We believe a slab-
on-grade floor is also appropriate for this site. Some movement of
slab-on-grade floors should be anticipated. We expect movements
will be minor, on the order of 1 inch or less. If movement cannot be
tolerated, structural floors should be considered.
7. Surface drainage should be designed, constructed and maintained
to provide rapid removal of surface runoff away from the building.
Conservative irrigation practices should be followed to avoid exces-
sive wetting.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
3
SITE CONDITIONS
The site is located at 3750 Mason Street at the southeast corner of South
Mason Street and Creger Drive in Fort Collins, Colorado (Figure 1). The existing
building, constructed in 1982, is a 1-story steel and masonry structure founded
on drilled piers. Midtown Arts Center currently occupies the building. There is an
asphalt parking lot on the north, west and south sides of the building. The south-
ern parking lot is shared with IBMC College. Landscaped berms with manicured
grass and trees are located adjacent to Mason Avenue and Creger Drive.
PROPOSED CONSTRUCTION
Based on our understanding, the project includes adaptive reuse of the ex-
isting Midtown Arts Center into 60-units of permanent supportive housing with
space for onsite supportive services. Up to three stories are planned for the exist-
ing single-story building. An elevator and requisite water-proof shaft pit will be
constructed. Minor adjustments to the existing paved areas are desired to ac-
commodate an outdoor amenity area. We have not been provided with founda-
tion loads or sizes, but we anticipate heavy structural loads. Additional piers
and/or underpinning will be required to carry the extra floors.
PREVIOUS INVESTIGATIONS
CTL | Thompson was provided structural plans for the existing building
prepared by KTM Associates (Project Number 975, dated March 26, 1982) and a
soils report by Empire Laboratories, Inc. (Project Number 4660-82, dated Janu-
ary 27, 1982). Information from the plans and the geotechnical report were con-
sidered in preparation of this report.
INVESTIGATION
The field investigation included drilling five exploratory borings at the loca-
tions presented on Figure 1. The borings were drilled to depths of approximately
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
4
30 to 35 feet using 4-inch diameter, continuous-flight augers and a truck-
mounted drill. Drilling was observed by our field representative who logged the
soils and bedrock. Summary logs of the borings, including results of field pene-
tration resistance tests, are presented on Figure 2.
Soil and bedrock samples obtained during drilling were returned to our la-
boratory and visually examined by our geotechnical engineer. Laboratory testing
was assigned and included moisture content, dry density, swell-consolidation,
particle-size analysis and water-soluble sulfate tests. Swell-consolidation test
samples were wetted at a confining pressure which approximated the weight of
overlying soils (overburden pressures). Results of the laboratory tests are pre-
sented in Appendix A and summarized in Table A-I.
SUBSURFACE CONDITIONS
Subsurface conditions encountered in our borings generally consisted of 0
to 12 feet of sandy clay overlying sandstone bedrock to the depths explored. Bor-
ings TH-3 and TH-5 had a 1 to 1½ foot layer of gravel and sand at depths of 6
and 4 feet respectively. The upper 3 to 6 feet of soil in three borings was deter-
mined to be fill. Approximately 5 inches of asphaltic concrete overlay borings TH-
1, TH-4 and TH-5. Samples tested for swell-consolidation exhibited nil to 0.8 per-
cent swell potential. A sample of the sandstone indicated a fines content (percent
passing No. 200 sieve) of 15 percent. Further descriptions of the subsurface con-
ditions are presented on our boring logs and in our laboratory test results.
Groundwater
Groundwater was encountered at depths of 8 to 29 feet in all the borings
during drilling. When measured several days later, groundwater was at depths of
4.5 to 8.5 feet in borings TH-2 and TH-3. The remaining borings were backfilled
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
5
before secondary groundwater measurements could be taken. Since this is a de-
veloped area we do not expect the groundwater levels to vary substantially from
the levels measured in our borings. We recommend a minimum 3-foot separation
between the lowest proposed floor elevation and groundwater if possible.
GEOLOGIC HAZARDS
Our investigation addressed potential geologic hazards, including expan-
sive soils and seismicity that should be considered during planning and construc-
tion. None of these hazards considered will preclude proposed construction.
The following sections discuss each of these geologic hazards and associated
development concerns.
Expansive Soils
Expansive soils and bedrock are present at the site. The presence of ex-
pansive soils and bedrock, collectively referred to as expansive or swelling soils,
constitutes a geologic hazard. There is a very low risk that ground heave will
damage slabs-on-grade and foundations. We expect that the existing slabs and
any new slab construction will perform satisfactory and will perform as the exist-
ing slabs have since original construction. We believe the recommendations in
this report will help control risk of foundations and/or slab damage; they will not
eliminate that risk.
Seismicity
This area, like most of central Colorado, is subject to a low degree of seis-
mic risk. As in most areas of recognized low seismicity, the record of the past
earthquake activity in Colorado is incomplete. According to the 2015 International
Building Code and the subsurface conditions encountered in our borings, this site
probably classifies as a Site Class C.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
6
SITE DEVELOPMENT
Demolition
Modification of the existing structure will require demolition of some of the
interior spaces. Exposed soils due to removed flooring or pavement should be
cleared of debris, moisture treated and properly compacted to specifications in
Fill Placement section below if they are to become loadbearing. A Phase I Envi-
ronmental Site Assessment was conducted by National Inspection Services on
December 23, 2016. No recognized environmental conditions, historical recog-
nized environmental conditions or controlled recognized environmental condi-
tions were identified on the property.
Excavations
We anticipate excavations up to approximately 3 feet below existing
grades may by required. Excavation for elevator or stairway cores may extend
deeper. The materials found in our borings can be excavated using conventional
heavy-duty excavation equipment. Excavations should be sloped or shored to
meet local, State and Federal safety regulations. Excavation slopes specified by
OSHA are dependent upon types of soil and groundwater conditions encoun-
tered. The contractor’s “competent person” should identify the soils and/or rock
encountered in the excavation and refer to OSHA standards to determine appro-
priate slopes.
Soft soils may be encountered at the bottom of excavations. Soft soils
should be stabilized. Stabilization can be accomplished by crowding 1.5-inch to
3-inch nominal size crushed rock or recycled concrete into the soft subsoils until
the base of the excavation does not deform more than about 3 inches when com-
pactive effort is applied. Acceptable rock materials include, but are not limited to,
No. 2 and No. 57, or 1 to 3-inch recycled concrete.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
7
Fill Placement
The existing onsite soils are suitable for re-use as fill material provided de-
bris or deleterious organic materials are removed. Soil particles larger than 3
inches in diameter should not be used for fill. If import material is used, it should
be tested and approved as acceptable fill by CTL|Thompson. In general, import
fill should meet or exceed the engineering qualities of the onsite soils. Areas to
receive fill should be scarified, moisture-conditioned and compacted to at least
95 percent of standard Proctor maximum dry density (ASTM D698, AASHTO
T99). Fill placed on the upper clayey sand and sandy clay may be difficult to
compact and may require a layer of granular material be crowded into soft soils
and stabilized prior to fill placement. Sand soils used as fill should be moistened
to within 2 percent of optimum moisture content. Clay soils should be moistened
between optimum and 3 percent above optimum moisture content. The fill
should be moisture-conditioned, placed in thin, loose lifts (8 inches or less) and
compacted as described above. We should observe placement and compaction
of fill during construction. Fill placement and compaction should not be con-
ducted when the fill material is frozen.
Existing fill was encountered in three borings to depths of up to 5 feet.
Deeper fill areas may be encountered during site development. The fill is of un-
known origin and age. We anticipate that the fill was placed during original site
development and that risk of additional settlement is low.
Site grading in areas of landscaping where no future improvements are
planned can be placed at a dry density of at least 90 percent of standard Proctor
maximum dry density (ASTM D 698, AASHTO T 99). Example site grading spec-
ifications are presented in Appendix B.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
8
Water and sewer lines are often constructed beneath areas where im-
provements are planned. Compaction of trench backfill can have a significant ef-
fect on the life and serviceability overlying structures. We recommend trench
backfill be moisture conditioned and compacted as described in the Fill Place-
ment section of this report. Placement and compaction of fill and backfill should
be observed and tested by a representative of our firm during construction.
FOUNDATIONS
The existing building is constructed on drilled piers which extended to
shallow depths. Additional drilled piers and/or micropiles may be used for in-
creased loads on existing foundation walls or for new load bearing walls. Design
criteria for drilled pier and micropile foundations developed from analysis of field
and laboratory data and our experience are presented below.
Drilled Piers Bottomed in Bedrock
1. Piers should be designed for a maximum allowable end pressure of
50,000 psf and an allowable skin friction of 5,000 psf for the portion
of pier in bedrock. Skin friction should be neglected for the upper 3
feet of pier below grade beams. Pier end pressure can be in-
creased 30 percent for short duration live loads such as wind loads.
2. Piers should penetrate at least 5 feet into competent sandstone
bedrock and have a minimum length of 25 feet.
3. There should be a 4-inch (or thicker) continuous void beneath all
grade beams, between piers, to concentrate the dead load of the
structure onto the piers.
4. Grade beams should be well reinforced. A qualified structural engi-
neer should design the reinforcement.
5. Pier borings should be drilled to a plumb tolerance of 1.5 percent
relative to the pier length.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
9
6. Piers should be carefully cleaned prior to placement of concrete.
Ground water was encountered during this investigation. We rec-
ommend a “drill-and-pour” procedure for pier installation. Concrete
should be on site and placed in the pier holes immediately after the
holes are drilled, cleaned and observed by our representative to
avoid collecting water and possible contamination of open pier
holes. We anticipate tremie equipment and/or pumping may be
necessary for proper cleaning, dewatering, and concrete place-
ment. Concrete should not be placed by free fall if there is more
than about 3 inches of water at the bottom of the hole.
7. Concrete placed by the free fall method should have a slump be-
tween 5 inches and 7 inches. Concrete placed by pump, tremie or
when temporarily cased should have a slump between 6 inches
and 8 inches.
8. Formation of “mushrooms” or enlargements at the top of piers
should be avoided during pier drilling and subsequent construction
operations.
9. We should observe installation of drilled piers to confirm the sub-
surface conditions are those we anticipated from our borings.
Micropiles
Micropiles should be designed and detailed in accordance with Section
1810.3.10 of the 2015 International Building Code (IBC). Further, construction
techniques and procedures contained in the FHWA “Micropile Design and Con-
struction Guidelines Manual” (Report No. FHWA-SA-97-070 dated June 2000)
should be implemented. We are available to review the design and specifications
developed by our structural engineer and contractor.
1. Commonly available micropile systems have a maximum working
capacity in the range of 20 to 100 kips. The micropiles should pene-
trate a minimum 5 feet into competent bedrock. Piles should bottom
in hard bedrock. Longer piles may be required for structural loads.
2. A 4-inch or thicker void should be established underneath the exist-
ing foundation between piles. The ability of the foundation to span
between micropiles should be determined by our structural engi-
neer.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
10
3. Four distinct classifications of micropiles have been standardized
based on various drilling and grouting techniques. A description of
the various micropile types (A, B, C, and D) is provided in the refer-
enced FHWA manual. The selection of micropile type should be left
to the discretion of the designer and/or contractor. Based on the
soil types encountered in our exploration (clay overburden under-
lain by bedrock), we anticipate a “Type A” and/or “Type B” micro-
piles will be utilized. Drilling methods should be determined by the
contractor.
4. Reinforce micropiles their full length. The area of reinforcing steel
should be sufficient to withstand axial compressive loads on the mi-
cropile and tension due to uplift. At a minimum, reinforcing steel
should be sized to resist 8 kips of uplift. Table 1810.3.2.6 of the
2015 IBC provides allowable stresses for material used in deep
foundation elements which includes micropiles. We interpret utiliz-
ing 0.3 f’c for micropile grout in compression, 0.4 Fy for micropile
structural steel in compression, and 0.6 Fy for micropile structural
steel in tension. We suggest utilizing minimum 28-day compressive
strength of 4,000 psi for the grout and utilizing either Grade 75 or
Grade 150 high-strength bar.
5. Drilling methods should be determined by the contractor. Dry rotary
or air flush methods are preferable to water flush due to moisture-
sensitive subsoils.
6. Micropiles should have a minimum diameter of 4 inches. Larger di-
ameters may be used, but the minimum dead load and area of rein-
forcing steel required for uplift tension should be increased propor-
tionately with the circumference of the micropile (i.e. 30 kips for 6-
inch diameter).
7. Values for the grout-to-ground nominal bond strength are com-
monly based on experience of local contractors and their design
engineers. Table 5-2 on page 5-16 of the manual presents ranges
of typical values for various installation methods and ground condi-
tions. For initial design calculations, micropiles should be designed
using grout/ground interface bond strength of 10,800 psf in bedrock
and a service load factor of 2.5 (i.e. = 4,320 psf allowable). The ac-
tual value can be affected by grouting procedures. The contractor
could verify whether the design value can be achieved by load
tests. We suggest ignoring any bond stress contribution of overbur-
den soils.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
11
8. At a minimum, micropiles should be spaced 3 feet apart or greater
to avoid group efficiency effects.
9. The top of micropiles should be capped with an anchor plate em-
bedded in concrete and sized to resist applied compression and ex-
pansive soil tensile loads. The concrete should be designed as a
haunch and rigidly doweled to the existing foundation. Effects of
moment and load eccentricity should be accounted for by our struc-
tural engineer.
10. A representative of our firm should observe the installation of micro-
piles to confirm the depth and penetration.
BELOW GRADE AREAS
An elevator shaft pit is planned for the building. The pit is expected to be
water proof; a perimeter drain is not necessary. Lateral earth pressure on the pit
walls can be calculated using an equivalent fluid density of 50 pcf. This value is
for horizontal backfill conditions and does not include pressure due to surcharge
or hydrostatic pressure.
Where interior areas are below exterior grades by more than 12 inches,
we recommend installing a perimeter drain. The drain should consist of a 4-inch
diameter open joint or slotted pipe encased in free draining gravel. The drain
should lead to a positive gravity outlet, such as a storm drain or to a sump where
water can be removed by pumping.
FLOOR SYSTEMS
In our opinion, it is reasonable to use slab-on-grade floors for the pro-
posed construction. Any fill placed for the floor subgrade should be built with
densely compacted, engineered fill as discussed in the Fill Placement section of
this report. The existing fill is not an acceptable subgrade for a slab-on-grade
floor and should be completely removed and re-compacted.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
12
It is impossible to construct slab-on-grade floors with no risk of movement.
We believe movements due to swell will be less than 1 inch at this site. If move-
ment cannot be tolerated, structural floors should be used. Structural floors can
be considered for specific areas that are particularly sensitive to movement or
where equipment on the floor is sensitive to movement.
Where structurally supported floors are selected, we recommend a mini-
mum void between the ground surface and the underside of the floor system of 4
inches. The minimum void should be constructed below beams and utilities that
penetrate the floor. The floor may be cast over void form. Void form should be
chosen to break down quickly after the slab is placed. We recommend against
the use of wax or plastic-coated void boxes.
Slabs may be subject to heavy point loads. The structural engineer
should design floor slab reinforcement. For design of slabs-on-grade, we recom-
mend a modulus of subgrade reaction of 100 pci for on-site soils.
If the owner elects to use slab-on-grade construction and accepts the risk
of movement and associated damage, we recommend the following precautions
for slab-on-grade construction at this site. These precautions can help reduce,
but not eliminate, damage or distress due to slab movement.
1. Slabs should be separated from exterior walls and interior bearing
members with a slip joint that allows free vertical movement of the
slabs. This can reduce cracking if some movement of the slab oc-
curs.
2. Slabs should be placed directly on exposed soils, sandstone bed-
rock or properly moisture conditioned and compacted fill. The 2015
International Building Code (IBC) requires a vapor retarder be
placed between the base course or subgrade soils and the con-
crete slab-on-grade floor. The merits of installation of a vapor re-
tarder below floor slabs depend on the sensitivity of floor coverings
and building use to moisture. A properly installed vapor retarder
(minimum 6-mil; 10-mil recommended) is more beneficial below
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
13
concrete slab-on-grade floors where floor coverings, painted floor
surfaces or products stored on the floor will be sensitive to mois-
ture. The vapor retarder is most effective when concrete is placed
directly on top of it, rather than placing a sand or gravel leveling
course between the vapor retarder and the floor slab. The place-
ment of concrete on the vapor retarder may increase the risk of
shrinkage cracking and curling. Use of concrete with reduced
shrinkage characteristics including minimized water content, max-
imized coarse aggregate content, and reasonably low slump will re-
duce the risk of shrinkage cracking and curling. Considerations
and recommendations for the installation of vapor retarders below
concrete slabs are outlined in Section 3.2.3 of the 2006 report of
American Concrete Institute (ACI) Committee 302, “Guide for Con-
crete Floor and Slab Construction (ACI 302.R1-04)”.
3. If slab-bearing partitions are used, they should be designed and
constructed to allow for slab movement. At least a 3-inch void
should be maintained below or above the partitions. If the “float” is
provided at the top of partitions, the connection between interior,
slab-supported partitions and exterior, foundation supported walls
should be detailed to allow differential movement.
4. Underslab plumbing should be eliminated where feasible. Where
such plumbing is unavoidable it should be thoroughly pressure
tested for leaks prior to slab construction and be provided with flexi-
ble couplings. Pressurized water supply lines should be brought
above the floors as quickly as possible.
5. Plumbing and utilities that pass through the slabs should be iso-
lated from the slabs and constructed with flexible couplings. Where
water and gas lines are connected to furnaces or heaters, the lines
should be constructed with sufficient flexibility to allow for move-
ment.
6. HVAC equipment supported on the slab should be provided with a
collapsible connection between the furnace and the ductwork, with
allowance for at least 3 inches of vertical movement.
7. The American Concrete Institute (ACI) recommends frequent con-
trol joints be provided in slabs to reduce problems associated with
shrinkage cracking and curling. To reduce curling, the concrete mix
should have a high aggregate content and a low slump. If desired,
a shrinkage compensating admixture could be added to the con-
crete to reduce the risk of shrinkage cracking. We can perform a
mix design or assist the design team in selecting a pre-existing mix.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
14
WATER-SOLUBLE SULFATES
Concrete that comes into contact with soils can be subject to sulfate at-
tack. We measured water-soluble sulfate concentrations in two samples from
this site. Concentrations were measured were less than 0.01 percent and 0.7
percent. Water-soluble sulfate concentrations between 0.2 and 2 percent indi-
cate Class 2 sulfate exposure, according to the American Concrete Institute
(ACI). For sites with Class 2 sulfate exposure, ACI recommends using a cement
meeting the requirements for Type V (sulfate resistant) cement or the equivalent,
with a maximum water-to-cementitious material ratio of 0.45 and air entrainment
of 5 to 7 percent. As an alternative, ACI allows the use of cement that conforms
to ASTM C 150 Type II requirements, if it meets the Type V performance require-
ments (ASTM C 1012) of ACI 201, or ACI allows a blend of any type of Portland
cement and fly ash that meets the performance requirements (ASTM C 1012) of
ACI 201. In Colorado, Type II cement with 20 percent Class F fly ash usually
meets these performance requirements. The fly ash content can be reduced to
15 percent for placement in cold weather months, provided a water-to-cementi-
tious material ratio of 0.45 or less is maintained. ACI also indicates concrete with
Class 2 sulfate exposure should have a minimum compressive strength of 4,500
psi.
Sulfate attack problems are comparatively rare in this area when quality
concrete is used. Considering the range of test results, we believe risk of sulfate
attack is lower than indicated by the couple laboratory tests performed. The risk
is also lowered to some extent by damp-proofing the surfaces of concrete walls
in contact with the soil. ACI indicates sulfate resistance for Class 1 exposure
can be achieved by using Type II cement, a maximum water-to-cementitious ma-
terial ratio of 0.50, and a minimum compressive strength of 4,000 psi. We be-
lieve this approach should be used as a minimum at this project. The more strin-
gent measures outlined in the previous paragraph will better control risk of sulfate
attack and are more in alignment with written industry standards.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
15
SURFACE DRAINAGE
Performance of foundations and flatwork are influenced by changes in
subgrade moisture conditions. Carefully planned and maintained surface grading
can reduce the risk of wetting of the subgrade soils. Positive drainage should be
provided away from foundations. Backfill around foundations should be moisture
treated and compacted as described in Fill Placement. Roof drains should be di-
rected away from buildings. Downspout extensions and splash blocks should be
provided at discharge points.
CONSTRUCTION OBSERVATIONS
We recommend that CTL | Thompson, Inc. provide construction observa-
tion services to allow us the opportunity to verify whether soil conditions are con-
sistent with those found during this investigation. Other observations are recom-
mended to review general conformance with design plans. If others perform
these observations, they must accept responsibility to judge whether the recom-
mendations in this report remain appropriate.
GEOTECHNICAL RISK
The concept of risk is an important aspect with any geotechnical evalua-
tion primarily because the methods used to develop geotechnical recommenda-
tions do not comprise an exact science. We never have complete knowledge of
subsurface conditions. Our analysis must be tempered with engineering judg-
ment and experience. Therefore, the recommendations presented in any ge-
otechnical evaluation should not be considered risk-free. Our recommendations
represent our judgment of those measures that are necessary to increase the
chances that the structure will perform satisfactorily. It is critical that all recom-
mendations in this report are followed during construction. Owners must assume
responsibility for maintaining the structures and use appropriate practices regard-
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
16
ing drainage and landscaping. Improvements performed by owners after con-
struction, such as construction of additions, retaining walls, landscaping and ex-
terior flatwork, should be completed in accordance with recommendations in this
report.
LIMITATIONS
This report has been prepared for the exclusive use of Housing Catalyst
for providing geotechnical design and construction criteria for the proposed pro-
ject. The information, conclusions, and recommendations presented herein are
based upon consideration of many factors including, but not limited to, the type of
construction proposed, the geologic setting, and the subsurface conditions en-
countered. The conclusions and recommendations contained in the report are
not valid for use by others. Standards of practice evolve in the area of geotech-
nical engineering. The recommendations provided are appropriate for about
three years. If the proposed construction is not constructed within about three
years, we should be contacted to determine if we should update this report.
Five borings were drilled during this investigation to obtain a reasonably
accurate picture of the subsurface conditions. Variations in the subsurface con-
ditions not indicated by our borings are possible. A representative of our firm
should observe the drilling of pier and micropile holes to confirm proper pier con-
struction.
We believe this investigation was conducted with that level of skill and
care ordinarily used by geotechnical engineers practicing in this area at this time.
No warranty, express or implied, is made.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
17
If we can be of further service in discussing the contents of this report or
in the analysis of the influence of subsurface conditions on design of the struc-
tures, please call.
CTLTHOMPSON, INC.
Trace Krausse, EIT Spencer Schram, PE
Staff Geotechnical Engineer Project Manager
Reviewed by:
Marc E. Cleveland, PE
Vice President
TSK:SAS:MEC
(2 Copies)
Via e-mail: kfritz@housingcatalyst.com
TH-5
TBM
TH-4
TH-2
TH-1
TH-3
Creger Drive
Mason Street
College Avenue
E. HARMONY RD.
E. HORSETOOTH RD.
DRAKE RD.
TIMBERLINE RD.
COLLEGE AVE.
SHIELDS ST.
LEMAY AVE.
SITE
MASON ST.
LEGEND:
INDICATES APPROXIMATE LOCATION
OF EXPLORATORY BORING
INDICATES APPROXIMATE LOCATION
OF TEMPORARY BENCHMARK; FIRST
FLOOR AT FRONT DOOR (ASSUMED
ELEVATION 100')
TH-1
TBM
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL I T PROJECT NO. FC08258-120
FIGURE 1
Locations of
Exploratory
Borings
VICINITY MAP
(FORT COLLINS, COLORADO)
NOT TO SCALE
150'
APPROXIMATE
SCALE: 1" = 150'
60
65
70
75
80
85
90
95
100
105
60
65
70
75
80
85
90
95
100
105
ELEVATION - FEET
FIGURE 2
ELEVATION - FEET
Summary Logs of
Exploratory Borings
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL | T PROJECT NO. FC08258-120
50/5
50/3
50/1
50/2
50/1
50/1
50/0
WC=9.1
DD=92
SW=0.0
SS=<0.01
WC=13.5
-200=15
TH-1
El. 100.0
14/12
50/3
50/1
50/1
50/1
50/2
WC=10.4
-200=29
WC=18.0
DD=101
SW=0.0
TH-2
El. 100.5
14/12
11/12
50/3
50/2
APPENDIX A
RESULTS OF LABORATORY TESTING
Sample of SANDSTONE, CLAYEY DRY UNIT WEIGHT= 92 PCF
From TH - 1 AT 4 FEET MOISTURE CONTENT= 9.1 %
Sample of SANDSTONE, CLAYEY DRY UNIT WEIGHT= 101 PCF
From TH - 2 AT 14 FEET MOISTURE CONTENT= 18.0 %
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL | T PROJECT NO. FC08258-120
APPLIED PRESSURE - KSF
APPLIED PRESSURE - KSF
COMPRESSION % EXPANSION
Swell Consolidation
Test Results
FIGURE A-1
COMPRESSION % EXPANSION
-4
-3
-2
-1
0
1
2
3
NO MOVEMENT DUE TO WETTING
-4
-3
-2
-1
0
1
2
3
NO MOVEMENT DUE TO WETTING
0.1 1.0 10 100
0.1 1.0 10 100
Sample of CLAY, SANDY (CL) DRY UNIT WEIGHT= 113 PCF
From TH - 3 AT 4 FEET MOISTURE CONTENT= 18.0 %
Sample of CLAY, SANDY (CL) DRY UNIT WEIGHT= 104 PCF
From TH - 3 AT 9 FEET MOISTURE CONTENT= 23.0 %
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL | T PROJECT NO. FC08258-120
APPLIED PRESSURE - KSF
APPLIED PRESSURE - KSF
COMPRESSION % EXPANSION
Swell Consolidation
Test Results
FIGURE A-2
COMPRESSION % EXPANSION
-4
-3
-2
-1
0
1
2
3
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
-4
-3
-2
-1
0
1
2
3
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
0.1 1.0 10 100
0.1 1.0 10 100
Sample of FILL, CLAY, SANDY, GRAVELLY DRY UNIT WEIGHT= 107 PCF
From TH - 4 AT 2 FEET MOISTURE CONTENT= 17.7 %
Sample of CLAY, SANDY (CL) DRY UNIT WEIGHT= 104 PCF
From TH - 5 AT 9 FEET MOISTURE CONTENT= 23.5 %
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL | T PROJECT NO. FC08258-120
APPLIED PRESSURE - KSF
APPLIED PRESSURE - KSF
COMPRESSION % EXPANSION
Swell Consolidation
Test Results
FIGURE A-3
COMPRESSION % EXPANSION
-4
-3
-2
-1
0
1
2
3
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
-4
-3
-2
-1
0
1
2
3
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
0.1 1.0 10 100
0.1 1.0 10 100
Sample of FILL, SAND, CLAYEY, GRAVELLY GRAVEL 20 % SAND 51
%
From TH - 2 AT 2 FEET SILT & CLAY 29 % LIQUID LIMIT %
PLASTICITY INDEX %
Sample of GRAVEL % SAND %
From SILT & CLAY % LIQUID LIMIT %
PLASTICITY INDEX %
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL | T PROJECT NO. FC08258-120
FIGURE A-4
Gradation
Test Results
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
PASSING WATER-
MOISTURE DRY APPLIED NO. 200 SOLUBLE
DEPTH CONTENT DENSITY SWELL* PRESSURE SIEVE SULFATES
BORING (FEET) (%) (PCF) (%) (PSF) (%) (%) DESCRIPTION
TH-1 4 9.1 92 0.0 500 <0.01 SANDSTONE, CLAYEY
TH-1 9 13.5 15 SANDSTONE, CLAYEY
TH-2 2 10.4 29 FILL, SAND, CLAYEY, GRAVELLY
TH-2 14 18.0 101 0.0 1,800 SANDSTONE, CLAYEY
TH-3 4 18.0 113 0.8 500 CLAY, SANDY (CL)
TH-3 9 23.0 104 0.6 1,100 CLAY, SANDY (CL)
TH-4 2 17.7 107 0.1 500 FILL, CLAY, SAND, GRAVELLY
TH-5 9 23.5 104 0.1 1,100 0.73 CLAY, SANDY (CL)
SWELL TEST RESULTS*
TABLE A-I
SUMMARY OF LABORATORY TESTING
Page 1 of 1
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTL|T PROJECT NO. FC08258-120
APPENDIX B
SAMPLE SITE GRADING SPECIFICATIONS
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
B-1
SAMPLE SITE GRADING SPECIFICATIONS
1. DESCRIPTION
This item shall consist of the excavation, transportation, placement and compac-
tion of materials from locations indicated on the plans, or staked by the Engineer,
as necessary to achieve building site elevations.
2. GENERAL
The Geotechnical Engineer shall be the Owner's representative. The Geotech-
nical Engineer shall approve fill materials, method of placement, moisture con-
tents and percent compaction, and shall give written approval of the completed
fill.
3. CLEARING JOB SITE
The Contractor shall remove all trees, brush and rubbish before excavation or fill
placement is begun. The Contractor shall dispose of the cleared material to pro-
vide the Owner with a clean, neat appearing job site. Cleared material shall not
be placed in areas to receive fill or where the material will support structures of
any kind.
4. SCARIFYING AREA TO BE FILLED
All topsoil and vegetable matter shall be removed from the ground surface upon
which fill is to be placed. The surface shall then be plowed or scarified to a depth
of 8 inches until the surface is free from ruts, hummocks or other uneven fea-
tures, which would prevent uniform compaction by the equipment to be used.
5. COMPACTING AREA TO BE FILLED
After the foundation for the fill has been cleared and scarified, it shall be disked
or bladed until it is free from large clods, brought to the proper moisture content
and compacted to not less than 95 percent of maximum dry density as deter-
mined in accordance with ASTM D 698 or AASHTO T 99.
6. FILL MATERIALS
On-site materials classifying as CL, SC, SM, SW, SP, GP, GC and GM are ac-
ceptable. Fill soils shall be free from organic matter, debris, or other deleterious
substances, and shall not contain rocks or lumps having a diameter greater than
three (3) inches. Fill materials shall be obtained from the existing fill and other
approved sources.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
B-2
7. MOISTURE CONTENT
Fill materials shall be moisture treated. Clay soils placed below the building en-
velope should be moisture-treated to between optimum and 3 percent above op-
timum moisture content as determined from Standard Proctor compaction tests.
Clay soil placed exterior to the building should be moisture treated between opti-
mum and 3 percent above optimum moisture content. Sand soils can be mois-
tened to within 2 percent of optimum moisture content. Sufficient laboratory com-
paction tests shall be performed to determine the optimum moisture content for
the various soils encountered in borrow areas.
The Contractor may be required to add moisture to the excavation materials in
the borrow area if, in the opinion of the Geotechnical Engineer, it is not possible
to obtain uniform moisture content by adding water on the fill surface. The Con-
tractor may be required to rake or disk the fill soils to provide uniform moisture
content through the soils.
The application of water to embankment materials shall be made with any type of
watering equipment approved by the Geotechnical Engineer, which will give the
desired results. Water jets from the spreader shall not be directed at the em-
bankment with such force that fill materials are washed out.
Should too much water be added to any part of the fill, such that the material is
too wet to permit the desired compaction from being obtained, rolling and all work
on that section of the fill shall be delayed until the material has been allowed to
dry to the required moisture content. The Contractor will be permitted to rework
wet material in an approved manner to hasten its drying.
8. COMPACTION OF FILL AREAS
Selected fill material shall be placed and mixed in evenly spread layers. After
each fill layer has been placed, it shall be uniformly compacted to not less than
the specified percentage of maximum dry density. Fill materials shall be placed
such that the thickness of loose material does not exceed 8 inches and the com-
pacted lift thickness does not exceed 6 inches.
Compaction, as specified above, shall be obtained by the use of sheepsfoot roll-
ers, multiple-wheel pneumatic-tired rollers, or other equipment approved by the
Engineer. Compaction shall be accomplished while the fill material is at the
specified moisture content. Compaction of each layer shall be continuous over
the entire area. Compaction equipment shall make sufficient trips to insure that
the required dry density is obtained.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
B-3
9. COMPACTION OF SLOPES
Fill slopes shall be compacted by means of sheepsfoot rollers or other suitable
equipment. Compaction operations shall be continued until slopes are stable,
but not too dense for planting, and there is no appreciable amount of loose soil
on the slopes. Compaction of slopes may be done progressively in increments of
three to five feet (3' to 5') in height or after the fill is brought to its total height.
Permanent fill slopes shall not exceed 3:1 (horizontal to vertical).
10. DENSITY TESTS
Field density tests shall be made by the Geotechnical Engineer at locations and
depths of his choosing. Where sheepsfoot rollers are used, the soil may be dis-
turbed to a depth of several inches. Density tests shall be taken in compacted
material below the disturbed surface. When density tests indicate that the dry
density or moisture content of any layer of fill or portion thereof is below that re-
quired, the particular layer or portion shall be reworked until the required dry den-
sity or moisture content has been achieved.
11. COMPLETED PRELIMINARY GRADES
All areas, both cut and fill, shall be finished to a level surface and shall meet the
following limits of construction:
A. Overlot cut or fill areas shall be within plus or minus 2/10 of one foot.
B. Street grading shall be within plus or minus 1/10 of one foot.
The civil engineer, or duly authorized representative, shall check all cut and fill
areas to observe that the work is in accordance with the above limits.
12. SUPERVISION AND CONSTRUCTION STAKING
Observation by the Geotechnical Engineer shall be continuous during the place-
ment of fill and compaction operations so that he can declare that the fill was
placed in general conformance with specifications. All site visits necessary to
test the placement of fill and observe compaction operations will be at the ex-
pense of the Owner. All construction staking will be provided by the Civil Engi-
neer or his duly authorized representative. Initial and final grading staking shall
be at the expense of the owner. The replacement of grade stakes through con-
struction shall be at the expense of the contractor.
HOUSING CATALYST
MIDTOWN ON THE MAX PSH
CTLT PROJECT NO. FC08258-120
B-4
13. SEASONAL LIMITS
No fill material shall be placed, spread or rolled while it is frozen, thawing, or dur-
ing unfavorable weather conditions. When work is interrupted by heavy precipi-
tation, fill operations shall not be resumed until the Geotechnical Engineer indi-
cates that the moisture content and dry density of previously placed materials are
as specified.
14. NOTICE REGARDING START OF GRADING
The contractor shall submit notification to the Geotechnical Engineer and Owner
advising them of the start of grading operations at least three (3) days in advance
of the starting date. Notification shall also be submitted at least 3 days in ad-
vance of any resumption dates when grading operations have been stopped for
any reason other than adverse weather conditions.
15. REPORTING OF FIELD DENSITY TESTS
Density tests performed by the Geotechnical Engineer, as specified under "Den-
sity Tests" above, shall be submitted progressively to the Owner. Dry density,
moisture content and percent compaction shall be reported for each test taken.
16. DECLARATION REGARDING COMPLETED FILL
The Geotechnical Engineer shall provide a written declaration stating that the site
was filled with acceptable materials, or was placed in general accordance with
the specifications.
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)
SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR. 7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSING
0
10
20
30
50
60
70
80
90
100
PERCENT RETAINED
40
0.002
15 MIN.
.005
60 MIN.
.009
19 MIN.
.019
4 MIN.
.037
1 MIN.
.074
*200
.149
*100
.297
*50
0.42
*40
.590
*30
1.19
*16
2.0
*10
2.38
*8
4.76
*4
9.52
3/8"
19.1
3/4"
36.1
1½"
76.2
3"
127
5"
152
6"
200
8"
.001
45 MIN.
0
10
20
30
40
50
60
70
80
90
100
CLAY (PLASTIC) TO SILT (NON-PLASTIC)
SANDS
FINE MEDIUM COARSE
GRAVEL
FINE COARSE COBBLES
DIAMETER OF PARTICLE IN MILLIMETERS
25 HR. 7 HR.
HYDROMETER ANALYSIS SIEVE ANALYSIS
TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
PERCENT PASSING
PERCENT RETAINED
0
10
20
30
40
50
60
70
80
90
100
50/3
50/3
50/3
WC=18.0
DD=113
SW=0.8
WC=23.0
DD=104
SW=0.6
TH-3
El. 98.0
12/12
3/12
50/2
50/2
50/2
50/2
50/2
WC=17.7
DD=107
SW=0.1
TH-4
El. 98.0
36/12
9/12
50/3
50/2
50/1
50/2
WC=23.5
DD=104
SW=0.1
SS=0.730
TH-5
El. 98.0
5" AC 5" AC 5" AC
FILL, SAND AND CLAY, GRAVELLY, MOIST, MEDIUM DENSE, STIFF, BROWN
-
-
-
-
-
WC
DD
SW
-200
SS
INDICATES MOISTURE CONTENT (%).
INDICATES DRY DENSITY (PCF).
INDICATES SWELL WHEN WETTED UNDER OVERBURDEN PRESSURE (%).
INDICATES PASSING NO. 200 SIEVE (%).
INDICATES SOLUBLE SULFATE CONTENT (%).
BULK SAMPLE FROM AUGER CUTTINGS.
DRIVE SAMPLE. THE SYMBOL 50/5 INDICATES 50 BLOWS OF A 140-POUND HAMMER
FALLING 30 INCHES WERE REQUIRED TO DRIVE A 2.5-INCH O.D. SAMPLER 5 INCHES.
2.
3.
ASPHALTIC CONCRETE (AC)
THE BORINGS WERE DRILLED ON MARCH 7 AND 8, 2018, USING 4-INCH DIAMETER
CONTINUOUS-FLIGHT AUGERS AND A TRUCK-MOUNTED DRILL RIG.
1.
LEGEND:
NOTES:
CLAY, SANDY, MOIST, STIFF TO VERY STIFF, DARK GRAY, BLUE (CL)
GRAVEL, SANDY, MOIST, MEDIUM DENSE, TAN (GP)
SANDSTONE, SLIGHTLY SILTY, MOIST, VERY HARD, OLIVE, BROWN (BEDROCK)
BORING ELEVATIONS WERE SURVEYED BY BY A REPRESENTATIVE OF OUR FIRM
REFERENCING THE TEMPORARY BENCH MARK SHOWN ON FIGURE 1.
THESE LOGS ARE SUBJECT TO THE EXPLANATIONS, LIMITATIONS AND CONCLUSIONS IN
THIS REPORT.
4.
WATER LEVEL MEASURED SEVERAL DAYS AFTER DRILLING.
WATER LEVEL MEASURED AT TIME OF DRILLING.