Meeting Purpose
2
• Check-in with Neighborhood Advisory Committee
• Share what we heard at the Ice Cream Social
• Identify what will make a successful first phase project
• Discuss next steps and schedule
• Listen to feedback
Preliminary Outreach
3
What we heard at the Ice Cream Social
4
Active and passive use; is it the right balance?
83% yes
Is playground and access the right phasing approach?
88% yes
What playground character do you prefer?
52% nature play/informal, 31% traditional, 17% both
What are the other desired features and/or issues?
swings, climbing elements, bathrooms, water features and safe
access from the neighborhoods.
What we have learned about phasing
5
Phasing a park is not easy, certain elements need to be considered to be successful.
Streets Facility Park Analysis:
• Safe pedestrian access
Temporary asphalt connection, parking, and signalized crossing
Study intersection at Vine/Lemay
Alta Vista needs sidewalks to park
• Shade trees with irrigation
• Shade shelter / gathering space
• Play elements
• Surfacing to accommodate pedestrian traffic
• Adequate site drainage
• Safety / site lighting
• Continuity in character/identity/materials
• Restroom facilities
Streets Park Concept Plan
6
Park Character
7
Large scale custom sugar beet play structure
rough, tough / coarse character
artist and playground design integration
interpretive elements
Great Western Sugar Beet Factory Architectural Character
shelter, future restroom, and site furnishings
8
Next steps
• Site Surveying
• Engineering of water quality features and site
drainage
• Artist coordination and beet play feature custom
design
• Site design of core area
playground elements, shelter, future
restroom, and landscape
• Ongoing funding opportunities; grants and
fundraising
9
Schedule
Park Design – ongoing
Artist coordination and play feature design – ongoing
Construction bid package - winter 2016/17
Phase One Park Construction - summer 2017
Site grading and drainage
playground and art feature
sidewalks and parking
core area shade trees
shelter/gathering space
core area lights
temporary restroom