August 20, 2014
Angie Milewski
BHA Design
1603 Oakridge Dr
Fort Collins, CO 80525
Comment Summary:
Department: Planning Services
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
08/18/2014: Will need to include an alternative compliance request that details how the criteria of such
request is being met.
06/17/2014: LUC 3.2.2(J) Along S College Ave the 15 ft. average minimum landscape setback from
the right of way is not being met.
This is an average of how much of parking frontage is meeting the required landscaped area 15'
setback.
Please provide details of the calculations of the average landscape setback area.
Comment Number: 3 Comment Originated: 06/17/2014
08/18/2014: Light plan needs to include the lighting on the top level of the parking structure both of
phase 1 and phase 2
06/17/2014: LUC 3.2.4 The lighting plan also needs to include the average foot-candle for only the
vehicle use areas.
Is there no lighting on the fourth story of the parking structure?
Is there any existing lighting that is remaining that was not included on the lighting plan?
Comment Number: 5 Comment Originated: 06/17/2014
Please see the following summary of comments from City staff and outside reviewing agencies for your submittal of
the above referenced project. If you have questions about any comments, you may contact the individual
commenter or direct your questions through the Project Planner, Noah Beals, at 970-416-2313 or
nbeals@fcgov.com.
RE: Pedersen Toyota Expansion, PDP140007, Round Number 2
Page 1 of 9
DRAFT
08/18/2014: The walk-in access on the trash enclosure is not clear, please identify.
06/17/2014: LUC 3.2.5 Trash and recycling enclosure shall be provided with walk-in access and at
least 20ft from a public sidewalk on a concrete pad.
Where is the trash and recycling enclosure?
Comment Number: 6 Comment Originated: 06/17/2014
08/18/2014: The column details that are included on the west side of the parking structure should be
addded to the east side.
Also can you provide a color rendering of the elevations throug email or 1 hard copy.
06/19/2014: LUC 3.5.3(E)(2)(a)1. Requires walls that face streets be subdivided every 30ft. in length to
create a human scale.
LUC 3.5.3(E)(3) Facades that face the street shall be broken up with architectural elements for at least
50% of the building
The parking structure wall that faces S Mason Street needs to be refined to include more human scale
architectural elements.
The Blank walls along college both with the existing structure and Parking structure should be broken
up with architectural elements to further create a human scale.
Comment Number: 10 Comment Originated: 06/19/2014
08/18/2014: The arch should be connected to the building by more than a roof.
06/19/2014: Is the arch element at east entrance attached to the building? This seems to be a large
sign rather than portion of the building.
Please provide further details
Comment Number: 11 Comment Originated: 06/19/2014
08/18/2014: The sheet index needs to include the lighting plan and elevations.
06/19/2014: The planning set will need to provide a cover sheet with a sheet index and signature
blocks. Or the site plan with the signature blocks and sheet index.
Comment Number: 13 Comment Originated: 06/19/2014
08/18/2014: The response indicated a note was included, but still not finding such note on the plans.
06/19/2014: Signs are not approved through this development process and a note will need to
indicate this or remove the signs from the plans.
Comment Number: 14 Comment Originated: 06/19/2014
Page 2 of 9
DRAFT
08/18/2014: The expansion of the service are on the north side during phase 2 is not appearing on the
elevations.
06/19/2014: There will need to be a set of plans for the site, landscape, and elevations. To show the
conditions of all phases.
It is not clear at all what is happening during the each phase.
Each phase will need to meet compliance with the LUC.
Comment Number: 15 Comment Originated: 06/19/2014
08/18/2014: The signature block on the site plan and the plat for the Planning Director should be
changed to Director of Community Development and Neighborhood Services.
Comment Number: 16 Comment Originated: 08/18/2014
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenberger@fcgov.com
Topic: General
06/12/2014: Per the submitted site plan there is 174,600 sq ft of new building being added to the site,
therefore the TDRF for PDP is less than was shown and calculated on the TDRF applicaiton. Unless
the square footage changes this project will only owe $125 for the TDRF FDP fee because of the
overpayment of the PDP fee.
Comment Number: 1 Comment Originated: 06/12/2014
08/19/2014: Please remove the type III barricade at the north side of the property where the 10ft
sidewalk ties into existing sidewalk. Can a temp concrete wedge be placed to transition the sidewalks
rather than placing a barricade?
06/25/2014: The sidewalk along College Ave should be extended as the 10 foot wide sidewalk further
north and transition to a narrower sidewalk just before the property line.
Comment Number: 2 Comment Originated: 06/25/2014
06/25/2014: Are there any existing services that need to be removed?
Comment Number: 6 Comment Originated: 06/25/2014
Contact: Tyler Siegmund, 970-221-6501, tsiegmund@fcgov.com
Topic: General
08/19/2014: 2. Per current road standards for an arterial roadway, a 15ft utility easement should be
provided along the College Ave frontage of the property. If this utility easement is not needed by
utility providers the 15ft UE requirement may be reduced in size or waived. Coordination with utility
providers (COFC Water, COFC Light and Power, COFC Storm water, Comcast, Century Link, Public
Service Company of Colorado) is needed to determine if this easement is needed.
Comment Number: 9 Comment Originated: 08/19/2014
08/19/2014: Please depict and note the existing western driveway along Kensington Dr to be
removed and replaced with curb and gutter. The new western drive location appears to shit to the east
from the existing driveway location.
Comment Number: 10 Comment Originated: 08/19/2014
Page 3 of 9
DRAFT
08/19/2014: Please widen the 10ft sidewalk along College Ave where it ties into the new handicap
ramp on Kensington. There is an existing traffic signal box located at the front of walk. Typically,
vertical encroachments need to be located a minimum 2ft clear from the sidewalk. By widening the
sidewalk on the backside it gives bikes and pedestrians room to maneuver around the traffic signal
box. This may require widening of the ped easement on the plat. See redlines.
Comment Number: 11 Comment Originated: 08/19/2014
08/19/2014: Per CDOT comments, an updated access control permit needs to be obtained.
Comment Number: 12 Comment Originated: 08/19/2014
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
07/11/2014: No comments.
Comment Number: 1 Comment Originated: 07/11/2014
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
06/25/2014:
Provide tree species diversity on final landscape plan and list percentages in the plant list. Identify all
species on final landscape plan.
Comment Number: 2 Comment Originated: 06/25/2014
08/19/2014:
Previous comment number two provided on 6/25/14 is continued and still active.
Comment Number: 5 Comment Originated: 08/19/2014
08/19/2014:
Thank you for adding the following note. Its been included under the tree protection notes but fits
better as a plant note. Please move it to the plant notes.
The Developer shall replace dead or dying street trees after planting until final maintenance inspection
and acceptance by the City of Fort Collins Forestry Division. All
City street trees in the project must be established, of an approved species and of acceptable
condition prior to acceptance.
Comment Number: 6 Comment Originated: 08/19/2014
08/19/2014:
For final Landscape plan include 22 upsized mitigation trees. Mitigation trees should be upsized as
follows.
Canopy shade trees 3.0 inch caliper
Ornamental trees 2.5 inch caliper
Evergreen Trees 8 feet height
Comment Number: 7 Comment Originated: 08/19/2014
Department: Internal Services
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
Page 4 of 9
DRAFT
06/23/2014:
Building Permit Pre-Submittal Meeting
Pre-Submittal meetings are offered to assist the designer/builder by assuring, early on in the design,
that the new commercial or multi-family projects are on track to complying with all of the adopted City
codes and Standards listed below. The proposed project should be in the early to mid-design stage
for this meeting to be effective and is typically scheduled after the Current Planning conceptual review
meeting. Applicants of new commercial or multi-family projects are advised to call 416-2341 to
schedule a pre-submittal meeting. Applicants should be prepared to present site plans, floor plans,
and elevations and be able to discuss code issues of occupancy, square footage and type of
construction being proposed.
Construction shall comply with the following adopted codes as amended:
2012 International Building Code (IBC)
2012 International Residential Code (IRC)
2012 International Energy Conservation Code (IECC)
2012 International Mechanical Code (IMC)
2012 International Fuel Gas Code (IFGC)
2012 International Plumbing Code (IPC) as amended by the State of Colorado
2011 National Electrical Code (NEC) as amended by the State of Colorado
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2009.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use
1. Single Family; Duplex; Townhomes: 2012 IRC Chapter 11 or 2012 IECC.
2. Multi-family and Condominiums 3 stories max: 2012 IECC residential chapter.
3. Commercial and Multi-family 4 stories and taller: 2012 IECC commercial chapter.
Fort Collins Green Code Amendments effective starting 1-1-2012. A copy of these requirements can
be obtained at the Building Office or contact the above phone number.
Pederson Toyota expansion – project specific concerns:
1. Fire-sprinkler systems are required for buildings more than 5k s.ft. unless fire containment is
provided.
2. Building code and State statute CRS 9-5 requires project provide accessible units.
3. For an non-sprinkled parking garage that is attached to other buildings, the Building Code will limit
the height to 3 stories and approx 30k per floor.
4. New Green Code requires:
a. Upgraded insulation is required for buildings using electric heat or cooling.
b. Exterior walls and roof must meet a STC (sound resistance) rating of 40 min. if building located
within 1000ft to train tracks.
c. Low-flow Watersense plumbing fixtures (toilet, faucets, shower heads) are required.
d. Special combustion safety requirements for natural draft gas appliances.
e. Low VOC interior finishes.
Comment Number: 1 Comment Originated: 06/23/2014
Page 5 of 9
DRAFT
City of Fort Collins
Building Services
Plan Review
416-2341
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
06/10/2014: The existing electric capacity to this service is 1600 amps at 120/208 volt three-phase.
Additional electric capacity fee for any increase will apply. A Commercial Electric Service (C-1) form
will need to be completed and supplied to Light & Power Engineering.
Comment Number: 1 Comment Originated: 06/10/2014
08/08/2014: It is estimated that the new electric transformer will require a minimum of 13 feet between
the building and the back of the curb at the parking lot. By the utility plan it appears that less than 10
feet is available.
06/10/2014: Relocation of the electric transformer will be at the owner's expense. The space shown
on the utility plan for the relocated transformer may not be adequate. Based on likely electric capacity,
and the resulting likely transformer size, the minimum east to west dimension required will be at least
10 feet. If the transformer is larger, additional space will be necessary. The transformer can be sized
upon receipt of a completed C-1 form. Contact Light & Power Engineering at (970)221-6700 with any
questions.
Comment Number: 2 Comment Originated: 06/10/2014
Department: Outside Agencies
Contact: Gloria Hice-Idler, ,
Topic: General
06/16/2014: I've reviewed the above submittal. Based upon the TIS, it appears that the intersection of
Kensington and College will see an increase of traffic of more than 20%. Per the State Highway
Access Code, the increase allows CDOT to re-evaluate the access and to require a new access
permit.
The review of the intersection indicates that no new highway improvements are necessary, but the
applicant should be required to obtain a new access permit.
If you have any questions, please do not hesitate to contact me.
P 970.350.2148 | C 970.381.2475 | F 970.350.2198
1420 2nd Street, Greeley, CO 80631
gloria.hice-idler@state.co.us
Comment Number: 1 Comment Originated: 06/16/2014
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
Page 6 of 9
DRAFT
06/25/2014: STRUCTURES EXCEEDING 30'
Due to the height of the parking garage, a 30' wide fire lane is required adjacent to the longest side of
the structure. This requirement has not been satisfactorily met with the proposed site plan and further
discussion is needed. Additionally, the 30' EAE width requirement shall be reflected on the plat.
IFC Appendix D; Poudre Fire Authority Administrative Policy 85-5: In order to accommodate the
access requirements for aerial fire apparatus (ladder trucks), required fire lanes shall be 30 foot wide
minimum on at least one long side of the building. At least one of the required access routes meeting
this condition shall be located within a minimum of 15 feet and a maximum of 30 feet from the building,
and shall be positioned parallel to one entire side of the building.
Comment Number: 1 Comment Originated: 06/25/2014
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
08/19/2014: The detention volume calculations need to be revised using the current Fort Collins
rainfall.
Comment Number: 7 Comment Originated: 08/19/2014
08/19/2014: Please document the area of LID facilities to verify compliance with City requirements.
Comment Number: 8 Comment Originated: 08/19/2014
08/19/2014: Please provide drainage easement for all porous paver sections.
Comment Number: 9 Comment Originated: 08/19/2014
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations
08/20/2014: No comments.
06/19/2014: No comments.
Comment Number: 1 Comment Originated: 06/19/2014
Topic: Construction Drawings
08/20/2014: There is still an issue on sheet 3. See redlines.
06/19/2014: There are line over text issues. See redlines.
Comment Number: 4 Comment Originated: 06/19/2014
08/20/2014: There is still an issue on sheet 4. See redlines.
06/19/2014: There are text over text issues. See redlines.
Comment Number: 5 Comment Originated: 06/19/2014
Topic: Landscape Plans
08/20/2014: Please change "Second" to "2nd" for Pedersen Auto Plaza. Please verify the recording
information. We are seeing differences.
06/19/2014: Please add the subdivision information for the surrounding properties as marked on sheet
1. See redlines.
Comment Number: 8 Comment Originated: 06/19/2014
Topic: Lighting Plan
Page 7 of 9
DRAFT
08/20/2014: No comments.
Comment Number: 16 Comment Originated: 08/20/2014
Topic: Plat
08/20/2014: Are there any Lienholders for this property? If so, please add a signature block. If not,
please add a note stating there are none.
Comment Number: 17 Comment Originated: 08/20/2014
08/20/2014: Please provide current acceptable monument records for the aliquot corners shown.
These should be emailed directly to Jeff at jcounty@fcgov.com.
Comment Number: 18 Comment Originated: 08/20/2014
08/20/2014: Please add leaders as marked. See redlines.
Comment Number: 19 Comment Originated: 08/20/2014
Topic: Site Plan
08/20/2014: Please change "Second" to "2nd" for Pedersen Auto Plaza. Please verify the recording
information. We are seeing differences.
06/19/2014: Please add the subdivision information for the surrounding properties as marked. See
redlines.
Comment Number: 10 Comment Originated: 06/19/2014
08/20/2014: There are still some issues. See redlines.
06/19/2014: There are line over text issues. See redlines.
Comment Number: 11 Comment Originated: 06/19/2014
08/20/2014: There are still some issues. See redlines.
06/19/2014: Mask text within hatching. See redlines.
Comment Number: 13 Comment Originated: 06/19/2014
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: General
08/19/2014: No new comments from traffic operations or transportation planning.
Comment Number: 5 Comment Originated: 08/19/2014
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
06/25/2014: Irrigation plans are required no later than at the time of building permit. The irrigation plans
must comply with the provisions outlined in Section 3.2.1(J) of the Land Use Code. Direct questions
concerning irrigation requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Comment Number: 1 Comment Originated: 06/25/2014
Department: Water-Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Construction Drawings
06/24/2014: Show all existing water and sewer mains and services.
Comment Number: 1 Comment Originated: 06/24/2014
Page 8 of 9
DRAFT
06/24/2014: Show/label existing curb stops and meter pits.
Comment Number: 2 Comment Originated: 06/24/2014
06/24/2014: Will the 6" fire line be adequate for the entire building? Water pressure in that area is
approximately 65 psi.
Comment Number: 4 Comment Originated: 06/24/2014
08/19/2014: Add additional information regarding abandonment of water/sewer service (see redlined
utility plans).
Comment Number: 6 Comment Originated: 08/19/2014